CN105507152A - Construction method of self-elevating walking templates for piers of building - Google Patents
Construction method of self-elevating walking templates for piers of building Download PDFInfo
- Publication number
- CN105507152A CN105507152A CN201510843804.2A CN201510843804A CN105507152A CN 105507152 A CN105507152 A CN 105507152A CN 201510843804 A CN201510843804 A CN 201510843804A CN 105507152 A CN105507152 A CN 105507152A
- Authority
- CN
- China
- Prior art keywords
- template
- mould
- liner
- oil cylinder
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
Abstract
The invention provides a construction method of self-elevating walking templates for piers of a building. The method comprises following steps: leveling the site; measuring, lofting and positioning; utilizing a self-elevating walking template device to finish pouring concrete pier bodies and binding rebars, and installing inner liner dies; utilizing a hydraulic elevating system to lift the walking template device in sync; clamping inner liner dies by upper outer die racks and lower outer die racks after lifting the device to the pre-determined position; brushing releasing agents, pouring concrete, binding rebars and installing inner liner dies; and repeating the above steps till pier construction is done. The construction method of self-elevating walking templates for the piers of the building has following beneficial effects: the method is favorable to installation of inner liner dies so that operation time is saved; construction speed is greatly increased; die rack elevation can be performed without great strength of concrete; and construction speed reaches more than 5 meters per day.
Description
Technical field
The present invention relates to a kind of building high pier construction method, being specifically related to the high pier of a kind of building from promoting walking template construction method.
Background technology
At present, the whole nation every year nearly 2.3 ten thousand kilometers of speedways goes into operation or is building, and wherein, having an appointment 1.1 ten thousand kilometers is in west area construction.And west area mostly is remote mountains area or Freeway of Mountain Range, surface relief is large, and massif is precipitous, gully jet-bedding is widely distributed, and this brings many difficulties to the construction of speedway.Particularly in order to cross over deep mountain valleys, bridge pier need be built and carry out supporting bridge panel.Traditional high pier construction, main employing turns over the construction methods such as mould, creeping formwork, sliding formwork, and uses these methods construct, or because of construction speed slow, or because of presentation quality poor, or because of reasons such as construction safety degree are low, gradually can not adapt to the construction requirement in modern times.
The Chinese invention patent being CN103147403A as publication number discloses a kind of roller die construction method for bridge high pier, use roller mould device, save after concreting completes at pier shaft one, utilize roller die conputer controlled Hoisting System, precise elevation template, in lifting process, outside framework scrolls up at liner mould external surface, guarantee that liner mould and concrete face keep static, after rising to assigned address, liner mould, brushing release agent, assembling reinforcement, concreting is reinstalled inside outside framework, then climbing shuttering, and so forth operation again, until this pier stud has been constructed.
According to prior art, liner template is promoted by roll mode, but liner template easily produces distortion under concrete lateral pressure effect; Main mould bases had both needed at liner mould rolls on surfaces, need again to utilize main mould bases to apply certain clamping force to offset concrete lateral pressure to liner mould, the fit dimension of winner's mould bases and liner mould is required very high, once dimensional errors, easily cause liner template movement, Surface Quality of Concrete declines serious; Main mould bases and liner mould are tight fit, cause the high pier center line difficulty of adjustment, once occur that deviation needs adjustment, easily cause support bar flexural deformation even to fracture; And main mould bases had both needed at liner mould rolls on surfaces, need again to utilize main mould bases to apply certain clamping force to offset concrete lateral pressure to liner mould, the fit dimension of winner's mould bases and liner mould is required very high, once dimensional errors, easily cause liner template movement, Surface Quality of Concrete is declined serious.
On construction period, of the prior artly turn over mould, creeping formwork about 3 to 4 days workflows, average every day, concreting height was 1-1.2 rice, roller die construction every day about 4 meters, and Modern Construction often requires the construction speed of about 5 meters every day.
Summary of the invention
The invention provides the high pier of a kind of building from promoting walking template construction method, easily causing liner template movement and the low defect of raising efficiency to solve in prior art climbing shuttering method of rolling.
For realizing above-mentioned technical purpose, reach above-mentioned technique effect, the present invention is achieved through the following technical solutions:
The high pier of a kind of building is from promoting walking template construction method, it is characterized in that: levelling of the land, surveying and locating and location, install from promoting walking plate device, utilizing from promoting walking plate device, after colligation first segment reinforcing bar, first segment liner mould being installed, in scope concreting surrounded to liner mould, utilize hydraulic lifting system Synchronous lifting walking plate device; Next joint reinforcing bar of colligation also installs next joint liner mould; Template system promote, in lifting process, upper outside mould bases and lower outside mould bases alternating movement, upper clamping template and lower clamping template alternately clamp liner mould, guarantee liner mould in mould bases lifting process with concrete face transfixion; After rising to precalculated position, upper outside mould bases and lower outside mould bases all clamp liner mould, then brush release agent, concreting, just promoting mould bases without the need to waiting for that concrete is formed under intensity, by so operation repeatedly, until complete the construction of this pier stud.
Its concrete construction method step is as follows:
Step a. levelling of the land: smooth location also uses hardening of concrete;
Step b. surveying and locating and location: surveying and locating, support bar 5 is located and is fixed;
Step c is installed from promoting walking plate device: comprise hydraulic lifting system and form frame system from promoting walking plate device, hydraulic lifting system comprises the machine of climbing 1, hydraulic power unit 2, control system 3, oil pipe 4, upper clamping oil cylinder (13.1,13.2,13.3,13.n), lower clamping oil cylinder (14.1,14.2,14.3 ... 14.n) with jacking cylinder (15.1,15.2,15.3 ... 15.n), the number of upper clamping oil cylinder, lower clamping oil cylinder and jacking cylinder is determined according to practice of construction area; Form frame system comprises support bar 5, link 6, liner mould 7, suspension rod 8, lower outside mould bases 9, lower clamping template 10, upper clamping template 11 and upper outside mould bases 12;
Hydraulic lifting system is fixed on the support bar 5 of form frame system, hydraulic lifting system and form frame system are coupled together by suspension rod 8 by link 6, by all for device load transfers on support bar 5, then level will be mixed up from lifting walking template construction device, colligation first segment concrete reinforcement 16a, first segment liner template 7 is installed, utilization clamps oil cylinder (13.1, 13.2, 13.3, 13.n), lower clamping oil cylinder (14.1, 14.2, 14.3, 14.n) respectively upper clamping template 11 and lower clamping template 10 are clamped liner mould 7 and apply certain thrust, in the scope that concreting is surrounded to liner mould, vibration compacting,
Steps d. next joint liner mould also installed by next joint reinforcing bar of colligation: next joint reinforcing bar of colligation 16b, install next joint liner mould 7b;
Step e. template system promote: first utilize under clamp oil cylinder (14.1,14.2,14.3 ..., 14.n) lower clamping template 10 is opened;
Then utilize hydraulic lifting system that lower outside mould bases 9 is promoted to predetermined altitude, clamp under utilization oil cylinder (14.1,14.2,14.3 ..., 14.n) under clamp template 10 and clamp;
Secondly clamp on utilizing oil cylinder (13.1,13.2,13.3 ..., 13.n) upper clamping template 11 is opened;
Utilize jacking cylinder (15.1,15.2,15.3 ..., 15.n) by the jacking of upper outside mould bases 12 to predetermined altitude, finally utilize on clamp oil cylinder (13.1,13.2,13.3 ..., 13.n) upper clamping template 11 is clamped;
Step f. concreting: coat release agent at the inner surface of liner mould 7, in the scope that concreting is surrounded to liner mould, vibration compacting;
Repeat steps d, step e, step f until complete the construction of this pier stud.
Advantage of the present invention:
1. use this method to carry out building high pier construction, promoted by template system, clamping template can be made, lower clamping template opens and clamp, be beneficial to the installation of liner mould, save the activity duration, raising construction speed;
2. on, clamp template, lower clamping die alternately clamping liner mould, without the need to waiting for that concrete forms intensity and just can carry out mould bases lifting, significantly improve efficiency of construction, construction speed can reach more than 5 meters every day, be turn over mould, climbing formwork for construction progress 4-5 doubly, the 1.2-1.5 of sliding formwork, roller die construction is doubly;
3. in lifting process, upper outside mould bases, lower outside mould bases alternating movement, upper clamping template, lower clamping template be clamping liner mould alternately, guarantee liner mould in mould bases lifting process with concrete face transfixion, obtain good presentation quality;
4. template and bridge pier noncontact when mould bases promotes, more easily correct skew and the torsion of mould bases, bridge center obtains more effective control;
5. template and bridge pier noncontact when mould bases promotes, required lifting force reduces greatly, and the specified lifting force of hydraulic lifting system can greatly reduce, and device fabrication cost obviously reduces.
Accompanying drawing explanation
Fig. 1 is structure of the present invention composition schematic diagram.
Fig. 2 is structure top view of the present invention.
Fig. 3 is work of the present invention (assembling reinforcement, install first segment liner template, build first segment concrete) schematic diagram.
Fig. 4 is work of the present invention (next joint reinforcing bar of colligation, install next joint liner mould) schematic diagram.
Fig. 5 is work of the present invention (lower clamping template is opened) schematic diagram.
Fig. 6 is work of the present invention (lower outside mould bases lifting, lower clamping die board clamping) schematic diagram.
Fig. 7 is work of the present invention (above clamping template to open) schematic diagram.
Fig. 8 is work of the present invention (upper outside mould bases jacking, upper clamping die board clamping) schematic diagram.
Fig. 9 is work of the present invention (concreting) schematic diagram.
In figure: 1 is the machine of climbing, 2 is hydraulic power unit, and 3 is control system, 4 is oil pipe, and 5 is support bar, and 6 is link, (7,7b) is liner mould, and 8 is suspension rod, 9 is lower outside mould bases, and 10 is lower clamping template, and 11 is upper clamping template, 12 is upper outside mould bases, (13.1,13.2,13.3 ..., 13.n) and be upper clamping oil cylinder, (14.1,14.2,14.3,, 14.n) and be lower clamping oil cylinder, (15.1,15.2,15.3 ... 15.n) be jacking cylinder, (16a, 16b) is reinforcing bar.
Detailed description of the invention
Its Specific construction step is as follows:
Step a. levelling of the land: smooth location also uses hardening of concrete;
Step b. surveying and locating and location: surveying and locating, support bar 5 is located and is fixed;
Step c as shown in Figure 1, install from promoting walking plate device: comprise hydraulic lifting system and form frame system from promoting walking plate device, hydraulic lifting system comprises the machine of climbing 1, hydraulic power unit 2, control system 3, oil pipe 4, upper clamping oil cylinder (13.1,13.2,13.3 ..., 13.n), lower clamping oil cylinder (14.1,14.2,14.3 ..., 14.n) and jacking cylinder (15.1,15.2,15.3 ..., 15.n), the number of upper clamping oil cylinder, lower clamping oil cylinder and jacking cylinder is determined according to practice of construction area, as shown in Figure 2; Form frame system comprises support bar 5, link 6, liner mould 7, suspension rod 8, lower outside mould bases 9, lower clamping template 10, upper clamping template 11 and upper outside mould bases 12;
Hydraulic lifting system is fixed on the support bar 5 of form frame system, hydraulic lifting system and form frame system are coupled together by suspension rod 8 by link 6, by all for device load transfers on support bar 5, then level will be mixed up from lifting walking template construction device, colligation first segment concrete reinforcement 16a, first segment liner template 7 is installed, utilization clamps oil cylinder (13.1, 13.2, 13.3, 13.n), lower clamping oil cylinder (14.1, 14.2, 14.3, 14.n) respectively upper clamping template 11 and lower clamping template 10 are clamped liner mould 7 and apply certain thrust, in the scope that concreting is surrounded to liner mould, vibration compacting, as shown in Figure 3,
Steps d. assembling reinforcement also installs liner mould: next joint of colligation reinforcing bar 16b, install next joint liner mould 7b, as shown in Figure 4;
Step e. template system promote: first utilize under clamp oil cylinder (14.1,14.2,14.3 ..., 14.n) lower clamping template 10 is opened, as shown in Figure 5;
Then utilize hydraulic lifting system that lower outside mould bases 9 is promoted to predetermined altitude, clamp under utilization oil cylinder (14.1,14.2,14.3 ..., 14.n) under clamp template 10 and clamp, as shown in Figure 6;
Secondly clamp on utilizing oil cylinder (13.1,13.2,13.3 ..., 13.n) upper clamping template 11 is opened, as shown in Figure 7;
Utilize jacking cylinder (15.1,15.2,15.3 ..., 15.n) by the jacking of upper outside mould bases 12 to predetermined altitude, finally utilize on clamp oil cylinder (13.1,13.2,13.3 ..., 13.n) upper clamping template 11 is clamped, as shown in Figure 8;
Step f. concreting: coat release agent at the inner surface of liner mould 7, in the scope that concreting is surrounded to liner mould, vibration compacting, as shown in Figure 9;
Repeat steps d, step e, step f until complete the construction of this pier stud.
The high pier of this building is from promoting the walking flow process time used of template construction as following table:
Conventional turns over mould, creeping formwork about 3 to 4 days workflows, average every day, concreting height was 1-1.2 rice, roller die is constructed every day 4 meters, and the high pier of the building that the present invention relates to can complete 9-10 working cycles from promoting walking template construction every day, and concreting height can reach every day 5 meters.
Claims (2)
1. the high pier of building is from promoting walking template construction method, it is characterized in that: levelling of the land, surveying and locating and location, install from promoting walking plate device, utilizing from promoting walking plate device, after colligation first segment reinforcing bar, first segment liner mould being installed, in scope concreting surrounded to liner mould, utilize hydraulic lifting system Synchronous lifting walking plate device; Next joint reinforcing bar of colligation also installs next joint liner mould; Template system promote, in lifting process, upper outside mould bases and lower outside mould bases alternating movement, upper clamping template and lower clamping template alternately clamp liner mould, guarantee liner mould in mould bases lifting process with concrete face transfixion; After rising to precalculated position, upper outside mould bases and lower outside mould bases all clamp liner mould, then brush release agent, concreting, just promoting mould bases without the need to waiting for that concrete is formed under intensity, by so operation repeatedly, until complete the construction of this pier stud.
2. the high pier of building as claimed in claim 1 is from promoting walking template construction method, it is characterized in that concrete construction method step is as follows:
Step a. levelling of the land: smooth location also uses hardening of concrete;
Step b. surveying and locating and location: surveying and locating, support bar 5 is located and is fixed;
Step c is installed from promoting walking plate device: comprise hydraulic lifting system and form frame system from promoting walking plate device, hydraulic lifting system comprises the machine of climbing 1, hydraulic power unit 2, control system 3, oil pipe 4, upper clamping oil cylinder (13.1,13.2,13.3,13.n), lower clamping oil cylinder (14.1,14.2,14.3 ... 14.n) with jacking cylinder (15.1,15.2,15.3 ... 15.n), the number of upper clamping oil cylinder, lower clamping oil cylinder and jacking cylinder is determined according to practice of construction area, form frame system comprises support bar 5, link 6, liner mould 7, suspension rod 8, lower outside mould bases 9, lower clamping template 10, upper clamping template 11 and upper outside mould bases 12, hydraulic lifting system is fixed on the support bar 5 of form frame system, hydraulic lifting system and form frame system are coupled together by suspension rod 8 by link 6, by all for device load transfers on support bar 5, then level will be mixed up from lifting walking template construction device, colligation first segment concrete reinforcement 16a, first segment liner template 7 is installed, utilization clamps oil cylinder (13.1, 13.2, 13.3, 13.n), lower clamping oil cylinder (14.1, 14.2, 14.3, 14.n) respectively upper clamping template 11 and lower clamping template 10 are clamped liner mould 7 and apply certain thrust, in the scope that concreting is surrounded to liner mould, vibration compacting,
Steps d. next joint liner mould also installed by next joint reinforcing bar of colligation: next joint reinforcing bar of colligation 16b, install next joint liner mould 7b;
Step e. template system promote: first utilize under clamp oil cylinder (14.1,14.2,14.3 ..., 14.n) lower clamping template 10 is opened; Then utilize hydraulic lifting system that lower outside mould bases 9 is promoted to predetermined altitude, clamp under utilization oil cylinder (14.1,14.2,14.3 ..., 14.n) under clamp template 10 and clamp; Secondly clamp on utilizing oil cylinder (13.1,13.2,13.3 ..., 13.n) upper clamping template 11 is opened; Utilize jacking cylinder (15.1,15.2,15.3 ..., 15.n) by the jacking of upper outside mould bases 12 to predetermined altitude, finally utilize on clamp oil cylinder (13.1,13.2,13.3 ..., 13.n) upper clamping template 11 is clamped;
Step f. concreting: coat release agent at the inner surface of liner mould 7, in the scope that concreting is surrounded to liner mould, vibration compacting;
Repeat steps d, step e, step f until complete the construction of this pier stud.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510843804.2A CN105507152B (en) | 2015-11-26 | 2015-11-26 | The high pier of one kind building lifts walking template construction method certainly |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510843804.2A CN105507152B (en) | 2015-11-26 | 2015-11-26 | The high pier of one kind building lifts walking template construction method certainly |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105507152A true CN105507152A (en) | 2016-04-20 |
CN105507152B CN105507152B (en) | 2017-08-25 |
Family
ID=55715430
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510843804.2A Active CN105507152B (en) | 2015-11-26 | 2015-11-26 | The high pier of one kind building lifts walking template construction method certainly |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105507152B (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105839542A (en) * | 2016-05-04 | 2016-08-10 | 中国十九冶集团有限公司 | High bridge pier self-lifting outer frame over-form device |
CN105926449A (en) * | 2016-05-04 | 2016-09-07 | 中国十九冶集团有限公司 | Bridge high pier rollover template disassembly method |
CN106087772A (en) * | 2016-08-24 | 2016-11-09 | 中交三公局第三工程有限公司 | Sliding varus constructing device and method outside Bridge High-pier |
CN108316657A (en) * | 2018-05-08 | 2018-07-24 | 许明达 | One kind is from hoisting type high building construction device and its method for improving |
CN108532940A (en) * | 2018-04-19 | 2018-09-14 | 中铁七局集团第四工程有限公司 | High pier is without holder over-form construction method |
CN109610320A (en) * | 2018-11-13 | 2019-04-12 | 柳州煜乾机械装备股份公司 | A kind of band crane slip form construction device and construction method |
CN110080118A (en) * | 2019-06-04 | 2019-08-02 | 中交一公局第一工程有限公司 | Vertical transport for slding form operation rises system and its construction method certainly |
CN112431395A (en) * | 2020-12-11 | 2021-03-02 | 余北京 | Steel scaffold for building engineering |
CN113062222A (en) * | 2021-03-17 | 2021-07-02 | 中交一公局集团有限公司 | Improved construction device and method for roller die of high pier of bridge |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1082019A (en) * | 1996-09-06 | 1998-03-31 | Taisei Corp | Constructing method of pier |
CN2660028Y (en) * | 2003-09-18 | 2004-12-01 | 山东省路桥集团有限公司 | Hydraulic self-lifting climbing mould |
CN1912314A (en) * | 2006-08-28 | 2007-02-14 | 杨秋利 | Automatic hydraulic climbing shuttering |
JP2011032814A (en) * | 2009-08-05 | 2011-02-17 | Ohbayashi Corp | Self-elevation type form device, and replacing method for shuttering panel using the same |
CN102345381A (en) * | 2011-10-12 | 2012-02-08 | 四川路桥建设股份有限公司 | Hydraulic creeping formwork system and creeping formwork construction method |
CN103046473A (en) * | 2013-01-15 | 2013-04-17 | 中国土木工程集团有限公司 | Construction method for constructing double-limb hollow high-pier mould side hydraulic jacking creeping formwork and double-limb hollow high-pier |
CN103147403A (en) * | 2013-03-29 | 2013-06-12 | 中交一公局第四工程有限公司 | Roller die construction method for bridge high pier |
CN103938856A (en) * | 2014-04-09 | 2014-07-23 | 中国化学工程第十三建设有限公司 | Tower structure slip-form construction operation platform free of bracing pieces and construction method |
-
2015
- 2015-11-26 CN CN201510843804.2A patent/CN105507152B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH1082019A (en) * | 1996-09-06 | 1998-03-31 | Taisei Corp | Constructing method of pier |
CN2660028Y (en) * | 2003-09-18 | 2004-12-01 | 山东省路桥集团有限公司 | Hydraulic self-lifting climbing mould |
CN1912314A (en) * | 2006-08-28 | 2007-02-14 | 杨秋利 | Automatic hydraulic climbing shuttering |
JP2011032814A (en) * | 2009-08-05 | 2011-02-17 | Ohbayashi Corp | Self-elevation type form device, and replacing method for shuttering panel using the same |
CN102345381A (en) * | 2011-10-12 | 2012-02-08 | 四川路桥建设股份有限公司 | Hydraulic creeping formwork system and creeping formwork construction method |
CN103046473A (en) * | 2013-01-15 | 2013-04-17 | 中国土木工程集团有限公司 | Construction method for constructing double-limb hollow high-pier mould side hydraulic jacking creeping formwork and double-limb hollow high-pier |
CN103147403A (en) * | 2013-03-29 | 2013-06-12 | 中交一公局第四工程有限公司 | Roller die construction method for bridge high pier |
CN103938856A (en) * | 2014-04-09 | 2014-07-23 | 中国化学工程第十三建设有限公司 | Tower structure slip-form construction operation platform free of bracing pieces and construction method |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105926449A (en) * | 2016-05-04 | 2016-09-07 | 中国十九冶集团有限公司 | Bridge high pier rollover template disassembly method |
CN105839542A (en) * | 2016-05-04 | 2016-08-10 | 中国十九冶集团有限公司 | High bridge pier self-lifting outer frame over-form device |
CN106087772A (en) * | 2016-08-24 | 2016-11-09 | 中交三公局第三工程有限公司 | Sliding varus constructing device and method outside Bridge High-pier |
CN106087772B (en) * | 2016-08-24 | 2017-12-29 | 中交三公局第三工程有限公司 | Sliding varus constructing device and method outside Bridge High-pier |
CN108532940B (en) * | 2018-04-19 | 2020-04-14 | 中铁七局集团第四工程有限公司 | High pier support-free rollover construction method |
CN108532940A (en) * | 2018-04-19 | 2018-09-14 | 中铁七局集团第四工程有限公司 | High pier is without holder over-form construction method |
CN108316657A (en) * | 2018-05-08 | 2018-07-24 | 许明达 | One kind is from hoisting type high building construction device and its method for improving |
CN108316657B (en) * | 2018-05-08 | 2024-02-02 | 许明达 | Self-lifting type high-rise building construction device and lifting method thereof |
CN109610320A (en) * | 2018-11-13 | 2019-04-12 | 柳州煜乾机械装备股份公司 | A kind of band crane slip form construction device and construction method |
CN110080118A (en) * | 2019-06-04 | 2019-08-02 | 中交一公局第一工程有限公司 | Vertical transport for slding form operation rises system and its construction method certainly |
CN112431395A (en) * | 2020-12-11 | 2021-03-02 | 余北京 | Steel scaffold for building engineering |
CN112431395B (en) * | 2020-12-11 | 2022-10-14 | 武汉港工建筑工程有限公司 | Steel scaffold for building engineering |
CN113062222A (en) * | 2021-03-17 | 2021-07-02 | 中交一公局集团有限公司 | Improved construction device and method for roller die of high pier of bridge |
Also Published As
Publication number | Publication date |
---|---|
CN105507152B (en) | 2017-08-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105507152A (en) | Construction method of self-elevating walking templates for piers of building | |
CN102230315B (en) | Prefabricated part and semi-prefabricated construction method for multistory building | |
CN102912900A (en) | Prefabricated assembled superposed plate type concrete shear wall and construction method thereof | |
CN104790676A (en) | Rapid leveling and alignment device and method for installation of prefabricated wallboards | |
KR101153430B1 (en) | Portable mold for curved psc girder, the girder and girder bridge construction method using the same | |
CN205063100U (en) | Prevent hot wall and prevent hot wall system | |
CN105507157B (en) | Construction method of variable curvature annular stiffening core cast-in-place concrete beam | |
CN107663951A (en) | The support system and construction technology of superimposed sheet and wallboard formed by integrally casting | |
CN106193589B (en) | Concrete superelevation heavy type beam and overlapping board combining structure method for supporting | |
CN106065681A (en) | Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology | |
CN101793006A (en) | Construction method for rapid construction of support cast-in-situ continuous beam | |
CN101922141B (en) | Structure and construction method of bearing pad stone | |
CN105714966A (en) | Inverted laminated slab provided with elevation adjustment devices and construction method | |
CN108914780A (en) | A kind of bridge tall pier and thin wall hydraulic sliding mould construction method | |
CN202925721U (en) | Prefabricated superimposed sheet-type concrete shear wall structure | |
CN110374113B (en) | Quick support changing method and movable joint suitable for steel pipe support foundation pit | |
CN205557336U (en) | Construct high mound from promoting walking template device | |
CN110700105B (en) | Synchronous construction method for high pier column and tie beam and template used in same | |
CN107806015B (en) | A kind of unit construction bridge beam flange plate formwork for placing concrete system and construction method | |
CN206969985U (en) | The lifting auxiliary balance instrument of multi-segmental precast beam | |
CN105839786A (en) | Air-supported membrane building concrete anchor bolt pre-buried structure and construction method thereof | |
CN107191201A (en) | Constructing middle partition wall in tunnel template and its constructing device | |
CN107160542A (en) | Bracket type inner form support system construction method | |
CN115198926B (en) | Frame structure assembled wall-beam connection structure and construction method thereof | |
CN205348505U (en) | Invert superimposed sheet with elevation adjusting device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |