CN105490281A - Layered and zoned reactive voltage analysis method based on boundary condition - Google Patents

Layered and zoned reactive voltage analysis method based on boundary condition Download PDF

Info

Publication number
CN105490281A
CN105490281A CN201510879612.7A CN201510879612A CN105490281A CN 105490281 A CN105490281 A CN 105490281A CN 201510879612 A CN201510879612 A CN 201510879612A CN 105490281 A CN105490281 A CN 105490281A
Authority
CN
China
Prior art keywords
voltage
load
reactive
power
limit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510879612.7A
Other languages
Chinese (zh)
Other versions
CN105490281B (en
Inventor
吴晓丹
韩建军
刘景远
肖冰
李袖
刘卫明
陈肖璐
李卓男
郑婷婷
张明明
耿文晶
陈颖
苏瑞
宋洋
王瑞
杨倩倩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Eastern Inner Mongolia Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Eastern Inner Mongolia Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Electric Power Research Institute of State Grid Eastern Inner Mongolia Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510879612.7A priority Critical patent/CN105490281B/en
Publication of CN105490281A publication Critical patent/CN105490281A/en
Application granted granted Critical
Publication of CN105490281B publication Critical patent/CN105490281B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/30Reactive power compensation

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

本发明属于电网无功电压控制技术领域,尤其涉及一种基于边界条件的分层分区无功电压分析方法。包括以下步骤:对电网进行分层分区;确定所研究区域及其边界;输入最大、最小负荷日负荷及发电机出力,边界条件,无功补偿配置情况,区域电网限值;进行潮流计算,调节无功补偿容量,将区域电网边界调至边界条件;判断区域内电压是否存在越限情况;判断各主变功率因数是否满足限值规定。本发明可以同时进行无功电压校核和无功电压优化,大幅提高大规模电网无功电压分析效率,并能针对局部电网开展重点分析,适用于区域电网数据较全,但大电网数据不足的情况下。易于理解和实现、并贴近电网运行实际,适合在线应用。

The invention belongs to the technical field of grid reactive voltage control, and in particular relates to a layered and partitioned reactive voltage analysis method based on boundary conditions. Including the following steps: layering and partitioning the power grid; determining the research area and its boundary; inputting the maximum and minimum load daily load and generator output, boundary conditions, configuration of reactive power compensation, and regional power grid limits; performing power flow calculations, adjusting Reactive power compensation capacity, adjusting the boundary of the regional power grid to the boundary conditions; judging whether the voltage in the region has exceeded the limit; judging whether the power factor of each main transformer meets the limit value regulations. The present invention can carry out reactive power voltage checking and reactive power voltage optimization at the same time, greatly improves the reactive power voltage analysis efficiency of large-scale power grids, and can carry out key analysis for local power grids, and is suitable for areas with relatively complete regional power grid data but insufficient large-scale power grid data case. It is easy to understand and implement, close to the actual operation of the power grid, and suitable for online applications.

Description

基于边界条件的分层分区无功电压分析方法Layered Partitioned Reactive Voltage Analysis Method Based on Boundary Conditions

技术领域technical field

本发明属于电网无功电压控制技术领域,尤其涉及一种基于边界条件的分层分区无功电压分析方法。The invention belongs to the technical field of grid reactive voltage control, and in particular relates to a layered and partitioned reactive voltage analysis method based on boundary conditions.

背景技术Background technique

在目前电力系统中,随着负荷增长和各项新增工程不断开展,电网运行情况愈加复杂,无功电压控制面临各种新挑战。为保障电压运行质量,有必要对电网无功电压情况变化进行跟踪,及时开展电网无功电压分析,提出切实可行的决策建议。无功电压分析已成为目前电网建设维护过程中的一项不可或缺的工作,对电网的安全、稳定、经济运行具有重要意义。随着大电网互联,电网规模不断扩大,无功电压分析效率亟待提高。In the current power system, with the increase of load and the continuous development of various new projects, the operation of the power grid is becoming more and more complicated, and the control of reactive power and voltage is facing various new challenges. In order to ensure the quality of voltage operation, it is necessary to track the changes in the reactive power and voltage of the power grid, carry out timely analysis of the reactive power and voltage of the power grid, and put forward practical decision-making suggestions. Reactive power and voltage analysis has become an indispensable work in the current power grid construction and maintenance process, which is of great significance to the safety, stability and economic operation of the power grid. With the interconnection of large power grids and the continuous expansion of the grid scale, the efficiency of reactive power and voltage analysis needs to be improved urgently.

目前,对无功电压控制的研究大多集中于无功优化方面,而对无功电压校核方法的研究较为缺乏,并且大电网分析效率不高,仅有局部电网数据时,电网无功电压分析受限。At present, most of the research on reactive power and voltage control focuses on reactive power optimization, while the research on reactive power and voltage calibration methods is relatively lacking, and the analysis efficiency of large power grids is not high. restricted.

发明内容Contents of the invention

为克服现有技术中存在的缺陷,本发明提供一种基于边界条件的分层分区无功电压分析方法,其目的是为了提供一种可以大幅提高电网无功电压分析效率,并能针对局部电网开展重点分析,为电网运行决策提供指导的无功电压分析方法。In order to overcome the defects existing in the prior art, the present invention provides a layered and partitioned reactive power voltage analysis method based on boundary conditions. A reactive power and voltage analysis method that provides guidance for power grid operation decision-making by carrying out key analysis.

为达到上述发明目的,本发明所采用的技术方案是:In order to achieve the above-mentioned purpose of the invention, the technical scheme adopted in the present invention is:

基于边界条件的分层分区无功电压分析方法,包括以下步骤:The stratified and partitioned reactive voltage analysis method based on boundary conditions includes the following steps:

步骤1:对电网进行分层分区;Step 1: Carry out hierarchical partitioning of the grid;

步骤2:确定所研究区域及其边界;Step 2: Identify the study area and its boundaries;

步骤3:输入最大、最小负荷日负荷及发电机出力,边界条件,无功补偿配置情况,区域电网限值;Step 3: Input the maximum and minimum daily load and generator output, boundary conditions, configuration of reactive power compensation, and regional power grid limits;

步骤4:进行潮流计算,调节无功补偿容量,将区域电网边界调至边界条件;Step 4: Perform power flow calculation, adjust reactive power compensation capacity, and adjust the boundary of the regional power grid to the boundary conditions;

步骤5:判断区域内电压是否存在越限情况;Step 5: Determine whether the voltage in the area exceeds the limit;

步骤6:判断各主变功率因数是否满足限值规定。Step 6: Determine whether the power factor of each main transformer meets the limit value regulations.

所述步骤1中分层分区采用的具体方法为:根据不同电压等级分层,同一电压等级电网分为一层;在同一层电网里,根据地理位置和负荷供电范围进行分区,变电站根据由哪一区供电划分在哪一区内,由不同区同时供电的变电站,按供电负荷大小分配到各区中。The specific method adopted in step 1 is as follows: according to different voltage levels, the same voltage level grid is divided into one layer; In which area is the power supply of a district divided? Substations that are simultaneously powered by different districts are allocated to each district according to the size of the power supply load.

所述步骤2中确定所研究区域,即根据研究需要确定接下来要研究的区域电网;所述确定边界,是指选出所研究区域电网与上一层电网相连接的变电站,作为该研究区域的边界。Determining the research area in the step 2, that is, determining the regional power grid to be studied next according to the research needs; the determination of the boundary refers to selecting the substation connected to the power grid in the research area and the upper power grid as the research area borders.

所述步骤3中所述最大负荷日、最小负荷日分别是指地区电网在一年当中负荷最大的一日和负荷最小的一日,此专利将最大负荷日和最小负荷日作为两种电压分析情况;所述输入最大、最小负荷日负荷及发电机出力,是指将最大负荷日中各厂站的负荷、各发电机出力作为一种电压分析情况,分析区域电网低电压问题;将最小负荷日中各厂站的负荷、各发电机出力作为一种电压分析情况,分析区域电网高电压问题;所述边界条件是指,将所研究区域电网边界变电站在最大、最小负荷日的电压及功率因数作为边界条件;所述无功补偿配置情况,是指得到所研究区域电网各变电站感性无功补偿装置配置总容量QLmax、容性无功补偿装置配置总容量QCmax;所述区域电网限制,是指区域电网各厂站正常运行电压限值、功率因数限值;The maximum load day and the minimum load day mentioned in the step 3 respectively refer to the day with the largest load and the day with the smallest load in the year of the regional power grid. This patent uses the maximum load day and the minimum load day as two types of voltage analysis Situation; the input maximum and minimum load daily load and generator output refer to the load of each station in the maximum load day and the output of each generator as a voltage analysis situation to analyze the low voltage problem of the regional power grid; the minimum load The load and output of each generator station in Japan and China are used as a voltage analysis situation to analyze the high voltage problem of the regional power grid; the boundary conditions refer to the voltage and power of the boundary substation of the studied regional power grid on the maximum and minimum load days The factor is used as a boundary condition; the configuration of reactive power compensation refers to the configuration of the total capacity Q Lmax of the inductive reactive power compensation device in each substation of the power grid under study, and the total capacity Q Cmax of the configuration of the capacitive reactive power compensation device; the regional power grid limit , refers to the normal operating voltage limit and power factor limit of each station in the regional power grid;

所述步骤4中所述进行潮流计算的方式包括:The method of performing power flow calculation described in step 4 includes:

方式一:各厂站负荷为最大负荷日负荷,各发电机出力为最大负荷日出力,在各变电站无功补偿装置配置总容量范围内,调节投入的无功补偿容量,将边界变电站的电压及功率因数调至最大负荷日水平,计算得到各厂站电压;Method 1: The load of each power station is the maximum load daily load, and the output of each generator is the maximum load daily output. Within the range of the total capacity of the reactive power compensation device configuration of each substation, adjust the input reactive power compensation capacity, and the voltage of the boundary substation and The power factor is adjusted to the maximum load daily level, and the voltage of each plant is calculated;

方式二:各厂站负荷为最小负荷日负荷,各发电机出力为最小负荷日出力,在各变电站无功补偿装置配置总容量范围内,调节投入的无功补偿容量,将边界变电站的电压及功率因数调至最大负荷日水平,计算得到各厂站电压。Method 2: The load of each station is the minimum load daily load, and the output of each generator is the minimum load daily output. Within the range of the total capacity of the reactive power compensation device configuration of each substation, adjust the input reactive power compensation capacity, and the voltage of the boundary substation and The power factor is adjusted to the maximum load daily level, and the voltage of each plant and station is calculated.

所述步骤5中所述判断区域内电压是否存在越限情况,是指将步骤4中得到的电压计算结果,与步骤3输入的各厂站正常运行电压限值进行比较,判断电压计算结果是否存在越限情况包括以下方式:In the step 5, judging whether the voltage in the region exceeds the limit refers to comparing the voltage calculation result obtained in step 4 with the normal operating voltage limit of each plant input in step 3, and judging whether the voltage calculation result is Existing limit situations include the following methods:

(1)若存在电压越限情况,则分析电压越限原因,对投入的无功补偿容量进行微调,重新进行电压计算;若仍存在变电站电压越限,则输出该变电站及越限电压,进行下一步;若不存在变电站电压越限,则进行下一步;(1) If there is a voltage exceeding the limit, analyze the cause of the voltage exceeding the limit, fine-tune the input reactive power compensation capacity, and re-calculate the voltage; if there is still a substation voltage exceeding the limit, output the substation and the exceeding voltage, and perform The next step; if there is no substation voltage exceeding the limit, proceed to the next step;

(2)若不存在电压越限情况,则输出区域电压情况良好,进行下一步。(2) If there is no voltage over-limit situation, the voltage in the output area is in good condition, and proceed to the next step.

所述步骤6中所述判断各主变功率因数是否满足限值规定的方式中,各主变的功率因数进行计算,将计算结果与步骤3输入的各厂站正常运行功率因数限值进行比较,判断各主变功率因数是否存在超出限值的情况;In the method of judging whether the power factor of each main transformer meets the limit value regulation described in step 6, the power factor of each main transformer is calculated, and the calculation result is compared with the normal operation power factor limit value of each plant station input in step 3 , to judge whether the power factor of each main transformer exceeds the limit;

(1)若不存在主变功率因数超出限值的情况,则输出该区域主变功率因数良好;(1) If there is no case where the power factor of the main transformer exceeds the limit, the power factor of the main transformer in the output area is good;

(2)若存在主变功率因数超出限值的情况,则输出越限主变和越限功率因数,并分析越限原因,并针对具体原因进行调整优化。(2) If there is a situation where the power factor of the main transformer exceeds the limit, output the main transformer and the power factor that exceed the limit, analyze the cause of the limit, and adjust and optimize for the specific reason.

所述步骤3中:输入最大、最小负荷日负荷及发电机出力,边界条件,无功补偿配置情况,区域电网限值,是指将电网信息输入PSASP仿真软件开展无功电压分析;所述PSASP仿真软件不局限于一种仿真计算软件。In the step 3: inputting the maximum and minimum load daily load and generator output, boundary conditions, configuration of reactive power compensation, and regional power grid limits means that the power grid information is input into the PSASP simulation software to carry out reactive power and voltage analysis; the PSASP The simulation software is not limited to one kind of simulation calculation software.

所述步骤4中:进行潮流计算能够用牛顿-拉夫逊法、高斯赛德尔法等多种计算方法进行计算,不局限于一种潮流计算方法。In the step 4: the power flow calculation can be performed by various calculation methods such as Newton-Raphson method, Gauss-Seidel method, etc., and is not limited to one power flow calculation method.

本发明的优点及有益效果是:Advantage of the present invention and beneficial effect are:

本发明通过分层分区和边界条件等效对所研究电网进行简化;通过调节现有无功补偿投入容量,进行电网潮流计算,判断电网内变电站电压是否越限,校核现有无功补偿设备配置情况是否满足相关规定和电压调整需要;通过调整主变功率因数至规定限值内,对电网无功分布进行优化。该方法较为全面,可以同时进行无功电压校核和无功电压优化;并且该方法通过边界条件等效对大电网分层分区,大幅提高大规模电网无功电压分析效率。并能重点针对大电网中的一个局部区域电网开展重点分析,不需要对全网建模,可适用于区域电网数据较全,但大电网数据不足的情况。易于理解和实现、并贴近电网运行实际,适合在线应用。The present invention simplifies the researched power grid by layering and partitioning and equivalence of boundary conditions; by adjusting the input capacity of the existing reactive power compensation, the power flow calculation of the power grid is performed to determine whether the voltage of the substation in the power grid exceeds the limit, and check the existing reactive power compensation equipment Whether the configuration meets the relevant regulations and voltage adjustment needs; optimize the reactive power distribution of the grid by adjusting the power factor of the main transformer to within the specified limit. This method is relatively comprehensive, and can simultaneously perform reactive power voltage calibration and reactive power voltage optimization; and this method uses boundary conditions to equivalently divide large power grids into layers, which greatly improves the efficiency of large-scale power grid reactive power voltage analysis. And it can focus on a local regional power grid in the large power grid to carry out key analysis without modeling the entire network, and is applicable to the situation where the data of the regional power grid is relatively complete, but the data of the large power grid is insufficient. It is easy to understand and implement, close to the actual operation of the power grid, and suitable for online applications.

下面结合附图和具体实施例,对本发明优选实施例作详细的说明。应该强调的是,下述说明仅仅是示例性的,而不是为了限制本发明的范围及其应用。The preferred embodiments of the present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be emphasized that the following description is only exemplary and not intended to limit the scope of the invention and its application.

附图说明Description of drawings

图1是本发明基于边界条件的分层分区无功电压分析方法流程图;Fig. 1 is the flow chart of the present invention's layered and partitioned reactive voltage analysis method based on boundary conditions;

图2是本发明实施例提供的电网接线图。Fig. 2 is a grid wiring diagram provided by an embodiment of the present invention.

具体实施方式detailed description

实施例1:Example 1:

本发明是一种基于边界条件的分层分区无功电压分析方法,如图1所示,图1是基于边界条件的分层分区无功电压分析方法流程图,具体操作步骤包括:The present invention is a layered and partitioned reactive voltage analysis method based on boundary conditions, as shown in Figure 1, Figure 1 is a flow chart of the layered and partitioned reactive voltage analysis method based on boundary conditions, the specific operation steps include:

步骤1:对电网进行分层分区。Step 1: Hierarchically partition the grid.

所述分层分区采用的具体方法为:根据不同电压等级分层,同一电压等级电网分为一层;在同一层电网里,根据地理位置和负荷供电范围进行分区,变电站根据由哪一区供电划分在哪一区内,由不同区同时供电的变电站,按供电负荷大小分配到各区中。The specific method used in the hierarchical partitioning is: according to different voltage levels, the power grid of the same voltage level is divided into one layer; in the same layer of the power grid, partitions are carried out according to the geographical location and the load power supply range, and the substation is based on which area the power is supplied to In which area it is divided, substations powered by different areas at the same time are allocated to each area according to the size of the power supply load.

步骤2:确定所研究区域及其边界。Step 2: Identify the study area and its boundaries.

所述确定所研究区域,即根据研究需要确定接下来要研究的区域电网。The determination of the research area is to determine the regional power grid to be studied next according to the research needs.

所述确定边界,是指选出所研究区域电网与上一层电网相连接的变电站,作为该研究区域的边界。The determination of the boundary refers to selecting the substation connected to the power grid of the research area and the power grid of the upper layer as the boundary of the research area.

步骤3:输入最大、最小负荷日负荷及发电机出力,边界条件,无功补偿配置情况,区域电网限值。Step 3: Input the maximum and minimum daily load and generator output, boundary conditions, configuration of reactive power compensation, and regional power grid limits.

所述最大负荷日、最小负荷日分别是指地区电网在一年当中负荷最大的一日和负荷最小的一日,此专利将最大负荷日和最小负荷日作为两种电压分析情况。The maximum load day and the minimum load day respectively refer to the day with the largest load and the day with the smallest load in the year of the regional power grid. This patent regards the maximum load day and the minimum load day as two voltage analysis situations.

所述输入最大、最小负荷日负荷及发电机出力,是指将最大负荷日中各厂站的负荷、各发电机出力作为一种电压分析情况,分析区域电网低电压问题;将最小负荷日中各厂站的负荷、各发电机出力作为一种电压分析情况,分析区域电网高电压问题。The daily load and generator output of the maximum and minimum loads of the input refer to the load of each plant station in the maximum load day and the output of each generator as a voltage analysis situation to analyze the low voltage problem of the regional power grid; The load of each plant and the output of each generator are used as a voltage analysis situation to analyze the high voltage problem of the regional power grid.

所述边界条件是指,将所研究区域电网边界变电站在最大、最小负荷日的电压及功率因数作为边界条件。The boundary conditions refer to taking the voltage and power factor of the boundary substation of the power grid in the research area on the maximum and minimum load days as the boundary conditions.

所述无功补偿配置情况,是指得到所研究区域电网各变电站感性无功补偿装置配置总容量QLmax、容性无功补偿装置配置总容量QCmaxThe configuration of reactive power compensation refers to the total configuration Q Lmax of inductive reactive power compensation devices and the total configuration Q Cmax of capacitive reactive power compensation devices of each substation in the power grid under study.

所述区域电网限值,是指区域电网各厂站正常运行电压限值、功率因数限值。The regional power grid limit refers to the normal operating voltage limit and power factor limit of each station in the regional power grid.

将上述电网信息输入PSASP等各种仿真软件开展无功电压分析,不局限于一种仿真软件。Inputting the above power grid information into various simulation software such as PSASP to carry out reactive power and voltage analysis is not limited to one simulation software.

步骤4:进行潮流计算,调节无功补偿容量,将区域电网边界调至边界条件。Step 4: Carry out power flow calculation, adjust reactive power compensation capacity, and adjust regional grid boundary to boundary conditions.

可在PSASP仿真软件中分两种方式进行潮流计算:Power flow calculation can be performed in two ways in the PSASP simulation software:

方式一:各厂站负荷为最大负荷日负荷,各发电机出力为最大负荷日出力,在各变电站无功补偿装置配置总容量范围内,调节投入的无功补偿容量,将边界变电站的电压及功率因数调至最大负荷日水平,计算得到各厂站电压。Method 1: The load of each power station is the maximum load daily load, and the output of each generator is the maximum load daily output. Within the range of the total capacity of the reactive power compensation device configuration of each substation, adjust the input reactive power compensation capacity, and the voltage of the boundary substation and The power factor is adjusted to the maximum load daily level, and the voltage of each plant and station is calculated.

方式二:各厂站负荷为最小负荷日负荷,各发电机出力为最小负荷日出力,在各变电站无功补偿装置配置总容量范围内,调节投入的无功补偿容量,将边界变电站的电压及功率因数调至最大负荷日水平,计算得到各厂站电压。Method 2: The load of each station is the minimum load daily load, and the output of each generator is the minimum load daily output. Within the range of the total capacity of the reactive power compensation device configuration of each substation, adjust the input reactive power compensation capacity, and the voltage of the boundary substation and The power factor is adjusted to the maximum load daily level, and the voltage of each plant and station is calculated.

该步骤中,进行潮流计算的方法还包括用牛顿-拉夫逊法、高斯赛德尔计算方法等计算方法进行潮流计算,不局限于一种潮流计算方法。In this step, the power flow calculation method also includes calculation methods such as Newton-Raphson method, Gauss-Seidel calculation method, etc., and is not limited to one power flow calculation method.

步骤5:判断区域内电压是否存在越限情况。Step 5: Determine whether the voltage in the area exceeds the limit.

上述步骤4中,PSASP潮流计算后,可输出方式一、方式二两种方式下的电压计算结果EACEL表,方便进行排序比较。In the above step 4, after the PSASP power flow calculation, the EACEL table of the voltage calculation results under the two modes of mode 1 and mode 2 can be output, which is convenient for sorting and comparison.

所述判断区域内电压是否存在越限情况,是指将步骤4中得到的电压计算结果,与步骤3输入的各厂站正常运行电压限值进行比较,判断电压计算结果是否存在越限情况。The judging whether the voltage in the area exceeds the limit refers to comparing the voltage calculation result obtained in step 4 with the normal operating voltage limit of each plant input in step 3, and judging whether the voltage calculation result exceeds the limit.

(1)若存在电压越限情况,则分析电压越限原因,对投入的无功补偿容量进行微调,重新在PSASP软件中进行潮流计算。若仍存在变电站电压越限,则输出该变电站及越限电压,进行下一步;若不存在变电站电压越限,则进行下一步。(1) If there is a voltage exceeding the limit, analyze the cause of the voltage exceeding the limit, fine-tune the input reactive power compensation capacity, and re-calculate the power flow in the PSASP software. If there is still a substation voltage exceeding the limit, output the substation and the exceeding voltage, and proceed to the next step; if there is no substation voltage exceeding the limit, proceed to the next step.

(2)若不存在电压越限情况,则输出区域电压情况良好,进行下一步。(2) If there is no voltage over-limit situation, the voltage in the output area is in good condition, and proceed to the next step.

步骤6:判断各主变功率因数是否满足限值规定。Step 6: Determine whether the power factor of each main transformer meets the limit value regulations.

在PSASP软件中对方式一、方式二两种方式分别进行潮流计算后,可方便输出各主变的功率因数,将主变功率因素计算结果与步骤3输入的各厂站正常运行功率因数限值进行比较,判断各主变功率因数是否存在超出限值的情况。In the PSASP software, after performing power flow calculations for the two methods of method 1 and method 2, the power factor of each main transformer can be conveniently output, and the calculation result of the power factor of the main transformer can be compared with the normal operation power factor limit value of each station input in step 3 Compare and judge whether the power factor of each main transformer exceeds the limit value.

(1)若不存在主变功率因数超出限值的情况,则输出该区域主变功率因数良好。(1) If the power factor of the main transformer does not exceed the limit, the power factor of the main transformer in the output area is good.

(2)若存在主变功率因数超出限值的情况,则输出越限主变和越限功率因数,并分析越限原因。并针对具体原因进行调整优化。(2) If there is a situation that the power factor of the main transformer exceeds the limit, output the main transformer and the power factor that exceed the limit, and analyze the cause of the limit. And adjust and optimize for specific reasons.

实施例2:Example 2:

下面以2015年内蒙古赤峰电网作为本发明的一个实施例,对本发明的发明内容做进一步说明。The content of the present invention will be further described below by taking the 2015 Inner Mongolia Chifeng Power Grid as an embodiment of the present invention.

首先对赤峰电网进行分层分区,按500kV、220kV、66kV、10kV分为四层;举例研究66kV层级电网,按负荷供电范围和地理位置分区,分为中京系统、平庄系统、锦山系统、赤峰系统、金沟梁系统、林东系统、天山系统、太本系统、西郊系统、宁城系统、热水系统、乌丹系统、大板系统、元宝山系统、新惠系统、铜都系统、城东系统共17个区域。Firstly, the Chifeng power grid is divided into four layers according to 500kV, 220kV, 66kV, and 10kV; for example, the 66kV level power grid is divided into Zhongjing system, Pingzhuang system, Jinshan system, Chifeng system, Jingouliang system, Lindong system, Tianshan system, Taiben system, Xijiao system, Ningcheng system, hot water system, Wudan system, Daban system, Yuanbaoshan system, Xinhui system, Tongdu system , Chengdong system has 17 areas in total.

确定研究区域为66kV锦山系统,内蒙古赤峰锦山地区电网接线图如图2所示。The research area is determined to be the 66kV Jinshan system, and the wiring diagram of the power grid in the Jinshan area of Chifeng, Inner Mongolia is shown in Figure 2.

确定该区域的边界为220kV锦山变,边界条件包括锦山变66kV侧电压、锦山变高压侧功率因数。The boundary of this area is determined to be 220kV Jinshan Substation, and the boundary conditions include Jinshan Substation 66kV side voltage and Jinshan Substation high voltage side power factor.

输入各站的最大负荷日负荷(最大负荷)、最小负荷日负荷(最小负荷),以及无功补偿装置配置情况,如表1所示。该地区无发电厂,所以不需输入发电机组负荷日出力情况。Input the maximum daily load (maximum load) and minimum daily load (minimum load) of each station, as well as the configuration of reactive power compensation devices, as shown in Table 1. There is no power plant in this area, so there is no need to input the daily load and output of the generator set.

输入锦山电网边界条件数值:Enter the boundary condition value of Jinshan power grid:

(1)低电压情况(最大负荷日):锦山变66kV侧电压为65.3kV;锦山变高压侧功率因数0.957;(1) Low voltage situation (maximum load day): Jinshan Substation 66kV side voltage is 65.3kV; Jinshan Substation high voltage side power factor is 0.957;

(2)高电压情况(最小负荷日):锦山变66kV侧电压为67.5kV;锦山变高压侧功率因数0.991。(2) High voltage situation (minimum load day): Jinshan Substation's 66kV side voltage is 67.5kV; Jinshan Substation's high voltage side power factor is 0.991.

输入区域电网限值包括:各66kV变电站正常运行母线电压控制在64.02-70.62kV之间;各变电站10kV侧母线电压控制10-10.7kV;接入66kV电网的发电机功率因数可控0.8-0.85控制;66kV主变功率因数控制在0.9-1;220kV主变功率因数控制在0.95-1。Input regional power grid limits include: the normal operation bus voltage of each 66kV substation is controlled between 64.02-70.62kV; the 10kV side bus voltage of each substation is controlled at 10-10.7kV; the power factor of the generator connected to the 66kV power grid can be controlled at 0.8-0.85 ; 66kV main transformer power factor is controlled at 0.9-1; 220kV main transformer power factor is controlled at 0.95-1.

运用PSASP软件对大小负荷两种方式进行潮流计算,调节配置的无功补偿容量,将区域电网边界分别调至边界条件。Use the PSASP software to calculate the power flow for both large and small loads, adjust the configured reactive power compensation capacity, and adjust the boundaries of the regional power grid to the boundary conditions.

经计算,大负荷方式下,旺业甸变66kV母线电压低至61.4kV,西山变投入电容器后10kV母线电压为9.95kV,均低于正常运行电压下限;旺业甸变10kV母线为10.87kV,高于电压运行上限。小负荷方式下,旺业甸变10kV母线电压为11kV,牛营子变10kV母线电压为10.8kV,均高于电压运行上限。According to calculations, under the heavy load mode, the 66kV busbar voltage of Wangyedian Substation is as low as 61.4kV, and the 10kV busbar voltage of Xishan Substation is 9.95kV after the capacitor is put in, which are all lower than the lower limit of normal operating voltage; the 10kV busbar of Wangyedian Substation is 10.87kV, Higher than the upper limit of voltage operation. Under the light load mode, the bus voltage of Wangyedian Substation 10kV is 11kV, and that of Niuyingzi Substation 10kV is 10.8kV, both of which are higher than the upper limit of voltage operation.

旺业甸变、牛营子变主变功率因数均低于0.9,不满足运行要求。The main transformer power factors of Wangyedian Substation and Niuyingzi Substation are all lower than 0.9, which do not meet the operation requirements.

1、分析原因:旺业甸变属于系统末端站,无功负荷较大,负荷功率因数低,为0.78,导致出现低电压问题,并且该站没有配置无功补偿装置。在将旺业甸变的负荷功率因数优化至0.9,并对同一线路上的小府变、四十家子变的无功负荷就地补偿后,旺业甸变新投入6Mvar电容器后,66kV母线电压可升至合格范围。1. Reason analysis: Wangyedian substation belongs to the terminal station of the system, with large reactive power load and low load power factor of 0.78, resulting in low voltage problems, and the station is not equipped with reactive power compensation device. After optimizing the load power factor of Wangyedian Substation to 0.9, and compensating the reactive loads of Xiaofu Substation and Shisijiazi Substation on the same line, Wangyedian Substation newly invested 6Mvar capacitors, and the 66kV bus The voltage can be raised to the qualified range.

并且,旺业甸两台主变变比不一致,分别为63±2×2.5%/11、66±2×2.5%/11。变比不一致导致站内无功流动,进一步降低了旺业甸变功率因数。两台主变可以调至变比相近的最高档位分别为1档和3档。Moreover, the main transformer ratios of Wangyedian's two sets are inconsistent, which are 63±2×2.5%/11 and 66±2×2.5%/11 respectively. The inconsistency of the transformation ratio leads to the flow of reactive power in the station, which further reduces the power factor of Wangyedian transformation. The two main transformers can be adjusted to the highest gears with similar transformation ratios, namely 1st gear and 3rd gear.

解决措施:建议提高负荷功率因数,将旺业甸变功率因数优化至0.9。目前旺业甸站没有配置无功补偿装置,考虑到该站移址新建,建议新站应至少配置6Mvar电容器。Solution: It is suggested to increase the load power factor and optimize the power factor of Wangyedian transformer to 0.9. At present, Wangyedian station is not equipped with reactive power compensation device. Considering that the station will be relocated and newly built, it is suggested that the new station should be equipped with at least 6Mvar capacitors.

2、分析原因:牛营子变目前有两台无载调压主变,一组1.2Mvar的电容器。负荷功率因数低和两台主变变比不一致导致主变功率因数低于0.9。在大小方式下,10kV母线电压存在调节困难的问题。经计算,主变分接开关调至2档为最合理的运行档位。2. Reason analysis: Niuyingzi Substation currently has two main transformers with no-load voltage regulation and a set of 1.2Mvar capacitors. The low load power factor and the inconsistent ratio of the two main transformers lead to the power factor of the main transformer being lower than 0.9. In the size mode, the 10kV bus voltage is difficult to adjust. After calculation, the main transformer tap changer is adjusted to the second gear as the most reasonable operating gear.

解决措施:建议提高负荷功率因数,将牛营子变功率因数优化至0.9,牛营子变有移址新建的计划,并且伴随负荷的增长,10kV侧的高电压问题将有所缓解。Solution: It is suggested to increase the load power factor and optimize the power factor of Niuyingzi Substation to 0.9. Niuyingzi Substation has a plan to relocate and build a new site, and with the increase of load, the problem of high voltage on the 10kV side will be alleviated.

3、分析原因:西山变10kV母线电压调压困难,目前配置一台1.5Mvar的电容器,#1主变共17档位,有载调压;#2主变共5档位,无载调压。#1主变在5档,#2在1档为相对合理的运行档位。3. Analysis of the reasons: Xishan Substation has difficulty in regulating the voltage of the 10kV busbar. Currently, it is equipped with a 1.5Mvar capacitor. The #1 main transformer has 17 gears in total, with on-load voltage regulation; the #2 main transformer has 5 gears in total, with off-load voltage regulation. . The #1 main transformer is in the 5th gear, and the #2 is in the 1st gear, which is a relatively reasonable operating gear.

解决措施:建议西山变增加一台2Mvar的电容器。Solution: It is recommended to add a 2Mvar capacitor to Xishan Substation.

经上述电压调整后,解决了电压和主变功率因数越限问题,地区电压情况良好,无功电压分布得以优化。After the above voltage adjustment, the problem of voltage and main transformer power factor exceeding the limit has been solved, the regional voltage is in good condition, and the distribution of reactive power and voltage has been optimized.

以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到的变化或替换,都应涵盖在本发明的保护范围之内。因此,本发明的保护范围应该以权利要求的保护范围为准。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto. Any person skilled in the art within the technical scope disclosed in the present invention can easily think of changes or Replacement should be covered within the protection scope of the present invention. Therefore, the protection scope of the present invention should be determined by the protection scope of the claims.

表1:输入信息表。Table 1: Input information table.

Claims (9)

1., based on the layering and zoning reactive voltage analytical method of boundary condition, it is characterized in that: comprise the following steps:
Step 1: layering and zoning is carried out to electrical network;
Step 2: determine institute's survey region and border thereof;
Step 3: input maximum, minimum load daily load and generator output, boundary condition, reactive power compensation configuring condition, regional power grid limit value;
Step 4: carry out Load flow calculation, regulates reactive compensation capacity, regional power grid border is adjusted to boundary condition;
Step 5: in judging area, whether voltage exists out-of-limit situation;
Step 6: judge whether each main transformer power factor meets limit value regulation.
2. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, is characterized in that: the concrete grammar that in described step 1, layering and zoning adopts is: according to different electric pressure layering, same electric pressure electrical network is divided into one deck; In same layer electrical network, carry out subregion according to geographical position and load supply district, which district transformer station is divided according to by which district being powered, and the transformer station of simultaneously being powered by not same district, is assigned in each district by supply load size.
3. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, is characterized in that: determine institute's survey region in described step 2, namely needs the regional power grid determining next will study according to research; Describedly determine border, refer to the transformer station selecting institute's survey region electrical network and be connected with last layer electrical network, as the border of this survey region.
4. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, it is characterized in that: peak day described in described step 3, refer to maximum a day of area power grid load in the middle of a year and minimum one day of load minimum load day respectively, this patent using peak day and minimum load day as two kinds of voltage analysis situations;
Described input is maximum, minimum load daily load and generator output, refers to using the load of Japan-China for peak load each plant stand, each generator output as a kind of voltage analysis situation, analyzed area electrical network low voltage problem; Using the load of Japan-China for minimum load each plant stand, each generator output as a kind of voltage analysis situation, analyzed area electrical network high voltage problem;
Described boundary condition refers to, using institute's survey region electrical network border transformer station in the voltage of maximum, minimum load day and power factor as boundary condition;
Described reactive power compensation configuring condition, refers to and obtains survey region electrical network each transformer station of institute inductive reactive power compensation device configuration total capacity, capacitive reactive power compensation arrangement configuration total capacity;
Described regional power grid restriction, refers to regional power grid each plant stand normal operating voltage limit value, power factor limit value.
5. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, is characterized in that: the mode of carrying out Load flow calculation described in described step 4 comprises:
Mode one: each plant stand load is peak load daily load, each generator output is peak load daily output, within the scope of each Reactive Power Compensation Eqyuipment in Substation configuration total capacity, regulate the reactive compensation capacity dropped into, the voltage of border transformer station and power factor are adjusted to peak day level, calculate each plant stand voltage;
Mode two: each plant stand load is minimum load daily load, each generator output is minimum load daily output, within the scope of each Reactive Power Compensation Eqyuipment in Substation configuration total capacity, regulate the reactive compensation capacity dropped into, the voltage of border transformer station and power factor are adjusted to peak day level, calculate each plant stand voltage.
6. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, it is characterized in that: in judging area described in described step 5, whether voltage exists out-of-limit situation, refer to the voltage result of calculation will obtained in step 4, the each plant stand normal operating voltage limit value inputted with step 3 compares, and judges whether voltage result of calculation exists out-of-limit situation and comprise with under type:
(1) if there is voltage out-of-limit situation, then the out-of-limit reason of analytical voltage, finely tunes the reactive compensation capacity dropped into, and re-starts voltage and calculates; If it is out-of-limit still to there is transformer substation voltage, then exports this transformer station and out-of-limit voltage, carry out next step; If it is out-of-limit to there is not transformer substation voltage, then carry out next step;
(2) if there is not voltage out-of-limit situation, then output area voltage condition is good, carries out next step.
7. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, it is characterized in that: described in described step 6, judge whether each main transformer power factor meets in the mode that limit value specifies, the power factor of each main transformer calculates, each plant stand normal operate power factor limit value result of calculation and step 3 inputted compares, and judges whether each main transformer power factor exists the situation exceeding limit value;
(1) situation that main transformer power factor exceeds limit value if do not exist, then export this region main transformer power factor good;
(2) situation that main transformer power factor exceeds limit value if exist, then export out-of-limit main transformer and out-of-limit power factor, and analyze out-of-limit reason, and carry out adjusting and optimizing for concrete reason.
8. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, it is characterized in that: in described step 3: input maximum, minimum load daily load and generator output, boundary condition, reactive power compensation configuring condition, regional power grid limit value, refers to that electric network information is inputted PSASP simulation software carries out reactive voltage analysis; Described PSASP simulation software is not limited to a kind of simulation calculation software.
9. the layering and zoning reactive voltage analytical method based on boundary condition according to claim 1, it is characterized in that: in described step 4: carrying out Load flow calculation can calculate by the multiple computational methods such as Newton-Raphson approach, gauss seidel method, is not limited to a kind of tidal current computing method.
CN201510879612.7A 2015-12-04 2015-12-04 Layering and zoning reactive voltage analysis method based on boundary condition Active CN105490281B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510879612.7A CN105490281B (en) 2015-12-04 2015-12-04 Layering and zoning reactive voltage analysis method based on boundary condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510879612.7A CN105490281B (en) 2015-12-04 2015-12-04 Layering and zoning reactive voltage analysis method based on boundary condition

Publications (2)

Publication Number Publication Date
CN105490281A true CN105490281A (en) 2016-04-13
CN105490281B CN105490281B (en) 2018-01-09

Family

ID=55677099

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510879612.7A Active CN105490281B (en) 2015-12-04 2015-12-04 Layering and zoning reactive voltage analysis method based on boundary condition

Country Status (1)

Country Link
CN (1) CN105490281B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106055744A (en) * 2016-05-20 2016-10-26 大连理工大学 A method for voltage drop analysis of three-dimensional integrated circuits based on grid points
CN106130005A (en) * 2016-05-13 2016-11-16 国家电网公司 220kV sub area division boundary node processing method based on geographical zone
CN109103947A (en) * 2018-08-24 2018-12-28 国家电网公司西北分部 A method of plant stand no-power vacancy is determined using reactive balance
CN109347117A (en) * 2018-11-30 2019-02-15 国网河北省电力有限公司 A kind of power distribution network energy storage bidirectional converter Reactive-power control method
CN110601212A (en) * 2019-09-23 2019-12-20 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 Method and system for determining main transformer transformation ratio of power grid based on reactive power optimization configuration
CN110797879A (en) * 2019-11-15 2020-02-14 国网浙江省电力有限公司经济技术研究院 A grid reactive power resource allocation method based on avoiding voltage overrun
CN110808583A (en) * 2019-11-06 2020-02-18 国网北京市电力公司 A Multi-objective-Oriented Optimal Control Method for Substations
CN111009906A (en) * 2019-12-04 2020-04-14 国网河北省电力有限公司雄安新区供电公司 Reactive compensation balance method of full cable net rack
CN118713225A (en) * 2024-06-06 2024-09-27 国网青海省电力公司电力科学研究院 A reactive power compensation method, device, equipment and storage medium for a substation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101039031A (en) * 2007-04-17 2007-09-19 清华大学 Method for controlling coordination voltage of regional power grid and provincial power grid
CN103001218A (en) * 2012-11-29 2013-03-27 清华大学 Reactive voltage coordination control method based on comprehensive benefits of transmission and distribution power grid
CN104201691A (en) * 2014-08-06 2014-12-10 国网上海市电力公司 Method and system for controlling reactive power optimization
CN104242308A (en) * 2014-09-26 2014-12-24 天津大学 Multisource system partitioning method considering voltage stabilization
CN104638654A (en) * 2015-02-02 2015-05-20 东南大学 STATCOM (static synchronous compensator) control method for voltage adjusting of wind farm and network nodes
CN105119267A (en) * 2015-07-08 2015-12-02 国家电网公司 Static voltage stable level analyzing method for power grid

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101039031A (en) * 2007-04-17 2007-09-19 清华大学 Method for controlling coordination voltage of regional power grid and provincial power grid
CN103001218A (en) * 2012-11-29 2013-03-27 清华大学 Reactive voltage coordination control method based on comprehensive benefits of transmission and distribution power grid
CN104201691A (en) * 2014-08-06 2014-12-10 国网上海市电力公司 Method and system for controlling reactive power optimization
CN104242308A (en) * 2014-09-26 2014-12-24 天津大学 Multisource system partitioning method considering voltage stabilization
CN104638654A (en) * 2015-02-02 2015-05-20 东南大学 STATCOM (static synchronous compensator) control method for voltage adjusting of wind farm and network nodes
CN105119267A (en) * 2015-07-08 2015-12-02 国家电网公司 Static voltage stable level analyzing method for power grid

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106130005A (en) * 2016-05-13 2016-11-16 国家电网公司 220kV sub area division boundary node processing method based on geographical zone
CN106130005B (en) * 2016-05-13 2021-09-28 国家电网公司 Geographical partition-based 220kV power grid partition boundary node processing method
CN106055744A (en) * 2016-05-20 2016-10-26 大连理工大学 A method for voltage drop analysis of three-dimensional integrated circuits based on grid points
CN106055744B (en) * 2016-05-20 2019-03-29 大连理工大学 A voltage drop analysis method for grid-based cell-level three-dimensional integrated circuits
CN109103947A (en) * 2018-08-24 2018-12-28 国家电网公司西北分部 A method of plant stand no-power vacancy is determined using reactive balance
CN109347117B (en) * 2018-11-30 2021-04-02 国网河北省电力有限公司 A kind of reactive power regulation method of energy storage bidirectional converter in distribution network
CN109347117A (en) * 2018-11-30 2019-02-15 国网河北省电力有限公司 A kind of power distribution network energy storage bidirectional converter Reactive-power control method
CN110601212A (en) * 2019-09-23 2019-12-20 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 Method and system for determining main transformer transformation ratio of power grid based on reactive power optimization configuration
CN110601212B (en) * 2019-09-23 2021-11-26 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 Method and system for determining main transformer transformation ratio of power grid based on reactive power optimization configuration
CN110808583A (en) * 2019-11-06 2020-02-18 国网北京市电力公司 A Multi-objective-Oriented Optimal Control Method for Substations
CN110797879A (en) * 2019-11-15 2020-02-14 国网浙江省电力有限公司经济技术研究院 A grid reactive power resource allocation method based on avoiding voltage overrun
CN111009906A (en) * 2019-12-04 2020-04-14 国网河北省电力有限公司雄安新区供电公司 Reactive compensation balance method of full cable net rack
CN111009906B (en) * 2019-12-04 2023-12-19 国网河北省电力有限公司雄安新区供电公司 Reactive compensation balancing method for full cable net rack
CN118713225A (en) * 2024-06-06 2024-09-27 国网青海省电力公司电力科学研究院 A reactive power compensation method, device, equipment and storage medium for a substation
CN118713225B (en) * 2024-06-06 2025-03-18 国网青海省电力公司电力科学研究院 A reactive power compensation method, device, equipment and storage medium for a substation

Also Published As

Publication number Publication date
CN105490281B (en) 2018-01-09

Similar Documents

Publication Publication Date Title
CN105490281B (en) Layering and zoning reactive voltage analysis method based on boundary condition
CN100570984C (en) Substation Voltage Control Method Realizing Comprehensive Coordination of Continuous Equipment and Discrete Equipment
CN100557918C (en) Coordinated voltage control method for power plants and substations based on real-time update of coordination constraints
CN102411645B (en) A Rural Power Grid Layout Optimization Method Based on Urban-rural Integration
CN101447671B (en) Automatic integrating and adjusting method for flow data
CN102157936A (en) Coordination control method
CN106992526A (en) The photovoltaic access distribution network voltage control system and method for a kind of layered distribution type
CN104158199B (en) Power system real-time status is carried out the system and method for reactive power and voltage control
CN103093021B (en) Tide deduction sandbox simulation system
CN109995089A (en) A method and system for evaluating the capacity of distributed power supply
CN104348158A (en) Automatic generation method for coordinated control area in region-county integrated automatic voltage control
CN106655209A (en) Data processing method of reactive voltage in urban power grid and data processing system
CN111614117A (en) Rapid response control method for transient voltage disturbance in centralized photovoltaic power station
CN103472325A (en) Detection platform for independent wave energy and tidal current energy power generation system
CN107910958A (en) A kind of regional power grid AVC systems and substation's DVQC control method for coordinating and device
CN104466972B (en) Voltage reactive distribution type control method making substation and power distribution network being harmonious
Singh et al. Energy savings in distribution network with smart grid-enabled CVR and distributed generation
CN102738807A (en) All-station reactive optimal control method for intensively integrating wind farms into public transformer substation
CN103730900A (en) Multi-time-scale province-region-county integrated reactive power optimization method of electric system
CN102904265B (en) Transformer station voltage reactive control method and system based on region tidal current
CN109980656B (en) Distributed reactive power optimization and voltage regulation and control method for power distribution network under two-layer cooperative architecture
CN107634523B (en) Reactive power and voltage control method of new energy centralized grid connection point based on multi-source hierarchical coordination
CN105071397A (en) Coordinated reactive voltage control method of different reactive compensation devices of wind power delivery
CN110601212B (en) Method and system for determining main transformer transformation ratio of power grid based on reactive power optimization configuration
CN201937278U (en) 10KV voltage-regulating and grouping reactive power compensation complete equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant