CN101806148A - Construction method for concrete beam with U-shaped steel bar connecting joints - Google Patents
Construction method for concrete beam with U-shaped steel bar connecting joints Download PDFInfo
- Publication number
- CN101806148A CN101806148A CN 201010134828 CN201010134828A CN101806148A CN 101806148 A CN101806148 A CN 101806148A CN 201010134828 CN201010134828 CN 201010134828 CN 201010134828 A CN201010134828 A CN 201010134828A CN 101806148 A CN101806148 A CN 101806148A
- Authority
- CN
- China
- Prior art keywords
- groove
- shaped steel
- steel bar
- construction method
- reinforcing bar
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention relates to a construction method for concrete beam with U-shaped steel bar connecting nodes. In the method, two ends of a precast frame beam are respectively provided with a groove; reserved steel bars on the end parts of the precast frame beam are only in the grooves; a temporary support frame is erected; U-shaped steel bars are put into the grooves of the precast frame beam; the back cut of each U-shaped steel bar is provided with a steel bar which is clamped in the groove; and beam-column joint steel bars are bound and concrete is cast into the grooves, so the U-shaped steel bars make the beams and columns connected into a whole. The construction method solves the problems that connected beams are easily corroded, the pretightening and loosening are needed on large stress occasions, the cost of monitoring and maintenance at later stage is high, equipment has large volume and is difficult to move, the construction cannot be carried out in a narrow space or without a crane, the qualification rate of joints is low, the power consumption is high and the like in a bolt connecting method and a welding connecting method. The construction method has the advantages of excellent earthquake resistance, construction period conservation by 50 percent, quality guarantee, low cost and revolving material conservation.
Description
Technical field
The present invention relates to a kind of new concrete structure main body construction method, particularly a kind of construction method for concrete beam with U-shaped steel bar connecting joints.
Background technology
Before the present invention, in building operations, what general concrete prefabricated frame construction beam column connected employing is nothing but two kinds of methods, and a kind of is the bolt method of attachment, and another kind is the method for being welded to connect.These two kinds of connected modes all have significant disadvantages: place, bolted slit has the generation of corrosion easily, lost efficacy thereby cause to connect, and stressed bigger occasion need carry out pretension and locking, and later stage monitoring, maintenance cost are bigger; The equipment volume that is welded to connect is bigger, moves inconvenience, narrow space or do not have crane and can not construct, and the joint qualification rate is low, and power consumption is bigger, and higher to operator's technical requirements, and influenced by workman's technical level bigger for welding quality in the operation.
Summary of the invention
Purpose of the present invention just is to overcome above-mentioned defective, and a kind of construction method for concrete beam with U-shaped steel bar connecting joints is provided.
Technical scheme of the present invention is:
Construction method for concrete beam with U-shaped steel bar connecting joints, its major technique step is:
(1) at precast frame beam two ends groove is set respectively, precast frame beam end reserved steel bar is only in groove;
(2) before the lifting of precast frame beam, set up interim bracing frame earlier, and can regulate interim bracing frame height;
(3) the U-shaped reinforcing bar is put into the groove of precast frame beam, added a reinforcing bar and be stuck in the middle of the groove in that the U-shaped reinforcing bar is suitable for reading, then colligation bean column node reinforcing bar as distribution bar;
(4) fluid concrete is to design elevation in groove, and the U-shaped reinforcing bar links into an integrated entity beam, post.
Advantage of the present invention is that with effect the job practices that adopts U-shaped reinforcing bar node to be connected precast beam, post has following advantage:
1, adopting the concrete beam and column node of U-shaped steel bar connecting joints is rigid joint, and anti-seismic performance is superior, is suitable for the mode that is articulated and connected that surpasses highly far away.
2, member can be produced in factory in advance, and directly install the job site, for beam end two reserved steel bar of routine, adopts the groove type bean column node, and reinforcing bar is reserved in the groove, and the duration can save 50%;
3, compare with traditional cast-in-place structural, this kind connected mode adopts millwork production, has changed the mode of on-the-spot armrest industry control system quality, the product quality guarantee that more is easy to get, hard outer beautiful, good endurance in the member, all common quality defects that can effectively avoid cast-in-place structural to bring;
4, adopt the concrete beam with U-shaped steel bar connecting joints, the scene only needs colligation U-shaped reinforcing bar, simple installation, and construction quality is easy to control, and this connected mode cost is lower than by manual welding connecting mode about 30%;
5, do not need template substantially, support and reduce more than 50%, save the circulation material total amount and reach 60%-80%;
6, reduce job site wet trade amount, help environmental protection, alleviate noise pollution, site operation is civilization more, satisfies the trend of national development low-carbon economy fully.
Job practices of the present invention is reliable, effective, economical, firm.
Other advantages of the present invention and effect will go on to say below.
Description of drawings
Fig. 1--structural principle schematic diagram of the present invention.
The specific embodiment
As shown in Figure 1:
Precast frame beam 2 two ends are provided with groove 3, and U-shaped reinforcing bar 4 is placed in the groove 3, utilize U-shaped reinforcing bar 4 that precast frame beam 2 and post 1 are linked together by fluid concrete.
The job practices explanation:
Hoisting prefabricated Vierendeel girder 2 is in place, and U-shaped reinforcing bar 4 is put into the groove 3 of precast frame beam 2, and placing of concrete links into an integrated entity U-shaped reinforcing bar 4 and post 1.
At precast frame beam 2 two ends groove 3 is set respectively, beam end reserved steel bar (anchor rib) only limits to not expose in the groove 3, with convenient on-the-spot the installation;
Before the lifting of precast frame beam, set up interim support earlier, and regulate bearing height, to guarantee the in place accurate of precast frame beam according to the control absolute altitude;
U-shaped reinforcing bar 4 is put into the groove 3 of precast frame beam 2, for guarantee U-shaped reinforcing bar 4 positions accurately, add a reinforcing bar and be stuck in the middle of the groove 3 in that U-shaped reinforcing bar 4 is suitable for reading, then colligation bean column node reinforcing bar as distribution bar;
It is moistening that pouring groove 3 concrete should shift to an earlier date 24 hours and water, and adopts the high grade microdilatancy pea gravel concreten and the vibration compacting of being sure to, and concreting utilizes the U-shaped reinforcing bar that beam, post are linked into an integrated entity to design elevation.
Claims (1)
1.U the construction method for concrete beam of shape steel bar connecting joints, its step is:
(1) at precast frame beam two ends groove is set respectively, precast frame beam end reserved steel bar is only in groove;
(2) before the lifting of precast frame beam, set up interim bracing frame earlier, and can regulate interim bracing frame height;
(3) the U-shaped reinforcing bar is put into the groove of precast frame beam, added a reinforcing bar and be stuck in the middle of the groove in that the U-shaped reinforcing bar is suitable for reading, then colligation bean column node reinforcing bar as distribution bar;
(4) fluid concrete is to design elevation in groove, and the U-shaped reinforcing bar links into an integrated entity beam, post.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010134828 CN101806148A (en) | 2010-03-29 | 2010-03-29 | Construction method for concrete beam with U-shaped steel bar connecting joints |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010134828 CN101806148A (en) | 2010-03-29 | 2010-03-29 | Construction method for concrete beam with U-shaped steel bar connecting joints |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101806148A true CN101806148A (en) | 2010-08-18 |
Family
ID=42608085
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010134828 Pending CN101806148A (en) | 2010-03-29 | 2010-03-29 | Construction method for concrete beam with U-shaped steel bar connecting joints |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101806148A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103046746A (en) * | 2012-12-03 | 2013-04-17 | 成军 | Construction method of conversion beam reinforcing bars for tall building structure |
CN103195172A (en) * | 2013-04-16 | 2013-07-10 | 东南大学 | Beam-column joint structure of prefabricated concrete frame |
CN104164920A (en) * | 2014-07-23 | 2014-11-26 | 南京长江都市建筑设计股份有限公司 | Bottom steel bar connecting structure of key groove node precast frame beam |
CN105625572A (en) * | 2016-02-29 | 2016-06-01 | 东南大学 | Prefabricated prestressed concrete frame beam-column joint making disparate use of high performance materials |
CN105649203A (en) * | 2016-02-29 | 2016-06-08 | 东南大学 | Prefabricated prestressed concrete frame beam column joint with U-shaped steel bar and sleeves |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3613325A (en) * | 1969-07-10 | 1971-10-19 | Yee Alfred A | Concrete construction |
US3867805A (en) * | 1972-05-18 | 1975-02-25 | Kajima Corp | Method of forming joint construction of precast concrete columns and beams |
CN1502756A (en) * | 2002-11-22 | 2004-06-09 | 钟肇鸿 | Beam column node structure for building frame and construction method |
CN2918572Y (en) * | 2006-07-17 | 2007-07-04 | 福州大学 | Beam-column connected node employed in building frame |
CN101492918A (en) * | 2008-01-24 | 2009-07-29 | 华东建筑设计研究院有限公司 | Beam column node for base pit engineering of topdown construction method |
-
2010
- 2010-03-29 CN CN 201010134828 patent/CN101806148A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3613325A (en) * | 1969-07-10 | 1971-10-19 | Yee Alfred A | Concrete construction |
US3867805A (en) * | 1972-05-18 | 1975-02-25 | Kajima Corp | Method of forming joint construction of precast concrete columns and beams |
CN1502756A (en) * | 2002-11-22 | 2004-06-09 | 钟肇鸿 | Beam column node structure for building frame and construction method |
CN2918572Y (en) * | 2006-07-17 | 2007-07-04 | 福州大学 | Beam-column connected node employed in building frame |
CN101492918A (en) * | 2008-01-24 | 2009-07-29 | 华东建筑设计研究院有限公司 | Beam column node for base pit engineering of topdown construction method |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103046746A (en) * | 2012-12-03 | 2013-04-17 | 成军 | Construction method of conversion beam reinforcing bars for tall building structure |
CN103046746B (en) * | 2012-12-03 | 2014-01-29 | 江苏通州四建集团有限公司 | Construction method of conversion beam reinforcing bars for tall building structure |
CN103195172A (en) * | 2013-04-16 | 2013-07-10 | 东南大学 | Beam-column joint structure of prefabricated concrete frame |
CN103195172B (en) * | 2013-04-16 | 2015-09-09 | 东南大学 | A kind of prefabrication and assembly construction concrete frame beam-column connection structure |
CN104164920A (en) * | 2014-07-23 | 2014-11-26 | 南京长江都市建筑设计股份有限公司 | Bottom steel bar connecting structure of key groove node precast frame beam |
CN105625572A (en) * | 2016-02-29 | 2016-06-01 | 东南大学 | Prefabricated prestressed concrete frame beam-column joint making disparate use of high performance materials |
CN105649203A (en) * | 2016-02-29 | 2016-06-08 | 东南大学 | Prefabricated prestressed concrete frame beam column joint with U-shaped steel bar and sleeves |
CN105625572B (en) * | 2016-02-29 | 2018-05-15 | 东南大学 | Distinctiveness uses the precast prestressed concrete frame bean column node of high performance material |
CN105649203B (en) * | 2016-02-29 | 2018-07-17 | 东南大学 | Precast prestressed concrete frame bean column node with U-shaped muscle and sleeve |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204023778U (en) | The connected node of prefabricated assembled concrete beam column | |
CN108951886B (en) | Prefabricated assembled concrete anti-seismic node | |
CN204185755U (en) | A kind of Wavelike steel webplate post-stressed concrete T beam | |
CN201826325U (en) | Foundation structure of tower crane | |
CN210857510U (en) | Beam tenon-and-mortise joint unit and connector of beam tenon-and-mortise joint unit and profile steel concrete beam | |
CN102477781A (en) | Integrally assembled steel-concrete superposed component and manufacturing method thereof | |
CN101806148A (en) | Construction method for concrete beam with U-shaped steel bar connecting joints | |
CN111962952A (en) | Steel tube concrete column-H-shaped steel beam-steel support-pi-shaped connecting piece combined type center pillar bottom node and manufacturing method | |
CN103437493B (en) | Connecting node of prefabricated reinforced concrete beam and construction method of connecting node | |
CN107355008B (en) | Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure | |
CN204112525U (en) | Band perps precast shear wall structure in strong concrete precast frame | |
CN202969410U (en) | SCOPE type pipe tower foundation | |
CN203755443U (en) | Assembly integrated type overlapping frame structure | |
CN102953344B (en) | Climbing cone type triangular cantilever bracket | |
CN203200745U (en) | Underground continuous wall's reinforcement support in reverse construction method construction | |
CN103790176A (en) | Embedded short limb column structure and construction method thereof | |
CN204023777U (en) | The connected node of prefabricated assembled concrete beam column | |
CN206928427U (en) | A kind of dry type assembled ECC protective layer node structures | |
CN103758208B (en) | Assembled integral composite frame structure | |
CN106978908B (en) | Embedded prestress assembly type frame reinforcing structure with shearing mild steel damper | |
CN203440993U (en) | Connection joint of prefabricated reinforced concrete beam | |
CN211548015U (en) | Prefabricated assembled steel-concrete composite beam | |
CN111962950A (en) | Steel tube concrete column-H-shaped steel beam-steel support-Pi-shaped connecting piece combined type corner column middle node and manufacturing method | |
CN111962951A (en) | Steel tube concrete column-H-shaped steel beam-steel support-Pi-shaped connecting piece combined type corner column bottom node and manufacturing method | |
CN203701386U (en) | Steel-structure floor slab group |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20100818 |