CN105298537A - Mounting method of conveying pipe for solid filling material - Google Patents

Mounting method of conveying pipe for solid filling material Download PDF

Info

Publication number
CN105298537A
CN105298537A CN201410289269.6A CN201410289269A CN105298537A CN 105298537 A CN105298537 A CN 105298537A CN 201410289269 A CN201410289269 A CN 201410289269A CN 105298537 A CN105298537 A CN 105298537A
Authority
CN
China
Prior art keywords
commissioning pipe
boring
pipe
commissioning
filling material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410289269.6A
Other languages
Chinese (zh)
Inventor
张吉雄
缪协兴
巨峰
高瑞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201410289269.6A priority Critical patent/CN105298537A/en
Publication of CN105298537A publication Critical patent/CN105298537A/en
Pending legal-status Critical Current

Links

Landscapes

  • Earth Drilling (AREA)

Abstract

The invention discloses a mounting method of a conveying pipe for solid filling material. The conveying pipe for solid filling material is mounted in a borehole vertically drilled. Preparations such as borehole inclination measuring and borehole smoothing are done before the mounting of feed pipes; a bottom feed pipe is mounted, the bottom feed pipe is lifted to an upper opening of the borehole by using a crane, the bottom feed pipe is fastened with a hoop, a next feed pipe is then aligned and welded to the bottom feed pipe, inclination measuring is performed on the feed pipes mounted, and all feed pipes are cyclically lowered in succession; finally, feed pipe wall post-grouting and fixation are finished by using a drill pipe. Since the conveying pipe for solid filling material is long and heavy, the method enables the safe, quick mounting of the conveying pipe for solid filling material, thus giving a greatly shortened well completion period.

Description

A kind of solid filling material conveyance conduit mounting method
Technical field
The present invention relates to a kind of solid filling material conveyance conduit mounting method, be particularly useful for colliery vertical feeding well Cheng Jing safely and fast.
Background technology
Filling mining technology is domestic and international mine for controlling a kind of method that strata movement and subsidence adopt, solid filling exploitation is a kind of new method of development in recent years, namely ground spoil is utilized, loess, the solids such as flyash are filled in underground goaf, therefore, solid filling thing must be transported to down-hole, by playing vertical feeding boring from ground, solid filling thing is directly thrown in down-hole, in order to ensure the throughput of solid filling material, feed intake boring in solid filling material conveyance conduit has been installed, and adopt the high-strength abrasion-proof pipeline of special manufacture, larger owing to vertically throwing in distance, general from 200m ~ 800m not etc., cause solid filling material conveyance conduit weight huge, usually the weight of every 100m just reaches more than 70t, in solid filling material conveyance conduit installation process, huge weight drastically influence installation safety and the efficiency of pipeline.Installing safely and fast to realize solid filling material conveyance conduit, ensureing to feed intake one-tenth well duration of well, have employed this mounting method.
Summary of the invention
Technical problem: the object of the invention is the deficiency overcome in prior art, provides a kind of method simple, safe and reliable, efficiency guaranteed solid filling material conveyance conduit mounting method.
Technical scheme: solid filling material conveyance conduit mounting method of the present invention, comprises the boring of vertically digging to down-hole along rock stratum, carries out deviational survey to boring and along behind hole, in the boring of vertically digging along rock stratum, installs commissioning pipe;
First suspend coxopodite commissioning pipe in midair with crane to transfer in boring, when coxopodite commissioning pipe upper port is positioned at boring upper port position, has adopted clip to be fixed on operating platform by the upper port of coxopodite commissioning pipe, unclamp crane lifting rope; Having suspended next joint commissioning pipe again in midair transfers to lower port and coxopodite commissioning pipe upper port place, alignment is firm welding also, two commissioning pipes that butt welding connects carry out deviational survey, unclamp clip, transfer commissioning pipe, until when next joint commissioning pipe upper port is positioned at boring upper port position, clip is adopted to be fixed on operating platform by the commissioning pipe upper port of continued access, go round and begin again, continuous continued access one saves commissioning pipe, until the commissioning pipe completed in whole boring is installed;
After commissioning pipe installation, in commissioning pipe, transfer the kickboard be connected with slip casting drilling rod, utilize slip casting drilling rod to be injected in the space between boring and commissioning pipe by kickboard by slurries, after grout cures, remove slip casting drilling rod, complete commissioning pipe installation work.
The described length often saving commissioning pipe is 5m ~ 10m; Two commissioning pipes that described butt welding connects carry out deviational survey, and its gradient is not more than 1 ‰, should adjust immediately if be greater than this value.
Beneficial effect: the present invention, by boring deviational survey and suitable hole in advance, transfers commissioning pipe section by section by crane and clip, adopts and cut open weldering welding procedure, achieve solid filling material carrier pipe and install safely and fast.This not only ensures the Completed advance rate fed intake in well construction, also for the installing engineering of domestic and international conditions of similarity pipe fitting provides technological borrowing, its method is simple, and easily construct, successful, has practicality widely.
Accompanying drawing explanation
Fig. 1 is solid filling material conveyance conduit mounting structure schematic diagram of the present invention;
Fig. 2 is the structural representation of clip 4 of the present invention.
In figure: 1-rock stratum, 2-holes, 3-commissioning pipe, 4-coxopodite commissioning pipe, 5-clip, next joint commissioning pipe of 6-, 7-slip casting drilling rod, 8-slurries, 9-kickboard, 10-operating platform.
Detailed description of the invention
Below in conjunction with accompanying drawing, one embodiment of the present of invention are further described:
Solid filling material conveyance conduit mounting method of the present invention, comprises the boring 2 of vertically digging to down-hole along rock stratum 1: deviational survey is carried out to boring 2 and along behind hole, in the boring 2 of vertically digging along rock stratum 1, commissioning pipe 3 is installed;
First suspend coxopodite commissioning pipe 4 in midair with crane to transfer in boring 2, when coxopodite commissioning pipe 4 upper port is positioned at boring 2 upper port position, has adopted clip 5 upper port of coxopodite commissioning pipe 4 to be fixed on operating platform 10, unclamp crane lifting rope; Having suspended next joint commissioning pipe 6 again in midair transfers to lower port and coxopodite commissioning pipe 4 upper port place, and alignment is firm welding also, and next joint commissioning pipe 6 lower port described is transferred and alignd to coxopodite commissioning pipe 4 upper port and weld, and the welding manner of employing is for cuing open weldering.Two commissioning pipes that butt welding connects carry out deviational survey, and its gradient is not more than 1 ‰, should adjust immediately if be greater than this value.Unclamp clip 5, transfer commissioning pipe, until when next joint commissioning pipe 6 upper port is positioned at boring 2 upper port position, clip 5 is adopted to be fixed on operating platform 10 by the commissioning pipe upper port of continued access, go round and begin again, continuous continued access one saves commissioning pipe 6, and the length often saving commissioning pipe is 5m ~ 10m, until the commissioning pipe completed in whole boring 2 is installed;
After commissioning pipe 3 installation, the kickboard 9 be connected with slip casting drilling rod 7 is transferred in commissioning pipe 3, utilize slip casting drilling rod 7 to be injected in the space between boring 2 and commissioning pipe by slurries 8 by kickboard 9, after slurries 8 solidify, remove slip casting drilling rod 7, complete commissioning pipe installation work.
Embodiment 1,
For Kai Luan group Tangshan Mine: according to on-site actual situations, actual batch depth is about 650m, the bore diameter that feeds intake is 960mm, commissioning pipe external diameter is 500mm, and the length of single-unit commissioning pipe is 8m, and the weight of single-unit commissioning pipe is 5.6t, the gross weight of all commissioning pipes is 455t, the lifting appliance adopted is straddle truck and heavy duty crane, and select J507 type carbon steel, the slurries of use are light water mud.
In the boring 2 of vertically digging along rock stratum 1, commissioning pipe 3 is installed, first, before installation commissioning pipe 3, first deviational survey is carried out to boring 2 and along hole, adopt JJX-3 type inclinometer and ZGL13-CX-1 type high definition television shooting-imaging modality clinograph associating deviational survey, adopt common steel tube along hole; Then, crane suspention coxopodite commissioning pipe 4 is adopted to transfer to boring 2 position of upper place, utilize clip 5 by coxopodite commissioning pipe fixing-stable, unclamp crane lifting rope, adopting crane to suspend next joint commissioning pipe 6 in midair again transfers to align also firm welding suitable for reading with coxopodite commissioning pipe 4, two commissioning pipes that butt welding connects carry out deviational survey, and the process of circulation c, d and e is until the commissioning pipe completed in whole boring 2 is installed; Finally, utilize slip casting drilling rod 7 to be injected in the space between boring 2 and commissioning pipe by slurries 8 by kickboard 9, after slurries 8 solidify, remove slip casting drilling rod 7, complete commissioning pipe installation work.

Claims (3)

1. a solid filling material conveyance conduit mounting method, comprise the boring (2) of vertically digging to down-hole along rock stratum (1), it is characterized in that: deviational survey is carried out to boring (2) and along behind hole, in the boring (2) of vertically digging along rock stratum (1), commissioning pipe (3) is installed;
First suspend coxopodite commissioning pipe (4) in midair with crane to transfer in boring (2), when coxopodite commissioning pipe (4) upper port is positioned at boring (2) upper port position, adopt clip (5) upper port of coxopodite commissioning pipe (4) to be fixed on operating platform (10), unclamp crane lifting rope; Having suspended next joint commissioning pipe (6) again in midair transfers to lower port and coxopodite commissioning pipe (4) upper port place, alignment is firm welding also, two commissioning pipes that butt welding connects carry out deviational survey, unclamp clip (5), transfer commissioning pipe, until when next joint commissioning pipe (6) upper port is positioned at boring (2) upper port position, clip (5) is adopted to be fixed on operating platform (10) by the commissioning pipe upper port of continued access, go round and begin again, continuous continued access one saves commissioning pipe (6), until the commissioning pipe completed in whole boring (2) is installed;
After commissioning pipe (3) installation, the kickboard (9) be connected with slip casting drilling rod (7) is transferred in commissioning pipe (3), slip casting drilling rod (7) is utilized to be injected in the space between boring (2) and commissioning pipe by slurries (8) by kickboard (9), after slurries (8) solidify, remove slip casting drilling rod (7), complete commissioning pipe installation work.
2. solid filling material conveyance conduit mounting method according to claim 1 and 2, is characterized in that: the length often saving commissioning pipe is 5m ~ 10m.
3. solid filling material conveyance conduit mounting method according to claim 1, is characterized in that: two commissioning pipes that described butt welding connects carry out deviational survey, and its gradient is not more than 1 ‰, should adjust immediately if be greater than this value.
CN201410289269.6A 2014-06-25 2014-06-25 Mounting method of conveying pipe for solid filling material Pending CN105298537A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410289269.6A CN105298537A (en) 2014-06-25 2014-06-25 Mounting method of conveying pipe for solid filling material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410289269.6A CN105298537A (en) 2014-06-25 2014-06-25 Mounting method of conveying pipe for solid filling material

Publications (1)

Publication Number Publication Date
CN105298537A true CN105298537A (en) 2016-02-03

Family

ID=55196266

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410289269.6A Pending CN105298537A (en) 2014-06-25 2014-06-25 Mounting method of conveying pipe for solid filling material

Country Status (1)

Country Link
CN (1) CN105298537A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105952452A (en) * 2016-04-22 2016-09-21 中国矿业大学 Oil bag type solid filling coal mining three-dimensional physical similarity simulation experiment device and method
CN110630321A (en) * 2019-10-29 2019-12-31 中冶沈勘秦皇岛工程设计研究总院有限公司 Goaf on-well filling equipment and method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101566072A (en) * 2009-05-22 2009-10-28 中国矿业大学 Large vertical depth solid feeding system and large vertical depth solid feeding process for filling extracted coal
CN201517424U (en) * 2009-09-15 2010-06-30 河北金牛能源股份有限公司 Adhesive solid material big falling deep block-resistant transmission equipment
CN202325670U (en) * 2011-12-01 2012-07-11 山西阳泉盂县东坪煤业有限公司 Comprehensive mechanized solid filling coal mining device
CN102889097A (en) * 2012-09-20 2013-01-23 河北煤炭科学研究院 System for feeding coal mine solid filling material

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101566072A (en) * 2009-05-22 2009-10-28 中国矿业大学 Large vertical depth solid feeding system and large vertical depth solid feeding process for filling extracted coal
CN201517424U (en) * 2009-09-15 2010-06-30 河北金牛能源股份有限公司 Adhesive solid material big falling deep block-resistant transmission equipment
CN202325670U (en) * 2011-12-01 2012-07-11 山西阳泉盂县东坪煤业有限公司 Comprehensive mechanized solid filling coal mining device
CN102889097A (en) * 2012-09-20 2013-01-23 河北煤炭科学研究院 System for feeding coal mine solid filling material

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
巨峰: "固体充填采煤物料垂直输送技术开发与工程应用", 《中国博士学位论文全文数据库》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105952452A (en) * 2016-04-22 2016-09-21 中国矿业大学 Oil bag type solid filling coal mining three-dimensional physical similarity simulation experiment device and method
CN110630321A (en) * 2019-10-29 2019-12-31 中冶沈勘秦皇岛工程设计研究总院有限公司 Goaf on-well filling equipment and method thereof
CN110630321B (en) * 2019-10-29 2024-05-17 中冶沈勘秦皇岛工程设计研究总院有限公司 Goaf aboveground filling equipment and goaf aboveground filling method

Similar Documents

Publication Publication Date Title
CN102182471B (en) Advance support method for coal mine tunnel high-risk area
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN104675422B (en) The hydraulic means of coal mine roadway temporary support for drivage face
CN107448214B (en) Large-scale two lane pre-pouring grout method of geological structure crack coal and rock superdeep holes high pressure
CN103867229A (en) Coal mine large-mining-depth and next-group coal exploitation water control comprehensive treatment method
CN103775127A (en) Method for comprehensively treating gas in low-air-permeability high-gas-content coal seam group
CN107816366B (en) A kind of multilayer goaf filling well is at well engineering method
CN105545353A (en) Artificial top construction method based on paste filling
CN101608552A (en) The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process
CN103670510B (en) Roadway tiretube process discharge water in gob area method
CN105351001A (en) Gas extraction method for region reinforcement of gob-side entry retaining
CN104989272A (en) Upward inverse well drilling process
CN102966359A (en) Working face ventilation oxidization zone roof control method
CN103670401B (en) A kind of drum shearer that can two-wayly creep into of certainly walking
CN110439463A (en) Mined-out Area control injected hole pore-creating technique
CN106837382A (en) A kind of subway tunnel country rock pre grouting from the surface reinforcement process
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN109779634B (en) Method for determining position of fractured hard top plate of coal mine ground vertical well
CN105298537A (en) Mounting method of conveying pipe for solid filling material
CN104481535B (en) A kind of drilling integral method for half-edge coal seam
CN108316925B (en) Simple gob-side entry retaining method for drilling and roof breaking of working face with three-soft coal layer thickness direct roof
CN105971504A (en) Drilling structure, method and device for uncertain stratum of target reservoir
CN105134125A (en) Construction process for blocking bottom end of annular space behind gas vertical well wall
CN105156148B (en) Gas vertical gas tube mounting process
CN109944634B (en) Coal seam top and bottom plate filling type goaf filling structure and filling method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160203