CN105401495B - Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway - Google Patents

Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway Download PDF

Info

Publication number
CN105401495B
CN105401495B CN201510691937.2A CN201510691937A CN105401495B CN 105401495 B CN105401495 B CN 105401495B CN 201510691937 A CN201510691937 A CN 201510691937A CN 105401495 B CN105401495 B CN 105401495B
Authority
CN
China
Prior art keywords
rail
long rail
sleeper
track
long
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510691937.2A
Other languages
Chinese (zh)
Other versions
CN105401495A (en
Inventor
杨东海
徐志刚
王新民
黄�俊
王国进
李浩宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 15th Bureau Group Co Ltd
Original Assignee
China Railway 15th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 15th Bureau Group Co Ltd filed Critical China Railway 15th Bureau Group Co Ltd
Priority to CN201510691937.2A priority Critical patent/CN105401495B/en
Publication of CN105401495A publication Critical patent/CN105401495A/en
Application granted granted Critical
Publication of CN105401495B publication Critical patent/CN105401495B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/05Transporting, laying, removing, or renewing both rails and sleepers

Abstract

The invention particularly discloses a method for rapidly and directly paving a 100 m long rail of a ballast track of a newly-built railway. The problems that an existing long rail paving method wastes time and labor in work, high in cost and longer in working period are solved. The method comprises the steps that a, a sleeper arrangement line is precisely paid off, and sleeper dismounting and sleeper scattering are carried out; b, when the middle portion of a sleeper is higher than the two ends, a rubber pad is used for temporarily raising the two ends of the sleeper; c, a roller is mounted; d, the 100 m long rail is pushed to fall into a line rail bearing groove; e, the front-and-back position of the long rail is adjusted, a buckle bolt is mounted, and a temporary line is formed; f, after a long rail transport vehicle leaves, sleeper distributing and putting work is done, and all remaining buckles are supplemented; g, a ballast bed is supplemented for a railway ballast; h, track raising and tamping work is done; I, the error between the line and design is precisely measured; j, precise ballast arrangement is carried out; and k, long rail stress relieving, rail line welding and long rail polishing operation are done, and then manual fine ballast arrangement is carried out. According to the method, the working period is shortened by more than 70%.

Description

The long rail fast direct laying methods of newly built railway Ballast track 100m
Technical field
The present invention relates to railway's long rail laying method, the long rail fast direct paving of specially a kind of newly built railway Ballast track 100m Method.
Background technology
With railway engineering technology progress, engineer equipment there has also been development at full speed, at present, track-laying machine, Bridge Erector, the fortune tiny fragments of stone, coal, etc. The large-scale special equipments such as train, railway ballast tamping tool, track lifting and lining machine, live rail gap welding equipment, track grinding machine, with mechanization The characteristics of degree is high, construction quality is good, it is deep to be favored by vast construction and one line of maintenance, have become China's trackways engineering construction And the conventional meanses of maintenance.
It is when roadbed and bridge, tunnel frequently replace paving frame operation, general more using laid process is changed, i.e., first use 25m rail Laying temporary line, then removes 25m rail, changes the long rails of paving 100m or 500m.
Laid process is changed except scene need to lay the bottom tiny fragments of stone, coal, etc. and the part face tiny fragments of stone, coal, etc. in advance, and one fixed width and depth is clawed in road center portion position Tiny fragments of stone, coal, etc. groove need by manually being constructed outside, remaining work completes subsequent construction by big machinery.I.e.:1st, utilize tracklaying base Section of track assembly production chain complete the section of track standardization assembling;2nd, the section of track is transported to laying scene by utilizing works train;3rd, profit The 25m standard sections of track are laid on circuit with track-laying machine, there is provided the large-scale rail such as track-laying machine, Bridge Erector, fortune tiny fragments of stone, coal, etc. car, Long rail pushing car The traveling occasional passage of row equipment;4th, by long rail transport vehicle by 100m Long rail pushings are to scene and unload and be placed on the heart, by manually tearing open Except 25m full-length tool tracks, track both sides are allocated to, then long rail is dialled in sleeper rail support groove, fastener for installing forms long path Road;5th, 25m standard gauges are reclaimed using receipts rail train, and sends tracklaying base back to and re-assembly the section of track;6th, using fortune tiny fragments of stone, coal, etc. train to line Road supplements railway ballast;7th, stabilized it using large-scale tamping tool ballast tamping;8th, stress is completed using special weldering rail and grinding apparatus Diffuse, rail gap welding, long rail polishing etc. operation;9th, fine whole road operation is carried out using large-scale track lifting and lining machine by design requirement, directly To reaching circuit design standard.
Entirely the process of laying a railway track must possess following condition:Enough duration, specially setting tracklaying base and section of track assembling stream Waterline, the substantial amounts of 25m standards rail of outfit walk row of channels, track-laying machine, standard steel temporarily as the various machineries of tool track laying Rail reclaims train etc..
However, current long rail gapless track laying method, by duration, tracklaying base section of track assembly production chain, lays a railway track Machine, rail reclaim the serious restriction of the conditions such as train, it is impossible to adapt to the duration tight, the railway Ballast track circuit without bridge formation task Laying construction.
The content of the invention
The present invention in order to solve to exist during existing long rail laying method operation waste time and energy, high cost and duration longer are asked A kind of topic, there is provided the long rail fast direct laying method of newly built railway Ballast track 100m.
The present invention adopts the following technical scheme that realization:The long rail fast direct laying methods of newly built railway Ballast track 100m, Using following steps:A, online lower engineering surface accurately release sleeper deployment line, carry out unloading pillow by hand fit's automobile and fork truck And dissipate pillow operation;B, check that sleeper contacts situation with bottom structures, when occurring two ends being higher by the middle part of sleeper, with rubber cushion by rail Pillow two ends are temporarily padded, prevent sleeper stress from fractureing;C, install according to a determining deviation and using pre-buried fastening bolt on sleeper Cylinder, remaining sleeper is worn over nut at the top of bolt to be prevented from damaging screw thread;D, using in long rail transport vehicle clamper push The long rails of 100m fall into circuit rail support groove, are reduced using cylinder and push resistance and control height and direction, just to complete single long rail Position;E, using drawing rail device to adjust long rail front and back position, manually installed fastening bolt forms temporary line, for long rail transport vehicle after It is continuous to be carried forward long rail laying operation;After f, long rail transport vehicle are left, manually carry out in time even pillow, side pillow operation, and polishing its Remaining all fasteners;G, using fortune tiny fragments of stone, coal, etc. car supply railway ballast according to design quantity into railway roadbed;H, raised track using large-scale tamping car And tamping operation;I, according to mono- pile spacings of every 5m, height, deflection error between accurate measurement circuit and design;J, large-scale dial Road machine carries out fine whole road;K, carry out long rail destressing, rail gap welding, artificial fine whole road after long rail polishing operation.
Need not carry out changing paving operation using the straight laying method, and eliminate section of track streamline and purchase and mounting cost, and Eliminate substantial amounts of interim 25m tool tracks operation and the expense such as purchases, transports, laying, removing, reclaiming;Do not require the use of simultaneously Track-laying machine and rail reclaimer, exist when overcoming existing long rail laying method operation waste time and energy, high cost and duration compared with Long problem.
The construction speed that straight laying method of the present invention is significantly accelerated, and eliminate large number quipments and section of track streamline Purchase, cost has obtained significantly reducing, compared with conventional laying technology, compression of time limit for a project more than 70%, economic benefit is very Significantly.
Specific embodiment
The long rail fast direct laying methods of newly built railway Ballast track 100m, using following steps:A, online lower engineering surface essence Sleeper deployment line is really released, is carried out unloading pillow by hand fit's automobile and fork truck and is dissipated pillow operation;B, inspection sleeper and bottom are constructed Thing contacts situation, when occurring being higher by two ends in the middle part of sleeper, will be sleeper two ends temporarily padded with rubber cushion, and prevent sleeper stress from rolling over It is disconnected;C, according to a determining deviation and using pre-buried fastening bolt mounting rotary drum on sleeper, nut is worn over bolt top by remaining sleeper Portion prevents from damaging screw thread;D, the long rails of 100m are pushed using the clamper in long rail transport vehicle fall into circuit rail support groove, using cylinder Reduce and push resistance and control height and direction, to complete the in place of single long rail;E, utilization draw rail device to adjust long rail front and back position, Manually installed fastening bolt, forms temporary line, continues to be carried forward long rail laying operation for long rail transport vehicle;F, the transport of long rail After car leaves, even pillow, side's pillow operation, and polishing remaining all fastener are manually carried out in time;G, utilization fortune tiny fragments of stone, coal, etc. car are used according to design Measure and supply railway ballast into railway roadbed;H, raised track and tamping operation using large-scale tamping car;I, according to mono- pile spacings of every 5m, accurately Height, deflection error between measurement circuitry and design;J, large-scale track lifting and lining machine carry out fine whole road;K, carry out long rail stress and put Artificial fine whole road after the welding of scattered, rail gap, long rail polishing operation.
In specific implementation process, one series cylinder is installed according to every 5 sleepers;Every 5 sleepers install one group of fastener spiral shell simultaneously Bolt.

Claims (1)

1. long rail fast direct laying methods of a kind of newly built railway Ballast track 100m, it is characterised in that:Using following steps:It is a, online Lower engineering surface accurately releases sleeper deployment line, carries out unloading pillow by hand fit's automobile and fork truck and dissipates pillow operation;B, inspection rail Pillow contacts situation with bottom structures, when occurring being higher by two ends in the middle part of sleeper, will be sleeper two ends temporarily padded with rubber cushion, and prevent Sleeper stress fractures;C, according to a determining deviation and using pre-buried fastening bolt mounting rotary drum on sleeper, remaining sleeper is by nut Being worn at the top of bolt prevents from damaging screw thread;D, the long rails of 100m are pushed using the clamper in long rail transport vehicle fall into circuit support rail Groove, is reduced using cylinder and pushes resistance and control height and direction, to complete the in place of single long rail;E, utilization draw rail device adjustment length Rail front and back position, manually installed fastening bolt form temporary line, continue to be carried forward long rail laying work for long rail transport vehicle Industry;After f, long rail transport vehicle are left, even pillow, side's pillow operation, and polishing remaining all fastener are manually carried out in time;G, the utilization fortune tiny fragments of stone, coal, etc. Car supplies railway ballast according to design quantity into railway roadbed;H, raised track and tamping operation using large-scale tamping car;I, according to every 5m One pile spacing, height, deflection error between accurate measurement circuit and design;J, large-scale track lifting and lining machine carry out fine whole road;K, enter The long rail destressing of row, rail gap welding, artificial fine whole road after long rail polishing operation.
CN201510691937.2A 2015-10-23 2015-10-23 Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway Active CN105401495B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510691937.2A CN105401495B (en) 2015-10-23 2015-10-23 Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510691937.2A CN105401495B (en) 2015-10-23 2015-10-23 Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway

Publications (2)

Publication Number Publication Date
CN105401495A CN105401495A (en) 2016-03-16
CN105401495B true CN105401495B (en) 2017-03-22

Family

ID=55467227

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510691937.2A Active CN105401495B (en) 2015-10-23 2015-10-23 Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway

Country Status (1)

Country Link
CN (1) CN105401495B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108951323A (en) * 2018-08-06 2018-12-07 中铁十局集团第三工程有限公司 A kind of Ballast track laying method
CN112982044B (en) * 2021-03-24 2023-01-06 广西柳州钢铁集团有限公司 Construction process for quickly forming integral road bed of road junction

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5528991A (en) * 1995-06-30 1996-06-25 Huber; Friedrich Apparatus and associated methods of laying track
CN101050615B (en) * 2007-04-28 2011-03-30 中铁四局集团有限公司 Constructing method for laying seamless line track by CPG 500 type seamless line long rail laying unit
CN102002897B (en) * 2010-12-11 2012-05-02 中铁二十五局集团有限公司 Long rail laying device and method
CN102071606B (en) * 2010-12-14 2012-03-21 株洲长远铁路建机有限公司 Multi-sleeper type long rail laying machine set and rail laying method thereof
CN102002898A (en) * 2010-12-15 2011-04-06 株洲长远铁路建机股份有限公司 Construction method of group-sleeper long rail track-laying unit for laying seamless track ballasted beds
CN102296495B (en) * 2011-05-25 2013-01-23 中铁二十局集团第四工程有限公司 Long steel rail laying and welding construction process under conditions of large temperature differences and strong sandstorms
CN203113177U (en) * 2013-01-30 2013-08-07 中铁十六局集团铁运工程有限公司宁阳制梁场 Ballast railway steel rail delivery cylinder
CN104790271B (en) * 2015-05-20 2016-11-30 中铁十五局集团有限公司 A kind of long rail of Ballast track straight Pu Qianzheng road method

Also Published As

Publication number Publication date
CN105401495A (en) 2016-03-16

Similar Documents

Publication Publication Date Title
CN104562863B (en) A kind of dual-purpose railway two-orbit
US4854243A (en) Mobile track renewal machine
CS235033B2 (en) Method of substructure continuous maintenance and mobile equipment for its application
CN103452018B (en) Track gauge correction method for double-block type ballastless track construction
CN105401495B (en) Method for rapidly and directly paving 100 m long rail of ballast track of newly-built railway
AT398097B (en) SYSTEM FOR PRODUCING A PLANUM PROTECTIVE LAYER
CZ89287A3 (en) Track packing machine
CN111827022A (en) Quick maintenance method for double-block ballastless track
CZ294637B6 (en) Track renewing machine
DE3819717A1 (en) CONTINUOUSLY (NON-STOP) TRAVELABLE TRACKING MACHINE
EP0712961A1 (en) Method and arrangement for the subgrade-rehabilitation of the ballast of a railway track
JP3267787B2 (en) Ballast updating machine
DE3908007A1 (en) TRACK CONSTRUCTION MACHINE WITH TRACK STABILIZER
US10385517B2 (en) Method for track renewal
CN203440722U (en) Gauge correction device for double-block type ballastless track construction
CN104790271A (en) Track finishing method before direct pavement of long rails of ballast track
DE3634398C2 (en) Mobile system for the continuous renewal of the rails and sleepers of a track
CN105926382B (en) A kind of general solid concrete roabed of metro depot reserves grooved tracks construction method
CN111794018A (en) Construction method of ballastless track with replaceable supporting blocks by tunnel sleeve shoe method
DE202008003589U1 (en) Track rehabilitation machine with base layer milling machine
EP2159323B1 (en) Device for reconditioning track sections for train transport
CN204551143U (en) A kind of dual-purpose railway two-rail
CN110258209B (en) Replacement method of high-speed rail ballastless transition plate support system
DE10008986A1 (en) Reconstruction/modification method for railway track uses appliance to remove/ regenerated old track materials and construct new track, in one single working phase and one direction only
RU2789281C1 (en) Method for packing a slab-based turnout

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant