CN105298537A - Mounting method of conveying pipe for solid filling material - Google Patents
Mounting method of conveying pipe for solid filling material Download PDFInfo
- Publication number
- CN105298537A CN105298537A CN201410289269.6A CN201410289269A CN105298537A CN 105298537 A CN105298537 A CN 105298537A CN 201410289269 A CN201410289269 A CN 201410289269A CN 105298537 A CN105298537 A CN 105298537A
- Authority
- CN
- China
- Prior art keywords
- commissioning pipe
- boring
- pipe
- commissioning
- filling material
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Earth Drilling (AREA)
Abstract
The invention discloses a mounting method of a conveying pipe for solid filling material. The conveying pipe for solid filling material is mounted in a borehole vertically drilled. Preparations such as borehole inclination measuring and borehole smoothing are done before the mounting of feed pipes; a bottom feed pipe is mounted, the bottom feed pipe is lifted to an upper opening of the borehole by using a crane, the bottom feed pipe is fastened with a hoop, a next feed pipe is then aligned and welded to the bottom feed pipe, inclination measuring is performed on the feed pipes mounted, and all feed pipes are cyclically lowered in succession; finally, feed pipe wall post-grouting and fixation are finished by using a drill pipe. Since the conveying pipe for solid filling material is long and heavy, the method enables the safe, quick mounting of the conveying pipe for solid filling material, thus giving a greatly shortened well completion period.
Description
Technical field
The present invention relates to a kind of solid filling material conveyance conduit mounting method, be particularly useful for colliery vertical feeding well Cheng Jing safely and fast.
Background technology
Filling mining technology is domestic and international mine for controlling a kind of method that strata movement and subsidence adopt, solid filling exploitation is a kind of new method of development in recent years, namely ground spoil is utilized, loess, the solids such as flyash are filled in underground goaf, therefore, solid filling thing must be transported to down-hole, by playing vertical feeding boring from ground, solid filling thing is directly thrown in down-hole, in order to ensure the throughput of solid filling material, feed intake boring in solid filling material conveyance conduit has been installed, and adopt the high-strength abrasion-proof pipeline of special manufacture, larger owing to vertically throwing in distance, general from 200m ~ 800m not etc., cause solid filling material conveyance conduit weight huge, usually the weight of every 100m just reaches more than 70t, in solid filling material conveyance conduit installation process, huge weight drastically influence installation safety and the efficiency of pipeline.Installing safely and fast to realize solid filling material conveyance conduit, ensureing to feed intake one-tenth well duration of well, have employed this mounting method.
Summary of the invention
Technical problem: the object of the invention is the deficiency overcome in prior art, provides a kind of method simple, safe and reliable, efficiency guaranteed solid filling material conveyance conduit mounting method.
Technical scheme: solid filling material conveyance conduit mounting method of the present invention, comprises the boring of vertically digging to down-hole along rock stratum, carries out deviational survey to boring and along behind hole, in the boring of vertically digging along rock stratum, installs commissioning pipe;
First suspend coxopodite commissioning pipe in midair with crane to transfer in boring, when coxopodite commissioning pipe upper port is positioned at boring upper port position, has adopted clip to be fixed on operating platform by the upper port of coxopodite commissioning pipe, unclamp crane lifting rope; Having suspended next joint commissioning pipe again in midair transfers to lower port and coxopodite commissioning pipe upper port place, alignment is firm welding also, two commissioning pipes that butt welding connects carry out deviational survey, unclamp clip, transfer commissioning pipe, until when next joint commissioning pipe upper port is positioned at boring upper port position, clip is adopted to be fixed on operating platform by the commissioning pipe upper port of continued access, go round and begin again, continuous continued access one saves commissioning pipe, until the commissioning pipe completed in whole boring is installed;
After commissioning pipe installation, in commissioning pipe, transfer the kickboard be connected with slip casting drilling rod, utilize slip casting drilling rod to be injected in the space between boring and commissioning pipe by kickboard by slurries, after grout cures, remove slip casting drilling rod, complete commissioning pipe installation work.
The described length often saving commissioning pipe is 5m ~ 10m; Two commissioning pipes that described butt welding connects carry out deviational survey, and its gradient is not more than 1 ‰, should adjust immediately if be greater than this value.
Beneficial effect: the present invention, by boring deviational survey and suitable hole in advance, transfers commissioning pipe section by section by crane and clip, adopts and cut open weldering welding procedure, achieve solid filling material carrier pipe and install safely and fast.This not only ensures the Completed advance rate fed intake in well construction, also for the installing engineering of domestic and international conditions of similarity pipe fitting provides technological borrowing, its method is simple, and easily construct, successful, has practicality widely.
Accompanying drawing explanation
Fig. 1 is solid filling material conveyance conduit mounting structure schematic diagram of the present invention;
Fig. 2 is the structural representation of clip 4 of the present invention.
In figure: 1-rock stratum, 2-holes, 3-commissioning pipe, 4-coxopodite commissioning pipe, 5-clip, next joint commissioning pipe of 6-, 7-slip casting drilling rod, 8-slurries, 9-kickboard, 10-operating platform.
Detailed description of the invention
Below in conjunction with accompanying drawing, one embodiment of the present of invention are further described:
Solid filling material conveyance conduit mounting method of the present invention, comprises the boring 2 of vertically digging to down-hole along rock stratum 1: deviational survey is carried out to boring 2 and along behind hole, in the boring 2 of vertically digging along rock stratum 1, commissioning pipe 3 is installed;
First suspend coxopodite commissioning pipe 4 in midair with crane to transfer in boring 2, when coxopodite commissioning pipe 4 upper port is positioned at boring 2 upper port position, has adopted clip 5 upper port of coxopodite commissioning pipe 4 to be fixed on operating platform 10, unclamp crane lifting rope; Having suspended next joint commissioning pipe 6 again in midair transfers to lower port and coxopodite commissioning pipe 4 upper port place, and alignment is firm welding also, and next joint commissioning pipe 6 lower port described is transferred and alignd to coxopodite commissioning pipe 4 upper port and weld, and the welding manner of employing is for cuing open weldering.Two commissioning pipes that butt welding connects carry out deviational survey, and its gradient is not more than 1 ‰, should adjust immediately if be greater than this value.Unclamp clip 5, transfer commissioning pipe, until when next joint commissioning pipe 6 upper port is positioned at boring 2 upper port position, clip 5 is adopted to be fixed on operating platform 10 by the commissioning pipe upper port of continued access, go round and begin again, continuous continued access one saves commissioning pipe 6, and the length often saving commissioning pipe is 5m ~ 10m, until the commissioning pipe completed in whole boring 2 is installed;
After commissioning pipe 3 installation, the kickboard 9 be connected with slip casting drilling rod 7 is transferred in commissioning pipe 3, utilize slip casting drilling rod 7 to be injected in the space between boring 2 and commissioning pipe by slurries 8 by kickboard 9, after slurries 8 solidify, remove slip casting drilling rod 7, complete commissioning pipe installation work.
Embodiment 1,
For Kai Luan group Tangshan Mine: according to on-site actual situations, actual batch depth is about 650m, the bore diameter that feeds intake is 960mm, commissioning pipe external diameter is 500mm, and the length of single-unit commissioning pipe is 8m, and the weight of single-unit commissioning pipe is 5.6t, the gross weight of all commissioning pipes is 455t, the lifting appliance adopted is straddle truck and heavy duty crane, and select J507 type carbon steel, the slurries of use are light water mud.
In the boring 2 of vertically digging along rock stratum 1, commissioning pipe 3 is installed, first, before installation commissioning pipe 3, first deviational survey is carried out to boring 2 and along hole, adopt JJX-3 type inclinometer and ZGL13-CX-1 type high definition television shooting-imaging modality clinograph associating deviational survey, adopt common steel tube along hole; Then, crane suspention coxopodite commissioning pipe 4 is adopted to transfer to boring 2 position of upper place, utilize clip 5 by coxopodite commissioning pipe fixing-stable, unclamp crane lifting rope, adopting crane to suspend next joint commissioning pipe 6 in midair again transfers to align also firm welding suitable for reading with coxopodite commissioning pipe 4, two commissioning pipes that butt welding connects carry out deviational survey, and the process of circulation c, d and e is until the commissioning pipe completed in whole boring 2 is installed; Finally, utilize slip casting drilling rod 7 to be injected in the space between boring 2 and commissioning pipe by slurries 8 by kickboard 9, after slurries 8 solidify, remove slip casting drilling rod 7, complete commissioning pipe installation work.
Claims (3)
1. a solid filling material conveyance conduit mounting method, comprise the boring (2) of vertically digging to down-hole along rock stratum (1), it is characterized in that: deviational survey is carried out to boring (2) and along behind hole, in the boring (2) of vertically digging along rock stratum (1), commissioning pipe (3) is installed;
First suspend coxopodite commissioning pipe (4) in midair with crane to transfer in boring (2), when coxopodite commissioning pipe (4) upper port is positioned at boring (2) upper port position, adopt clip (5) upper port of coxopodite commissioning pipe (4) to be fixed on operating platform (10), unclamp crane lifting rope; Having suspended next joint commissioning pipe (6) again in midair transfers to lower port and coxopodite commissioning pipe (4) upper port place, alignment is firm welding also, two commissioning pipes that butt welding connects carry out deviational survey, unclamp clip (5), transfer commissioning pipe, until when next joint commissioning pipe (6) upper port is positioned at boring (2) upper port position, clip (5) is adopted to be fixed on operating platform (10) by the commissioning pipe upper port of continued access, go round and begin again, continuous continued access one saves commissioning pipe (6), until the commissioning pipe completed in whole boring (2) is installed;
After commissioning pipe (3) installation, the kickboard (9) be connected with slip casting drilling rod (7) is transferred in commissioning pipe (3), slip casting drilling rod (7) is utilized to be injected in the space between boring (2) and commissioning pipe by slurries (8) by kickboard (9), after slurries (8) solidify, remove slip casting drilling rod (7), complete commissioning pipe installation work.
2. solid filling material conveyance conduit mounting method according to claim 1 and 2, is characterized in that: the length often saving commissioning pipe is 5m ~ 10m.
3. solid filling material conveyance conduit mounting method according to claim 1, is characterized in that: two commissioning pipes that described butt welding connects carry out deviational survey, and its gradient is not more than 1 ‰, should adjust immediately if be greater than this value.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410289269.6A CN105298537A (en) | 2014-06-25 | 2014-06-25 | Mounting method of conveying pipe for solid filling material |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410289269.6A CN105298537A (en) | 2014-06-25 | 2014-06-25 | Mounting method of conveying pipe for solid filling material |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105298537A true CN105298537A (en) | 2016-02-03 |
Family
ID=55196266
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410289269.6A Pending CN105298537A (en) | 2014-06-25 | 2014-06-25 | Mounting method of conveying pipe for solid filling material |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105298537A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105952452A (en) * | 2016-04-22 | 2016-09-21 | 中国矿业大学 | Oil bag type solid filling coal mining three-dimensional physical similarity simulation experiment device and method |
CN110630321A (en) * | 2019-10-29 | 2019-12-31 | 中冶沈勘秦皇岛工程设计研究总院有限公司 | Goaf on-well filling equipment and method thereof |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101566072A (en) * | 2009-05-22 | 2009-10-28 | 中国矿业大学 | Large vertical depth solid feeding system and large vertical depth solid feeding process for filling extracted coal |
CN201517424U (en) * | 2009-09-15 | 2010-06-30 | 河北金牛能源股份有限公司 | Adhesive solid material big falling deep block-resistant transmission equipment |
CN202325670U (en) * | 2011-12-01 | 2012-07-11 | 山西阳泉盂县东坪煤业有限公司 | Comprehensive mechanized solid filling coal mining device |
CN102889097A (en) * | 2012-09-20 | 2013-01-23 | 河北煤炭科学研究院 | System for feeding coal mine solid filling material |
-
2014
- 2014-06-25 CN CN201410289269.6A patent/CN105298537A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101566072A (en) * | 2009-05-22 | 2009-10-28 | 中国矿业大学 | Large vertical depth solid feeding system and large vertical depth solid feeding process for filling extracted coal |
CN201517424U (en) * | 2009-09-15 | 2010-06-30 | 河北金牛能源股份有限公司 | Adhesive solid material big falling deep block-resistant transmission equipment |
CN202325670U (en) * | 2011-12-01 | 2012-07-11 | 山西阳泉盂县东坪煤业有限公司 | Comprehensive mechanized solid filling coal mining device |
CN102889097A (en) * | 2012-09-20 | 2013-01-23 | 河北煤炭科学研究院 | System for feeding coal mine solid filling material |
Non-Patent Citations (1)
Title |
---|
巨峰: "固体充填采煤物料垂直输送技术开发与工程应用", 《中国博士学位论文全文数据库》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105952452A (en) * | 2016-04-22 | 2016-09-21 | 中国矿业大学 | Oil bag type solid filling coal mining three-dimensional physical similarity simulation experiment device and method |
CN110630321A (en) * | 2019-10-29 | 2019-12-31 | 中冶沈勘秦皇岛工程设计研究总院有限公司 | Goaf on-well filling equipment and method thereof |
CN110630321B (en) * | 2019-10-29 | 2024-05-17 | 中冶沈勘秦皇岛工程设计研究总院有限公司 | Goaf aboveground filling equipment and goaf aboveground filling method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102182471B (en) | Advance support method for coal mine tunnel high-risk area | |
CN103835661B (en) | A kind of local excavation pre support mine shaft rising boring technique | |
CN104675422B (en) | The hydraulic means of coal mine roadway temporary support for drivage face | |
CN107448214B (en) | Large-scale two lane pre-pouring grout method of geological structure crack coal and rock superdeep holes high pressure | |
CN103867229A (en) | Coal mine large-mining-depth and next-group coal exploitation water control comprehensive treatment method | |
CN103775127A (en) | Method for comprehensively treating gas in low-air-permeability high-gas-content coal seam group | |
CN107816366B (en) | A kind of multilayer goaf filling well is at well engineering method | |
CN105545353A (en) | Artificial top construction method based on paste filling | |
CN101608552A (en) | The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process | |
CN103670510B (en) | Roadway tiretube process discharge water in gob area method | |
CN105351001A (en) | Gas extraction method for region reinforcement of gob-side entry retaining | |
CN104989272A (en) | Upward inverse well drilling process | |
CN102966359A (en) | Working face ventilation oxidization zone roof control method | |
CN103670401B (en) | A kind of drum shearer that can two-wayly creep into of certainly walking | |
CN110439463A (en) | Mined-out Area control injected hole pore-creating technique | |
CN106837382A (en) | A kind of subway tunnel country rock pre grouting from the surface reinforcement process | |
CN104863183B (en) | Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction | |
CN109779634B (en) | Method for determining position of fractured hard top plate of coal mine ground vertical well | |
CN105298537A (en) | Mounting method of conveying pipe for solid filling material | |
CN104481535B (en) | A kind of drilling integral method for half-edge coal seam | |
CN108316925B (en) | Simple gob-side entry retaining method for drilling and roof breaking of working face with three-soft coal layer thickness direct roof | |
CN105971504A (en) | Drilling structure, method and device for uncertain stratum of target reservoir | |
CN105134125A (en) | Construction process for blocking bottom end of annular space behind gas vertical well wall | |
CN105156148B (en) | Gas vertical gas tube mounting process | |
CN109944634B (en) | Coal seam top and bottom plate filling type goaf filling structure and filling method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20160203 |