CN108677780A - A kind of roadmarking and production method - Google Patents

A kind of roadmarking and production method Download PDF

Info

Publication number
CN108677780A
CN108677780A CN201810744152.0A CN201810744152A CN108677780A CN 108677780 A CN108677780 A CN 108677780A CN 201810744152 A CN201810744152 A CN 201810744152A CN 108677780 A CN108677780 A CN 108677780A
Authority
CN
China
Prior art keywords
groove
roadmarking
prefabricated
reticle structure
prefabricated groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810744152.0A
Other languages
Chinese (zh)
Inventor
赵含
栾海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JILIN COMMUNICATIONS PLANNING AND DESIGN INSTITUTE
Original Assignee
JILIN COMMUNICATIONS PLANNING AND DESIGN INSTITUTE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JILIN COMMUNICATIONS PLANNING AND DESIGN INSTITUTE filed Critical JILIN COMMUNICATIONS PLANNING AND DESIGN INSTITUTE
Priority to CN201810744152.0A priority Critical patent/CN108677780A/en
Publication of CN108677780A publication Critical patent/CN108677780A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F9/00Arrangement of road signs or traffic signals; Arrangements for enforcing caution
    • E01F9/50Road surface markings; Kerbs or road edgings, specially adapted for alerting road users
    • E01F9/506Road surface markings; Kerbs or road edgings, specially adapted for alerting road users characterised by the road surface marking material, e.g. comprising additives for improving friction or reflectivity; Methods of forming, installing or applying markings in, on or to road surfaces
    • E01F9/512Preformed road surface markings, e.g. of sheet material; Methods of applying preformed markings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F9/00Arrangement of road signs or traffic signals; Arrangements for enforcing caution
    • E01F9/50Road surface markings; Kerbs or road edgings, specially adapted for alerting road users
    • E01F9/576Traffic lines
    • E01F9/578Traffic lines consisting of preformed elements, e.g. tapes, block-type elements specially designed or arranged to make up a traffic line
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01FADDITIONAL WORK, SUCH AS EQUIPPING ROADS OR THE CONSTRUCTION OF PLATFORMS, HELICOPTER LANDING STAGES, SIGNS, SNOW FENCES, OR THE LIKE
    • E01F9/00Arrangement of road signs or traffic signals; Arrangements for enforcing caution
    • E01F9/50Road surface markings; Kerbs or road edgings, specially adapted for alerting road users
    • E01F9/576Traffic lines
    • E01F9/582Traffic lines illuminated

Abstract

The present invention discloses a kind of roadmarking, including prefabricated groove and reticle structure, and the reticle structure is filled in the prefabricated groove, and the upper surface of the reticle structure is overlapped with the notch plane of the prefabricated groove.Roadmarking provided by the invention is compared with existing spreading type protrusion reticle structure, and reticle structure is mounted in prefabricated groove small by wearing away;Restore not having to scribing line when reticle structure, directly reticle structure material is dispensed or is positioned in prefabricated groove, has the characteristics that construction is simple;Prefabricated graticule material of giving out light is placed in prefabricated groove, effect on environment is negligible, has the advantages that environmental protection.Invention additionally discloses a kind of roadmarking production methods, have above-mentioned advantageous effect.

Description

A kind of roadmarking and production method
Technical field
The present invention relates to each standard highway and town road field, more particularly to a kind of roadmarking and making side Method.
Background technology
Longitudinal graticules such as the driveway edge line of traditional municipal administration and highway road, driveway boundary and people's row horizontal line, The structure of the horizontal markings such as space confirmation graticule is directly existed using pavement marking paints such as heat molten type, marking paints by one fixed width Road surface is dispensed or is poured.Although traditional reticle structure directly dispensed, have the characteristics that construction is simple, convenient, But gage mark coating directly dispenses on road surface, belongs to the structure of convex type, being vulnerable to the effects that vehicle tyre is worn away causes The reticle structure of protrusion is damaged, and especially for the area that winter needs to remove the snow, forklift is easily to graticule during snow removal with machine Structure damages, and the missing of graticule can cause harmful effect to traffic channelling and traffic safety etc..In addition, traditional graticule is logical It often needs to heat, the gage mark coating after heating generates peculiar smell, has slight pollution to environment, generates harmful effect.
Therefore, how to provide it is a kind of be hardly damaged while roadmarking free from environmental pollution, be those skilled in the art urgently Technical problem to be solved.
Invention content
It is simple in structure the object of the present invention is to provide a kind of roadmarking, it is easy to make, special construction is not easy to be passed through Vehicle tyre damages, while manufacturing process will not generate pollution to environment, has the advantages that good be used for a long time and environmentally friendly excellent Point.
In order to solve the above technical problems, the present invention provides a kind of roadmarking, including prefabricated groove and reticle structure, it is described Reticle structure is filled in the prefabricated groove, and the notch plane weight of the upper surface of the reticle structure and the prefabricated groove It closes.
Preferably, the notch edges of the prefabricated groove open up chamfering.
Preferably, the cross sectional shape of the prefabricated groove is rectangle.
Preferably, the depth of the prefabricated groove is at least 2mm.
Preferably, the reticle structure is marking line belt of giving out light.
Preferably, further include be set on the prefabricated groove inner wall, the articulamentum for fixing the reticle structure.
Preferably, the surfaces externally and internally of the articulamentum is all provided with toughness fat.
A kind of roadmarking production method, including:
Make the groove with given cross-sectional shape;
Preformed material is filled to the groove, so that the notch of the preformed material upper surface and the groove after filling Plane overlaps.
Preferably, the process for making the groove with given cross-sectional shape, including:
Road pavement carries out milling or sandblasting, to make the groove with given cross-sectional shape.
Preferably, the preformed material includes give out light marking line belt or graticule paper.
Roadmarking provided by the present invention and preparation method thereof includes mainly prefabricated groove and reticle structure, graticule knot Structure is filled in prefabricated groove, and the upper surface of reticle structure is overlapped with the notch plane of prefabricated groove.Road provided by the invention Marking lines are compared with existing spreading type protrusion reticle structure, and reticle structure is mounted in prefabricated groove small by wearing away;Restore mark Do not have to scribing line when cable architecture, directly reticle structure material is dispensed or is positioned in prefabricated groove, has the characteristics that construction is simple; Prefabricated graticule material of giving out light is placed in prefabricated groove, effect on environment is negligible, has the advantages that environmental protection.
The roadmarking structure made by this method is compared with existing spreading type protrusion reticle structure, prefabricated graticule peace Dress is in a groove, small by wearing away;Restore not having to scribing line when prefabricated graticule, directly prefabricated graticule material be positioned in groove, Has the characteristics that construction is simple;Prefabricated graticule material of giving out light is placed in groove, effect on environment is negligible, has environmental protection Advantage.
Description of the drawings
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technology description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this The embodiment of invention for those of ordinary skill in the art without creative efforts, can also basis The attached drawing of offer obtains other attached drawings.
Fig. 1 is a kind of overall structure diagram of specific implementation mode provided by the present invention;
Fig. 2 is the production flow diagram of roadmarking in Fig. 1.
Wherein, in Fig. 1:
Prefabricated groove -1, reticle structure -2, articulamentum -3.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Referring to FIG. 1, Fig. 1 is a kind of overall structure diagram of specific implementation mode provided by the present invention.
In a kind of specific implementation mode provided by the present invention, roadmarking includes mainly prefabricated groove 1 and graticule knot Structure 2, reticle structure 2 are filled in prefabricated groove 1, and the upper surface of reticle structure 2 is overlapped with the notch plane of prefabricated groove 1.
Wherein, prefabricated groove 1 is pre-set according to the road mark that existing road needs, the shape of prefabricated groove 1 also because This has being not fixed property;The road mark that reticle structure 2 is needed also according to existing road is pre-set, reticle structure 2 Shape it is identical as the shape of prefabricated groove 1;After setting roadmarking, the upper surface of reticle structure 2 and prefabricated groove 1 Plane overlaps where notch.
Specifically, in the roadmarking overall structure of completion, reticle structure 2 and the outer contour shape of prefabricated groove 1 are Consistent, and can closely " block " in prefabricated groove 1 after the insertion prefabricated groove 1 of reticle structure 2, meanwhile, reticle structure 2 Upper surface overlapped with plane where prefabricated groove 1 notch.Roadmarking provided by the invention and existing spreading type protrusion graticule Structure is compared, and reticle structure 2 is mounted in prefabricated groove 1 small by wearing away;Restore not having to scribing line when reticle structure 2, directly will 2 material of reticle structure is dispensed or is positioned in prefabricated groove 1, has the characteristics that construction is simple;Prefabricated put is placed in prefabricated groove 1 Cursor wire material, effect on environment is negligible, has the advantages that environmental protection.
In order to optimize the nonabradable advantage of roadmarking in above-described embodiment, the notch edges of prefabricated groove 1 open up down Angle;There is the buckle structure with the cooperation installation of above-mentioned chamfering at 2 edge of reticle structure simultaneously.By buckling the cooperation with chamfering, make mark The installation of cable architecture 2 and prefabricated groove 1 more stablizes, is close, when vehicle passes through, so that it is vibrated very little, largely subtracts The small abrasion condition of roadmarking.
Further, the cross sectional shape of prefabricated groove 1 is rectangle.In the present embodiment, in pavement or two-way lane Line of demarcation all sets prefabricated groove 1 to rectangle, and corresponding reticle structure 2 is similarly rectangle, may be arranged as other shapes, Such as:At the crossing turned left and turned right, prefabricated groove 1 and reticle structure 2 can be set to left-hand rotation and right-hand rotation shape, Concrete shape is determined according to the demand of road segment segment, is not specifically limited herein.
Further, the depth of prefabricated groove 1 is at least 2mm, is preferably 5mm~10mm in the present embodiment.Prefabricated groove 1 Depth it is deeper, the stability of roadmarking is stronger, can determine prefabricated groove 1 according to the flow of road vehicular traffic Depth, since increase roadmarking stability, the rate of wear of roadmarking can be reduced.Such as:It is smaller in vehicle flow Road segment segment can set the depth of prefabricated groove 1 to 5mm~10mm, the larger road segment segment of vehicle flow can will be prefabricated The depth of groove 1 is set as 10mm~20mm.
Further, reticle structure 2 is marking line belt of giving out light.Set reticle structure 2 to marking line belt of giving out light, it can be to avoid making Graticule is carried out with coating, marking line belt effect on environment of giving out light is negligible, has the advantages that environmental protection, certainly, reticle structure is also Can be fillable cast-type graticule material or prefabricated graticule material.
Further, roadmarking further include be set on 1 inner wall of prefabricated groove, the connection for fixing reticle structure 2 Layer 3;And the surfaces externally and internally of articulamentum 3 is all provided with toughness fat.The design of articulamentum 3 can make prefabricated groove 1 and reticle structure 2 it Between connection more stablize, further decrease the vibrating effect that roadmarking when vehicle passes through generates, slow down the mill of roadmarking Damage speed;3 inner surface of articulamentum is equipped with sticky fat, so that prefabricated groove 1 and the connection of reticle structure 2 is further stablized, more The rate of wear of roadmarking is slowed down in big degree.
To sum up, the cross sectional shape of groove 1 can be designed manufacture according to actual needs, can be filled for nothing in groove 1 People drives the sheet metal of Radar for vehicle scanning;The shape of groove 1 can require design alternative according to road markings, to meet not With roadmarking requirement.
Referring to FIG. 2, Fig. 2 is the production flow diagram of roadmarking in Fig. 1.
A kind of roadmarking production method, including:
Step 1:Make the groove with given cross-sectional shape;
Wherein, step 1 makes the process of the groove with given cross-sectional shape, including:
Road pavement carries out milling or sandblasting, to make the groove with given cross-sectional shape.
In actual manufacturing process, groove is made by the manually techniques such as reserved, sandblasting and milling, first new The roadmarking of road needs can be reserved by reserving technique on the road of paving, such as:When being routed to pavement, in advance Parallel, a plurality of rectangular recess is reserved as groove, then for example:When being routed to normal vehicle operation section, two-way vehicle is reserved The line of demarcation in road, line of demarcation is the rectangular recess of segmented can also reserve the recessed of the other forms of needs as groove Slot is determined with current laying road demand, is not specifically limited herein;The techniques such as sandblasting and milling are only compared to reserved technique It is technical operation flow difference, pre-seting for groove is identical, i.e., needs the road segment segment setting that road sign is arranged in existing road The groove needed;
Step 2:Preformed material is filled to groove, so that the notch of the preformed material upper surface and groove after filling is flat Face overlaps.Then, preformed material is set in above-mentioned groove, you can the manufacturing process for completing roadmarking needs to illustrate It is that preformed material is completed by installing the specific road sign structure of prefabricated formation, such as:It directly will be advance in the groove on pavement The rectangle reticle structure insertion groove set, then for example:It will directly be pre-set in the groove in the line of demarcation of two-way lane Good preformed material is embedded in groove, you can completes the connection work of preformed material and groove, completes the making of whole roadmarking.
The roadmarking structure made by this method is compared with existing spreading type protrusion reticle structure, prefabricated graticule peace Dress is in a groove, small by wearing away;Restore not having to scribing line when prefabricated graticule, directly prefabricated graticule material be positioned in groove, Has the characteristics that construction is simple;Prefabricated graticule material of giving out light is placed in groove, effect on environment is negligible, has environmental protection Advantage.
It should be noted that preformed material includes give out light marking line belt or graticule paper, cursor line band or graticule paper are to environment shadow It rings and can be neglected, have the advantages that environmental protection.Certainly, preformed material can also be other materials, be not specifically limited herein.
In conclusion the roadmarking that the present embodiment is provided includes mainly prefabricated groove and reticle structure, reticle structure It is filled in prefabricated groove, and the upper surface of reticle structure is overlapped with the notch plane of prefabricated groove.Road provided by the invention Graticule is compared with existing spreading type protrusion reticle structure, and reticle structure is mounted in prefabricated groove small by wearing away;Restore graticule Do not have to scribing line when structure, directly reticle structure material is dispensed or is positioned in prefabricated groove, has the characteristics that construction is simple;In advance Prefabricated graticule material of giving out light is placed in groove processed, effect on environment is negligible, has the advantages that environmental protection.Pass through our legal system The roadmarking structure of work is compared with existing spreading type protrusion reticle structure, and prefabricated graticule installation in a groove, is worn away It is small;Restore not having to scribing line when prefabricated graticule, directly prefabricated graticule material is positioned in groove, has the characteristics that construction is simple; Prefabricated graticule material of giving out light is placed in groove, effect on environment is negligible, has the advantages that environmental protection.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest range caused.

Claims (10)

1. a kind of roadmarking, which is characterized in that including prefabricated groove (1) and reticle structure (2), the reticle structure (2) is filled out It fills in the prefabricated groove (1), and the notch plane weight of the upper surface of the reticle structure (2) and the prefabricated groove (1) It closes.
2. roadmarking according to claim 1, which is characterized in that the notch edges of the prefabricated groove (1) open up down Angle.
3. roadmarking according to claim 2, which is characterized in that the cross sectional shape of the prefabricated groove (1) is rectangle.
4. roadmarking according to claim 3, which is characterized in that the depth of the prefabricated groove (1) is at least 2mm.
5. roadmarking according to claim 1, which is characterized in that the reticle structure (2) is marking line belt of giving out light.
6. according to the roadmarking described in claim 1-5 any one, which is characterized in that further include be set to it is described prefabricated recessed Articulamentum (3) on slot (1) inner wall, for fixing the reticle structure (2).
7. roadmarking according to claim 6, which is characterized in that the surfaces externally and internally of the articulamentum (3) is equipped with viscous Property fat.
8. a kind of roadmarking production method, which is characterized in that including:
Make the groove with given cross-sectional shape;
Preformed material is filled to the groove, so that the notch plane of the preformed material upper surface and the groove after filling It overlaps.
9. roadmarking production method according to claim 8, which is characterized in that described make has given cross-sectional shape Groove process, including:
Road pavement carries out milling or sandblasting, to make the groove with given cross-sectional shape.
10. roadmarking production method according to claim 8, which is characterized in that the preformed material includes mark of giving out light Tape or graticule paper.
CN201810744152.0A 2018-07-09 2018-07-09 A kind of roadmarking and production method Pending CN108677780A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810744152.0A CN108677780A (en) 2018-07-09 2018-07-09 A kind of roadmarking and production method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810744152.0A CN108677780A (en) 2018-07-09 2018-07-09 A kind of roadmarking and production method

Publications (1)

Publication Number Publication Date
CN108677780A true CN108677780A (en) 2018-10-19

Family

ID=63813476

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810744152.0A Pending CN108677780A (en) 2018-07-09 2018-07-09 A kind of roadmarking and production method

Country Status (1)

Country Link
CN (1) CN108677780A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778731A (en) * 2019-03-21 2019-05-21 四川泓毅通建设工程有限公司 A kind of preparation process of land marking pattern
CN111691259A (en) * 2020-06-11 2020-09-22 无锡市政设计研究院有限公司 Method for improving overall skid resistance of roadway

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2595864Y (en) * 2002-07-02 2003-12-31 深圳市夜明珠高新技术有限责任公司 Ceramic marking line for road
KR20130019719A (en) * 2011-08-17 2013-02-27 주식회사 토탈페이브시스템 Repair method for pavement using precast block
CN106320159A (en) * 2016-08-19 2017-01-11 杨波 Construction method for uneven pavement marking
CN206090357U (en) * 2016-05-31 2017-04-12 浙江国远建设有限公司 Road marking structure
CN206090354U (en) * 2016-05-31 2017-04-12 浙江国远建设有限公司 Novel road marking structure
CN208415128U (en) * 2018-07-09 2019-01-22 吉林省交通规划设计院 A kind of roadmarking

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2595864Y (en) * 2002-07-02 2003-12-31 深圳市夜明珠高新技术有限责任公司 Ceramic marking line for road
KR20130019719A (en) * 2011-08-17 2013-02-27 주식회사 토탈페이브시스템 Repair method for pavement using precast block
CN206090357U (en) * 2016-05-31 2017-04-12 浙江国远建设有限公司 Road marking structure
CN206090354U (en) * 2016-05-31 2017-04-12 浙江国远建设有限公司 Novel road marking structure
CN106320159A (en) * 2016-08-19 2017-01-11 杨波 Construction method for uneven pavement marking
CN208415128U (en) * 2018-07-09 2019-01-22 吉林省交通规划设计院 A kind of roadmarking

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109778731A (en) * 2019-03-21 2019-05-21 四川泓毅通建设工程有限公司 A kind of preparation process of land marking pattern
CN111691259A (en) * 2020-06-11 2020-09-22 无锡市政设计研究院有限公司 Method for improving overall skid resistance of roadway

Similar Documents

Publication Publication Date Title
Miller et al. Distress identification manual for the long-term pavement performance program
CN208415128U (en) A kind of roadmarking
CN108677780A (en) A kind of roadmarking and production method
CN103541310A (en) Long-united bridge widening splicing structure and construction method thereof
US3529517A (en) Marked roadway and method of making the same
US11124924B2 (en) Steel girder pavement structure for high-speed road for bicycle, and roadbed pavement method therefor
CN111996895A (en) Construction method of road marking
RU194029U1 (en) COVERING STONE
CN206784110U (en) A kind of novel and multifunctional curb
Orr Pavement Maintenance
US2033028A (en) Pavement curb
CN103541543B (en) Cone curvilinear plane structure resin interlining steel form and preparation method thereof can not be opened up
CN208981055U (en) A kind of rigid base pavement structure in active delayed reflex crack
Corley-Lay et al. Ultrathin bonded wearing course as pavement preservation treatment for jointed concrete pavements
CN208023372U (en) The reserved displacement mold of asphalt concrete pavement cast-in-place curb stone
CN106192699A (en) A kind of homophase out-phase road surface cutting method and device
CN207891677U (en) A kind of cement pavement structure
US2223083A (en) Molding plate for joint structures
CN210002778U (en) circular mosaic paving structure
Bateman Design Guide for Road Surface Dressing
CN211689744U (en) Bend antiskid road surface
JP7224079B1 (en) Construction method of lane marking
CN216006472U (en) Antiskid pavement restoration paste
CN202347469U (en) Road surface marking line
CN210368496U (en) Ultra-thin bituminous paving repairs structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination