CN105421455A - 一种采用复合式静压植桩机的水上植桩方法 - Google Patents
一种采用复合式静压植桩机的水上植桩方法 Download PDFInfo
- Publication number
- CN105421455A CN105421455A CN201510736447.XA CN201510736447A CN105421455A CN 105421455 A CN105421455 A CN 105421455A CN 201510736447 A CN201510736447 A CN 201510736447A CN 105421455 A CN105421455 A CN 105421455A
- Authority
- CN
- China
- Prior art keywords
- combined type
- type static
- planting machine
- pile planting
- pressure pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/20—Placing by pressure or pulling power
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
本发明公开了一种采用复合式静压植桩机的水上植桩方法,涉及桥梁中钢板桩围堰的施工领域。该方法包括以下步骤:S1:将复合式静压植桩机安装在反力基座上,在反力基座上添加配重块;S2:通过配重块提供的反力,复合式静压植桩机将4根定位桩植入设计位置;S3:移除反力基座,将植入设计位置的4根定位桩作为反力桩,将复合式静压植桩机移至反力桩上;复合式静压植桩机的液压系统将复合式静压植桩机与已植入的反力桩锚固后,通过复合式静压植桩机进行后续植桩施工。本发明不仅对地层的适应性较强,范围比较广泛而且定位精度和施工效率均较高,对地层扰动较小、比较环保;本发明尤其适用于环保要求高、河床底层坚硬的水上植桩施工。
Description
技术领域
本发明涉及桥梁中钢板桩(钢管桩)围堰的施工领域,具体涉及一种采用复合式静压植桩机的水上植桩方法。
背景技术
目前,在桥梁水中墩施工中,对钢板桩(钢管桩)的围堰进行施工时,一般的施工方法为通过振动打桩锤将钢板桩(钢管桩)打入设计位置后合龙形成围堰。但是,振动打桩锤的使用条件较高,适用范围比较单一,例如当遇到地质坚硬、环保要求高或施工空间狭小的水域时,振动打桩锤无法使用,进而使得现有的施工方法受到限制。
发明内容
针对现有技术中存在的缺陷,本发明的目的在于提供一种采用复合式静压植桩机的水上植桩方法。本发明不仅对地层的适应性较强,范围比较广泛而且定位精度和施工效率均较高,对地层扰动较小、比较环保;本发明尤其适用于环保要求高、河床底层坚硬的水上植桩施工。
为达到以上目的,本发明提供的采用复合式静压植桩机的水上植桩方法,包括以下步骤:
S1:将复合式静压植桩机安装在反力基座上,在反力基座上添加配重块,转到S2;
S2:通过配重块提供的反力,复合式静压植桩机将4根定位桩植入设计位置,转到S3;
S3:移除反力基座,将植入设计位置的4根定位桩作为反力桩,将复合式静压植桩机移至反力桩上;复合式静压植桩机的液压系统将复合式静压植桩机与已植入的反力桩锚固后,通过复合式静压植桩机进行后续植桩施工。
在上述技术方案的基础上,S1和S2之间还包括以下步骤:当施工时存在直角转弯的情况时,通过复合式静压植桩机在直角转弯处植入辅助桩。
在上述技术方案的基础上,S3还包括以下步骤:当施工环境为深水区时,根据桩顶距河床的高度,在已植入的桩群上安装横向限位装置,通过横向限位装置固定已植入的桩群。
在上述技术方案的基础上,所述反力基座根据复合式静压植桩机的需求制作而成。
在上述技术方案的基础上,所述定位桩采用围堰钢板桩。
与现有技术相比,本发明的优点在于:
与现有技术中的振动打桩锤打桩相比,本发明采用复合式静压植桩机以及相应的植桩方法进行水上植桩,只需较少的施工人员操作即可,不仅对地层的适应性较强,而且定位精度和施工效率均较高,对地层扰动较小、比较环保。因此,本发明的适用范围比较广泛,尤其适用于环保要求高、河床底层坚硬的水上植桩施工。
附图说明
图1为本发明实施例中采用复合式静压植桩机的水上植桩方法的反力桩压入示意图;
图2为本发明实施例中采用复合式静压植桩机的水上植桩方法的深水区植桩示意图。
图中:1-液压系统,2-复合式静压植桩机,3-配重块,4-反力基座,5-定位桩,6-横向限位装置。
具体实施方式
以下结合附图及实施例对本发明作进一步详细说明。
参见图1所示,本发明实施例中的采用复合式静压植桩机的水上植桩方法,包括以下步骤:
S1:将复合式静压植桩机2安装在与植桩机配合的反力基座4上,反力基座4根据复合式静压植桩机2的需求制作而成,在反力基座4上添加配重块3,转到S2。
S2:通过配重块3提供的反力,复合式静压植桩机2将4根定位桩5植入设计位置,定位桩5采用围堰钢板桩,转到S3。
S3:移除反力基座4,将植入设计位置的4根定位桩5作为反力桩,将复合式静压植桩机2移至反力桩上;复合式静压植桩机2的液压系统1将复合式静压植桩机2与已植入的反力桩锚固后,通过复合式静压植桩机2进行后续植桩施工。
S1和S2之间还包括以下步骤:当施工时存在直角转弯的情况时,通过复合式静压植桩机2在直角转弯处植入辅助桩。
参见图2所示,S3还包括以下步骤:当施工环境为深水区时,根据桩顶距河床的高度,在已植入的桩群上安装横向限位装置6;横向限位装置6能够固定已植入的桩群,进而减小水流影响、提高植桩精度。
本发明不局限于上述实施方式,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以做出若干改进和润饰,这些改进和润饰也视为本发明的保护范围之内。本说明书中未作详细描述的内容属于本领域专业技术人员公知的现有技术。
Claims (5)
1.一种采用复合式静压植桩机的水上植桩方法,其特征在于,包括以下步骤:
S1:将复合式静压植桩机(2)安装在反力基座(4)上,在反力基座(4)上添加配重块(3),转到S2;
S2:通过配重块(3)提供的反力,复合式静压植桩机(2)将4根定位桩(5)植入设计位置,转到S3;
S3:移除反力基座(4),将植入设计位置的4根定位桩(5)作为反力桩,将复合式静压植桩机(2)移至反力桩上;复合式静压植桩机(2)的液压系统(1)将复合式静压植桩机(2)与已植入的反力桩锚固后,通过复合式静压植桩机(2)进行后续植桩施工。
2.如权利要求1所述的采用复合式静压植桩机的水上植桩方法,其特征在于,S1和S2之间还包括以下步骤:当施工时存在直角转弯的情况时,通过复合式静压植桩机(2)在直角转弯处植入辅助桩。
3.如权利要求1所述的采用复合式静压植桩机的水上植桩方法,其特征在于,S3还包括以下步骤:当施工环境为深水区时,根据桩顶距河床的高度,在已植入的桩群上安装横向限位装置(6),通过横向限位装置(6)固定已植入的桩群。
4.如权利要求1至3任一项所述的采用复合式静压植桩机的水上植桩方法,其特征在于:所述反力基座(4)根据复合式静压植桩机(2)的需求制作而成。
5.如权利要求1至3任一项所述的采用复合式静压植桩机的水上植桩方法,其特征在于:所述定位桩(5)采用围堰钢板桩。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510736447.XA CN105421455A (zh) | 2015-11-03 | 2015-11-03 | 一种采用复合式静压植桩机的水上植桩方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510736447.XA CN105421455A (zh) | 2015-11-03 | 2015-11-03 | 一种采用复合式静压植桩机的水上植桩方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105421455A true CN105421455A (zh) | 2016-03-23 |
Family
ID=55499966
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510736447.XA Pending CN105421455A (zh) | 2015-11-03 | 2015-11-03 | 一种采用复合式静压植桩机的水上植桩方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105421455A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107869144A (zh) * | 2017-11-17 | 2018-04-03 | 中铁二十二局集团第四工程有限公司 | 一种预掏槽环封双壁钢围堰深水基础综合施工方法 |
CN113585260A (zh) * | 2021-07-14 | 2021-11-02 | 中交一公局集团有限公司 | 一种转角桩施工方法 |
CN114411780A (zh) * | 2021-12-29 | 2022-04-29 | 中铁十九局集团有限公司 | 一种深水岩层地基静压植桩机拉森钢板桩围堰施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5777723A (en) * | 1980-10-29 | 1982-05-15 | Giken Seisakusho:Kk | Pressing-in and pulling-out machine for sheet pile |
CN104060610A (zh) * | 2014-04-30 | 2014-09-24 | 上海长凯岩土工程有限公司 | 一种自给压桩反力的锚杆静压桩装置及其施工方法 |
CN104831728A (zh) * | 2014-02-12 | 2015-08-12 | 任丘市永基建筑安装工程有限公司 | 静压桩机加压技术 |
CN104863154A (zh) * | 2015-06-11 | 2015-08-26 | 鞍山紫竹工程设备制造有限公司 | 一种液压多功能植桩机的转动机构 |
-
2015
- 2015-11-03 CN CN201510736447.XA patent/CN105421455A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS5777723A (en) * | 1980-10-29 | 1982-05-15 | Giken Seisakusho:Kk | Pressing-in and pulling-out machine for sheet pile |
CN104831728A (zh) * | 2014-02-12 | 2015-08-12 | 任丘市永基建筑安装工程有限公司 | 静压桩机加压技术 |
CN104060610A (zh) * | 2014-04-30 | 2014-09-24 | 上海长凯岩土工程有限公司 | 一种自给压桩反力的锚杆静压桩装置及其施工方法 |
CN104863154A (zh) * | 2015-06-11 | 2015-08-26 | 鞍山紫竹工程设备制造有限公司 | 一种液压多功能植桩机的转动机构 |
Non-Patent Citations (1)
Title |
---|
罗海 等: "现代静力压入桩基工法及应用前景探讨", 《地下空间与工程学报》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107869144A (zh) * | 2017-11-17 | 2018-04-03 | 中铁二十二局集团第四工程有限公司 | 一种预掏槽环封双壁钢围堰深水基础综合施工方法 |
CN113585260A (zh) * | 2021-07-14 | 2021-11-02 | 中交一公局集团有限公司 | 一种转角桩施工方法 |
CN114411780A (zh) * | 2021-12-29 | 2022-04-29 | 中铁十九局集团有限公司 | 一种深水岩层地基静压植桩机拉森钢板桩围堰施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
NZ593256A (en) | A hydroelectric turbine with aligning means and method of deployment | |
WO2009080035A3 (en) | Method for installing an offshore wind turbine and a barge system | |
CN205530280U (zh) | 一种新型预制两墙合一基坑围护体系 | |
CN105421455A (zh) | 一种采用复合式静压植桩机的水上植桩方法 | |
CN101235649A (zh) | 一种盖挖基坑系统 | |
CN106697189A (zh) | 一种浮拖法离岸型海上升压站的安装方法 | |
CN102041813B (zh) | 一种带稳定翼的海上风力发电机单桩基础结构 | |
WO2013113873A3 (de) | Geräuscharm zu installierende gründungskonstruktion einer offshore-anlage, insbesondere einer offshore-windenergieanlage und montageverfahren hierfür | |
CN104805854A (zh) | 一种潮汐环境下深水超长钢板桩围堰施工方法 | |
CN102587405A (zh) | 海上风机导管架基础安装方法及分离式导管架装置 | |
CN106088120B (zh) | 一种围堰下放施工方法 | |
CN105604072A (zh) | 一种钢护筒围堰及应用钢护筒围堰的钢护筒沉放就位方法 | |
GB2524460A (en) | Offshore foundation | |
KR20150070843A (ko) | 수평지지력 증대용 마이크로파일 시공방법 | |
CN201232180Y (zh) | 新型板桩墙 | |
CN106638651A (zh) | 一种海上风机浮式基础整体式安装工艺 | |
CN105220689A (zh) | 一种光伏打桩机 | |
CN209979858U (zh) | 一种gnss三维姿态定位打桩导航辅助系统 | |
CN105887909A (zh) | 瓣式伞型复合单桩基础 | |
CN201554033U (zh) | 一种用于深基坑的塔式吊机基础 | |
CN201459770U (zh) | 深基坑中两种不同围护体间的接头结构 | |
CN104404963A (zh) | 一种地铁换乘车站深基坑交叉施工方法 | |
CN105443311A (zh) | 固定于水底的潮流能发电装置 | |
CN103465742B (zh) | 步履式半潜两栖工程船 | |
CN103321261A (zh) | 一种定向胀升纠偏工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160323 |