CN105201009A - Tower foundation negative-pressure construction method for river channel - Google Patents

Tower foundation negative-pressure construction method for river channel Download PDF

Info

Publication number
CN105201009A
CN105201009A CN201510578641.XA CN201510578641A CN105201009A CN 105201009 A CN105201009 A CN 105201009A CN 201510578641 A CN201510578641 A CN 201510578641A CN 105201009 A CN105201009 A CN 105201009A
Authority
CN
China
Prior art keywords
mould
foundation ditch
river
place
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510578641.XA
Other languages
Chinese (zh)
Other versions
CN105201009B (en
Inventor
陈晓垒
王静
王文博
张天一
韩耀辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
State Grid Liaoning Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Liaoning Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201510578641.XA priority Critical patent/CN105201009B/en
Publication of CN105201009A publication Critical patent/CN105201009A/en
Application granted granted Critical
Publication of CN105201009B publication Critical patent/CN105201009B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Revetment (AREA)

Abstract

The invention provides a tower foundation negative-pressure construction method for a river channel. The quality of a tower foundation can be improved, and a tower can be stable and safe in the use process. The method comprises steps as follows: a dam is constructed on the upstream of a place where the river channel is to be constructed for drainage; construction is performed in the place where the river channel is to be constructed in a natural sloping heavy-excavation manner, and a water pump is used for draining river water seeping into a foundation pit to the downstream of the foundation pit in the excavation process; a square die formed by splicing four templates two by two is put in the center of the bottom surface of the foundation pit; the water pump is used for draining the water in the die and discharging the water to the downstream of the foundation pit; high-grade concrete is applied to the inner bottom surface of the die for blocking; a water pumping pipe of the water pump is put in the foundation pit outside the die, so that river water seeping into the foundation pit outside the die can be continuously discharged to the downstream of the foundation pit, and the water pumping port is located in the position 1/3-1/2 of the height of the die; the concrete is directly cast into the die after a steel reinforcement cage is put into the die and vibrated with a vibrator; the concrete is cured.

Description

A kind of pole and tower foundation negative pressure construction method for river course
Technical field
The present invention relates to a kind of pole and tower foundation negative pressure construction method for river course.
Background technology
Power department is when cross a river transmits electric power circuit, and when especially river surface is wider, part shaft tower is inevitably built in river course.Construct in river course pole and tower foundation time, foundation ditch to be dug out in river course, and put into mould in foundation ditch, the river in mould is discharged concreting in backward mould.Due to the sandstone in river course, soil loosely, the concrete mortar in mould can sandstone below mould, soil be leaked in the foundation ditch outside mould, causes pole and tower foundation of poor quality, shaft tower is in use easily toppled over, dangerous.
Summary of the invention
The present invention is to solve the problems of the technologies described above, and provide a kind of pole and tower foundation negative pressure construction method for river course, it can improve pole and tower foundation quality, guarantees shaft tower in use firm, safety.
For the pole and tower foundation negative pressure construction method in river course, its special character is, concrete steps are as follows:
1. drainage
On the fill dam, 5m-10m place, upstream of pre-job location, river is tackled, and do drainage and river is walked around pre-job location to downstream drain;
2. excavation of foundation pit
Adopt the heavy excavation form of natural discharging slope to construct in pre-job location, and use water pump to be discharged to foundation ditch downstream by the river infiltered in foundation ditch in the process of excavation; When running into drift sand, expand the excavation gradient, until dig designated depth;
3. place mould
Place at place of foundation ditch bottom center the square dies that is mutually spliced between two by four pieces of templates, and install additional to enclose outside mould and stupefied mould tightly to be fixed;
4. mould internal drainage
Water pump is used to be blotted by the water infiltered in mould and be discharged into the downstream of foundation ditch;
5. mould shutoff
High-grade concrete shutoff is smeared at the inner bottom part of mould;
6. the outer draining of mould
The drinking-water pipe of water pump is placed in the foundation ditch outside mould, makes to infilter river continued emissions in the outer foundation ditch of mould to foundation ditch downstream, and keep pump mouth to be positioned at the 1/3-1/2 position of mold height;
7. basis is built
Place in mould directly to concreting in mould after reinforcing cage, and vibrate with vibrator;
8. concrete curing
Natural Health preservation more than 30 days, switches off the pump, and removes mould, fulfils assignment.
Further, under, the expansion excavation gradient serious at drift sand can not eliminate the condition of drift sand impact, around foundation ditch, beat deal pile, place breast boards and stop drift sand.
Further, deal pile beats the place being not less than 200mm on distance foundation ditch limit, makes a call to one every being not more than 300mm.
The invention has the beneficial effects as follows: after the river infiltered in mould being drained owing to using water pump, high-grade concrete shutoff is smeared at the inner bottom part of mould, and the drinking-water pipe of water pump is placed in the foundation ditch outside mould, pump mouth is kept to be positioned at mould 1/3 to 1/2 height, make to infilter river continued emissions in the outer foundation ditch of mould to foundation ditch downstream, when ensureing that the river infiltered in the outer foundation ditch of mould does not diffuse in mould, at the high-grade concrete of mould inner bottom surface, water seal is carried out to shutoff, and prevent the water body at pumping for water pump mouth place from stirring destruction foundation ditch bottom surface, thus the concrete avoided in mould leaks, ensure the quality of pole and tower foundation, guarantee that shaft tower is in use firm, safety, and then ensured electric power safety operation.
Accompanying drawing explanation
Fig. 1 is construction schematic diagram of the present invention;
In figure: 1-dykes and dams, 2-foundation ditch, 3-water pump, 4-square dies, 5-encloses stupefied, 6-high-grade concrete, 7-deal pile, 8-breast boards, 9-column foot concrete.
Detailed description of the invention
Embodiment 1
As shown in the figure, a kind of pole and tower foundation negative pressure construction method for river course, its step is as follows:
1. drainage: on the fill dam, 6m place, upstream 1 of pre-job location, river is tackled, and do drainage and river is walked around pre-job location to downstream drain.
2. excavation of foundation pit: the heavy excavation form construction adopting natural discharging slope, and use water pump 3 to be discharged to foundation ditch 2 downstream by the river infiltered in foundation ditch 2 in the process of excavation; When running into drift sand, expand the excavation gradient, until dig designated depth.
Under, the expansion excavation gradient serious at drift sand can not eliminate the condition of drift sand impact, adopt and beat deal pile 7 around foundation ditch 2, place the construction method that breast boards 8 stops drift sand.
Deal pile 7 dozens, in the place of distance foundation ditch 2 limit 200mm, makes a call to one every 300mm.
3. place mould: place at place of foundation ditch 2 bottom center the square dies 4 that is mutually spliced between two by template, and install additional outside mould and enclose stupefied 5 mould is tightly fixed.
4. mould internal drainage: use water pump 3 blotted by the water infiltered in mould and be discharged into the downstream of foundation ditch 2.
5. mould shutoff: smear high-grade concrete 6 shutoff at the inner bottom part of mould.
6. the outer draining of mould: be placed on by the drinking-water pipe of water pump 3 in the foundation ditch 2 outside mould, makes to infilter river continued emissions in the outer foundation ditch 2 of mould to foundation ditch 2 downstream, and 1/3 place keeping pump mouth to be positioned at mould dispatching.
7. basis is built: directly to building column foot concrete 9 in mould place reinforcing cage in mould after, and vibrate with vibrator.
8. concrete curing: natural Health preservation, after 30 days, switches off the pump 3, removes mould, fulfils assignment.
Embodiment 2
As shown in the figure, a kind of pole and tower foundation negative pressure construction method for river course, its step is as follows:
1. drainage: on the fill dam, 8m place, upstream 1 of pre-job location, river is tackled, and do drainage and river is walked around pre-job location to downstream drain.
2. excavation of foundation pit: the heavy excavation form construction adopting natural discharging slope, and use water pump 3 to be discharged to foundation ditch 2 downstream by the river infiltered in foundation ditch 2 in the process of excavation; When running into drift sand, expand the excavation gradient, until dig designated depth.
Under, the expansion excavation gradient serious at drift sand can not eliminate the condition of drift sand impact, adopt and beat deal pile 7 around foundation ditch 2, place the construction method that breast boards 8 stops drift sand.
Deal pile 7 dozens, in the place of distance foundation ditch 2 limit 300mm, makes a call to one every 240mm.
3. place mould: place at place of foundation ditch 2 bottom center the square dies 4 that is mutually spliced between two by template, and install additional outside mould and enclose stupefied 5 mould is tightly fixed.
4. mould internal drainage: use water pump 3 blotted by the water infiltered in mould and be discharged into the downstream of foundation ditch 2.
5. mould shutoff: smear high-grade concrete 6 shutoff at the inner bottom part of mould.
6. the outer draining of mould: be placed on by the drinking-water pipe of water pump 3 in the foundation ditch 2 outside mould, makes to infilter river continued emissions in the outer foundation ditch 2 of mould to foundation ditch 2 downstream, and keeps pump mouth to be positioned at 1/2 place of mold height.
7. basis is built: directly to building column foot concrete 9 in mould place reinforcing cage in mould after, and vibrate with vibrator.
8. concrete curing: natural Health preservation, after 35 days, switches off the pump 3, removes mould, fulfils assignment.

Claims (3)

1., for the pole and tower foundation negative pressure construction method in river course, its step is as follows:
1), drainage
On the fill dam, 5m-10m place, upstream of pre-job location, river is tackled, and do drainage and river is walked around pre-job location to downstream drain;
2), excavation of foundation pit
Adopt the heavy excavation form of natural discharging slope to construct in pre-job location, and use water pump to be discharged to foundation ditch downstream by the river infiltered in foundation ditch in the process of excavation; When running into drift sand, expand the excavation gradient, until dig designated depth;
3), mould is placed
Place at place of foundation ditch bottom center the square dies that is mutually spliced between two by four pieces of templates, and install additional to enclose outside mould and stupefied mould tightly to be fixed;
4), mould internal drainage
Water pump is used to be blotted by the water infiltered in mould and be discharged into the downstream of foundation ditch;
5), mould shutoff
High-grade concrete shutoff is smeared at the inner bottom part of mould;
6), the outer draining of mould
The drinking-water pipe of water pump is placed in the foundation ditch outside mould, makes to infilter river continued emissions in the outer foundation ditch of mould to foundation ditch downstream, and keep pump mouth to be positioned at the 1/3-1/2 position of mold height;
7), basis is built
Place in mould directly to concreting in mould after reinforcing cage, and vibrate with vibrator;
8), concrete curing
Natural Health preservation more than 30 days, switches off the pump, and removes mould, fulfils assignment.
2. further, under, the expansion excavation gradient serious at drift sand can not eliminate the condition of drift sand impact, around foundation ditch, beat deal pile, place breast boards and stop drift sand.
3. further, deal pile beats the place being not less than 200mm on distance foundation ditch limit, makes a call to one every being not more than 300mm.
CN201510578641.XA 2015-09-12 2015-09-12 Tower foundation negative-pressure construction method for river channel Active CN105201009B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510578641.XA CN105201009B (en) 2015-09-12 2015-09-12 Tower foundation negative-pressure construction method for river channel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510578641.XA CN105201009B (en) 2015-09-12 2015-09-12 Tower foundation negative-pressure construction method for river channel

Publications (2)

Publication Number Publication Date
CN105201009A true CN105201009A (en) 2015-12-30
CN105201009B CN105201009B (en) 2017-01-25

Family

ID=54948942

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510578641.XA Active CN105201009B (en) 2015-09-12 2015-09-12 Tower foundation negative-pressure construction method for river channel

Country Status (1)

Country Link
CN (1) CN105201009B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453729A (en) * 2019-08-22 2019-11-15 中国建筑第七工程局有限公司 Flexible particle waterproof protective layer construction punching block baffle assembly and construction method
CN110924425A (en) * 2019-11-09 2020-03-27 国网辽宁省电力有限公司锦州供电公司 Iron tower foundation construction method for river channel in winter
CN111809618A (en) * 2020-08-04 2020-10-23 林瑞 Power plant transmission tower foundation treatment method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Foundation for existing foundation reinforcing steel tower and construction method for it
CN104294839A (en) * 2014-11-14 2015-01-21 句容华源电器设备有限公司 High-voltage pole tower foundation construction method
CN104358271A (en) * 2014-11-17 2015-02-18 句容华源电器设备有限公司 High-voltage tower pole foundation construction method
CN104775438A (en) * 2015-04-08 2015-07-15 国家电网公司 Method for carrying out tower site foundation pit construction on karst landform foundation in rainy season

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002256573A (en) * 2001-03-02 2002-09-11 Chubu Electric Power Co Inc Foundation for existing foundation reinforcing steel tower and construction method for it
CN104294839A (en) * 2014-11-14 2015-01-21 句容华源电器设备有限公司 High-voltage pole tower foundation construction method
CN104358271A (en) * 2014-11-17 2015-02-18 句容华源电器设备有限公司 High-voltage tower pole foundation construction method
CN104775438A (en) * 2015-04-08 2015-07-15 国家电网公司 Method for carrying out tower site foundation pit construction on karst landform foundation in rainy season

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
宋书伟: "浅水区铁塔基础的施工措施", 《农村电气化》 *
郑江: "湖区铁塔基础施工方法研究", 《湖北电力》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453729A (en) * 2019-08-22 2019-11-15 中国建筑第七工程局有限公司 Flexible particle waterproof protective layer construction punching block baffle assembly and construction method
CN110924425A (en) * 2019-11-09 2020-03-27 国网辽宁省电力有限公司锦州供电公司 Iron tower foundation construction method for river channel in winter
CN111809618A (en) * 2020-08-04 2020-10-23 林瑞 Power plant transmission tower foundation treatment method
CN111809618B (en) * 2020-08-04 2021-11-02 湖南湘投铜湾水利水电开发有限责任公司 Power plant transmission tower foundation treatment method

Also Published As

Publication number Publication date
CN105201009B (en) 2017-01-25

Similar Documents

Publication Publication Date Title
US10309072B2 (en) Water-permeable pipe pile system capable of accelerating soil consolidation and method of using the same
CN101936010B (en) Construction method of dewatering well in underground concrete structure
CN104196034A (en) Foundation pit construction method employing steel sheet piles as support cofferdam
CN103498486B (en) A kind of sleeve pipe that adopts implements the method for shutoff to ater-casting precipitation pipe well
CN101713197A (en) Method for sealing foundation pit pressure reduction well
CN106320353A (en) Basement construction dewatering and drainage device and construction method thereof
CN107268688B (en) Construction method for reinforcing and sealing I-shaped steel joint of underground continuous wall
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN104358275B (en) Darker elevator shaft or collecting well construction method
CN105201009B (en) Tower foundation negative-pressure construction method for river channel
CN110761307B (en) Earth-rock cofferdam water seepage treatment structure and construction method
CN106677198A (en) Well plugging method under dynamic water level state
CN203939060U (en) The slight leakage plugging structure of a kind of diaphragm wall
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN212129150U (en) Deep basal pit precipitation well block structure
CN203514332U (en) Casing for blocking dewatering tube well of post-cast strip
CN209854754U (en) Sand flow stratum semi-closed open caisson structure
CN103174154A (en) Underground building bottom plate water burst well pit solid seal method and auxiliary water lowering device
CN108867676A (en) A kind of shut off tool and its construction method at round sump foundation pit bottom
CN113152414B (en) Plugging construction method for water-flushing point of bottom plate of water delivery and drainage gallery
CN208917857U (en) A kind of tool that shuts off at round sump foundation pit bottom
CN104988930B (en) It is applicable to the construction method in the combined type cofferdam of Unfavorable geology deep basal pit
CN105780791B (en) Deep-well precipitation well head shut-in well construction method in underground garage foundation pit
CN107419811A (en) The method and its structure of basement bottom board support pile and spilled water hole waterproofing and leakage-stopping
CN104264656B (en) Vacuum preloading downward stabilization by drainage soft soil foundation method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant