CN101620800A - 500 KV substation analog simulation training system - Google Patents

500 KV substation analog simulation training system Download PDF

Info

Publication number
CN101620800A
CN101620800A CN200810039853A CN200810039853A CN101620800A CN 101620800 A CN101620800 A CN 101620800A CN 200810039853 A CN200810039853 A CN 200810039853A CN 200810039853 A CN200810039853 A CN 200810039853A CN 101620800 A CN101620800 A CN 101620800A
Authority
CN
China
Prior art keywords
substation
simulation
training
analog simulation
simulation training
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200810039853A
Other languages
Chinese (zh)
Inventor
林尉
庄建
沈勇
冯可
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Shanghai Municipal Electric Power Co
Beijing Kedong Electric Power Control System Co Ltd
Original Assignee
Shanghai Ultra-HV Transmission and Distribution Company Shanghai Electric Power C
Beijing Kedong Electric Power Control System Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Ultra-HV Transmission and Distribution Company Shanghai Electric Power C, Beijing Kedong Electric Power Control System Co Ltd filed Critical Shanghai Ultra-HV Transmission and Distribution Company Shanghai Electric Power C
Priority to CN200810039853A priority Critical patent/CN101620800A/en
Publication of CN101620800A publication Critical patent/CN101620800A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Testing And Monitoring For Control Systems (AREA)

Abstract

The invention relates to a 500 KV substation analog simulation training system, which has three functions of secondary equipment full three-dimensional simulation, automation equipment full three-dimensional simulation and microcomputer five-prevention monitoring system simulation. The system can operate perambulation and inspection of secondary equipment of the whole substation system by the OPENGL (Open Graphics Library) three-dimensional technology, and can carry out non-simulation analog on automation equipment, such as a front-end processor, a measuring and controlling unit and the like in the substation. The set microcomputer five-prevention monitoring system simulation has great significance for the actual simulation operation of the whole substation system at the same time. The 500 KV substation analog simulation training system improves the fidelity of the training environment, improves the training effect, and is suitable for the field of analog simulation training of various electric networks or substations.

Description

A kind of 500 kv substation analog simulation training systems
Technical field
The present invention relates to a kind of equipment or method field that is specially adapted for the digital computation or the data processing of application-specific, more specifically a kind ofly use a computer auxiliaryly, belong to administration of power networks training facilities technical field substation analog simulation training system for relating to.
Background technology
Interior existing substation simulation training system product in the market has only the full three-dimensional artificial of transforming plant primary equipment and this two class of integrated automation of transformation stations background monitoring system emulation.
Wherein the full three-dimensional artificial of primary equipment can only be maked an inspection tour, check, operate the primary equipment in the virtual scene, can not realistic simulation and only can carry out front panel equipment simulating emulation and secondary device panel physical location and screen back equipment to secondary device, sense true to nature is not strong; And the emulation of integrated automation of transformation stations background monitoring system does not have analogue simulation for automation equipment such as automation equipment such as front end processor, measurement and control unit in the transformer station, lacks the fidelity of Training Environment, and result of training is very poor.
Therefore now need a kind of can be to the emulation of substation secondary device and integrated automation of transformation stations background monitoring system, and can to its carry out picket surveillance operation can be to fidelity with the enhancement training environment, the full three-dimensional artificial simulation system of enhancement training effect.
Summary of the invention
In order to address the above problem, the invention provides a kind of 500 kv substation analog simulation training systems, it specifies as follows:
A kind of 500 kv substation analog simulation training systems comprise main control teacher machine, student's terminating machine and storage server, it is characterized in that: described main control teacher machine connects student's terminating machine, and the two all connects storage server.Server is responsible for the storage emulation module, and the backup management historical data is included the examination question teaching notes, functions such as test item bank and file of cadt and operation note.
According to 500 kv substation analog simulation training systems of the present invention, it is characterized in that: described main control teacher machine may command student terminating machine.Main control teacher machine is used to edit study course, examination question is set, can and use various training projects by network download, monitor the state and the authority of giving its corresponding training project of each student's machine simultaneously, main is whole analog simulation training system to be detected safeguard and data management.
According to 500 kv substation analog simulation training systems of the present invention, it is characterized in that: described student's machine quantity is 20~40 or more according to the capacity of storage server.Student's machine provides man-machine interactive interface.
According to 500 kv substation analog simulation training systems of the present invention, it is characterized in that: described analog simulation training system can be based upon on Windows2000, the Window XP operating system platform.Be applicable on the at present popular various operating platforms, make things convenient for Installation and Debugging.
Description of drawings
Fig. 1 is the whole interface of 500 a kv substation analog simulation training systems of the present invention synoptic diagram
Concrete enforcement
Below in conjunction with drawings and Examples 500 kv substation analog simulation training systems of the present invention are described further:
Embodiment 1: the full three-dimensional artificial of secondary device
It is a kind of function in the 500 kv substation analog simulation training systems of the present invention that substation secondary device carries out full three-dimensional artificial; interactive substation secondary protection equipment, automation equipment scene simulation technology have been adopted based on OPENGL (the open graphic package interface of Open Graphics Library) technology; with the fidelity of enhancement training environment, the enhancement training effect.
500 kv substation analog simulation training systems of the present invention are in the simulation process of transformer station, virtual instrument technique and component technology have been adopted in secondary device emulation to transformer station, completely three-dimensional various secondary devices are generated separately virtual unit respectively according to separately physical characteristics, utilize component technology that the virtual unit that generates is packaged into the device emulation assembly then, utilize the device emulation assembly to build the emulation main control room as " playing with building blocks ".
By adopting technique scheme, substation secondary device has been carried out full three-dimensional artificial, its secondary device panel position is consistent with true bearing and screen is preceding, screen back equipment also can be simulated, and not only can make an inspection tour, check the secondary device in the virtual scene, and can operate.Improved the fidelity of Training Environment, made result of training better than in the past.
Embodiment 2: the full three-dimensional artificial of automation equipment
The full three-dimensional artificial of automation of transformation substations equipment is the 3rd function in the 500 kv substation analog simulation training systems of the present invention.In the domestic existing substation simulation training system product report emulation of integrated automation of transformation stations background monitoring system is only arranged, and automation equipment such as automation equipment such as front end processor, measurement and control unit in the transformer station is not had analogue simulation, 500 kv substation analog simulation training systems of the present invention have for this reason been done full three-dimensional artificial to the automation equipment of whole transformer station and have been carried out full three-dimensional artificial, with the fidelity of enhancement training environment, the enhancement training effect.
Owing to adopted interactive automation of transformation substations device context emulation technology based on OPENGL (the open graphic package interface of Open Graphics Library) technology.In substation simulation software, virtual instrument technique and component technology have been adopted in automation equipment emulation to transformer station, various automation equipments are generated separately virtual unit respectively according to separately physical characteristics, utilize component technology that the virtual unit that generates is packaged into the device emulation assembly then, utilize the device emulation assembly to build the emulation automation equipment as " playing with building blocks ".
By adopting technique scheme, 500 kv substation automation equipments have been carried out full three-dimensional artificial, make and to carry out the emulation of comprehensive automation background monitoring system, also can be before and the screen consistent with true bearing to its robotization panel position, screen back equipment also can simulate, not only can make an inspection tour, check, and can operate the automation equipment in the virtual scene.Improved the fidelity of Training Environment, made result of training better than in the past.
Embodiment 3: the emulation of micro_computer five_proof surveillance
Transformer station's micro_computer five_proof surveillance emulation is the 3rd function in the 500 kv substation analog simulation training systems of the present invention.Primary equipment simulation operations five-defence block imperfection in the domestic existing substation simulation training system product report, different with the five-defence block mode that use at the scene, can not supervise the automatic contraposition of system with the robotization backstage as five-preventing system, can not carry out the simulated operation preview, simulated operation can not be previewed step is transferred in the Electrical key, the order of operation and the mode of operation function of restriction primary equipment can not be free be thrown five anti-devices and are moved back etc.500 kv substation analog simulation training systems of the present invention for this reason carry out simulating developer to transformer station's micro_computer five_proof surveillance, the micro_computer five_proof surveillance function of using in the present electric network synthetic automating power substation is simulated, with the fidelity of enhancement training environment, the enhancement training effect.
" five anti-" computer anti-misoperation and lockout simulation system is according to actual " five is anti-" apparatus function, based on the system development of Simulation Substation human-computer interaction interface.Form by analogue simulation dish, artificial electronic lock, artificial electronic key etc.Have to throw and move back blocking device, the contraposition of mimic panel element, the simulated operation preview is write down automatically and is shown the preview content, to simulated field primary equipment transmit operation ticket, functions such as the order of operation of restriction primary equipment and mode of operation.
Each function is described in detail as follows:
(1) system of moving back is thrown in the emulation of micro_computer five_proof surveillance.
By the switching controls of man-machine interface, can realize the input of anti-error system and withdraw from.Under anti-error system input state, must carry out simulated operation in strict accordance with the anti-error rule of " five is anti-", and functions such as the order of operation of primary equipment and mode of operation. When anti-error system withdraws from, just can arbitrarily carry out the operation of simulated operation and primary equipment, this moment as generation maloperation; to produce consequence; relevant protection, switch will move, and under this state, use when desiring to know the maloperation consequence when generally being used for training and examination or during the Student Training.
(2) micro_computer five_proof surveillance analogue simulation operation.
By starting the analog functuion on the mimic panel, can realize the element on the mimic panel, automatic contraposition with on-the-spot primary equipment state, if once the physical location of equipment takes place inconsistent with the position of the analog element on the mimic panel, on the liquid crystal indication of mimic panel, point out out the title of each inconsistent equipment in position successively, revise the state of element on the mimic panel for the operator.Contraposition can be carried out the simulated operation on the mimic panel after finishing.
(3) contraposition is forced in the emulation of micro_computer five_proof surveillance.
Confirming can to use pressure to bit function under the situation of physical location with the position consistency of the analog element on the mimic panel of primary equipment, above omitting to bit function, to save time, like this, can carry out the simulated operation on the mimic panel immediately.
(4) emulation of micro_computer five_proof surveillance shows preview.
Start display simulation operation note function, can when carrying out simulated operation, see equipment and the mode of operation operated.Can close this window, cancellation shows; Also can when carrying out the primary equipment operation, provide contrast and reference.
(5) the automatic record of micro_computer five_proof surveillance emulation.
When mimic panel was operated, system got off operation process recording automatically.
(6) micro_computer five_proof surveillance emulation transmit operation ticket.
Finish at simulated operation, through confirm errorless after, by starting the transmit operation ticket function, the primary system operation order that generates is sent on the once on-the-spot five-defence block device, form a virtual artificial electronic key simultaneously, there is the identical operations ticket the inside.
(7) micro_computer five_proof surveillance emulation blocking function.
After operation order sends end, just can carry out the operation of primary equipment.Operation must be carried out release and operation in strict accordance with the order of simulated operation.If go to the wrong way at interval, perhaps draw wrong disconnecting link etc., block sytem can successfully realize anti-misoperation locking, and provides the correct prompting that should operate.
By adopting technique scheme, the on-the-spot micro_computer five_proof function of using of analog synthesis automating power substation has improved the fidelity of Training Environment, makes result of training better than in the past.
Three embodiment in sum, 500 kv substation analog simulation training systems of the present invention have been described fully owing to adopted the 3-D technology of OPENGL (the open graphic package interface of Open Graphics Library), has bigger improvement directly perceived than the various electrical networks of existing two-dimensional planar technique or the analog simulation training system of transformer station, more since secondary device panel position consistent with true bearing and shield before, screen back equipment also can be simulated, not only can make an inspection tour the secondary device in the virtual scene, check, and can operate, more can be to automation equipment in the transformer station such as front end processor, automation equipments such as measurement and control unit do not have analogue simulation, and the micro_computer five_proof surveillance emulation of She Zhiing simultaneously has great significance to the artificial actual operation of whole transformer substation system.
500 kv substation analog simulation training systems of the present invention have improved the fidelity of Training Environment, make result of training better than in the past, are applicable to various electrical networks or or the analog simulation training field of transformer station.

Claims (4)

1. a kv substation analog simulation training system comprises main control teacher machine, student's terminating machine and storage server, it is characterized in that: described main control teacher machine connects student's terminating machine, and the two all connects storage server.
2. a kind of 500 kv substation analog simulation training systems as claimed in claim 1 is characterized in that: described main control teacher machine can connect control student terminating machine.
3. a kind of 500 kv substation analog simulation training systems as claimed in claim 1 is characterized in that: described student's machine quantity is 20~40 or more according to the capacity of storage server.
4. a kind of 500 kv substation analog simulation training systems as claimed in claim 1, described analog simulation training system can be based upon on Windows2000, the Window XP operating system platform.
CN200810039853A 2008-06-30 2008-06-30 500 KV substation analog simulation training system Pending CN101620800A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200810039853A CN101620800A (en) 2008-06-30 2008-06-30 500 KV substation analog simulation training system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200810039853A CN101620800A (en) 2008-06-30 2008-06-30 500 KV substation analog simulation training system

Publications (1)

Publication Number Publication Date
CN101620800A true CN101620800A (en) 2010-01-06

Family

ID=41514014

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200810039853A Pending CN101620800A (en) 2008-06-30 2008-06-30 500 KV substation analog simulation training system

Country Status (1)

Country Link
CN (1) CN101620800A (en)

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101866564A (en) * 2010-05-28 2010-10-20 国网电力科学研究院武汉南瑞有限责任公司 Live working table type simulation training system and method
CN101894488A (en) * 2009-07-15 2010-11-24 上海市电力公司超高压输变电公司 Distributed three-dimensional simulation training system for regional power system transformer station
CN102054386A (en) * 2011-01-07 2011-05-11 广东电网公司电力科学研究院 Transformer station simulation training system based on mixed digital/analogy simulation technology
CN102163382A (en) * 2011-04-29 2011-08-24 国网电力科学研究院武汉南瑞有限责任公司 Live working helmet type simulation training system and method
CN102540001A (en) * 2012-02-16 2012-07-04 云南电网公司 Method of checking alternating current loop of a 500kV transformer substation through carrying out simulated through-type three-phase short circuit
CN102571385A (en) * 2010-12-17 2012-07-11 沈阳易讯科技股份有限公司 Safety management system for communication transmission network
CN102568270A (en) * 2010-12-31 2012-07-11 上海久隆信息工程有限公司 Method for performing pre-control treatment on dangerous point of transformer substation by utilizing three-dimensional simulation technique
CN102800224A (en) * 2012-07-20 2012-11-28 广州供电局有限公司 Simulation method for experimental training on electric power equipment test based on the Internet
CN102819971A (en) * 2012-07-20 2012-12-12 广州供电局有限公司 Test experiment training simulation method of power equipment based on internet
CN102945629A (en) * 2012-11-28 2013-02-27 广东电网公司电力科学研究院 Generating method and system of three-dimensional simulation training case of power grid substation
CN104331570A (en) * 2014-11-14 2015-02-04 国家电网公司 System and method for simulating power transformation equipment for inspection
CN104466761A (en) * 2014-10-21 2015-03-25 深圳供电局有限公司 Transformer substation temporary wiring anti-misoperation locking system, detection method and computer key
CN107978194A (en) * 2017-12-27 2018-05-01 国网山东省电力公司潍坊供电公司 The special policer operation training device of electric power system
CN107993509A (en) * 2017-12-27 2018-05-04 国网山东省电力公司潍坊供电公司 Electric system regulates and controls skills training all-in-one machine
CN108269450A (en) * 2018-02-02 2018-07-10 上海九洲信息技术有限公司 The method and system of substation inspection training are realized based on virtual reality technology
CN109242439A (en) * 2018-09-21 2019-01-18 国家电网有限公司 Feature extraction recognition methods based on substation equipment associated data
CN111091609A (en) * 2019-12-11 2020-05-01 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
于家河等: "《广东500kV变电站与电网仿真系统设计》", 《中国电力教育》 *
彭词: "《天津500kv变电仿真培训系统的研制和应用》", 《天津电力技术》 *

Cited By (25)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101894488A (en) * 2009-07-15 2010-11-24 上海市电力公司超高压输变电公司 Distributed three-dimensional simulation training system for regional power system transformer station
CN101866564A (en) * 2010-05-28 2010-10-20 国网电力科学研究院武汉南瑞有限责任公司 Live working table type simulation training system and method
CN101866564B (en) * 2010-05-28 2011-12-28 国网电力科学研究院武汉南瑞有限责任公司 Live working table type simulation training system and method
CN102571385A (en) * 2010-12-17 2012-07-11 沈阳易讯科技股份有限公司 Safety management system for communication transmission network
CN102568270A (en) * 2010-12-31 2012-07-11 上海久隆信息工程有限公司 Method for performing pre-control treatment on dangerous point of transformer substation by utilizing three-dimensional simulation technique
CN102054386A (en) * 2011-01-07 2011-05-11 广东电网公司电力科学研究院 Transformer station simulation training system based on mixed digital/analogy simulation technology
CN102054386B (en) * 2011-01-07 2013-07-17 广东电网公司电力科学研究院 Transformer station simulation training system based on mixed digital/analogy simulation technology
CN102163382B (en) * 2011-04-29 2013-07-31 国网电力科学研究院武汉南瑞有限责任公司 Live working helmet type simulation training system and method
CN102163382A (en) * 2011-04-29 2011-08-24 国网电力科学研究院武汉南瑞有限责任公司 Live working helmet type simulation training system and method
CN102540001A (en) * 2012-02-16 2012-07-04 云南电网公司 Method of checking alternating current loop of a 500kV transformer substation through carrying out simulated through-type three-phase short circuit
CN102540001B (en) * 2012-02-16 2014-09-24 云南电网公司 Method of checking alternating current loop of a 500kV transformer substation through carrying out simulated through-type three-phase short circuit
CN102800224A (en) * 2012-07-20 2012-11-28 广州供电局有限公司 Simulation method for experimental training on electric power equipment test based on the Internet
CN102819971A (en) * 2012-07-20 2012-12-12 广州供电局有限公司 Test experiment training simulation method of power equipment based on internet
CN102800224B (en) * 2012-07-20 2015-05-13 广州供电局有限公司 Simulation method for experimental training on electric power equipment test based on the Internet
CN102945629A (en) * 2012-11-28 2013-02-27 广东电网公司电力科学研究院 Generating method and system of three-dimensional simulation training case of power grid substation
CN102945629B (en) * 2012-11-28 2014-09-17 广东电网公司电力科学研究院 Generating method and system of three-dimensional simulation training case of power grid substation
CN104466761A (en) * 2014-10-21 2015-03-25 深圳供电局有限公司 Transformer substation temporary wiring anti-misoperation locking system, detection method and computer key
CN104331570A (en) * 2014-11-14 2015-02-04 国家电网公司 System and method for simulating power transformation equipment for inspection
CN107978194A (en) * 2017-12-27 2018-05-01 国网山东省电力公司潍坊供电公司 The special policer operation training device of electric power system
CN107993509A (en) * 2017-12-27 2018-05-04 国网山东省电力公司潍坊供电公司 Electric system regulates and controls skills training all-in-one machine
CN108269450A (en) * 2018-02-02 2018-07-10 上海九洲信息技术有限公司 The method and system of substation inspection training are realized based on virtual reality technology
CN109242439A (en) * 2018-09-21 2019-01-18 国家电网有限公司 Feature extraction recognition methods based on substation equipment associated data
CN109242439B (en) * 2018-09-21 2021-10-26 国家电网有限公司 Feature extraction and identification method based on associated data of substation equipment
CN111091609A (en) * 2019-12-11 2020-05-01 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling
CN111091609B (en) * 2019-12-11 2023-09-19 云南电网有限责任公司保山供电局 Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling

Similar Documents

Publication Publication Date Title
CN101620800A (en) 500 KV substation analog simulation training system
CN109855651B (en) Ground test system and test method for modern aircraft radio communication navigation system
CN1982863B (en) Universal micro-satellite comprehensive testing platform based on PXI system
CN108345709A (en) Safety measure demonstration simulation display method and device for transformer substation current loop operation
CN106775746A (en) A kind of intelligent substation three-dimensional artificial training soft ware system and its platform building method
CN102568270B (en) Method for performing pre-control treatment on dangerous point of transformer substation by utilizing three-dimensional simulation technique
CN106355971A (en) Simulating training system for overhauling substation equipment
CN104166892A (en) Engineering management and control method and system based on three-dimensional design system
CN102054377A (en) Remote simulation training system for electrical tests of transformer
CN109697903A (en) A kind of substation relay protection safety practical training method based on VR
CN101158847B (en) Electric power substation software emulation platform building method and no power off upgrading improved method
CN105067933A (en) Universal system for electronic equipment testability validation and evaluation and testing method
CN104181908B (en) A kind of DFDAU test platform and method of testing
CN103559822A (en) Substation simulation training system
CN103177642A (en) Method for improving reality of power grid dispatcher training simulation system
CN204291050U (en) A kind of dispatching and monitoring information check system
CN104007978A (en) Intelligent substation secondary equipment logic emulation system
CN110189568A (en) A kind of substation simulation system and method based on virtual reality technology
CN107819647A (en) Intelligent substation station level network tester
CN106779508A (en) Secondary system of intelligent substation safety measure analogue simulation and O&M control platform
CN106681313A (en) Function testing method of dynamic stability control system and dynamic stability control system
CN104142451A (en) Method and system for achieving checking simulation of secondary circuit simulated failure in electric system
CN116580610A (en) Virtual transformer station operation and maintenance VR training and real training system
CN111665805A (en) Control system training device and method based on 3D technology
CN105847076A (en) Signal testing system, method and device for substation control level equipment of transformer substation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: SHANGHAI ELECTRIC POWER CORP.

Free format text: FORMER OWNER: SHANGHAI ULTRA-HV TRANSMISSION + DISTRIBUTION COMPANY, SHANGHAI ELECTRIC POWER C

Effective date: 20111114

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 200063 PUTUO, SHANGHAI TO: 200122 PUDONG NEW AREA, SHANGHAI

TA01 Transfer of patent application right

Effective date of registration: 20111114

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Co-applicant after: Beijing Kedong Power Control System Co., Ltd.

Address before: 200063 No. 600, Wuning Road, Shanghai, Putuo District

Applicant before: Shanghai Ultra-HV Transmission & Distribution Company, Shanghai Electric Power C

Co-applicant before: Beijing Kedong Power Control System Co., Ltd.

ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP. BEIJING KEDONG POWER CONT

Free format text: FORMER OWNER: BEIJING KEDONG POWER CONTROL SYSTEM CO., LTD.

Effective date: 20121019

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20121019

Address after: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant after: Shanghai Electric Power Corporation

Applicant after: State Grid Corporation of China

Applicant after: Beijing Kedong Power Control System Co., Ltd.

Address before: 200122 Shanghai City, Pudong New Area source deep road, No. 1122

Applicant before: Shanghai Electric Power Corporation

Applicant before: Beijing Kedong Power Control System Co., Ltd.

C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20100106