CN105442412A - Sponge fitness site and construction method thereof - Google Patents
Sponge fitness site and construction method thereof Download PDFInfo
- Publication number
- CN105442412A CN105442412A CN201510986765.1A CN201510986765A CN105442412A CN 105442412 A CN105442412 A CN 105442412A CN 201510986765 A CN201510986765 A CN 201510986765A CN 105442412 A CN105442412 A CN 105442412A
- Authority
- CN
- China
- Prior art keywords
- layer
- building field
- waste rubber
- rubber grain
- sponge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01C—CONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
- E01C13/00—Pavings or foundations specially adapted for playgrounds or sports grounds; Drainage, irrigation or heating of sports grounds
- E01C13/06—Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003
- E01C13/065—Pavings made in situ, e.g. for sand grounds, clay courts E01C13/003 at least one in situ layer consisting of or including bitumen, rubber or plastics
Abstract
The invention relates to a fitness site and particularly relates to a sponge fitness site which is characterized by mainly comprising a hardened road surface (1), a glue layer (2) and a waste rubber particle layer (3) from bottom to top, wherein the surface of the waste rubber particle layer (3) is provided with a hard ironing layer (4) formed by electrically heating an iron plate. The sponge fitness site provided by the invention has the advantages of elasticity, fast water penetration, large water storage capacity and long service life.
Description
Technical field
The present invention relates to a kind of body-building field, especially relate to a kind of sponge body-building field and construction method thereof.
Background technology
Along with the raising of health of people consciousness, outdoor body-building field is opened more and more.Existing outdoor body-building field is in security consideration, is mostly rubber brick one piece of block splicing laying and forms.It has anti-skidding, flexible, that safety is high feature.But this kind of rubber brick shrinks, the coefficient of expansion is large, and after heavy rain attacks, water suction can be expanded, to arch upward distortion after making the body-building field immersion after laying, can shrink after dehydration, generation gap, and some bights can tilt, safety reduces greatly, and its application life is short.
And once form to position concrete brick or asphalt paving, infiltration water-holding capacity is poor, do not meet the planning in sponge city, and due to its material comparatively firmly, people are when upper exercise, and comfort is poor, once fall down or slide into, easy tumble injury.
Summary of the invention
An object of the present invention is to overcome above-mentioned deficiency, provides that a kind of planarization is good, long service life, sponge body-building field that infiltration retaining is fast.
Two of object of the present invention is the construction method providing a kind of body-building field of sponge efficiently.
The object of the present invention is achieved like this: a kind of sponge body-building field, and described sponge body-building field is formed primarily of hard surface, glue layer and waste rubber grain layer from bottom to top, the hard pressing layer that described waste rubber grain layer has electrical heating iron plate to be formed; The gross thickness of described glue layer, waste rubber grain layer and hard pressing layer is 8-10mm.
The rubber grain average grain diameter of described waste rubber grain layer is 1-2mm.
Described hard surface is tamped by mountain yellow mud and is formed.
A kind of construction method of sponge body-building field, it is characterized in that: first body-building field roadbed is tamped, and then its surperficial glue coating, be that the waste rubber grain of 1-2mm to be layed on glue and compacting again by mean particle size, after cured, is plated with electrical heating iron plate in waste rubber grain layer surface, form one deck hard pressing layer.
The invention has the beneficial effects as follows:
After sponge body-building field of the present invention is laid, rainwater can rapid osmotic, and rapid dispersion is dredged, when heavy rain comes, play rapid infiltrated effect, alleviate underdrainage pipe pressure, the sun shines again after the rain, the water-holding capacity of floor tile, can volatilize gradually, alleviate air dried pressure, and not easily play dirt, haze phenomenon can be reduced.
The hard pressing layer on surface, can make loose rubber grain be solidified into entirety, extend its application life.And there will not be tilting phenomenon.
Material of main part adopts waste rubber grain, with low cost, and good springiness, the skid resistance of rubber itself can reduce the possibility slipped, and elastomeric material both can ensure the comfort property of body-building personnel, the injury to human body after also can lessly slipping.
Accompanying drawing explanation
Fig. 1 is the section structure schematic diagram of sponge body-building field of the present invention.
Wherein:
Hard surface 1;
Glue layer 2;
Waste rubber grain layer 3;
Pressing layer 4.
Detailed description of the invention
As Fig. 1, the present invention relates to a kind of sponge body-building field, described sponge body-building field is from bottom to top primarily of hard surface 1, glue layer 2 and waste rubber grain layer 3; The hard pressing layer 4 that described waste rubber grain layer 3 surface has electrical heating iron plate to be formed.
The gross thickness of described glue layer, waste rubber grain layer and pressing layer is 8-10mm.
The rubber grain average grain diameter of described waste rubber grain layer is 1-2mm.
Described hard surface 1 is tamped by mountain yellow mud and is formed.
During construction, first body-building field roadbed is tamped, and then its surperficial glue coating, be that the waste rubber grain of 1-2mm to be layed on glue and compacting again by mean particle size, after cured, is plated with electrical heating iron plate in waste rubber grain layer surface, form one deck hard pressing layer.
Adopt the sponge body-building field made of the method, as sponge, good " elasticity " can be had, water suction when raining, retaining, infiltration, water purification in conform change and reply natural calamity etc., when needing, the water stored " release " is used.
Claims (5)
1. a sponge body-building field, is characterized in that: described sponge body-building field is from bottom to top primarily of hard surface (1), glue layer (2) and waste rubber grain layer (3); The hard pressing layer (4) that described waste rubber grain layer (3) surface has electrical heating iron plate to be formed.
2. sponge body-building field according to claim 1, is characterized in that: the gross thickness of described glue layer, waste rubber grain layer and pressing layer is 8-10mm.
3. sponge body-building field according to claim 1, is characterized in that: the rubber grain average grain diameter of described waste rubber grain layer is 1-2mm.
4. sponge body-building field according to claim 1, is characterized in that: described hard surface (1) is tamped by mountain yellow mud and formed.
5. the construction method of a sponge body-building field, it is characterized in that: first body-building field roadbed is tamped, and then its surperficial glue coating, be that the waste rubber grain of 1-2mm to be layed on glue and compacting again by mean particle size, after cured, is plated with electrical heating iron plate in waste rubber grain layer surface, form one deck hard pressing layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510986765.1A CN105442412A (en) | 2015-12-26 | 2015-12-26 | Sponge fitness site and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510986765.1A CN105442412A (en) | 2015-12-26 | 2015-12-26 | Sponge fitness site and construction method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105442412A true CN105442412A (en) | 2016-03-30 |
Family
ID=55553010
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510986765.1A Pending CN105442412A (en) | 2015-12-26 | 2015-12-26 | Sponge fitness site and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105442412A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112252117A (en) * | 2020-10-16 | 2021-01-22 | 魏恒业 | Manufacturing and construction method of improved plastic track |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1329199A (en) * | 2000-06-16 | 2002-01-02 | 上海航伟科技发展有限公司 | Plastic cement track, sports ground and manufacturing method thereof |
CN1379158A (en) * | 2002-01-30 | 2002-11-13 | G·K株式会社 | Spreading method of elastic ground material |
CN202482735U (en) * | 2012-01-05 | 2012-10-10 | 上海杰唯时新材料技术有限公司 | Reclaimed rubber non-motorized vehicle lane |
CN205329470U (en) * | 2015-12-26 | 2016-06-22 | 江阴市人人达科技有限公司 | Sponge body -building place |
-
2015
- 2015-12-26 CN CN201510986765.1A patent/CN105442412A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1329199A (en) * | 2000-06-16 | 2002-01-02 | 上海航伟科技发展有限公司 | Plastic cement track, sports ground and manufacturing method thereof |
CN1379158A (en) * | 2002-01-30 | 2002-11-13 | G·K株式会社 | Spreading method of elastic ground material |
CN202482735U (en) * | 2012-01-05 | 2012-10-10 | 上海杰唯时新材料技术有限公司 | Reclaimed rubber non-motorized vehicle lane |
CN205329470U (en) * | 2015-12-26 | 2016-06-22 | 江阴市人人达科技有限公司 | Sponge body -building place |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112252117A (en) * | 2020-10-16 | 2021-01-22 | 魏恒业 | Manufacturing and construction method of improved plastic track |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204401390U (en) | A kind of novel pavement drainage system | |
CN206707150U (en) | Underground garage ramp | |
CN104480829A (en) | Pavement structure internal draining system for eliminating road surface water seepage | |
CN105442406A (en) | High-water penetration high-water storage sponge floor tile | |
CN204097832U (en) | Multi-functional pavement bricks | |
CN105442412A (en) | Sponge fitness site and construction method thereof | |
CN205329470U (en) | Sponge body -building place | |
CN204139025U (en) | A kind of drainage Anti-slid floor tile | |
CN207776308U (en) | A kind of anti-skidding staircase boards of green | |
CN207391983U (en) | A kind of sponge-type parking system | |
CN205134501U (en) | Prefabricated ground in bathroom | |
CN205368951U (en) | Sponge garden way | |
CN205077363U (en) | Road surface is laid to ceramic tile that permeates water fast | |
CN206337787U (en) | A kind of indoor moisture proof cracking resistance earth construction | |
CN210563193U (en) | High-efficient skid-proof terrace structure | |
CN105421193A (en) | Sponge-like garden road and construction method of same | |
CN207537835U (en) | A kind of novel water permeable brick | |
CN209443316U (en) | A kind of permeable tile work pavement structure that closely knit asphalt macadam concrete layer is set | |
CN205077351U (en) | Road surface is laid to wear -resisting ceramic tile | |
CN203188083U (en) | Anti-sliding tunnel pavement | |
CN204940072U (en) | A kind of ground tile paving road surface | |
CN106996063A (en) | A kind of pavement structure of permeable road | |
CN205934635U (en) | Roller compacted concrete interlayer structure suitable for arch slope highway | |
CN208472497U (en) | A kind of municipal road pavement | |
CN207512879U (en) | Suitable for the stepped rain water seepage well of sponge urban construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160330 |
|
RJ01 | Rejection of invention patent application after publication |