CN105442694A - 预应力钢筋混凝土污水截流管顶管施工方法 - Google Patents
预应力钢筋混凝土污水截流管顶管施工方法 Download PDFInfo
- Publication number
- CN105442694A CN105442694A CN201510785775.9A CN201510785775A CN105442694A CN 105442694 A CN105442694 A CN 105442694A CN 201510785775 A CN201510785775 A CN 201510785775A CN 105442694 A CN105442694 A CN 105442694A
- Authority
- CN
- China
- Prior art keywords
- pipe
- jacking
- tube coupling
- construction
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E03—WATER SUPPLY; SEWERAGE
- E03F—SEWERS; CESSPOOLS
- E03F3/00—Sewer pipe-line systems
- E03F3/06—Methods of, or installations for, laying sewer pipes
Landscapes
- Health & Medical Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Public Health (AREA)
- Water Supply & Treatment (AREA)
- Sewage (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
一种预应力钢筋混凝土污水截流管顶管施工方法,包括以下步骤:步骤一,对污水截流管的管位下工程地质情况进行勘探,并对管网进行初步的平面设计;步骤二,工作坑的支护和开挖;步骤三,顶管的工艺平台及其专用设施的安装;步骤四,顶管施工。该方法在中、小型工程中,采用机械顶进和人工开挖相结合的方式,造价低、操作简单,对周边的环境影响小,能够进行昼夜施工,施工质量稳定。
Description
技术领域
本发明涉及顶管施工方法,尤其是涉及预应力钢筋混凝土污水截流管顶管施工方法。
背景技术
目前,地下管线施工中经常需要在地下挖槽铺设管线及其对管线进行修复,用开挖的方式施工周期很长,特别是城市中心路段的地下管线非常密集,管线交叉重叠分布,想要再进行新管线的铺设通过传统的开挖方式无法进行,且如果地表有建筑物,也将无法进行开挖,在闹市中对马路进行开挖施工对交通及人们生活带来极大的不便,通常需要搭设专门的路障然后封闭施工,防止出现安全事故,但是在一些主要的交通干道,由于交通压力或者人流,车流情况,不便于封闭施工,这就给传统的施工方式造成了困难;采用长距离全机械顶进技术和设备,造价高且对周围结构的破坏大。
发明内容
为了解决现有技术存在的不足,本发明提供了一种预应力钢筋混凝土污水截流管顶管施工方法,该施工方法能够减少对道路的影响,保证道路的通畅,对周边的环境影响小,能够进行昼夜施工,施工质量稳定,造价低。
本发明解决其技术问题所采用的技术方案是:
预应力钢筋混凝土污水截流管顶管施工方法,包括以下步骤:
步骤一,对污水截流管的管位下工程地质情况进行勘探,并对管网进行初步的平面设计;
步骤二,工作坑的支护和开挖;工作坑包括接收坑和顶进坑,根据管网的平面设计,作适当的调整,选择交通便利,人员不易集中的地段,将钢桩一次打到位,确定工作坑的设置位置,进行人工开挖,开挖的过程中不断焊接钢板挡土,每隔两米加设一道横梁和稳定斜撑,开挖到设计标高时,顶进坑施工集水井、砂浆砌筑后背及混凝土地坪,接收坑施工集水井和混凝土地坪,接收坑的钢桩间距大于顶进坑的钢桩间距,接收坑的施工晚于顶进坑的施工,在浇筑地坪的过程中,埋入导轨和其他预埋件,排除工作坑内的积水;
步骤三,顶管的工艺平台及其专用设施的安装:在工作坑内设置工艺平台,以便于管节的固定,将工艺平台支腿焊接在预埋件上,顶管内设置半圆形的四轮小车,坑内设置箱斗,在工作坑的开口部设置起吊龙门架及起吊器具;采用槽钢焊接工作棚的主支架,角铁焊接工作棚的分布架,分布架上设置防水棚布,完成工作棚的设置,在工作坑顶部的地面上设置工作台,用工字钢焊接形成工作台,用于吊运管道和吊运管中的土;
步骤四,顶管施工:根据设计要求,选择适当尺寸和长度的管节,对管节的外观进行检查,管节端面的平直度、管节壁表面的光洁度和管端面下有无纵向裂缝,检查合格后,将管节进行安装,为了保证每节管节尾部变压而不变形,加套圆形顶铁,扩大管节端的承压面积,对工作面进行挖土,挖土时,严格规范施工,不得超挖,顶进的过程中,对管节进行实时监测,正常顶进间距30cm测量一次,以检查管节是否沉降,每顶进80cm-100cm对整个顶管段进行复测,检查整个管节是否发生沉降,挖土后利用半圆形四轮小车进行管内运土,小车的土卸到坑内的箱斗中,然后进行土方提升,将其提升到地面,顶管完成后,对每节管节进行测量,绘制管道竣工纵断面图并做闭水试验。
其中所述的顶管施工方法,还包括步骤五,地面观察测量:看地面有无沉陷和隆起现象,即观察顶管施工是否会造成地面的沉降和隆起,如发现异常情况,可以调整顶管施工的进度和方式,对顶管进行强制校正,保证工程的正常进行。
其中所述的导轨为滑动式导轨,导轨的轨距为0.8米。
其中所述的顶管材质为预应力钢筋混凝土,管节的长度为2米,内径为1.2米,该长度既能保证管节的强度,又能兼顾成本,同时,也能容纳四轮小车进行运土。
本发明的有益效果是:在中、小型工程中,采用机械顶进和人工开挖相结合的方式,造价低、操作简单,对周边的环境影响小,能够进行昼夜施工,施工质量稳定。
附图说明
图1为顶管施工流程图。
具体实施方式
下面结合附图和实施例对本发明作进一步说明。
预应力钢筋混凝土污水截流管顶管施工方法,包括以下步骤:
步骤一,对污水截流管的管位下工程地质情况进行勘探,并对管网进行初步的平面设计;
步骤二,工作坑的支护和开挖;工作坑包括接收坑和顶进坑,根据管网的平面设计,作适当的调整,选择交通便利,人员不易集中的地段,将钢桩一次打到位,确定工作坑的设置位置,进行人工开挖,开挖的过程中不断焊接钢板挡土,每隔两米加设一道横梁和稳定斜撑,开挖到设计标高时,顶进坑施工集水井、砂浆砌筑后背及混凝土地坪,接收坑施工集水井和混凝土地坪,接收坑的钢桩间距大于顶进坑的钢桩间距,接收坑的施工晚于顶进坑的施工,在浇筑地坪的过程中,埋入导轨和其他预埋件,排除工作坑内的积水;
步骤三,顶管的工艺平台及其专用设施的安装:在工作坑内设置工艺平台,以便于管节的固定,将工艺平台支腿焊接在预埋件上,顶管内设置半圆形的四轮小车,坑内设置箱斗,在工作坑的开口部设置起吊龙门架及起吊器具;采用槽钢焊接工作棚的主支架,角铁焊接工作棚的分布架,分布架上设置防水棚布,完成工作棚的设置,在工作坑顶部的地面上设置工作台,用工字钢焊接形成工作台,用于吊运管道和吊运管中的土;
步骤四,顶管施工:根据设计要求,选择适当尺寸和长度的管节,对管节的外观进行检查,管节端面的平直度、管节壁表面的光洁度和管端面下有无纵向裂缝,检查合格后,将管节进行安装,为了保证每节管节尾部变压而不变形,加套圆形顶铁,扩大管节端的承压面积,对工作面进行挖土,挖土时,严格规范施工,不得超挖,顶进的过程中,对管节进行实时监测,正常顶进间距30cm测量一次,以检查管节是否沉降,每顶进80cm-100cm对整个顶管段进行复测,检查整个管节是否发生沉降,挖土后利用半圆形四轮小车进行管内运土,小车的土卸到坑内的箱斗中,然后进行土方提升,将其提升到地面,顶管完成后,对每节管节进行测量,绘制管道竣工纵断面图并做闭水试验。
接收坑包括导轨、混凝土地坪和基础等。
顶进坑包括导轨、混凝土地坪、后背和基础等。
接收坑和顶进坑是竖井,顶进过程中,顶管的管节不断被吊入工作坑内安装顶进,管内土方陆续从坑下提升到地面运走。工作坑的尺寸是根据地形、地质条件和顶管管径确定的,其中顶进坑的尺寸为长*宽*高=6m*5.5m*6m,接收坑的尺寸为长*宽*高=5m*5m*6m,工作坑基础为C20现浇混凝土。
根据力的平衡原理,管节的顶力值为管前的贯入阻力和沿着顶进长度的摩擦力之和,顶力的理论计算公式为:
Rf=K[f(2Pv+2Ph+Pb)+Pa]——————(1)
式中,Rf为计算顶力,单位为KN;
Pv为管顶上的垂直压力,单位为KN;
Ph为管侧土压力,单位为KN;
Pb为全部欲顶进管段的重量,单位为Kg;
f为管壁与土间的摩擦系数;
Pa为管端部贯入阻力,单位为KN;
K为安全系数;
其中,Pv的计算公式为:
Pv=Kp*r*H*D1*L——————(2)
式中,Kp为垂直压力系数;
r为土的容重,单位为T/m3;
H为管顶覆土深度,单位为m;
D1为顶入管节的外径,单位为m;
L为顶进管段的长度,单位为m。
其中Ph的计算公式为:
Ph=r(H+D1/2)D1*L*tg2(45°-φ)——————(3)
式中,r为土的容量,单位为T/m3;
H为管顶覆土深度,单位为m;
D1为顶入管节的外径,单位为m;
L为顶进管段的长度,单位为m;
φ为土的内摩擦角。
其中,Pb的计算公式为:
Pb=G*L——————(4)
式中,G为管节单元长度重量,单位为Kg/m;
L为顶进管段的长度,单位为m。
后背的抗力计算公式为;
Rc=Kr*B*H*(h+H/2)*r*Kp——————(5)
式中,Rc为后背抗力,单位为KN;
B为后背宽度,单位为m;
H为后背宽度,单位为m;
h为后背体顶到地面高度,单位为m;
r为毛石的容重,单位为t/m3;
Kp为被动体压力系数;
Kr为后背抗力系数。
顶管施工方法还包括步骤五,地面观察测量:看地面有无沉陷和隆起现象。
导轨为滑动式导轨,导轨的轨距为0.8米。
顶管材质为预应力钢筋混凝土,管节的长度为2米,内径为1.2米。
以上所述仅为本发明的优选实施例而已,并不用于限制本发明,对于本领域的技术人员来说,本发明可以有各种更改和变化。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均包含在本发明的保护范围之内。
Claims (4)
1.预应力钢筋混凝土污水截流管顶管施工方法,其特征在于包括以下步骤:
步骤一,对污水截流管的管位下工程地质情况进行勘探,并对管网进行初步的平面设计;
步骤二,工作坑的支护和开挖;工作坑包括接收坑和顶进坑,根据管网的平面设计,作适当的调整,选择交通便利、人员不易集中的地段,将钢桩一次打到位,确定工作坑的设置位置,进行人工开挖,开挖的过程中不断焊接钢板挡土,每隔两米加设一道横梁和稳定斜撑,开挖到设计标高时,顶进坑施工集水井、砂浆砌筑后背及混凝土地坪,接收坑施工集水井和混凝土地坪,接收坑的钢桩间距大于顶进坑的钢桩间距,接收坑的施工晚于顶进坑的施工,在浇筑地坪的过程中,埋入导轨和其他预埋件,排除工作坑内的积水;
步骤三,顶管的工艺平台及其专用设施的安装:在工作坑内设置工艺平台,以便于管节的固定,将工艺平台支腿焊接在预埋件上,顶管内设置半圆形的四轮小车,坑内设置箱斗,在工作坑的开口部设置起吊龙门架及起吊器具;采用槽钢焊接工作棚的主支架,角铁焊接工作棚的分布架,分布架上设置防水棚布,完成工作棚的设置,在工作坑顶部的地面上设置工作台,用工字钢焊接形成工作台,用于吊运管道和吊运管中的土;
步骤四,顶管施工:根据设计要求,选择适当尺寸和长度的管节,对管节的外观进行检查,管节端面的平直度、管节壁表面的光洁度和管端面下有无纵向裂缝,检查合格后,将管节进行安装,为了保证每节管节尾部变压而不变形,加套圆形顶铁,扩大管节端的承压面积,对工作面进行挖土,挖土时,严格规范施工,不得超挖,顶进的过程中,对管节进行实时监测,正常顶进间距30cm测量一次,以检查管节是否沉降,每顶进80cm-100cm对整个顶管段进行复测,检查整个管节是否发生沉降,挖土后利用半圆形四轮小车进行管内运土,小车的土卸到坑内的箱斗中,然后进行土方提升,将其提升到地面,顶管完成后,对每节管节进行测量,绘制管道竣工纵断面图并做闭水试验。
2.根据权利要求1所述的预应力钢筋混凝土污水截流管顶管施工方法,其特征在于:
还包括步骤五,地面观察测量:看地面有无沉陷和隆起现象。
3.根据权利要求1所述的预应力钢筋混凝土污水截流管顶管施工方法,其特征在于:
所述的导轨为滑动式导轨,导轨的轨距为0.8米。
4.根据权利要求1所述的预应力钢筋混凝土污水截流管顶管施工方法,其特征在于:
所述的顶管材质为预应力钢筋混凝土,管节的长度为2米,内径为1.2米。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510785775.9A CN105442694B (zh) | 2015-11-16 | 2015-11-16 | 预应力钢筋混凝土污水截流管顶管施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510785775.9A CN105442694B (zh) | 2015-11-16 | 2015-11-16 | 预应力钢筋混凝土污水截流管顶管施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105442694A true CN105442694A (zh) | 2016-03-30 |
CN105442694B CN105442694B (zh) | 2017-07-25 |
Family
ID=55553288
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510785775.9A Active CN105442694B (zh) | 2015-11-16 | 2015-11-16 | 预应力钢筋混凝土污水截流管顶管施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105442694B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108561139A (zh) * | 2018-04-09 | 2018-09-21 | 中国水利水电第五工程局有限公司 | 一种水平钢筋混凝土钢管桩预支护方法 |
CN111794343A (zh) * | 2020-05-29 | 2020-10-20 | 杭州江润科技有限公司 | 管道沟上连接整体下沟施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003286743A (ja) * | 2002-03-28 | 2003-10-10 | Kurimoto Ltd | パイプインパイプ工法及びその実施装置 |
CN101982688A (zh) * | 2010-09-30 | 2011-03-02 | 中铁四局集团有限公司 | 一种大口径长距离钢顶管施工系统 |
CN103046638A (zh) * | 2011-04-28 | 2013-04-17 | 朱奎 | 一种顶管施工方法 |
CN103938703A (zh) * | 2014-05-07 | 2014-07-23 | 中国五冶集团有限公司 | 一种顶管施工方法 |
CN104358927A (zh) * | 2014-10-30 | 2015-02-18 | 国强建设集团有限公司 | 一种顶管施工方法及顶管装置 |
KR101513589B1 (ko) * | 2014-08-06 | 2015-04-20 | (주)나스텍이앤씨 | 노후관 재생방법 및 이에 사용되는 노후관 재생장치 |
-
2015
- 2015-11-16 CN CN201510785775.9A patent/CN105442694B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2003286743A (ja) * | 2002-03-28 | 2003-10-10 | Kurimoto Ltd | パイプインパイプ工法及びその実施装置 |
CN101982688A (zh) * | 2010-09-30 | 2011-03-02 | 中铁四局集团有限公司 | 一种大口径长距离钢顶管施工系统 |
CN103046638A (zh) * | 2011-04-28 | 2013-04-17 | 朱奎 | 一种顶管施工方法 |
CN103938703A (zh) * | 2014-05-07 | 2014-07-23 | 中国五冶集团有限公司 | 一种顶管施工方法 |
KR101513589B1 (ko) * | 2014-08-06 | 2015-04-20 | (주)나스텍이앤씨 | 노후관 재생방법 및 이에 사용되는 노후관 재생장치 |
CN104358927A (zh) * | 2014-10-30 | 2015-02-18 | 国强建设集团有限公司 | 一种顶管施工方法及顶管装置 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108561139A (zh) * | 2018-04-09 | 2018-09-21 | 中国水利水电第五工程局有限公司 | 一种水平钢筋混凝土钢管桩预支护方法 |
CN111794343A (zh) * | 2020-05-29 | 2020-10-20 | 杭州江润科技有限公司 | 管道沟上连接整体下沟施工方法 |
CN111794343B (zh) * | 2020-05-29 | 2021-11-19 | 杭州江润科技有限公司 | 管道沟上连接整体下沟施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105442694B (zh) | 2017-07-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106369223B (zh) | 一种粉砂土地层顶管施工方法 | |
Tan et al. | Measured performance of a 26 m deep top-down excavation in downtown Shanghai | |
Cui et al. | Field performance of concrete pipes during jacking in cemented sandy silt | |
CN106436720B (zh) | 顶管施工用小尺寸深基坑支护结构的施工方法 | |
Cheng et al. | Observed performance of a 30.2 m deep-large basement excavation in Hangzhou soft clay | |
CN103243747A (zh) | 预应力混凝土管桩桩基的纠偏方法 | |
CN102635119A (zh) | 一种用于旋流井施工的支护方法 | |
CN101638898A (zh) | 顶管竖井悬挂式施工方法 | |
Ledyaev et al. | An assessment of the sewer tunnel stress-strain behavior during the reconstruction of an object of cultural heritage | |
CN105442694A (zh) | 预应力钢筋混凝土污水截流管顶管施工方法 | |
CN101319894A (zh) | 地下空间开挖引起的地面沉降测试方法 | |
CN104631486A (zh) | 狭窄环境下的独立柱基施工方法 | |
Li et al. | Distress evaluation and remediation for a high-rise building with pile-raft foundation | |
CN110512594A (zh) | 旋挖钻机遇空洞成孔成桩的简易方法 | |
CN214993928U (zh) | 一种自然放坡与smw工法桩结合的复合支护结构 | |
CN205116215U (zh) | 支撑式挡墙结构 | |
Campelo et al. | Georeferenced monitoring of displacements of gabion walls | |
CN109837911B (zh) | 一种利用双液注浆进行基坑支护设计的方法 | |
CN107023012B (zh) | 多道环形砼支撑深基坑土方外运施工方法 | |
Demenkov et al. | Emergency Assessment of Semi-Embedded Construction | |
CN106968271B (zh) | 地下管廊开挖及支撑的施工方法 | |
Zhou et al. | Study on anti-buoyancy design and engineering measures for gas pipeline in cross-river shield tunnel | |
Aversa et al. | Ground movements induced by TBM excavation under an historic church in Napoli | |
Zhang et al. | Excavation Failure Cases and Analysis | |
Li | A Research on the stability and support technology of pit in half water in the soft soil foundation |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |