CN105277444B - Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading - Google Patents

Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading Download PDF

Info

Publication number
CN105277444B
CN105277444B CN201510190227.1A CN201510190227A CN105277444B CN 105277444 B CN105277444 B CN 105277444B CN 201510190227 A CN201510190227 A CN 201510190227A CN 105277444 B CN105277444 B CN 105277444B
Authority
CN
China
Prior art keywords
pile
model
frame
loading
groove
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510190227.1A
Other languages
Chinese (zh)
Other versions
CN105277444A (en
Inventor
任连伟
詹俊峰
杨权威
张敏霞
王辉
李建委
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201510190227.1A priority Critical patent/CN105277444B/en
Publication of CN105277444A publication Critical patent/CN105277444A/en
Application granted granted Critical
Publication of CN105277444B publication Critical patent/CN105277444B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Foundations (AREA)
  • Investigating Strength Of Materials By Application Of Mechanical Stress (AREA)

Abstract

Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading, including vertically disposed four groove columns on bottom land seat and bottom land seat, groove sidewall is provided between adjacent slot column, two groove column tops of homonymy are respectively equipped with capital crossbeam, reaction frame is connected between two capital crossbeams, it is between each part of the experimental rig to be bolted more, connected for fully mechanical, it is easy to dismount, multiple combinations can be carried out according to content of the test, and can be strong according to the width and height of test requirements document adjusting apparatus, regulating power.The test method design of the present invention is reasonable, technique is simple, it is easy to operate, more single pile load tests or the multidirectional load test of single pile can be carried out simultaneously, during experiment, it can be achieved to sentence steady, automatic voltage regulation dimension lotus, automatically automatic loading, record and automatic data collection automatically, test accuracy is can ensure that, test efficiency can be improved, and main frame is placed in laboratory, it is good by radio control operations, operating environment.

Description

Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading
Technical field
The invention belongs to large-scale pile foundation modeling techniques field, more particularly to a kind of fully mechanical based on multidirectional loading Pile foundation model test apparatus and test method.
Background technology
With the rapid development of the national economy, pile foundation answering in the engineerings such as high-rise building, high ferro, deep foundation pit support Also become more and more important with more and more, related to pile foundation pile tests.Due to pile foundation on-the-spot test have it is costly, The defects of engineering pile can not be loaded into the degree of destruction, Consideration is limited, therefore, in the case that experimental condition is limited at the scene Large scale model test is carried out, destruction is may be loaded under various operating modes, can more consider single pile and clump of piles load The influence factor of energy, there is important meaning to grasping various pile foundation pile-soil interaction mechanism and optimization Design of Foundation Justice.
At present, Patent No. ZL 03125454.3 patent of invention discloses a kind of unsaturated soil pile foundation model test dress Put, it is made up of the upper demountable pressure vessel of lid and bottom seat, by that to upper lid, base and groove specially treated, can try The geology suction of soil sample is easily controlled in testing, realizes the load-carrying properties test of Model Pile in the unsaturation soil body;But the device Middle model scale is small, and belongs to non-fully mechanical connection, it is impossible to realizes effective loading of leveling peg.Separately there is Patent No. ZL 201210081275.3 patent of invention, it discloses a kind of pile pressing device of geotechnical centrifugal model test Model Pile, the device Push operation can be implemented for single pile and clump of piles etc., the press-in angle and speed of stake can be adjusted, ensure Model Pile burial place Accuracy, piling process can be completed under 1g and Centrifugal Environment;But the device is limited only to realize mould under Centrifugal Environment The accurate press-in of type stake, without reference to the multidirectional load test method of large scale Model Pile, and belong to non-fully mechanical connection side Formula.
In addition, general models experimental rig is mostly reinforced concrete structure, model side wall can not be adjusted, and can only be realized mostly Unidirectional static load test, and the stake simulated in loading is long and method of testing is single, simultaneously multidirectional load or not can not be realized It is larger using limitation with the long model test of stake.
The content of the invention
It is an object of the invention to provide it is a kind of it is rational in infrastructure, be easy to regulation, easy to operate and can be to model single pile or a clump of piles Carry out the fully mechanical pile foundation model test apparatus and test method based on multidirectional loading of multidirectional load test.
Technical solution of the present invention is:Fully mechanical pile foundation model test apparatus based on multidirectional loading, including bottom land seat and Vertically disposed four groove columns on bottom land seat, groove sidewall, two groove column tops difference of homonymy are provided between adjacent slot column Provided with capital crossbeam, reaction frame is connected between two capital crossbeams.
The bottom land seat includes default anchor hole on basement top layer and basement top layer;Groove column include base for post and The H-shaped steel column being vertical on base for post, base for post are fixed on basement top layer by the anchor bolt in anchor hole, H-shaped The wing plate edge of steel column is laid with bolt hole, and plane and the length direction of capital crossbeam are put down where the wing plate of H-shaped steel column OK;Capital crossbeam is H-shaped body beam, and H-shaped body beam both ends clamp with corresponding H-shaped steel column and are connected, and the edge of H-shaped body beam is equal It is laid with bolt hole;Reaction frame includes reaction beam and the fixed mechanism at reaction beam both ends, and fixed mechanism includes consolidating for edge apertured Fixed board and the bolt being located in hole, reaction beam are arranged on the crossbeam of capital by fixed plate and bolt;Groove sidewall includes multistage Baffle plate, every grade of baffle plate include the panel in frame and frame, and the adjacent screen in same side is connected by frame.
The panel includes steel plate or armorplate glass;It is laid with bolt hole on frame, it is adjacent in same side Baffle plate is threadedly coupled by frame.
The wing plate edge of the H-shaped steel column is bolted with side reaction frame, and side reaction frame is equal leg angle, side reaction frame Both sides be equipped with bolt hole, side reaction frame another side is threadedly coupled with frame.
Longitudinally superposition is provided with hollow square steel for the top of the groove sidewall, and hollow square steel both ends connect with side reaction frame screw thread Connect or connect with the groove inwall of H-shaped steel column.
The hollow square steel the top is less than capital crossbeam.
The base for post is groove profile, between the groove inwall and side reaction frame of base for post, anchor bolt and side reaction frame Or bottom land cushion block is equipped between baffle plate, bottom land cushion block is the long steel bar of rectangle.
The basement top layer is made up of armored concrete, and its thickness is not less than 15cm, and strength grade of concrete is not less than C40, anchor hole equidistantly distributed, the diameter of anchor hole are not less than 10cm;The height of H-shaped steel column is 3~5m, adjacent H-shaped steel column Level interval be 2~3m, and height and level interval ratio be 1.5~2;The diameter of anchor bolt is not less than 10cm;Often The height of level baffle plate is 50cm, length is 2~3m, and the height of groove sidewall is 2~4m;The thickness of steel plate is not less than 3mm, tempering glass The thickness of glass plate is not less than 1cm, and the quantity of hollow square steel is 20~30, and the section length of side of hollow square steel is 5cm;Reaction beam Cross-sectional width is not less than 1cm not less than 15cm, thickness.
The described large-scale methods of model pile test based on multidirectional loading system, comprises the following steps:(1), laying groove Base, fixed model stake, the fully mechanical pile foundation model test dress based on multidirectional loading is installed around Model Pile in bottom land seat upper measurement Put, including the groove sidewall and installation capital horizontal stroke that installation panel is the groove sidewall of steel plate from bottom to top and panel is armorplate glass Beam and reaction frame, and the fixation hollow square steel above the groove sidewall for needing to provide horizontal reacting force;(2), installation horizontal reacting force device: The fixed hydraulic jack on the inside of hollow square steel, hydraulic jack top ends installation load transducer, lotus is connected using spherical bearing The pile crown of set sensor and Model Pile, to ensure that Model Pile is acted on by horizontal loading all the time;(3), installation vertical counter-force dress Put:First, position of the reaction frame on the crossbeam of capital is adjusted according to Model Pile present position, reaction frame is located at Model Pile to be measured Surface, to ensure that the vertical loading of each position model stake can be smoothed out;Then, fixed load passes on reaction frame Sensor, the pile crown of Model Pile set hydraulic jack, connect load transducer and hydraulic jack;(4), arrangement it is multidirectional loading system System:To match based on the fully mechanical pile foundation model test apparatus of multidirectional loading as principle, multidirectional loading system includes main frame, end Preceding controller and wireless communicator, main frame can meet at most while control the requirement of three directions loadings, to realize that control is single The purpose that three directions of Model Pile load simultaneously or three Model Piles unidirectionally load simultaneously;(5), loading test:By wireless Communicator controls multidirectional loading system, and multidirectional loading system sentences steady, automatic voltage regulation dimension lotus, loads automatically, be automatic automatically in experiment Record, automatic data collection.
The Model Pile is single pile or a clump of piles, i.e., single Model Pile or more Model Piles;In step(2)In, it is hollow The backing plate positioned at hydraulic jack top/bottom part is provided with the inside of square steel, makes hollow square steel uniform force, the height and hollow square steel of backing plate Superposition is highly equal, length is not less than 1m;In step(3)In, the pile crown of Model Pile is provided with backing plate, backing plate and hydraulic jack Top is connected, and the thick sands of 5mm is laid between backing plate and the pile crown of Model Pile, to ensure Model Pile uniform stressed;In step(4) In, main frame is placed in laboratory.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, the invention discloses a kind of fully mechanical pile foundation model test apparatus based on multidirectional loading, the experimental rig are each It is between part to be bolted more, connected for fully mechanical, be easy to dismount, multiple combinations can be carried out according to content of the test, and can It is strong according to the width and height of test requirements document adjusting apparatus, regulating power;Groove sidewall is spliced for multistage, the panel of groove sidewall During from armorplate glass, it is easy to observe soil strength variation, while can be needed to set up hollow square steel according to experiment, according to experiment needs Larger horizontal load can be born in one side, two-sided, three faces or four sides arrangement hollow square steel, hollow square steel, ensure that structure is strong Degree and stability, so as to realize multidirectional horizontal addload.
2nd, test method design of the invention is reasonable, and technique is simple, easy to operate, can carry out more single pile loading examinations simultaneously Test or the multidirectional load test of single pile, during experiment, can be achieved automatic to sentence steady, automatic voltage regulation dimension lotus, automatic loading, automatic note Record and automatic data collection, it can be ensured that test accuracy, test efficiency can be improved, and main frame is placed in laboratory, by wireless Control operation, operating environment are good;Multidirectional loading system is radio transmitting device, can meet single pile it is multidirectional loading or more simultaneously The requirement of loading, the scope of application are wide.
3rd, capital crossbeam is respectively equipped with two groove column tops of homonymy, reaction frame, post is connected between two capital crossbeams Head piece is act as:4 H-shaped steel columns are fixed, form overall steel frame construction, make apparatus structure stability strong;Can be according to reality Test requirements document adjusts oneself height, enables devices to adapt to the multi-load experiment of different length Model Pile, and trial stretch is wide;For Reaction frame provides support, and vertical counter-force is provided to the single pile in bottom land seat or a clump of piles;, can be as needed as the support of reaction frame The position of any adjustment reaction frame, realize that optional position pile crown can be located at the underface of reaction beam, be easy to provide it vertically Load, the pile anchoring difficulty of Model Pile can be substantially reduced.
4th, reaction frame includes reaction beam and the fixed mechanism at reaction beam both ends, and fixed mechanism includes the fixed plate of edge apertured With the bolt being located in hole, reaction beam is arranged on the crossbeam of capital by fixed plate and bolt, and fixed mechanism fixes reaction beam, To provide the force of vertical load basis, vertical load includes vertical compression and resistance to plucking load;It is easy to adjust the position of reaction beam, Realize that optional position model pile head can be located at the underface of reaction beam, the pile anchoring difficulty of Model Pile can be substantially reduced.
5th, it is bolted with side reaction frame at the wing plate edge of H-shaped steel column, side reaction frame is equal leg angle, side reaction frame Both sides be equipped with bolt hole, side reaction frame another side is threadedly coupled with frame, and side reaction frame can be born after carrying out self-chambering soil The outside horizontal direction pressure of groove sidewall, to prevent groove sidewall stress outward-dipping.
6th, longitudinally it is superimposed in the top of groove sidewall and is provided with hollow square steel, and hollow square steel the top is less than capital crossbeam; Hollow square steel both ends are threadedly coupled with side reaction frame or connected with the groove inwall of H-shaped steel column, and hollow square steel is overlapped mutually shape Into steel bar side wall there is advantages below:1st, hollow square steel has larger bending rigidity, can bear larger horizontal direction lotus Carry, almost without deformation under horizontal force action, be greatly improved horizontal addload accuracy;2nd, hollow square steel can directly overlay groove In side wall, counter-force can be provided for four direction, make it possible horizontal multidirectional loading;3rd, more single pile hydraulic tests can be provided Multiple counter-force side walls, more single piles are made to complete single pile horizontal static-load experiment under operating mode of once banketing, easy to operate, experiment Efficiency high;4th, apply horizontal direction load on the outside of hollow square steel, soil body lateral movement can be realized to single pile or clump of piles load The test objective that can be influenceed.
7th, between the groove inwall and side reaction frame of base for post, between anchor bolt and side reaction frame or baffle plate Provided with bottom land cushion block, bottom land cushion block is the long steel bar of rectangle, and the effect of bottom land cushion block is the undermost baffle plate of fixed groove sidewall, and is held By from the horizontal direction pressure banketed, orlop baffle plate is set to keep vertical.
8th, in the present invention, the spacing of the bolt hole on H-shaped steel column, the spacing of the bolt hole on frame, on H-shaped body beam Pitch of holes in the spacing and fixed plate of bolt hole is equal, is easy to assemble and adjusts the position of each part.
9th, H-shaped steel column of the invention can need lengthening and adjusting position according to experiment, can have space on top and level To installing actuator, there is provided dynamic load, realize and carry out vertical and horizontal direction dynamic loading experiment purpose to Model Pile.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of another angle of the present invention;
Fig. 3 is Fig. 1 side view;
Fig. 4 is Fig. 3 side view;
Fig. 5 is Fig. 3 top view.
Embodiment
As shown in Figure 1, Figure 2, the fully mechanical pile foundation model test apparatus based on multidirectional loading shown in Fig. 3, Fig. 4 and Fig. 5, its Including vertically disposed four groove columns on bottom land seat and bottom land seat, be provided with groove sidewall 3 between adjacent slot column, groove column and Groove sidewall 3 surrounds square cavity jointly.Capital crossbeam 4 is respectively equipped between the top of two groove columns of homonymy, two capitals are horizontal Beam 4 is parallel to each other, and reaction frame 5 is also associated between two capital crossbeams 4.
Bottom land seat includes default anchor hole 12 on basement top layer 11 and basement top layer 11, and anchor hole 12 equidistantly divides Cloth, the diameter of anchor hole 12 are not less than 10cm.Basement top layer 11 is poured by armored concrete to be formed, and its thickness is not less than 15cm, and strength grade of concrete is not less than C40.
Groove column includes base for post 24 and the H-shaped steel column 21 being vertical on base for post 24, and H-shaped steel column welds with base for post 24 Connect to form groove column, base for post 24 is fixed on basement top layer 11 by the anchor bolt 25 in anchor hole 12, makes groove column Keep being rigidly connected with bottom land seat.Bolt hole 22, and the wing of H-shaped steel column 21 are laid with the wing plate edge of H-shaped steel column 21 Plane where plate is parallel with the length direction of capital crossbeam 4.
Capital crossbeam 4 is made up of H-shaped body beam 41, and bolt hole 42, H-shaped case are laid with the edge of H-shaped body beam 41 The both ends of body beam 41 clamp with corresponding H-shaped steel column 21 and are threadedly coupled.Capital crossbeam 4 is act as:1st, 4 H-shaped steel columns 21 are fixed, Overall steel frame construction is formed, makes apparatus structure stability strong;2nd, capital crossbeam 4 can require adjustment from height according to actual tests Degree, enables devices to adapt to the multi-load experiment of different length Model Pile, and trial stretch is wide;3rd, support is provided for reaction frame 5, Vertical counter-force is provided to the single pile in bottom land seat or a clump of piles;4th, the support as reaction frame 5, counter-force can be arbitrarily adjusted as needed The position of frame 5, realize that optional position pile crown can be located at the underface of reaction beam 51, be easy to provide it vertical load, can be big The big pile anchoring difficulty for reducing Model Pile.
Reaction frame 5 includes reaction beam 51 and the fixed mechanism 52 at the both ends of reaction beam 51, and fixed mechanism 52 includes edge apertured Fixed plate 53 and the bolt 54 that is located in hole, reaction beam 51 be arranged on by fixed plate 53 and bolt 54 on capital crossbeam 4. Fixed mechanism 52 is act as:1st, fixed reaction beam 51, there is provided the force basis of vertical load, vertical load include vertical compression With resistance to plucking load;2nd, it is easy to adjust the position of reaction beam 51, realizes that optional position model pile head can be located at reaction beam 51 Underface, the pile anchoring difficulty of Model Pile can be substantially reduced.
Groove sidewall 3 includes multistage baffle plate 31, and every grade of baffle plate 31 includes the panel in frame 32 and frame 32, on frame 32 It is laid with bolt hole 36, the adjacent screen 31 in same side is threadedly coupled by frame 32.Panel includes steel plate 33 or steel Change glass plate 34.It is bolted with side reaction frame 23 at the wing plate edge of H-shaped steel column 21, side reaction frame 23 is equal leg angle, side The both sides of face reaction frame 23 are equipped with bolt hole, and the another side of side reaction frame 23 is threadedly coupled with frame 32.Side reaction frame 23 The outside horizontal direction pressure of groove sidewall 3 after self-chambering soil can be born to come, to prevent the stress of groove sidewall 3 outward-dipping.
Longitudinally it is superimposed in the top of groove sidewall 3 and is provided with hollow square steel 35, and the top of hollow square steel 35 is horizontal less than capital Beam 4;The both ends of hollow square steel 35 are threadedly coupled with side reaction frame 23 or connected with the groove inwall of H-shaped steel column 21.Hollow square steel 35, which are overlapped mutually the steel bar side wall to be formed, has advantages below:1st, hollow square steel 35 has larger bending rigidity, can bear compared with Big horizontal direction load, almost without deformation under horizontal force action, it is greatly improved horizontal addload accuracy;2nd, hollow square steel 35 can directly overlay in groove sidewall 3, can provide counter-force for four direction, make it possible horizontal multidirectional loading;3rd, can be to more The hydraulic test of root single pile provides multiple counter-force side walls, more single piles is completed single pile horizontal load under operating mode of once banketing Experiment, easy to operate, test efficiency is high;4th, apply horizontal direction load in the outside of hollow square steel 35, can realize that the soil body laterally moves The dynamic test objective influenceed on single pile or clump of piles load-carrying properties.
In the present invention, base for post 24 is groove profile, and H-shaped steel column 21 is located in the groove of base for post 24, in the groove of base for post 24 Bottom land cushion block 13 is equipped between wall and side reaction frame 23, between anchor bolt 25 and side reaction frame 23 or baffle plate 31, Bottom land cushion block 13 is the long steel bar of rectangle, and the effect of bottom land cushion block 13 is the undermost baffle plate 31 of fixed groove sidewall 33, and bears to come From the horizontal direction pressure banketed, orlop baffle plate 31 is set to keep vertical.Reaction beam 51 is the girder steel of square hollow arbor braid dividing plate, its Interior dividing plate can improve the bending resistance of reaction beam 51, can be to provide larger vertical counter-force to provide safeguard.
In the present invention, the spacing of the bolt hole 22 on H-shaped steel column 21, the spacing of bolt hole 36 on frame 32, H-shaped case Pitch of holes in the spacing and fixed plate 53 of bolt hole 42 on body beam 41 is equal, is easy to assemble and adjusts the position of each part Put.
In the present embodiment, the height of H-shaped steel column 21 is 3~5m, and the level interval of adjacent H-shaped steel column 21 is 2 ~3m, and the ratio of height and level interval is 1.5~2;The diameter of anchor bolt 25 is not less than 10cm;The height of every grade of baffle plate 31 It is 2~3m to spend for 50cm, length, and the height of groove sidewall 3 is 2~4m, i.e., baffle plate 31 is 4~8 grades;The thickness of steel plate 33 is not less than 3mm, the thickness of armorplate glass 34 are not less than 1cm, and the quantity of hollow square steel 35 is 20~30, the section side of hollow square steel 35 A length of 5cm;The cross-sectional width of reaction beam 51 is not less than 1cm not less than 15cm, thickness.
Test method of the present invention comprises the following steps:
(1), laying groove base, fixed model stake, bottom land seat upper measurement around Model Pile install the full machine based on multidirectional loading Tool formula pile foundation model test apparatus, including installation panel is the groove sidewall 3 of steel plate 33 from bottom to top and panel is armorplate glass 34 groove sidewall 3 and mounting post head piece 4 and reaction frame 5, and it is fixed empty above the groove sidewall 3 for needing to provide horizontal reacting force Heart square steel 35;
(2), installation horizontal reacting force device:In the inner side fixed hydraulic jack of hollow square steel 35, hydraulic jack top ends peace Load transducer is filled, load transducer and the pile crown of Model Pile are connected using spherical bearing, to ensure Model Pile all the time by water The effect of flat load;
(3), the vertical counterforce device of installation:First, reaction frame 5 is adjusted on capital crossbeam 4 according to Model Pile present position Position, reaction frame 5 is located at the surface of Model Pile to be measured, to ensure that the vertical loading of each position model stake can be smooth Carry out;Then, the fixed load sensor on reaction frame 5, the pile crown of Model Pile set hydraulic jack, connect load transducer With hydraulic jack;
(4), the multidirectional loading system of arrangement:To match based on the fully mechanical pile foundation model test apparatus of multidirectional loading as original Then, multidirectional loading system includes controller and wireless communicator before main frame, end, and main frame is placed in laboratory, and main frame can meet The requirement of three directions loadings is at most controlled simultaneously, and single three directions of Model Pile loading or three moulds simultaneously are controlled to realize The purpose that type stake unidirectionally loads simultaneously;
(5), loading test:Multidirectional loading system is controlled by wireless communicator, multidirectional loading system is sentenced automatically in experiment Surely, automatic voltage regulation dimension lotus, automatic loading, automatic record, automatic data collection.
In above-mentioned steps, Model Pile can be single pile or a clump of piles, i.e., single Model Pile or more Model Piles.
In step(2)In, the inner side of hollow square steel 35 is provided with the backing plate positioned at hydraulic jack top/bottom part, make hollow square steel 35 by Power is uniform, and the height of backing plate is highly equal with the superposition of hollow square steel 35, length is not less than 1m.
In step(3)In, the pile crown of Model Pile is provided with backing plate, and backing plate is connected with hydraulic jack, backing plate and Model Pile Pile crown between lay the thick sands of 5mm, to ensure Model Pile uniform stressed.
In the present invention, the height of H-shaped steel column 21 and level interval can be adjusted according to actual tests requirement, and should expire The sufficient likelihood ratio is not less than 1:8 clump of piles model test requirement.

Claims (7)

1. the fully mechanical pile foundation model test apparatus based on multidirectional loading, it is characterised in that including on bottom land seat and bottom land seat Vertically disposed four groove columns, groove sidewall are provided between adjacent slot column, two groove column tops of homonymy are respectively equipped with capital Crossbeam, reaction frame is connected between two capital crossbeams;
The bottom land seat includes default anchor hole on basement top layer and basement top layer;Groove column is including base for post and vertically H-shaped steel column on base for post, base for post are fixed on basement top layer by the anchor bolt in anchor hole, H-shaped steel column Wing plate edge be laid with bolt hole, and plane where the wing plate of H-shaped steel column is parallel with the length direction of capital crossbeam;Post Head piece is H-shaped body beam, and H-shaped body beam both ends are clamped with corresponding H-shaped steel column and are connected, and the edge of H-shaped body beam is laid There is bolt hole;Reaction frame includes reaction beam and the fixed mechanism at reaction beam both ends, and fixed mechanism includes the fixed plate of edge apertured With the bolt being located in hole, reaction beam is arranged on the crossbeam of capital by fixed plate and bolt;Groove sidewall includes multistage baffle plate, Every grade of baffle plate includes the panel in frame and frame, and the adjacent screen in same side is connected by frame;
The wing plate edge of the H-shaped steel column is bolted with side reaction frame, and side reaction frame is equal leg angle, and the two of side reaction frame While being equipped with bolt hole, side reaction frame another side is threadedly coupled with frame;
Longitudinally superposition is provided with hollow square steel for the top of the groove sidewall, hollow square steel both ends be threadedly coupled with side reaction frame or Person connects with the groove inwall of H-shaped steel column.
2. the fully mechanical pile foundation model test apparatus based on multidirectional loading as claimed in claim 1, it is characterised in that described Panel includes steel plate or armorplate glass;It is laid with bolt hole on frame, the adjacent screen in same side passes through frame Threaded connection.
3. the fully mechanical pile foundation model test apparatus based on multidirectional loading as claimed in claim 2, it is characterised in that described Hollow square steel the top is less than capital crossbeam.
4. the fully mechanical pile foundation model test apparatus based on multidirectional loading as claimed in claim 3, it is characterised in that described Base for post is groove profile, and bottom land cushion block is equipped between the groove inwall and side reaction frame of base for post, between anchor bolt and baffle plate, Bottom land cushion block is the long steel bar of rectangle.
5. the fully mechanical pile foundation model test apparatus based on multidirectional loading as claimed in claim 4, it is characterised in that described Basement top layer is made up of armored concrete, and its thickness is not less than 15cm, and strength grade of concrete is not less than C40, anchor hole etc. Spacing is distributed, and the diameter of anchor hole is not less than 10cm;The height of H-shaped steel column is 3~5m, and the level interval of adjacent H-shaped steel column is 2 ~3m, and the ratio of height and level interval is 1.5~2;The diameter of anchor bolt is not less than 10cm;The height of every grade of baffle plate is 50cm, length are 2~3m, and the height of groove sidewall is 2~4m;The thickness of steel plate is not less than 3mm, and the thickness of armorplate glass is not small In 1cm, the quantity of hollow square steel is 20~30, and the section length of side of hollow square steel is 5cm;The cross-sectional width of reaction beam is not less than 15cm, thickness are not less than 1cm.
6. the experiment side of the fully mechanical pile foundation model test apparatus based on multidirectional loading described in claim 1-5 any one Method, it is characterised in that comprise the following steps:(1), laying groove base, fixed model stake, bottom land seat upper measurement around Model Pile install Fully mechanical pile foundation model test apparatus based on multidirectional loading, including groove sidewall and face of the installation panel for steel plate from bottom to top Plate is the groove sidewall and mounting post head piece and reaction frame of armorplate glass, and in the groove sidewall for needing to provide horizontal reacting force Square fixation hollow square steel;(2), installation horizontal reacting force device:The fixed hydraulic jack on the inside of hollow square steel, hydraulic jack top Load transducer is installed in portion, and the pile crown of load transducer and Model Pile is connected using spherical bearing, with ensure Model Pile all the time by To the effect of horizontal loading;(3), the vertical counterforce device of installation:First, reaction frame is adjusted in capital according to Model Pile present position Position on crossbeam, reaction frame is set to be located at the surface of Model Pile to be measured, to ensure the vertical loading energy of each position model stake Enough it is smoothed out;Then, the fixed load sensor on reaction frame, the pile crown of Model Pile set hydraulic jack, connect load Sensor and hydraulic jack;(4), the multidirectional loading system of arrangement:To match the fully mechanical pile foundation model based on multidirectional loading Experimental rig is principle, and multidirectional loading system includes controller and wireless communicator before main frame, end, and main frame can meet at most simultaneously The requirement of three directions loadings is controlled, single three directions of Model Pile are controlled with realization while loading or three Model Piles are simultaneously The purpose unidirectionally loaded;(5), loading test:Multidirectional loading system is controlled by wireless communicator, multidirectional loading system in experiment It is automatic to sentence steady, automatic voltage regulation dimension lotus, automatic loading, automatic record, automatic data collection.
7. the test method of the fully mechanical pile foundation model test apparatus based on multidirectional loading as claimed in claim 6, it is special Sign is, the Model Pile is single pile or a clump of piles, i.e., single Model Pile or more Model Piles;In step(2)In, hollow side The backing plate positioned at hydraulic jack top/bottom part is provided with the inside of steel, makes hollow square steel uniform force, the height of backing plate and hollow square steel Superposition is highly equal, length is not less than 1m;In step(3)In, the pile crown of Model Pile is provided with backing plate, backing plate and hydraulic jack It is connected, the thick sands of 5mm is laid between backing plate and the pile crown of Model Pile, to ensure Model Pile uniform stressed;In step(4)In, Main frame is placed in laboratory.
CN201510190227.1A 2015-04-21 2015-04-21 Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading Expired - Fee Related CN105277444B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510190227.1A CN105277444B (en) 2015-04-21 2015-04-21 Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510190227.1A CN105277444B (en) 2015-04-21 2015-04-21 Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading

Publications (2)

Publication Number Publication Date
CN105277444A CN105277444A (en) 2016-01-27
CN105277444B true CN105277444B (en) 2018-03-09

Family

ID=55146838

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510190227.1A Expired - Fee Related CN105277444B (en) 2015-04-21 2015-04-21 Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading

Country Status (1)

Country Link
CN (1) CN105277444B (en)

Families Citing this family (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105738176B (en) * 2016-03-07 2017-04-19 河海大学 Pile foundation manufacturing device for model test
CN106018105B (en) * 2016-05-17 2019-02-05 重庆大学 The multi-functional physical simulation experiment system of coal petrography engineering and coal petrography model test method
CN106738233B (en) * 2016-12-19 2022-12-16 席成松 Cast-in-place post of concrete and well hole assembling die and concrete mould
CN106769514A (en) * 2017-01-13 2017-05-31 绍兴文理学院 The multiple dimensioned testing machine transverse direction loading device of rock uniaxiality strength
CN107014670B (en) * 2017-04-28 2023-10-17 浙江科技学院 Testing device for multi-directional horizontal bearing capacity of single pile under composite load
CN107063665A (en) * 2017-05-09 2017-08-18 广西大学 It is a kind of to limit the experimental rig that out-of-plain failure and guarantee are symmetrically destroyed
CN106989921A (en) * 2017-06-10 2017-07-28 武汉轻工大学 Structural test reaction frame with early warning system
CN107505206B (en) * 2017-08-10 2023-11-03 山东建筑大学 Automatic multifunctional test system and method for testing bearing performance of soil layer anti-pulling foundation
CN107460862B (en) * 2017-09-22 2023-10-13 中国路桥工程有限责任公司 Combined testing device for substrate bearing capacity and frictional resistance
CN107560947B (en) * 2017-10-10 2024-09-20 河南省产品质量监督检验院 Assembled smoke exhaust pipeline pressure testing machine and application method thereof
CN108088733A (en) * 2017-10-31 2018-05-29 青岛昊河水泥制品有限责任公司 A kind of external pressure load loading device and test method for concrete box culvert
CN107630478B (en) * 2017-11-02 2023-05-12 中国建筑第八工程局有限公司 Simulation test device and method for action mechanism of pile-soil-anchor combined support system
CN107748244A (en) * 2017-12-18 2018-03-02 兰州理工大学 Visualization combined model case and installation method for rock earth model test
CN108387454A (en) * 2018-03-23 2018-08-10 成都市伺服液压设备有限公司 A kind of novel structural elements and shield duct piece experimental system
CN108951717B (en) * 2018-05-07 2021-04-27 重庆大学 Multifunctional pile foundation model test box device and using method thereof
CN108918828A (en) * 2018-07-08 2018-11-30 北京工业大学 A kind of side slope or the indoor model test method that comes down
CN108918277A (en) * 2018-07-08 2018-11-30 北京工业大学 Multifunctional self-leveling weighing apparatus stress model chamber
CN108918278A (en) * 2018-07-08 2018-11-30 北京工业大学 Pile foundation indoor model test method
CN108982216B (en) * 2018-07-16 2020-09-15 西南交通大学 Device for researching pile-soil effect under horizontal load by utilizing transparent soil and testing method thereof
CN110044715B (en) * 2019-05-15 2020-06-05 东北大学 Visual soil body failure mode trapping apparatus
CN110616751B (en) * 2019-09-24 2024-06-18 华侨大学 Experimental device for simulating influence of foundation pit excavation on bearing capacity of adjacent building foundation piles
CN110657977A (en) * 2019-10-14 2020-01-07 河南工业大学 Loading support for detecting structural performance of assembled prefabricated staircase
CN114061992A (en) * 2020-08-06 2022-02-18 中国电建集团华东勘测设计研究院有限公司 Assembled model groove device for indoor shield tunneling test and test method thereof
CN112922051B (en) * 2021-02-01 2021-09-10 唐山学院 Device and method for static load model test
CN112854323B (en) * 2021-02-04 2022-02-22 太原理工大学 Device and method for testing bearing capacity of multiple rows of group columns under single-shaft loading of inclined goaf
CN113740172B (en) * 2021-09-14 2024-04-30 中建八局第一建设有限公司 Steel constructs composite column loading test device
CN115977174B (en) * 2023-01-05 2023-10-27 江苏科技大学 Multidirectional loading test device and method for foundation model

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2145379Y (en) * 1992-11-26 1993-11-03 沈昌鲁 Experimental device for stake base static load
CN1355356A (en) * 2000-11-30 2002-06-26 武汉南方岩土工程新技术开发公司 Remote measuring method and equipment for vertical settling without reference beam
CN101413274A (en) * 2008-11-26 2009-04-22 李道华 Upper-stacking and lower-hanging combined load static load test pile apparatus
CN101876175A (en) * 2009-10-16 2010-11-03 中国科学院武汉岩土力学研究所 Soft soil electrochemistry reinforced model testing device capable of simulating overlying burden
CN202305346U (en) * 2011-09-29 2012-07-04 中国建筑第二工程局有限公司 Bending resistance test pedestal for prestressed concrete sheet pile
CN102605806A (en) * 2012-03-26 2012-07-25 浙江大学 Pile pressing device for model piles of geotechnical centrifugal model tests
CN202347547U (en) * 2011-12-06 2012-07-25 湖北省电力勘测设计院 Foundation basic model tester capable of being loaded bidirectionally
CN103510551A (en) * 2013-09-18 2014-01-15 中交公路长大桥建设国家工程研究中心有限公司 Three-directional static and dynamic loading model test platform for deep water foundations of bridges
CN203795485U (en) * 2014-04-10 2014-08-27 山东电力工程咨询院有限公司 Horizontal bearing characteristics test model of prestressed concrete pipe pile
CN203924147U (en) * 2014-05-30 2014-11-05 北京东方新星石化工程股份有限公司 The compound counterforce device of anchoring pile ballast
CN104198295A (en) * 2014-09-24 2014-12-10 北京铁五院工程机械有限公司 Large-tonnage pressure test bed

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6363776B1 (en) * 1999-11-12 2002-04-02 Gary L. Reinert, Sr. Pile testing reaction anchor apparatus and method

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2145379Y (en) * 1992-11-26 1993-11-03 沈昌鲁 Experimental device for stake base static load
CN1355356A (en) * 2000-11-30 2002-06-26 武汉南方岩土工程新技术开发公司 Remote measuring method and equipment for vertical settling without reference beam
CN101413274A (en) * 2008-11-26 2009-04-22 李道华 Upper-stacking and lower-hanging combined load static load test pile apparatus
CN101876175A (en) * 2009-10-16 2010-11-03 中国科学院武汉岩土力学研究所 Soft soil electrochemistry reinforced model testing device capable of simulating overlying burden
CN202305346U (en) * 2011-09-29 2012-07-04 中国建筑第二工程局有限公司 Bending resistance test pedestal for prestressed concrete sheet pile
CN202347547U (en) * 2011-12-06 2012-07-25 湖北省电力勘测设计院 Foundation basic model tester capable of being loaded bidirectionally
CN102605806A (en) * 2012-03-26 2012-07-25 浙江大学 Pile pressing device for model piles of geotechnical centrifugal model tests
CN103510551A (en) * 2013-09-18 2014-01-15 中交公路长大桥建设国家工程研究中心有限公司 Three-directional static and dynamic loading model test platform for deep water foundations of bridges
CN203795485U (en) * 2014-04-10 2014-08-27 山东电力工程咨询院有限公司 Horizontal bearing characteristics test model of prestressed concrete pipe pile
CN203924147U (en) * 2014-05-30 2014-11-05 北京东方新星石化工程股份有限公司 The compound counterforce device of anchoring pile ballast
CN104198295A (en) * 2014-09-24 2014-12-10 北京铁五院工程机械有限公司 Large-tonnage pressure test bed

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JPP桩不同组合水平承载性能模型试验研究;任连伟 等;《岩土力学》;20141031;第35卷;102页第1栏,附图1 *
大型桩基模型试验系统的开发;刘汉龙 等;《岩土工程学报》;20090331;第31卷(第3期);第452-457页 *

Also Published As

Publication number Publication date
CN105277444A (en) 2016-01-27

Similar Documents

Publication Publication Date Title
CN105277444B (en) Fully mechanical pile foundation model test apparatus and test method based on multidirectional loading
CN207300722U (en) A kind of bean column node Experimental Study on Seismic Behavior device
CN206496970U (en) Crab-bolt pull-out test system
CN204255832U (en) Crab-bolt pullout tests charger
CN106120559A (en) A kind of bridge limited bracket construction method and bridge
CN102706734A (en) Loading test device and method of asymmetric lateral-force-resisting structure
CN105002939B (en) Model device and method for grouped pile field test
CN105040749A (en) Pile foundation pulling resistance and compression resistance test system and test method
CN107354961B (en) Variable-rigidity pre-stressed anchor-pull type retaining wall soil arch effect test model device and method
CN210529777U (en) High-speed railway goaf foundation simulated power loading model test device
CN107063896A (en) One kind can adjust pressing-shearing combined pilot system technology platform
CN103698210A (en) Comprehensive mechanical property test device of fuel assembly and test method thereof
CN109235275A (en) Frock suitable for continuous rigid frame overweight 0# piece bracket pre-compaction of high mound large-span
CN106193330B (en) A kind of steel building construction land tenure foot bolt pre-embedded construction method
CN204898744U (en) Pile foundation resistance to plucking resistance to compression testing system
CN206740534U (en) Axial push-pull experimental rig under effect of contraction
CN206408969U (en) A kind of support meanss for being used to adjust bent cap vertical and horizontal gradient
CN105758658A (en) Experiment loading device for realizing large-size model multipoint load distribution
CN110726825A (en) Geotechnical engineering test device
CN214668208U (en) Wall horizontal loading test device
CN206710210U (en) Axial tension experimental rig under effect of contraction
CN202383026U (en) Column performance test device under horizontal and vertical load coupling effects
CN112065043B (en) Large cantilever safe intelligent construction system and method for finite element synchronous analysis
CN115436167A (en) Operating tunnel surrounding rock-lining long-term interaction simulation test device and method
CN108593420A (en) It is a kind of can three-dimensional load physical test model casing and its application method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180309