CN105401522A CN201410416562.4A CN201410416562A CN105401522A CN 105401522 A CN105401522 A CN 105401522A CN 201410416562 A CN201410416562 A CN 201410416562A CN 105401522 A CN105401522 A CN 105401522A
Authority
CN
China
Prior art keywords
pier
bridge
ground
bridge pier
framework
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410416562.4A
Other languages
Chinese (zh)
Inventor
朱连吉
李春艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Renqiu Yongji Construction and Installation Engineering Co Ltd
Original Assignee
Renqiu Yongji Construction and Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Renqiu Yongji Construction and Installation Engineering Co Ltd filed Critical Renqiu Yongji Construction and Installation Engineering Co Ltd
Priority to CN201410416562.4A priority Critical patent/CN105401522A/en
Publication of CN105401522A publication Critical patent/CN105401522A/en
Pending legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to the field of bridges, in particular to a steel bright pier installation technology. Firstly, after a pier frame and pier studs are prefabricated on a plant production line according to the actual bridge building drawing requirements and are transported to a bridge building site; as the road surface is unsmooth, the pier studs need to be embedded in the ground firstly, it is guaranteed that the upper surfaces of the installed pier studs are located on the same horizontal face, and then the overall pier frame is stably placed on the pier studs and fixed through bolts; and it is guaranteed that C30 concrete casting in place is carried out after the pier frame is firmly and stably placed on the pier studs, the pier studs, the ground and the pier are tightly and firmly connected together, and therefore the load of the overall bridge is conveniently supported. The steel bright pier installation technology is simple in design, convenient to construct and short in construction period; and the problems that the overall bridge structure is unstable due to insufficient contact between the pier and the ground in a common pier stud installation process, and casting of concrete is uneven are solved, pier installation is more firm, and the load of the overall bridge can be supported.

Description

Steel bridge bridge pier mounting technique
Technical field
The present invention relates to bridge field, particularly relate to steel bridge bridge pier mounting technique.
Background technology
At present, bridge construction has abandoned traditional form of construction work gradually, is more and more tending towards adopting steel plate to build skeleton, then uses the mode of concreting.In the building course of bridge, it is particularly important that the construction of bridge pier is installed, only have bridge pier install steadily firmly after, the weight of bed rearrangement bridge can be supported.General bridge pier is all the structure adopting bridge pier and pier stud to be integrated in installation process, so just the contact area of bridge pier and ground is diminished, the load of bearing just corresponding reduction, often occur that concreting uneven when bridge pier is built simultaneously, between bridge pier and ground contact surface, have gap to cause bridge pier that the problems such as not steady are installed.
Summary of the invention
The present invention is just in order to solve the deficiency in above-mentioned bridge pier installation process, provide a kind of steel bridge bridge pier mounting technique, the method makes the contact area on bridge pier and ground in bridge pier installation process larger, the load that can bear is larger, ensure that the stationarity of bed rearrangement steel bridge, and better achieve fully contacting of bridge pier and ground, effectively can support the load of bed rearrangement bridge, and shorten the construction period of bridge.
To achieve these goals, the present invention adopts following technical method to realize: steel bridge bridge pier mounting technique, be first according to actual bridge construction drawing requirement by bridge pier framework and pier stud shop production line is prefabricated complete after, be transported to bridge construction ground,
First by pre-buried for prefabricated pier stud in ground, and guarantee that the upper surface of mounted pier stud is in same level, again bridge pier framework bolt is fixed on pier stud stably, then carries out cast in situs with C30 concrete, built and regularly carried out concrete maintenance work afterwards.
Described steel bridge bridge pier framework, good at workshop Plate Welding according to actual bridge construction drawing requirement, its stationarity must be ensured when mounted.
Described pier stud, good in shop-fabricated according to unified specification according to actual bridge construction drawing requirement, when installing with building, its upper surface must ensure in same level.
Described bridge pier framework was realized by Bolt Connection with connecting of pier stud, was first by after pre-buried for pier stud getting well, was placed on stably on pier stud by bridge pier framework, fixes with bolt.
The invention has the beneficial effects as follows: by steel bridge bridge pier mounting technique in the present invention, bridge pier framework can be made more steady, and bridge pier and contact area of ground are larger, and bearing load ability is stronger, the load of support bed rearrangement bridge that can be strong, shortens the construction period of bridge.
Accompanying drawing explanation
Fig. 1 is bridge pier scheme of installation on the right side of steel bridge; Fig. 2 is that on the right side of steel bridge, left view installed by bridge pier; Fig. 3 is whole steel bridge bridge pier scheme of installation.Wherein 1 is steel bridge bridge pier framework, and 2 is pier studs, and 3 is ground, and 4 is bolts.
Detailed description of the invention
Below in conjunction with accompanying drawing, the invention will be further described: as depicted in figs. 1 and 2, steel bridge bridge pier mounting technique, by the size first according to bridge pier and pier stud drawing requirement in actual bridge construction, at shop production line by steel bridge bridge pier framework 1, pier stud 2 is prefabricated to be completed, then bridge construction ground is transported to, consider that ground 3 is rough, need first to arrive 3 li, ground by pre-buried for pier stud 2, and the upper surface guaranteeing pre-buried good pier stud 2 in the same horizontal line, afterwards bridge pier framework 1 is placed on pier stud 2 stably, and with bolt 4, bridge pier framework 1 is fixed on pier stud 2, as shown in Figure 3, by pre-buried for bed rearrangement bridge pier column 2 good after, be fixed on pier stud 2 by bridge pier framework 1 with bolt 4, fixation is built with C30 concrete later, has built regularly to carry out concrete maintenance work afterwards.
By steel bridge bridge pier mounting technique in the present invention, bridge pier can be made to install steadily, larger with the contact area on ground, the ability of bearing load is stronger, the weight supporting bed rearrangement steel bridge that can be strong.

Claims (4)

1. steel bridge bridge pier mounting technique, comprise bridge pier framework, pier stud, coupling method between ground, it is characterized in that, described coupling method, be first according to actual bridge construction drawing requirement by bridge pier framework and pier stud Workshop Production is prefabricated complete after, be transported to bridge construction ground, first by pre-buried for prefabricated pier stud in ground, and determine that the upper surface of mounted pier stud is in same level, again bridge pier framework bolt is fixed on pier stud stably, then cast in situs is carried out with C30 concrete, build and regularly carried out concrete maintenance work afterwards.
2. steel bridge bridge pier mounting technique as claimed in claim 1, is characterized in that, described bridge pier framework, good at workshop Plate Welding according to actual bridge construction drawing requirement, must ensure its stationarity when mounted.
3. steel bridge bridge pier mounting technique as claimed in claim 1, is characterized in that, described pier stud, good in shop-fabricated according to uniform sizes according to actual bridge construction drawing requirement, must make its upper surface in same level when installing with building.
4. steel bridge bridge pier mounting technique as claimed in claim 1, it is characterized in that, described bridge pier framework was realized by Bolt Connection with connecting of pier stud, was first by after pre-buried for pier stud getting well, was placed on stably on pier stud by bridge pier framework, fixes with bolt.
CN201410416562.4A 2014-08-22 2014-08-22 Steel bridge pier installation technology Pending CN105401522A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410416562.4A CN105401522A (en) 2014-08-22 2014-08-22 Steel bridge pier installation technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410416562.4A CN105401522A (en) 2014-08-22 2014-08-22 Steel bridge pier installation technology

Publications (1)

Publication Number Publication Date
CN105401522A true CN105401522A (en) 2016-03-16

Family

ID=55467254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410416562.4A Pending CN105401522A (en) 2014-08-22 2014-08-22 Steel bridge pier installation technology

Country Status (1)

Country Link
CN (1) CN105401522A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201581656U (en) * 2009-12-04 2010-09-15 中建四局第六建筑工程有限公司 Steel trestle for large-scale complicated construction sites
KR20110002998A (en) * 2009-07-03 2011-01-11 부림산업(주) Pier basis caisson structure using a pulling oil jack system
CN202055271U (en) * 2011-04-21 2011-11-30 贵阳铝镁设计研究院有限公司 Reinforcing structure of foundation of high-temperature furnace
CN202672023U (en) * 2012-07-09 2013-01-16 东莞市科旺网络能源有限公司 Modular detachable emergency steel bridge
CN203160420U (en) * 2013-04-08 2013-08-28 李涛 H-shaped steel-structure support frame and H-shaped steel-structure bridge thereof
CN203505258U (en) * 2013-09-24 2014-04-02 巫溪县文鑫农牧有限责任公司 Cowshed stand column reinforcing structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110002998A (en) * 2009-07-03 2011-01-11 부림산업(주) Pier basis caisson structure using a pulling oil jack system
CN201581656U (en) * 2009-12-04 2010-09-15 中建四局第六建筑工程有限公司 Steel trestle for large-scale complicated construction sites
CN202055271U (en) * 2011-04-21 2011-11-30 贵阳铝镁设计研究院有限公司 Reinforcing structure of foundation of high-temperature furnace
CN202672023U (en) * 2012-07-09 2013-01-16 东莞市科旺网络能源有限公司 Modular detachable emergency steel bridge
CN203160420U (en) * 2013-04-08 2013-08-28 李涛 H-shaped steel-structure support frame and H-shaped steel-structure bridge thereof
CN203505258U (en) * 2013-09-24 2014-04-02 巫溪县文鑫农牧有限责任公司 Cowshed stand column reinforcing structure

Similar Documents

Publication Publication Date Title
CN203640309U (en) Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame
CN204059395U (en) The pre-buried location structure of stone bolt
CN104912099B (en) A kind of prefabricated concrete box culvert
CN204607405U (en) A kind of large deformation Rock Crane Rail Support orbital arrangement structure
CN103469735A (en) Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN204418654U (en) For the aluminum alloy pattern plate between body of wall
CN101806148A (en) Construction method for concrete beam with U-shaped steel bar connecting joints
CN105401522A (en) Steel bridge pier installation technology
CN204098224U (en) Detachable concrete prefabricated wall plate structure house
CN203100853U (en) Foundation-free trunk scale
CN203621841U (en) Tubular bus welding platform
CN210049373U (en) Assembly type I-steel composite floor slab mounting structure
CN103362152A (en) Method for transforming roller way foundation
CN203593526U (en) Movable type hoisting device
CN203495535U (en) Hinging type construction device for installation and removal of gantry crane
CN104532743A (en) Tower girder fixed-connection mechanism, corresponding cable-stayed bridge and building method of cable-stayed bridge
CN202540273U (en) Support for inclined stay bar
CN202000266U (en) Supporting structure of bridge coping template
CN203320420U (en) Temporary locking structure for corrugated steel webs of steel and concrete combined box girder
CN201850655U (en) T-shaped connector for new and old buildings
CN201827604U (en) Base for high-precision universal mechanical equipment
CN202023143U (en) Support special for steel box girder
CN104251014A (en) Connecting structure of concrete bent frame column and roof steel beam
CN202324664U (en) Steel beam lifting and supporting device
CN203654796U (en) Steel ladder cage installation structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160316