CN105421161A - 一种防止黄土路堤湿化变形的路堤结构 - Google Patents
一种防止黄土路堤湿化变形的路堤结构 Download PDFInfo
- Publication number
- CN105421161A CN105421161A CN201510761834.9A CN201510761834A CN105421161A CN 105421161 A CN105421161 A CN 105421161A CN 201510761834 A CN201510761834 A CN 201510761834A CN 105421161 A CN105421161 A CN 105421161A
- Authority
- CN
- China
- Prior art keywords
- embankment
- loess
- bedding
- water proof
- drainage blanket
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2/00—General structure of permanent way
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B2204/00—Characteristics of the track and its foundations
- E01B2204/07—Drainage
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Road Paving Structures (AREA)
Abstract
本发明公开了一种防止黄土路堤湿化变形的路堤结构,它涉及土木工程技术领域;基床与路堤之间设置有隔水排水层;隔水排水层可采中粗砂夹渗透系数小于防渗复合土工材料,复合土工材料的渗透系数小于10-11cm/s,复合土工材料上下分别设置5~15cm的中粗砂;本发明能防止黄土路堤湿化变形,延长使用寿命,提高了安全性。
Description
技术领域:
本发明涉及土木工程技术领域,具体涉及一种防止黄土路堤湿化变形的路堤结构。
背景技术:
目前的铁路路堤结构分为基床和基床以下路堤,基床多采用透水填料填筑,在干旱半干旱地区,黄土是典型的非饱和土,相应的强度、变形和湿陷都具有非饱和上的机理,黄土的压实过程实际是一个与非饱和土有关的工程问题,其目的是改善土的力学和水力学特性。许多湿陷性黄土用做路基填料时常处于非饱和状态,在遇到水分长时间的浸泡就会出现湿化变形。
压实黄土渗透系数一般在10-6cm/s~10-4cm/s数量级,在含水量增大的情况下,压实黄土会产生较大的变形,从而引起上部结构的功能丧失和破坏,如:甘肃境内的包兰铁路、陇海铁路、兰青铁路、兰新铁路等用黄土作为路堤填料的地段,在低降雨强度下长历时降雨后的路堤沉降问题长期困扰该段铁道的维护,这一病害的根源在于非饱和压实黄土的增湿变形和强度损失。西北地区黄土分布较广泛,受到工程成本和地质条件的影响,不得不选用黄土作为路基的填料。铁路工程的相关规范明确要求“旅客列车速度目标值≤200km/h或货物列车速度目标值≤120km/h的铁路,黄土仅能做为基床底层或基床以下路堤的填筑材料”。因此,研究压实黄土路堤的湿化变形,找到一种能够避免因降雨等因素而引起路堤湿化变形的新型路堤结构形式显得非常重要。
目前铁路设计规范规定,在旅客列车设计行车速度≤200km/h或货物列车设计行车速度≤200km/h时,I级铁路基床底层可采用黄土改良土做填料,基床以下路堤可以采用黄土做填料,II级铁路基床底层可采用黄土做填料,基床以下路堤可以采用黄土做填料,但是基床表层都为渗透系数较大的级配碎石、级配砂砾石、天然砂砾石等填筑,黄土做为基床底层或基床以下路堤时会受到湿化变形的问题。
发明内容:
本发明的目的在于针对现有技术的缺陷和不足,提供一种防止黄土路堤湿化变形的路堤结构。
为了解决背景技术所存在的问题,本发明的一种防止黄土路堤湿化变形的路堤结构,它包含基床、路堤;它还包含隔水排水层;基床与路堤之间设置有隔水排水层;隔水排水层可采中粗砂夹渗透系数小于防渗复合土工材料,复合土工材料的渗透系数小于10-11cm/s,复合土工材料上下分别设置5~15cm的中粗砂。
作为优选,所述的隔水排水层可采用≥30cm厚的经水泥、石灰、粉煤灰等改性的黄土。
作为优选,所述的基床的厚度大于60cm,顶面设置4%的人字形排水坡,在中间最高,两侧边缘最低;基床表层采用三种填料,第一种为掺加一定比例的石灰、水泥、粉煤灰的级配碎石、级配砂砾石、天然砂砾石;第二种为级配碎石、级配砂砾石、天然砂砾石;第三种为满足承载力、强度和级配的其它材料。
本发明有益效果为:能防止黄土路堤湿化变形,延长使用寿命,提高了安全性。
附图说明:
图1为本发明的结构示意图。
附图标记说明:
1-基床;2-路堤;3-隔水排水层。
具体实施方式:
下面结合附图,对本发明作进一步的说明。
为了使本发明的目的、技术方案及优点更加清楚明白,以下结合附图及具体实施方式,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施方式仅用以解释本发明,并不用于限定本发明。
如图1所示,本具体实施方式采用如下技术方案:它包含基床1、路堤2;它还包含隔水排水层3;基床1与路堤2之间设置有隔水排水层3。
基床表层的设置。基床表层的厚度应在60cm以上,顶面设置4%的人字形排水坡,在中间最高,两侧边缘最低。基床表层按照铁路路基设计规范要求,一般采用三种填料,第一种为掺加一定比例的石灰、水泥、粉煤灰的级配碎石、级配砂砾石、天然砂砾石;第二种为级配碎石、级配砂砾石、天然砂砾石;第三种为满足承载力、强度和级配的其他材料。
基床底层的设置。基床底层厚度的设置按照铁路工程路基设计规范,采用不同的厚度,一般的厚度要求大于190cm。填筑材料可同基床表层的填料,也可采用强度高、水稳定性好、继配等指标符合铁路工程路基设计施工规范的碎石土、卵石土、砂土、砂质粘土等材料,也可采用经过掺加石灰、水泥、粉煤灰等材料的改良土。
基床与基床以下黄土路堤之间隔水排水层的设置。隔水排水层可采中粗砂夹渗透系数小于防渗复合土工材料,复合土工材料的渗透系数小于10-11cm/s,土工材料上下分别设置5~15cm的中粗砂。排水隔水层也可采用≥30cm厚的经水泥、石灰、粉煤灰等改性的黄土,经发明人研究后,确定水泥含量在4%~5%,石灰含量在6%~9%,粉煤灰含量在10%的改性黄土在冻融循环下的渗透性达到10-8cm/s,能够满足工程要求的,同时微观结构最为稳定和优越。
以上所述,仅用以说明本发明的技术方案而非限制,本领域普通技术人员对本发明的技术方案所做的其它修改或者等同替换,只要不脱离本发明技术方案的精神和范围,均应涵盖在本发明的权利要求范围当中。
Claims (3)
1.一种防止黄土路堤湿化变形的路堤结构,其特征在于:它包含基床、路堤;它还包含隔水排水层;基床与路堤之间设置有隔水排水层;隔水排水层可采中粗砂夹渗透系数小于防渗复合土工材料,复合土工材料的渗透系数小于10-11cm/s,复合土工材料上下分别设置5~15cm的中粗砂。
2.根据权利要求1所述的一种防止黄土路堤湿化变形的路堤结构,其特征在于:所述的隔水排水层可采用≥30cm厚的经水泥、石灰、粉煤灰等改性的黄土。
3.根据权利要求1所述的一种防止黄土路堤湿化变形的路堤结构,其特征在于:所述的基床的厚度大于60cm,顶面设置4%的人字形排水坡,在中间最高,两侧边缘最低;基床表层采用三种填料,第一种为掺加一定比例的石灰、水泥、粉煤灰的级配碎石、级配砂砾石、天然砂砾石;第二种为级配碎石、级配砂砾石、天然砂砾石;第三种为满足承载力、强度和级配的其它材料。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510761834.9A CN105421161A (zh) | 2015-11-05 | 2015-11-05 | 一种防止黄土路堤湿化变形的路堤结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510761834.9A CN105421161A (zh) | 2015-11-05 | 2015-11-05 | 一种防止黄土路堤湿化变形的路堤结构 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105421161A true CN105421161A (zh) | 2016-03-23 |
Family
ID=55499679
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510761834.9A Pending CN105421161A (zh) | 2015-11-05 | 2015-11-05 | 一种防止黄土路堤湿化变形的路堤结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105421161A (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160201460A1 (en) * | 2013-08-14 | 2016-07-14 | China Shenhua Energy Company Limited | An artificial dam of distributed coal mine underground reservoir and its constructing method |
CN116876280A (zh) * | 2023-09-07 | 2023-10-13 | 中交第一航务工程局有限公司 | 一种高路堤的施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101974877A (zh) * | 2010-10-18 | 2011-02-16 | 中铁第四勘察设计院集团有限公司 | 高速铁路软岩改良土路基结构 |
CN102330398A (zh) * | 2011-07-23 | 2012-01-25 | 中铁二院工程集团有限责任公司 | 平原地区非饱和土地基高速铁路路基结构 |
CN202369864U (zh) * | 2011-12-21 | 2012-08-08 | 中铁第四勘察设计院集团有限公司 | 盐渍土铁路路基结构 |
KR20130064192A (ko) * | 2011-12-08 | 2013-06-18 | 김철각 | 스톤 바스켓을 이용한 도로포장 방법 |
CN104358188A (zh) * | 2014-11-20 | 2015-02-18 | 中铁八局集团有限公司 | 湿陷性黄土路基填筑施工方法 |
-
2015
- 2015-11-05 CN CN201510761834.9A patent/CN105421161A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101974877A (zh) * | 2010-10-18 | 2011-02-16 | 中铁第四勘察设计院集团有限公司 | 高速铁路软岩改良土路基结构 |
CN102330398A (zh) * | 2011-07-23 | 2012-01-25 | 中铁二院工程集团有限责任公司 | 平原地区非饱和土地基高速铁路路基结构 |
KR20130064192A (ko) * | 2011-12-08 | 2013-06-18 | 김철각 | 스톤 바스켓을 이용한 도로포장 방법 |
CN202369864U (zh) * | 2011-12-21 | 2012-08-08 | 中铁第四勘察设计院集团有限公司 | 盐渍土铁路路基结构 |
CN104358188A (zh) * | 2014-11-20 | 2015-02-18 | 中铁八局集团有限公司 | 湿陷性黄土路基填筑施工方法 |
Non-Patent Citations (1)
Title |
---|
吕擎峰等: ""改性黄土的冻融特性"", 《中南大学学报(自然科学版)》 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20160201460A1 (en) * | 2013-08-14 | 2016-07-14 | China Shenhua Energy Company Limited | An artificial dam of distributed coal mine underground reservoir and its constructing method |
US9689128B2 (en) * | 2013-08-14 | 2017-06-27 | China Shenhua Energy Company Limited | Artificial dam of distributed coal mine underground reservoir and its constructing method |
CN116876280A (zh) * | 2023-09-07 | 2023-10-13 | 中交第一航务工程局有限公司 | 一种高路堤的施工方法 |
CN116876280B (zh) * | 2023-09-07 | 2023-11-10 | 中交第一航务工程局有限公司 | 一种高路堤的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106522037B (zh) | 基于既有铁路路基的帮宽路基结构及其施工方法 | |
CN105887609B (zh) | 一种海绵城市生态渗滤地面的构建方法 | |
CN209178724U (zh) | 一种膨胀土地基有砟轨道高速铁路路堤加固结构 | |
CN102587243A (zh) | 城市道路透水性水泥混凝土铺面结构及其施工工艺 | |
CN103255694B (zh) | 季节性冻土地区无砟轨道高速铁路路堑基床结构 | |
CN203346730U (zh) | 市域铁路有砟轨道路堤基床结构 | |
CN103266546B (zh) | 季节性冻土地区无砟轨道高速铁路路堤基床结构 | |
CN205368926U (zh) | 透水性强的园路路面层结构 | |
CN104110009B (zh) | 一种水体净化防渗结构及方法 | |
CN109440543B (zh) | 千枚岩风化土与红粘土混合改良方法及拌合方法 | |
CN105421161A (zh) | 一种防止黄土路堤湿化变形的路堤结构 | |
CN107151960A (zh) | 软基区临时便道铺设结构及铺设方法 | |
CN205741814U (zh) | 一种沥青路面结构 | |
CN202519561U (zh) | 城市道路透水性水泥混凝土铺面结构 | |
CN210529400U (zh) | 一种固化建筑渣土道路结构 | |
CN107268373A (zh) | 一种透水性沥青混凝土道路及其施工方法 | |
CN208884292U (zh) | 软土路基与正常路基交界处防沉降结构 | |
CN216663671U (zh) | 一种公路路面铺装结构 | |
CN209636588U (zh) | 一种内部具有土工透水管的加强路基路面 | |
CN103898824B (zh) | 高寒冻土地区路基用塑料排水板处理基底的方法 | |
CN209686150U (zh) | 一种软质岩铁路路基 | |
CN209836710U (zh) | 一种适用于季节性冻土地区的填方路基结构 | |
CN203320371U (zh) | 季节性冻土地区无砟轨道高速铁路路堑基床结构 | |
CN1478961A (zh) | 地基延缓固结处理法 | |
CN111608026A (zh) | 一种适用于川渝红层泥岩地区400km时速高铁路堤构造 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160323 |