CN105429027B - Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M - Google Patents

Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M Download PDF

Info

Publication number
CN105429027B
CN105429027B CN201510778912.6A CN201510778912A CN105429027B CN 105429027 B CN105429027 B CN 105429027B CN 201510778912 A CN201510778912 A CN 201510778912A CN 105429027 B CN105429027 B CN 105429027B
Authority
CN
China
Prior art keywords
safety measure
pressing plate
secondary safety
module
electrical
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510778912.6A
Other languages
Chinese (zh)
Other versions
CN105429027A (en
Inventor
罗美玲
刘志远
温靖华
寿海宁
陈鑫
程华伟
于家旭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd
State Grid Ningxia Electric Power Co Ltd
Original Assignee
SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd
State Grid Ningxia Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd, State Grid Ningxia Electric Power Co Ltd filed Critical SHANDONG ROOF NEW INFORMATION TECHNOLOGY Co Ltd
Priority to CN201510778912.6A priority Critical patent/CN105429027B/en
Publication of CN105429027A publication Critical patent/CN105429027A/en
Application granted granted Critical
Publication of CN105429027B publication Critical patent/CN105429027B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B3/00Apparatus specially adapted for the manufacture, assembly, or maintenance of boards or switchgear

Abstract

System and construction method, including application layer, service layer and interface layer are supported the invention discloses secondary safety measure in a kind of maintenance of intelligent substation O&M, wherein:Application layer, for generate it is graphical intend secondary safety measure during ticket, complete the security isolation of secondary device and electrical secondary system;Service layer, for setting up electrical secondary system model, previews secondary safety measure, whether secondary safety measure violates the rule set in advance during test patternization intends ticket, judges the validity of secondary safety measure using electrical secondary system simulation;Interface layer obtains pressing plate and loop state from Network Analyzer, and the clamp operation that pressing plate state check module is issued is converted into the operation information that integrated information platform can be recognized.The present invention intuitively sees the interoperation relation of secondary device in pressing plate, loop, and whole electrical secondary system, operations staff can be aided in formulate the purpose of secondary safety measure for the formulation of secondary safety measure.

Description

Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M
Technical field
System and construction method are supported the present invention relates to secondary safety measure in a kind of maintenance of intelligent substation O&M.
Background technology
In recent years, with intelligent substation Large scale construction, put into operation, design, debug related capital construction ability and quickly strengthen, respectively Net company is saved progressively by intelligent substation center of gravity by more ripe planning construction is transferred in operation maintenance.Wherein secondary safety Measure is related to power network safety operation as the security perimeter between equipment to be isolated and operational outfit, in intelligent power transformation Stand and occupy critical role in O&M.
Because intelligent substation employs IEC61850 standards systems, its communication pattern, equipment form are different from conventional become Power station.The related method of the secondary safety measure of conventional substation, technological means have been not applied for intelligent substation fortune completely Dimension, is mainly manifested in:
1) intelligent substation introduces maintenance pressing plate.Overhaul the use of pressing plate so that Awaiting Overhaul secondary device need not be disconnected Loop be the purpose that can reach security isolation;
2) hardwire in conventional substation is become into empty loop, isolation is realized by way of " tearing hardwire open " no longer It is applicable;
3) isolation in empty loop is realized by soft clamp operation.For remote operation, it is automatically brought into operation there is provided technical foundation;
4) because the change of technological means causes the reliability verification method of secondary safety measure to change.
Analysis can be seen that above, it is necessary to build the secondary safety measure branch of an adaptation intelligent substation technical characterstic System is held, the O&M maintenance of intelligent substation is supported, so as to support the Large scale construction of intelligent substation.
The content of the invention
The present invention is in order to solve the above problems, it is proposed that secondary safety measure is supported in a kind of intelligent substation O&M maintenance System and construction method, this method by analyze intelligent substation technical characterstic, analysis O&M during each service node skill The reasonable application of art method, efficiently solves secondary device security isolation in current intelligent substation O&M, verifies secondary safety The problem of reliability, the safety of measure perform secondary safe.
To achieve these goals, the present invention is adopted the following technical scheme that:
Secondary safety measure supports system, including application layer, service layer and interface layer in transformer station's O&M maintenance, wherein:
The application layer, for realizing business course management, and provides system operatio interface, for operations staff and system Interaction;
The service layer, the realization for support applications layer is accessed and secondary safety measure school there is provided electrical secondary system model The service of testing;
The interface layer obtains pressing plate and loop state from Network Analyzer, and pressing plate state is checked into the pressing plate that module is issued Operation is converted into the operation information that integrated information platform can be recognized.
The application layer includes figure auxiliary and intends ticket module, preview module and control module, wherein:
The figure auxiliary intends ticket module, the secondary safety measure ticket for generating particular substation, according to secondary operation Working specification is managed, corresponding clamp operation is performed on graphical interfaces, the operation on figure is changed into computer capacity automatically The pressing plate enough recognized is thrown and moves back operation information;
The preview module, based on the electrical secondary system of emulation, the simulation before being performed for secondary safety measure is performed Checking, the feedback information in secondary safety measure implementation procedure is showed with patterned way;
Order is moved back in the control module, the implementation procedure for being responsible for the secondary safety measure of control, the throwing for sending pressing plate, is moved State shows order feedback result.
The service layer includes anti-error detection module, electrical secondary system analog simulation module, electrical secondary system model module and tested Module is demonstrate,proved, wherein:
The anti-error detection module, integrality, correctness and validity for analyzing secondary safety measure, are that figure is auxiliary Plan tickets-raise up is helped for supporting;
The electrical secondary system analog simulation module, for emulating electrical secondary system in preview, to simulate secondary safety measure Influence to loop, the influence to electrical secondary system function;
The electrical secondary system model module, for obtaining electrical secondary system model from SCD file, to obtain electrical secondary system Static logic structures, support is provided for electrical secondary system analog simulation module;
The authentication module, obtains pressing plate from control module and throws and move back order, and from Network Analyzer interface obtain pressing plate and Loop state, for verifying whether the execution of secondary safety measure is correctly completed, order and pressing plate shape are moved back by analyzing pressing plate throwing Whether the uniformity of state, judge that pressing plate is thrown to move back and succeed.
The figure auxiliary intends ticket module, and centered on segregate secondary device, interval, displaying is isolated object and week The loop of side secondary device, pressing plate information.
The figure auxiliary intends ticket module, is divided to two levels to show graphical information, and the first level shows secondary device and week The information flow of side secondary device, the second level shows detailed loop between secondary device, pressing plate information.
The control module, is the operational feedback setting time limit of secondary safety measure, is prescribed a time limit during more than setting, remind operation Personnel's feeding back unsuccessful is, it is necessary to carry out manual intervention.
The anti-error detection module, detects integrality, correctness and the validity of secondary safety measure, wherein, integrality For detecting whether secondary safety measure has omission;Correctness is used to detect whether the execution sequence of secondary safety measure is correct; Validity is used to detect whether current secondary safety measure is necessary.
Secondary safety measure supports the construction method of system in a kind of intelligent substation O&M maintenance, comprises the following steps:
(1) the secondary safety measure ticket of particular substation is generated, according to secondary operational management working specification, in graphical interfaces Upper to perform corresponding clamp operation, the pressing plate that the operation on figure is changed into computer automatically to recognize, which is thrown, moves back operation letter Breath, anti-error detection module analysis verification figure auxiliary intends integrality, correctness and the validity of the secondary safety measure of ticket module;
(2) electrical secondary system model is obtained from SCD file, to obtain the static logic structures of electrical secondary system, in preview Electrical secondary system is emulated, to simulate influence of the secondary safety measure to loop, the influence to electrical secondary system function, with the secondary of emulation Based on system, carry out the simulation before secondary safety measure execution and perform checking, will be anti-in secondary safety measure implementation procedure Feedforward information is showed with patterned way;
(3) control module is responsible for controlling the implementation procedure of secondary safety measure, and order, Dynamic Display are moved back in the throwing for sending pressing plate Order feedback result;
(4) obtain pressing plate throwing from control module and move back order, and pressing plate and loop state are obtained from Network Analyzer interface, use Whether it is correctly completed in the execution for verifying secondary safety measure, order and the uniformity of pressing plate state is moved back by analyzing pressing plate throwing, Judge that pressing plate is thrown to move back whether to succeed.
In the step (1), figure auxiliary intend ticket module, centered on segregate secondary device, interval, displaying by every Loop, pressing plate information from object and periphery secondary device;It is divided to two levels to show graphical information, the first level shows secondary set The standby information flow with periphery secondary device, the second level shows detailed loop between secondary device, pressing plate information.
In the step (1), anti-error detection module detects integrality, correctness and the validity of secondary safety measure, its In, integrality is used to detect whether secondary safety measure has omission;Correctness is used for the execution sequence for detecting secondary safety measure It is whether correct;Validity is used to detect whether current secondary safety measure is necessary.
Beneficial effects of the present invention are:
(1) for the formulation of secondary safety measure, intuitively see two in pressing plate, loop, and whole electrical secondary system The interoperation relation of secondary device, contributes to operations staff's understanding to meet the secondary safety measure of intelligent substation technical characterstic really Implication is cut, reaches that auxiliary operations staff formulates the purpose of secondary safety measure;
(2) simultaneously, according to technical requirements of the intelligent substation to secondary safety measure, in formulation process, automatic detection The reasonability of secondary safety measure, can help operations staff to evade some and not allow intelligible mistake;
(3) for verification, the present invention is emulated according to the secondary model in SCD file to electrical secondary system, dynamic Verify the reasonability of secondary safety measure;
(4) for safety performs secondary safety measure, the present invention makes full use of existing system in intelligent substation, The collection of issuing for soft clamp operation order, and pressing plate state, loop state etc. is realized, whether is accorded with the effect for verifying execution Close and be expected.
Brief description of the drawings
Fig. 1 is system architecture diagram of the invention.
Embodiment:
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
As shown in figure 1, secondary safety operation support system can logically be divided into three layers, i.e.,:Application layer, service layer, Interface layer.
Application layer services, by intending ticket, preview, performing three functions, complete secondary device and secondary system in operations staff The security isolation of system.Service layer provides support to application layer.
Wherein, anti-error detection module supports graphical plan ticket module, for secondary safety during test patternization plan ticket Whether measure violates the rule set in advance;Electrical secondary system analog simulation module supports preview, by the electrical secondary system of simulation, Correctness Analysis for the secondary safety measure of preview provides support;Validation verification is operated to support safety measure control.By dividing The current state in the empty loop of analysis, judges whether clamp operation is effective.
Interface layer provides support to the operation validation verification of service layer, and pressing plate state on the one hand is checked into what module was issued Clamp operation is converted into the operation that integrated information platform can be recognized, on the other hand obtains pressing plate and loop from Network Analyzer State, so that pressing plate state checks the correctness of module verification clamp operation.
1st, figure auxiliary intends ticket
Figure auxiliary intends the secondary safety measure ticket that ticket module is used to generate particular substation, and operations staff is according to secondary fortune Row management working specification, performs corresponding clamp operation on graphical interfaces.Operation on figure is changed into meter by module automatically The pressing plate that calculation machine can be recognized is thrown and moves back operation.
Figure centered on segregate secondary device, interval, displaying be isolated object and periphery secondary device loop, Pressing plate information.Wherein, figure is divided to two levels to show.Level one shows the information flow of secondary device and periphery secondary device, layer Secondary two show detailed loop between secondary device, pressing plate information.
Operations staff is not inconsistent such as normally, module auto-alarming or prompting when performing per single stepping.
2nd, preview
Preview module is used for the simulation before secondary safety measure is performed and performs checking, and module is using the electrical secondary system that emulates as base Plinth, the feedback information in secondary safety measure implementation procedure is shown with patterned way, is that operations staff intuitively shows Safety measure implementation effect.
3rd, control
Control module is responsible for controlling the implementation procedure of secondary safety measure, and order, Dynamic Display life are moved back in the throwing for sending pressing plate Feedback result is made, the repeatable, revocable of any operation is supported.
Control module is that operational feedback sets the time limit, is prescribed a time limit during more than setting, and module reminds operations staff's feeding back unsuccessful, and Carry out manual intervention.Hard pressing plate for that can not realize control by software etc., control module prompting is accomplished manually.
4th, anti-error detection
Anti- error detection is used for the integrality, correctness, validity for analyzing secondary safety measure, is that figure auxiliary intends tickets-raise up's confession Support.Wherein, integrality is used to detect whether secondary safety measure has omission;Correctness is used to detect holding for secondary safety measure Whether row order is correct;Validity is used to detect whether current secondary safety measure is necessary.
5th, electrical secondary system analog simulation
Electrical secondary system analog simulation is used to emulate electrical secondary system in preview.In this programme, module is used to emulate secondary peace Influence of the full measure to loop, the influence to electrical secondary system function.In preview, pressing plate is thrown to the influence moved back to electrical secondary system and moved State shows operations staff.
6th, validation verification is operated
Operation validation verification module is used to verify whether the execution of secondary safety measure is correctly completed.Module on the one hand from Control module obtains pressing plate throwing and moves back order, on the other hand obtains pressing plate and loop state from Network Analyzer interface.Pass through analysis Whether pressing plate, which is thrown, moves back order and the uniformity of pressing plate state, judge that pressing plate is thrown to move back and succeed.
7th, electrical secondary system model
Electrical secondary system model is:The static logic structures of electrical secondary system, serve the service of all application secondary models.Two Subsystem model is main to be obtained from SCD file.For the information that does not have in SCD file such as:Overhaul pressing plate, intelligent terminal outlet Pressing plate etc., requirement of the electrical secondary system model module in No. 396 texts of state's net, is automatically replenished configuration.
8th, with Network Analyzer interface
The communication of system and Network Analyzer is mainly realized with the interface of Network Analyzer, is responsible for collecting from Network Analyzer Pressing plate and loop state.
9th, with integrated information platform interface
The communication with integrated information platform is realized with integrated information platform interface.It will be pressed by integrated information platform Plate throwing moves back order and is issued to electrical secondary system, completes the execution of secondary safety measure.
Although above-mentioned the embodiment of the present invention is described with reference to accompanying drawing, not to present invention protection model The limitation enclosed, one of ordinary skill in the art should be understood that on the basis of technical scheme those skilled in the art are not Need to pay various modifications or deform still within protection scope of the present invention that creative work can make.

Claims (9)

1. secondary safety measure supports system in the maintenance of intelligent substation O&M, it is characterized in that:Including application layer, service layer and connect Mouth layer, wherein:
The application layer, for realizing business course management, and provides system operatio interface, is handed over for operations staff and system Mutually;
The service layer, the realization for support applications layer is accessed and secondary safety measure verification clothes there is provided electrical secondary system model Business;
The interface layer obtains pressing plate and loop state from Network Analyzer, and pressing plate state is checked into the clamp operation that module is issued It is converted into the operation information that integrated information platform can be recognized;
The application layer includes figure auxiliary and intends ticket module, preview module and control module, wherein:
The figure auxiliary intends ticket module, the secondary safety measure ticket for generating particular substation, according to secondary operational management Working specification, performs corresponding clamp operation on graphical interfaces, and the operation on figure is changed into computer automatically to know Other pressing plate is thrown and moves back operation information;
The preview module, based on the electrical secondary system of emulation, the simulation before being performed for secondary safety measure performs checking, Feedback information in secondary safety measure implementation procedure is showed with patterned way;
Order, dynamic exhibition are moved back in the control module, the implementation procedure for being responsible for the secondary safety measure of control, the throwing for sending pressing plate Show order feedback result.
2. secondary safety measure supports system in intelligent substation O&M maintenance as claimed in claim 1, it is characterized in that:It is described Service layer includes anti-error detection module, electrical secondary system analog simulation module, electrical secondary system model module and authentication module, wherein:
The anti-error detection module, integrality, correctness and validity for analyzing secondary safety measure are figure auxiliary plan Tickets-raise up is for supporting;
The electrical secondary system analog simulation module, for emulating electrical secondary system in preview, to simulate secondary safety measure to returning The influence on road, the influence to electrical secondary system function;
The electrical secondary system model module, for obtaining electrical secondary system model from SCD file, to obtain the static state of electrical secondary system Logical construction, support is provided for electrical secondary system analog simulation module;
The authentication module, obtains pressing plate throwing from control module and moves back order, and obtain pressing plate and loop from Network Analyzer interface State, for verifying whether the execution of secondary safety measure is correctly completed, order and pressing plate state are moved back by analyzing pressing plate throwing Whether uniformity, judge that pressing plate is thrown to move back and succeed.
3. secondary safety measure supports system in intelligent substation O&M maintenance as claimed in claim 1, it is characterized in that:It is described Figure auxiliary intends ticket module, centered on segregate secondary device or interval, and displaying is isolated object and periphery secondary device Loop, pressing plate information.
4. secondary safety measure supports system in intelligent substation O&M maintenance as claimed in claim 1, it is characterized in that:It is described Figure auxiliary intends ticket module, is divided to two levels to show graphical information, and the first level shows secondary device and periphery secondary device Information flow, the second level shows detailed loop between secondary device, pressing plate information.
5. secondary safety measure supports system in intelligent substation O&M maintenance as claimed in claim 1, it is characterized in that:It is described Control module, is the operational feedback setting time limit of secondary safety measure, is prescribed a time limit during more than setting, reminds operations staff that feedback is lost Lose, it is necessary to carry out manual intervention.
6. secondary safety measure supports system in intelligent substation O&M maintenance as claimed in claim 1, it is characterized in that:It is described Anti-error detection module, detects integrality, correctness and the validity of secondary safety measure, wherein, integrality is used to detect secondary Whether safety measure has omission;Correctness is used to detect whether the execution sequence of secondary safety measure is correct;Validity is used to examine Whether necessary survey current secondary safety measure.
7. secondary safety measure supports the construction method of system in a kind of intelligent substation O&M maintenance, it is characterized in that:Including with Lower step:
(1) the secondary safety measure ticket of particular substation is generated, according to secondary operational management working specification, is held on graphical interfaces The corresponding clamp operation of row, the pressing plate that the operation on figure is changed into computer automatically to recognize, which is thrown, moves back operation information, prevents Error detection module analysis verification figure auxiliary intends integrality, correctness and the validity of the secondary safety measure of ticket module;
(2) electrical secondary system model is obtained from SCD file, to obtain the static logic structures of electrical secondary system, is emulated in preview Electrical secondary system, to simulate influence of the secondary safety measure to loop, the influence to electrical secondary system function, with the electrical secondary system of emulation Based on, carry out the simulation before secondary safety measure execution and perform checking, by the feedback letter in secondary safety measure implementation procedure Breath is showed with patterned way;
(3) control module is responsible for controlling the implementation procedure of secondary safety measure, and order, Dynamic Display order are moved back in the throwing for sending pressing plate Feedback result;
(4) obtain pressing plate throwing from control module and move back order, and pressing plate and loop state are obtained from Network Analyzer interface, for testing Whether the execution for demonstrate,proving secondary safety measure is correctly completed, and moves back order and the uniformity of pressing plate state by analyzing pressing plate throwing, judges Whether pressing plate is thrown to move back succeeds.
8. secondary safety measure supports the construction method of system in intelligent substation O&M maintenance as claimed in claim 7, its It is characterized in:In the step (1), figure auxiliary intend ticket module, centered on segregate secondary device or interval, displaying by every Loop, pressing plate information from object and periphery secondary device;It is divided to two levels to show graphical information, the first level shows secondary set The standby information flow with periphery secondary device, the second level shows detailed loop between secondary device, pressing plate information.
9. secondary safety measure supports the construction method of system in intelligent substation O&M maintenance as claimed in claim 7, its It is characterized in:In the step (1), anti-error detection module detects integrality, correctness and the validity of secondary safety measure, its In, integrality is used to detect whether secondary safety measure has omission;Correctness is used for the execution sequence for detecting secondary safety measure It is whether correct;Validity is used to detect whether current secondary safety measure is necessary.
CN201510778912.6A 2015-11-12 2015-11-12 Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M Expired - Fee Related CN105429027B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510778912.6A CN105429027B (en) 2015-11-12 2015-11-12 Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510778912.6A CN105429027B (en) 2015-11-12 2015-11-12 Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M

Publications (2)

Publication Number Publication Date
CN105429027A CN105429027A (en) 2016-03-23
CN105429027B true CN105429027B (en) 2017-08-18

Family

ID=55507045

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510778912.6A Expired - Fee Related CN105429027B (en) 2015-11-12 2015-11-12 Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M

Country Status (1)

Country Link
CN (1) CN105429027B (en)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106058695B (en) * 2016-06-16 2018-09-18 国网福建省电力有限公司 A kind of relay protection visualization maintenance peace based on SCD arranges system and its implementation
CN106159759B (en) * 2016-07-13 2018-03-20 国网四川省电力公司电力科学研究院 A kind of method for automatically generating secondary system of intelligent substation maintenance safety measure
CN106296456B (en) * 2016-08-10 2019-05-24 国家电网公司 Intelligent substation secondary maintenance safety measure support system and construction method
CN106483897B (en) * 2016-09-20 2019-04-19 山东鲁能奥特科技有限公司 A kind of peace arranges the peace of automatic arrangement system to arrange automatic method for arranging
CN106340818B (en) * 2016-10-17 2018-03-27 南京国电南自电网自动化有限公司 Intelligent substation relay protection device maintenance peace arranges assistant analysis method for early warning
CN106845003B (en) * 2017-02-15 2023-09-22 国网安徽省电力公司宣城供电公司 Intelligent substation security measure offline previewing method under virtual environment
CN106779508A (en) * 2017-03-21 2017-05-31 国网河南省电力公司平顶山供电公司 Secondary system of intelligent substation safety measure analogue simulation and O&M control platform
CN107025279B (en) * 2017-03-28 2020-03-10 国网江苏省电力公司电力科学研究院 SCD file online parallel configuration system and method based on database interface layer operation flow
EP3392987B1 (en) * 2017-04-21 2020-12-02 Rittal GmbH & Co. KG Method and system for automated support of a connection process, in particular for components in a switch cabinet or on a mounting system
CN107563520A (en) * 2017-07-26 2018-01-09 国网安徽省电力公司 A kind of intelligent substation secondary safety measure method for visualizing
CN107819323B (en) * 2017-09-30 2018-06-22 国网山东省电力公司 The online O&M method and system of secondary equipment of intelligent converting station based on visual presentation
CN109962443B (en) * 2017-12-26 2021-09-28 上海毅昊信息科技股份有限公司 SCD-based protection, overhaul and safety measure automatic generation system and method
CN112949271A (en) * 2021-02-07 2021-06-11 国网安徽省电力有限公司宣城供电公司 Maintenance safety measure analysis method and system

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN202218068U (en) * 2011-08-30 2012-05-09 中国电力科学研究院 MU emulator used for detection of smart substation
CN102879662B (en) * 2011-09-15 2014-11-19 国家电网公司 Device and method for detecting secondary virtual loop of intelligent transformer substation
CN102932167B (en) * 2012-10-10 2015-04-22 华南理工大学 Information stream control method and system for improving relay protection reliability of intelligent substation
CN103729805A (en) * 2014-01-04 2014-04-16 国家电网公司 500kV intelligent substation security arrangement ticket expert system
CN104821662B (en) * 2015-05-19 2017-11-24 国家电网公司 A kind of various dimensions intelligent error preventing system and method

Also Published As

Publication number Publication date
CN105429027A (en) 2016-03-23

Similar Documents

Publication Publication Date Title
CN105429027B (en) Secondary safety measure supports system and construction method in the maintenance of intelligent substation O&M
CN105067933B (en) General-purpose system and test method for electronics testability demonstration and assessment
CN103439612B (en) Based on the intelligent substation Auto-Test System of SCD
CN204790550U (en) Nuclear power DCS platform testing arrangement based on simulation system
CN101893867A (en) Operation ticket management system and method
CN108008209A (en) A kind of relay protection automated closed-loop detection method
CN103197271B (en) A kind of method of inspection of MMC topological flexibility direct current transportation test platform
CN102591223B (en) Intelligentized diagnostic system of substation-operation operation tickets
CN109754663B (en) Method and device for realizing power transformation operation and maintenance operation full-process simulation training evaluation
CN110784020A (en) Automatic checking and accepting equipment, system and method for monitoring information
CN104142448A (en) Method for automatically checking protection functions of microcomputer main-transformer differential protection device
CN204291050U (en) A kind of dispatching and monitoring information check system
CN101620800A (en) 500 KV substation analog simulation training system
CN103955571B (en) A kind of soft error injection and verification method for Flouride-resistani acid phesphatase chip
CN111858372A (en) Automatic testing system and method for TSRS system
CN109150636A (en) A kind of intelligent substation of full link information stream is assisted to experimental tests method and system
CN108446197A (en) A kind of control protection board automatic checkout system and method
CN106405286A (en) Electric energy quality monitoring device automatic test method and system
CN106779508A (en) Secondary system of intelligent substation safety measure analogue simulation and O&M control platform
CN107608291A (en) A kind of intelligent substation application function linkage rule verification method and system
CN109086197A (en) The acceptance testing method and system of urban track traffic CBTC system
CN104504952A (en) Subway multimedia teaching system and method
CN110611312B (en) On-line simulation system and method for panoramic data of substation bay level
CN110335008A (en) A kind of net source coordination management method and platform for dispatching of power netwoks
CN102590661B (en) Field distribution type intelligence test method for network-based smart substation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170818