CN105421470A - Construction method for assembled type anchor rod and arch framework combined type ecological slope protection - Google Patents

Construction method for assembled type anchor rod and arch framework combined type ecological slope protection Download PDF

Info

Publication number
CN105421470A
CN105421470A CN201510794517.7A CN201510794517A CN105421470A CN 105421470 A CN105421470 A CN 105421470A CN 201510794517 A CN201510794517 A CN 201510794517A CN 105421470 A CN105421470 A CN 105421470A
Authority
CN
China
Prior art keywords
prefabricated
anchor pole
arch
arched framework
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510794517.7A
Other languages
Chinese (zh)
Other versions
CN105421470B (en
Inventor
胡彪
黄赞旭
胡仲强
涂文军
张文华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangxi Shuangde Building Engineering Co Ltd
Original Assignee
Jiangxi Shuangde Building Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangxi Shuangde Building Engineering Co Ltd filed Critical Jiangxi Shuangde Building Engineering Co Ltd
Priority to CN201510794517.7A priority Critical patent/CN105421470B/en
Publication of CN105421470A publication Critical patent/CN105421470A/en
Application granted granted Critical
Publication of CN105421470B publication Critical patent/CN105421470B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • E02D17/202Securing of slopes or inclines with flexible securing means
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/20Restraining of underground water by damming or interrupting the passage of underground water by displacing the water, e.g. by compressed air
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Revetment (AREA)

Abstract

The invention relates to a construction method for assembled type anchor rod and arch framework combined type ecological slope protection. The method mainly comprises the following steps of construction of anchor rods, excavation of a foundation trench, installation of an arch framework, pouring of connecting bands, tensioning of the anchor rods and transplanting of glass blankets. The construction method has the following characteristics and the beneficial effects that arch rings and arch columns of the arch framework are prefabricated, anchor rod holes and connection ribs are reserved on the prefabricated arch columns and arch rings, the prefabricated arch columns and the prefabricated connection ribs of the prefabricated arch rings are welded together and provided with the anchor rods, concrete is poured into the connecting bands, and therefore the integrity and stability of the arch framework are ensured, field assembly of the arch framework and the anchor rods is also achieved, stability is high, and the construction efficiency is high. A built-in type three-dimensional road foundation drainage system is formed, and the drainage effect is good. The ecological glass blankets are arranged on the bare soil parts in the arch rings and pressed firmly through outwards protruding structures of the arch framework, so that protection of the ecological environment and conservation of water and soil are facilitated.

Description

Assembling anchor pole arched framework combined type ecological revetment construction method
Technical field
The present invention relates to a kind of combined type ecological revetment construction method, particularly relate to assembling anchor pole arched framework combined type ecological revetment construction method.
Technical background
Under the fast development of China's communication, high-fill roadbed Quantity constantly increases.Due to the particularity of high-fill roadbed self, roadbed is easy to the situation occurring landslide, causes great impact to the safety traffic of vehicle.Therefore, high earth roadbed side slope protection is had higher requirement.
Traditional bank protecting method is generally main building materials with hard materials such as cement, building stones, concrete, goes to think deeply stability of slope in design with the angle of mechanics.Traditional bank protection is broadly divided into shallow-layer protection class bank protection, stone-laying class bank protection, sash bank protection, facing wall bank protection and the mixed class bank protection of spray.There is a lot of shortcoming in traditional bank protecting method; as: high-fill roadbed difficulty of construction is large; engineering time is long; safety and stability is difficult to ensure; high slope prop up gear protection and drainage unsound, easily there are the quality problems such as distortion, depression in tall earth fill bank protection, and one-time investment is large; be difficult to recover natural vegetation, be unfavorable for protection and the water and soil conservation of ecological environment.Comparatively dull in appearance stiff, in most cases inharmonious with the view of periphery, disagree with the development trend focusing on preserving the ecological environment at present.Although traditional anchor pole arched framework bank protection is conducive to improving the safety factor of soil layer and strengthening the stability of rock slope, this technology greatly alleviate works deadweight, save engineering material and guarantee the safety of engineering and stable, absorb again simultaneously mortar flag stone (concrete block) skeleton plant grass and protect handsome in appearance, be convenient to the advantage of afforesting, but traditional arched framework bank protection is all cast-in-place, drainage system is also unsound, for high-fill roadbed difficulty of construction, the easy impeded drainage of bank protection and cause bank protection unstability.
Given this, need a kind of easy construction of invention at present badly, stability is strong, shortens the engineering time, can realize the assembling anchor pole arched framework combined type ecological revetment construction method of anchor pole and arched framework site assembly and built-in three-dimensional drainage system.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, stability is strong, shortens the engineering time, can realize anchor pole and arched framework site assembly, and arched framework inside arranges the assembling anchor pole arched framework combined type ecological revetment construction method of the features such as drainage system.
For achieving the above object, present invention employs following technical scheme:
This assembling anchor pole arched framework combined type ecological revetment construction method, mainly comprises the following steps:
1) anchor bolt construction: adopt anhydrous dry drill method to be drilled with bolthole at side slope of embankment assigned address, after scaffold building is good, machinery according to the position, hole of reserving in advance, holed by bottom carrying out by rows, play what a boring, before laying anchor pole, with material, aperture must be blocked.When rig is holed, drilling rod perpendicular to side slope face, must be squeezed in embankment by drilling direction uniform speed slow.After bolthole is drilled to type, carry out hole clearly.Arrange anchor pole positioning bar at the assigned address of anchor pole, to ensure that anchor pole is fixed on position, hole central authorities, anchor pole inserts in bolthole with artificial after making by anchor pole, then carries out bolthole slip casting.
2) foundation trench excavation: arch form skeleton foundation trench adopts the method for hand excavation, should note the accurate of physical dimension position during foundation trench excavation, every 2 ~ 3m excavation together anti-skidding step in vertical skeleton foundation trench.For the excavation of arch ring circular arc portion foundation trench, the instrument of selection of small is answered to carry out excavating to ensure that arch section is natural, level and smooth.
3) arched framework is installed: arrange pin wall after sough excavates, then prefabricated counterfort and the installation of prefabricated arch ring is carried out, prefabricated counterfort A and prefabricated arch ring A is temporarily fixed in the arched framework foundation trench dug in advance, then prefabricated counterfort A is welded with the main muscle of reserved arched framework of prefabricated arch ring A, utilize branch sleeve built-in PVC drain pipe to be linked together, anchor pole is linked together by anchor pole positioning bar and the main muscle of arched framework; L-type pvc pipe exposed parts arranges anti-blocking filter screen; The reserved thin PVC drain pipe outer wall of bank protection top prefabricated counterfort B is coated with one deck marine glue, and be then inserted in the inner PVC drain pipe of prefabricated arch ring B, top prefabricated counterfort B and prefabricated arch ring A is connected and fixed by screw rod faulting of slab ends.
4) connecting band construction: the anchor pole positioning bar of anchor pole welds then to concreting in the reserved bolthole of prefabricated arched framework by the part for reserved bolthole with the main muscle of arched framework, template is installed, then concreting for prefabricated counterfort A and prefabricated arch ring A junction.
5) anchor pole stretch-draw: after anchor pole stretch-draw, with ground tackle, anchor pole is fixed.
6) careless blanket is transplanted: utilize arched framework by embedding for careless blanket pressure and coordinate wooden peg by firm for careless blanket.
The present invention has following feature and beneficial effect:
(1) arch ring of arched framework and counterfort are prefabricated in advance, prefabricated counterfort and arch ring reserve bolthole and reserved dowel, the reserved dowel of prefabricated counterfort and prefabricated arch ring welds together and arranges anchor pole, connecting band concreting both ensure that globality and the stability of arched framework, realize again the site assembly of arched framework and anchor pole, stability is strong, and efficiency of construction is high.
(2) the inner pre-buried gutter of arched framework, gutter is connected and fixed by locating steel ring and positioning bar and the main muscle of arched framework, the reserved drainpipe of prefabricated counterfort and arch ring is linked together by branch sleeve, and form built-in three-dimensional subgrade drainage system, drainage effect is good.
(3) in arch ring, soil body exposed part arranges ecological grass mat, and ecological grass mat is pressed solidly by the outer male structure of arched framework, is conducive to protection and the water and soil conservation of ecological environment.
Accompanying drawing explanation
Fig. 1 is assembling anchor pole arched framework combined type ecological revetment schematic diagram of the present invention;
Fig. 2 is assembling anchor pole arched framework combined type ecological revetment detail side elevation;
Fig. 3 is delay-pour joint band detail side elevation;
Fig. 4 is that faulting of slab ends connects and anchor pole detail side elevation;
Fig. 5 is arched framework inner PVC drain pipe location detail drawing;
Fig. 6 is that arched framework presses solidly ecological grass mat detail drawing;
The main muscle of Fig. 7 delay-pour joint band arched framework, PVC drain pipe, anchor pole connect detail drawing;
The anchor pole that Fig. 8 reserves in bolthole is connected detail drawing with the main muscle of arched framework;
Fig. 9 is construction flow chart of the present invention;
In figure: 1. pin wall; 2. gutter; 3. prefabricated counterfort A; 4. prefabricated arch ring A; 5. anchor pole; 6. reserved bolthole; 7.PVC gutter; 8. branch sleeve; 9.L type PVC drain pipe; 10. sleeve pipe three-dimensional joint; 11. screw rods; 12. delay-pour joint bands; 13. careless blankets; 14. deformation joints; 15. curbs; 16. reserved screw holes; 17. boltholes; 18. road structures; 19. embankments; 20. anchor pole positioning bars; The main muscle of 21. arched framework; The thin gutter of 22.PVC; 23. location steel rings; 24. spacer barss; 25. externally drained grooves; 26. filter screens; 27. wooden pegs; 28. mark time; 29. prefabricated counterfort B; 30. prefabricated arch ring B.
Detailed description of the invention
Fig. 1 is assembling anchor pole arched framework combined type ecological revetment schematic diagram of the present invention.With reference to shown in Fig. 1, high-fill roadbed assembling anchor pole arched framework combined type ecological revetment of the present invention mainly comprises: prefabricated counterfort A3, prefabricated counterfort B29, prefabricated arch ring A4, prefabricated arch ring B30, anchor pole 5, reserved bolthole 6, PVC drain pipe 7, branch sleeve 8, L-type PVC drain pipe 9, sleeve pipe three joints 10, careless blanket 13, screw rod 11.
First hole at side slope assigned address according to designing requirement, carry out anchor pole 5 to construct, then roadbed fluting, prefabricated counterfort A3 and prefabricated arch ring A4 is installed, carry out the main muscle 21 of reserved arched framework at delay-pour joint band 12 place, reserved PVC drain pipe 7 connects and concreting, again stretch-draw is carried out to anchor pole 5, finally by arched framework, careless blanket 13 is pressed solidly.
With reference to shown in Fig. 1, prefabricated arch ring A4 centre position arranges anchor pole 5, and prefabricated counterfort A3 two ends arrange anchor pole 5; Prefabricated counterfort and prefabricated arch ring are divided into two kinds of connection types: the built-in PVC drain pipe 7 in delay-pour joint band 12 place is connected by branch sleeve, and prefabricated counterfort B29 and prefabricated arch ring B30 is connected and fixed by screw rod 11 faulting of slab ends.
With reference to shown in Fig. 2, the superiors prefabricated counterfort B29 and prefabricated arch ring B30 is connected and fixed by screw rod 11; All the other prefabricated counterforts 3 are together with prefabricated arch ring A4 and anchor pole 5 monobloc cast; Gutter 2 is led in built-in gutter 7 bottom.
With reference to shown in Fig. 3 and Fig. 7, the arched framework reserving rib 21 at delay-pour joint band 12 place welds together; Built-in gutter 7 is linked together by branch sleeve 8; Anchor pole 5 is positioned in bolthole 17 by positioning bar 20; Anchor pole 5 is welded together by positioning bar 20 and arched framework reserving rib 21.
With reference to shown in Fig. 4, the superiors prefabricated counterfort B29 reserves the thin gutter of built-in PVC 22 and interts in the built-in PVC drain pipe 7 of prefabricated arch ring A4, prefabricated counterfort B29 and prefabricated arch ring B30 faulting of slab ends is linked together by screw rod 11.
With reference to shown in Fig. 5, built-in PVC drain pipe 7 is welded together with positioning bar 24 and the main muscle 21 of arched framework by location steel ring 23.
With reference to shown in Fig. 6, prefabricated counterfort is by embedding for ecological grass mat 13 pressure and coordinate wooden peg 27 to fix.
As shown in Figure 9, the construction method of assembling anchor pole arched framework combined type ecological revetment, mainly comprises the following steps:
1) anchor bolt construction: adopt anhydrous dry drill method to be drilled with bolthole 17 at side slope of embankment assigned address, after scaffold building is good, machinery according to the position, hole of reserving in advance, holed by bottom carrying out by rows, play what a boring, before laying anchor pole, with material, aperture must be blocked.When rig is holed, drilling rod perpendicular to side slope face, must be squeezed in embankment by drilling direction uniform speed slow.After bolthole is drilled to type, carry out hole clearly.Arrange anchor pole positioning bar 20 at the assigned address of anchor pole, to ensure that anchor pole 5 is fixed on bolthole 17 central authorities, anchor pole 5 inserts in bolthole 17 with artificial after making by anchor pole 5, then carries out bolthole 17 slip casting.
2) roadway excavation: arch form skeleton foundation trench adopts the method for hand excavation, should note the accurate of physical dimension position during foundation trench excavation, every 2 ~ 3m excavation together anti-skidding step in vertical skeleton foundation trench.For the excavation of arch ring circular arc portion foundation trench, the instrument of selection of small is answered to carry out excavating to ensure that arch section is natural, level and smooth.
3) arched framework is installed: arrange pin wall 1 after sough excavates, then prefabricated counterfort A3 is carried out and prefabricated arch ring A4 installs, prefabricated counterfort A3 and prefabricated arch ring A4 is temporarily fixed in the arched framework foundation trench dug in advance, then prefabricated counterfort A3 is welded with the main muscle 21 of the reserved arched framework of prefabricated arch ring A4, utilize branch sleeve 8 built-in PVC drain pipe 7 to be linked together, anchor pole 5 is linked together by anchor pole positioning bar 20 and the main muscle 21 of arched framework; L-type PVC drain pipe 9 exposed parts arranges anti-blocking filter screen 26; Reserved PVC thin gutter 22 outer wall of bank protection top prefabricated counterfort B29 is coated with one deck marine glue, and be then inserted in the thick PVC drain pipe 7 of prefabricated arch ring B30 inside setting, top prefabricated counterfort B29 and prefabricated arch ring B30 is connected and fixed by screw rod 11 faulting of slab ends.
4) connecting band is built: for the part of reserved bolthole 6, the spacer bars 24 of anchor pole 5 is welded with the main muscle of arched framework 21 then to concreting in the reserved bolthole 6 of prefabricated arched framework, template is installed, then concreting for prefabricated counterfort A3 and prefabricated arch ring A4 junction.
5) anchor pole stretch-draw: after anchor pole 5 stretch-draw, with ground tackle, anchor pole 5 is fixed.
6) careless blanket is transplanted: utilize arched framework by the embedding pressure of careless blanket 13 and coordinate wooden peg 27 to fix.

Claims (1)

1. assembling anchor pole arched framework combined type ecological revetment construction method, is characterized in that, mainly comprise the following steps:
1) anchor bolt construction: adopt anhydrous dry drill method to be drilled with bolthole (17) at side slope of embankment assigned address, after scaffold building is good, machinery according to the position, hole of reserving in advance, holed by bottom carrying out by rows, play what a boring, laying, anchor pole (5) is front, with material, aperture must be blocked; When rig is holed, drilling rod must, perpendicular to side slope face, be squeezed in embankment by drilling direction uniform speed slow; After bolthole (17) is drilled to type, carry out hole clearly; At the assigned address of anchor pole (5), anchor pole positioning bar (20) is set, to ensure that anchor pole (5) is fixed on bolthole (17) central authorities, after anchor pole (5) is made, anchor pole (5) is inserted in bolthole (17), then carries out bolthole (17) slip casting;
2) foundation trench excavation: arch form skeleton foundation trench excavates, every 2 ~ 3m excavation together anti-skidding step in vertical skeleton foundation trench;
3) arched framework is installed: arrange pin wall (1) after sough excavates, then prefabricated counterfort A (3) and prefabricated arch ring A (4) installation is carried out, prefabricated counterfort A (3) and prefabricated arch ring A (4) are temporarily fixed in the arched framework foundation trench dug in advance, then the reserved arched framework main muscle (21) of prefabricated counterfort A (3) with prefabricated arch ring A (4) is welded, branch sleeve (8) is utilized built-in PVC drain pipe (7) to be linked together, anchor pole (5) is linked together by anchor pole positioning bar (20) and the main muscle of arched framework (21), L-type PVC drain pipe (9) exposed parts arranges anti-blocking filter screen (26), the thin gutter of reserved PVC (22) outer wall at bank protection top prefabricated counterfort B (29) is coated with one deck marine glue, then be inserted in the PVC drain pipe (7) of prefabricated arch ring B (30) inside setting, top prefabricated counterfort A (3) and prefabricated arch ring A (4) are connected and fixed by screw rod (11) faulting of slab ends,
4) connecting band is built: welded by the spacer bars (24) of anchor pole (5) then to reserved bolthole (6) the interior concreting of prefabricated arched framework with the main muscle of arched framework (21), template is installed, then concreting for prefabricated counterfort A (3) and prefabricated arch ring A (4) junction;
5) anchor pole stretch-draw: after anchor pole (5) stretch-draw, fixes anchor pole (5) with ground tackle;
6) careless blanket is transplanted: utilize the main muscle of arched framework (21) by careless blanket (13) embedding pressure and coordinate wooden peg (27) that careless blanket (13) is firm.
CN201510794517.7A 2015-11-18 2015-11-18 Assembled anchor pole arched framework combined type ecological revetment construction method Active CN105421470B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510794517.7A CN105421470B (en) 2015-11-18 2015-11-18 Assembled anchor pole arched framework combined type ecological revetment construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510794517.7A CN105421470B (en) 2015-11-18 2015-11-18 Assembled anchor pole arched framework combined type ecological revetment construction method

Publications (2)

Publication Number Publication Date
CN105421470A true CN105421470A (en) 2016-03-23
CN105421470B CN105421470B (en) 2017-09-08

Family

ID=55499981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510794517.7A Active CN105421470B (en) 2015-11-18 2015-11-18 Assembled anchor pole arched framework combined type ecological revetment construction method

Country Status (1)

Country Link
CN (1) CN105421470B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649093A (en) * 2016-04-05 2016-06-08 山东净金新能源有限公司 Arch fixing rack for highway/railway tunnel and manufacturing method of arch fixing rack
CN105839651A (en) * 2016-05-16 2016-08-10 中交第公路勘察设计研究院有限公司 Roadbed slope assembly type deformation self-adaptive protective framework and splicing method thereof
CN106869146A (en) * 2017-02-22 2017-06-20 安徽省交通建设股份有限公司 A kind of careless blanket ecoscape slope protection system and construction method
CN108487266A (en) * 2018-06-01 2018-09-04 宁夏力丰农机制造有限公司 A kind of cutting arched framework beam forms
CN108532662A (en) * 2018-05-30 2018-09-14 田振刚 A kind of subgrade protection construction equipment and its application method
CN108643205A (en) * 2018-06-25 2018-10-12 成都市市政工程(集团)有限责任公司 Arched framework slope protection construction method
CN110144906A (en) * 2019-06-04 2019-08-20 中铁三局集团第二工程有限公司 A kind of mechanical slotting method in railway slope protection construction
CN110409471A (en) * 2019-08-27 2019-11-05 中水北方勘测设计研究有限责任公司 Prefabricated supporting and retaining system guard assembly for soil-slope
CN111794184A (en) * 2020-07-17 2020-10-20 胡杨 River course slope protection construction method
CN112376588A (en) * 2020-11-28 2021-02-19 辽宁大学 Stock ground beam adds grout rubble lattice slope protection integrated configuration
CN113463668A (en) * 2021-07-21 2021-10-01 中信国安建工集团有限公司 Highway slope stability protection structure and construction operation method
CN114108662A (en) * 2021-11-16 2022-03-01 洛阳城市建设勘察设计院有限公司 Novel roadbed precast block arch skeleton slope protection structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004084402A (en) * 2002-08-29 2004-03-18 Ohbayashi Corp Greening anchoring plate, greening anchoring structure, and method of construction
KR20050079706A (en) * 2004-02-06 2005-08-11 최제인 Slope protection structure and reinforcement method of construction attached to pressure shotsoils or soilcement
CN202164615U (en) * 2011-07-26 2012-03-14 王建军 Structure of ecological slope protection
CN102691306A (en) * 2012-06-06 2012-09-26 中国科学院地质与地球物理研究所 Environment-friendly and energy-saving slope protection bamboo-wood lattice beam for mountain highway

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004084402A (en) * 2002-08-29 2004-03-18 Ohbayashi Corp Greening anchoring plate, greening anchoring structure, and method of construction
KR20050079706A (en) * 2004-02-06 2005-08-11 최제인 Slope protection structure and reinforcement method of construction attached to pressure shotsoils or soilcement
CN202164615U (en) * 2011-07-26 2012-03-14 王建军 Structure of ecological slope protection
CN102691306A (en) * 2012-06-06 2012-09-26 中国科学院地质与地球物理研究所 Environment-friendly and energy-saving slope protection bamboo-wood lattice beam for mountain highway

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105649093A (en) * 2016-04-05 2016-06-08 山东净金新能源有限公司 Arch fixing rack for highway/railway tunnel and manufacturing method of arch fixing rack
CN105649093B (en) * 2016-04-05 2017-03-08 山东净金新能源有限公司 A kind of manufacture method for encircleing solid frame for public, railway tunnel
CN105839651A (en) * 2016-05-16 2016-08-10 中交第公路勘察设计研究院有限公司 Roadbed slope assembly type deformation self-adaptive protective framework and splicing method thereof
CN106869146A (en) * 2017-02-22 2017-06-20 安徽省交通建设股份有限公司 A kind of careless blanket ecoscape slope protection system and construction method
CN108532662A (en) * 2018-05-30 2018-09-14 田振刚 A kind of subgrade protection construction equipment and its application method
CN108487266A (en) * 2018-06-01 2018-09-04 宁夏力丰农机制造有限公司 A kind of cutting arched framework beam forms
CN108643205A (en) * 2018-06-25 2018-10-12 成都市市政工程(集团)有限责任公司 Arched framework slope protection construction method
CN110144906A (en) * 2019-06-04 2019-08-20 中铁三局集团第二工程有限公司 A kind of mechanical slotting method in railway slope protection construction
CN110409471A (en) * 2019-08-27 2019-11-05 中水北方勘测设计研究有限责任公司 Prefabricated supporting and retaining system guard assembly for soil-slope
CN111794184A (en) * 2020-07-17 2020-10-20 胡杨 River course slope protection construction method
CN112376588A (en) * 2020-11-28 2021-02-19 辽宁大学 Stock ground beam adds grout rubble lattice slope protection integrated configuration
CN113463668A (en) * 2021-07-21 2021-10-01 中信国安建工集团有限公司 Highway slope stability protection structure and construction operation method
CN114108662A (en) * 2021-11-16 2022-03-01 洛阳城市建设勘察设计院有限公司 Novel roadbed precast block arch skeleton slope protection structure

Also Published As

Publication number Publication date
CN105421470B (en) 2017-09-08

Similar Documents

Publication Publication Date Title
CN105421470A (en) Construction method for assembled type anchor rod and arch framework combined type ecological slope protection
CN102678134B (en) Collapse and sink intrusion limit construction method for treating wind accumulated sand loess tunnel through stride shed pipe
CN109026064B (en) Construction method for large-span multi-arch tunnel with semi-bright and semi-dark
CN106013191A (en) Environmental-friendly grass concrete highway slope protection structure and construction method thereof
CN205999903U (en) Environment-friendly type grass planting Concrete Highway protective slope structure
CN104989425B (en) A kind of tunneling is into hole supporting construction and its method for protecting support
CN107762535A (en) Cut-and-cover tunnel secretly does construction technology under complicated geological environment
CN102758458B (en) Underground continuous wall repairing method
CN109594568B (en) Rock slope ecological protection structure and method thereof
CN210975741U (en) Reinforced structure of earth and rockfill dam
CN201027311Y (en) Water discharge type anchor stock frame beam for reinforcing side slope
CN105863650A (en) Tunneling construction method with first wall construction and second tunneling construction
CN104878719B (en) Mutual embedding reinforcement formula Ecological Retaining Wall construction method
CN110685286A (en) Deep foundation pit supporting construction process for adjacent road under complex geological condition
CN111042053A (en) Permanent temporary combined retaining wall structure in urban hydraulic engineering and construction method thereof
CN104653195A (en) Gully landform tunnel portal structure and construction method thereof
CN101793027B (en) Core-grouted static pressure anchor rod pile
CN105040707A (en) Combined densely-arrayed pile deep foundation pit supporting and enclosure structure used as basement external wall
CN213143117U (en) Assembled keyway basis retaining wall structure
CN205134338U (en) Ecological slope protection structure of assembled stock arch skeleton combined type
CN204877495U (en) Secretly dig into hole supporting construction
CN209324377U (en) Ledge method tunneling subway station arch springing ruggedized construction
CN110965577B (en) Construction method of chain lock type ecological block retaining wall
CN208023591U (en) A kind of foundation pit supporting construction of steel sheet pile combined deposited pile
CN110607795A (en) Arch skeleton for highway and railway tunnel and manufacturing method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
CB03 Change of inventor or designer information

Inventor after: Xu Shen

Inventor after: Hu Biao

Inventor after: Huang Zanxu

Inventor after: Hu Zhongqiang

Inventor after: Tu Wenjun

Inventor after: Zhang Wenhua

Inventor before: Hu Biao

Inventor before: Huang Zanxu

Inventor before: Hu Zhongqiang

Inventor before: Tu Wenjun

Inventor before: Zhang Wenhua