CN105155549A - 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法 - Google Patents

一种大面积深基坑分区顺逆工况下的支撑体系及施工方法 Download PDF

Info

Publication number
CN105155549A
CN105155549A CN201510340434.0A CN201510340434A CN105155549A CN 105155549 A CN105155549 A CN 105155549A CN 201510340434 A CN201510340434 A CN 201510340434A CN 105155549 A CN105155549 A CN 105155549A
Authority
CN
China
Prior art keywords
deep foundation
construction
support
foundation ditch
fender post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510340434.0A
Other languages
English (en)
Other versions
CN105155549B (zh
Inventor
邓兰艳
彭文
郭剑飞
周杨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Group Jiangsu Co ltd
China Construction Third Engineering Bureau Second Construction And Installation Co ltd
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
China Construction Third Bureau Green Industry Investment Co Ltd
Original Assignee
Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Engineering Co Ltd of China Construction Third Engineering Division filed Critical Second Construction Engineering Co Ltd of China Construction Third Engineering Division
Priority to CN201510340434.0A priority Critical patent/CN105155549B/zh
Publication of CN105155549A publication Critical patent/CN105155549A/zh
Application granted granted Critical
Publication of CN105155549B publication Critical patent/CN105155549B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明涉及一种大面积深基坑分区顺逆工况下的支撑体系及施工方法,支撑体系为由TRD止水帷幕形成深基坑外侧封闭止水墙;TRD止水帷幕的内侧设置一排围护桩;在深基坑中部设置一道三轴搅拌桩将深基坑分成两个区域,并在三轴搅拌桩一侧设置一排围护桩;深基坑内设若干立柱桩,每个立柱桩上连接一格构柱;在围护桩内设置若干道钢筋混凝土内支撑,各内支撑之间通过对应格构柱承载组成深基坑的内支撑形式。本发明一个区域先进行土方开挖和支撑施工,从基础底板开始向上进行结构施工,待施工至第一道支撑拆除之前,进行型钢斜撑梁换撑施工,确保另一个区域的水平应力传递到先施工的这个区域的结构梁板上;另一个区域从上往下进行土方开挖和支撑施工。

Description

一种大面积深基坑分区顺逆工况下的支撑体系及施工方法
技术领域
本发明涉及一种建筑工程中的大面积深基坑的支撑体系及施工方法,特别涉及一种大面积深基坑分区顺逆工况下的支撑体系及施工方法。
背景技术
目前,大面积深基坑均是设置多道钢筋混凝土内支撑和多层地下室结构,故在施工时,均是在整个基坑的上一道内支撑施工完成后,才开始下一层土方开挖;然后是在下层结构全部施工完成后,再进行上一道内支撑的拆除工作。如此一来,每次支撑施工和每层结构施工的流水时间较长,使得整个深基坑在长度和宽度上都是大距离的整体长时间暴露,使得内支撑在轴力方向上的徐变提前达到设计报警值,引起周边道路、管线和建筑物沉降过大,对基坑和周边环境造成重大安全隐患。
发明内容
为了克服现有施工方法不能完全满足现场施工和周边环境安全的要求。本发明提供了一种大面积深基坑分区顺逆工况下的支撑体系及施工方法,本发明不仅可以减少工程造价,还能减少深基坑大面积的长期暴露所带来的对深基坑本身和周边环境的安全隐患。
本发明所采用的技术方案是:
一种大面积深基坑分区顺逆工况下的支撑体系,包括TRD止水帷幕、围护桩、三轴搅拌桩、格构柱、立柱桩、钢筋混凝土内支撑,其特征在于:由TRD止水帷幕形成深基坑外侧封闭止水墙;TRD止水帷幕的内侧设置一排围护桩作为深基坑的支护体系;在深基坑的中部设置一道三轴搅拌桩将深基坑分成两个区域,并在三轴搅拌桩的一侧设置一排围护桩;深基坑内设置若干立柱桩,每个立柱桩上连接一格构柱组成内支撑的竖向承力结构;在围护桩内设置若干道钢筋混凝土内支撑,各内支撑之间通过对应格构柱承载组成深基坑的内支撑形式。
利用所述的大面积深基坑分区顺逆工况下的支撑体系的施工方法,其特征在于按以下步骤进行:(1)在深基坑外侧由TRD止水帷幕1形成封闭止水墙,TRD止水帷幕的内侧设置一排围护桩作为深基坑的支护体系;在深基坑的中部设置一道三轴搅拌桩将深基坑分成两个区域,并在三轴搅拌桩的一侧设置一排围护桩;深基坑内设置若干立柱桩,每个立柱桩上连接一格构柱组成内支撑的竖向承力结构;在围护桩内设置若干道钢筋混凝土内支撑,各内支撑之间通过对应格构柱承载组成深基坑的内支撑形式;(2)先对一个区域的土方开挖和钢筋混凝土支撑施工,并进行钢筋混凝土内支撑的拆除和地下室结构层及换撑板带的施工,从基础底板开始向上进行结构施工,每拆除一钢筋混凝土内支撑同时建好一地下室结构层和换撑板带,换撑板带一端固定在围护桩上另一端与地下室结构层固定,地下室结构层另一端与对应的围护桩固定,待一个区域施工至地下室负一层时,在进行型钢斜撑换撑施工,型钢斜撑换撑一端固定在地下室结构层上,另一端固定在对应的围护桩上;(3)同按步骤(2)进行另一个区域的施工。
本发明一个区域由下向上进行结构层施工时,另一个区域由上向下进行土方开挖;待另一个区域的地下室结构施工完成后,进行深基坑分区界处的围护桩破除,并将两个区的结构梁板连接起来形成整个地下室结构。
在大面积深基坑的中部设置三轴水泥土搅拌桩和围护桩,将大面积深基坑分为两个闭合的止水围护区域后,一个区域先进行土方开挖和支撑施工,减少了整个深基坑的长度距离,达到减小内支撑在轴力方向上的徐变值的效果,从而减小对周边道路、管线和建筑物的沉降。
本发明一个区域先进行土方开挖和支撑施工,从基础底板开始向上进行结构施工,待施工至第一道支撑拆除之前,进行型钢斜撑梁换撑施工,确保另一个区域的水平应力传递到先施工的这个区域的结构梁板上;另一个区域从上往下进行土方开挖和支撑施工。
本发明的有益效果是,可以减少整个深基坑的长度距离,缩短每次支撑施工和每层结构施工的流水时间,减少整个深基坑在长度和宽度上大距离的整体暴露时间,达到减小内支撑在轴力方向上的徐变值的效果,从而减小对周边道路、管线和建筑物的沉降。
附图说明
下面结合附图和实施例对本发明进一步说明。
图1是本发明的深基坑平面图。
图2是本发明的深基坑施工工况图一。
图3是本发明的深基坑施工工况图二。
图4是本发明的深基坑施工工况图三。
图5是本发明的深基坑施工工况图四。
图6是本发明的深基坑施工工况图五。
图中1-TRD止水帷幕,2-围护桩,3-三轴搅拌桩,4-格构柱,5-立柱桩,6-钢筋混凝土内支撑,7-换撑板带,8-型钢斜撑换撑,9-基础底板,10-地下室结构层。
具体实施方式
如图1、图2、图3、图4、图5、图6所示,本发明的一种大面积深基坑分区顺逆工况下的支撑体系,包括TRD止水帷幕1、围护桩2、三轴搅拌桩3、格构柱4、立柱桩5、钢筋混凝土内支撑6,其特征在于:由TRD止水帷幕1形成深基坑外侧封闭止水墙;TRD止水帷幕1的内侧设置一排围护桩2作为深基坑的支护体系;在深基坑的中部设置一道三轴搅拌桩3将深基坑分成两个区域,并在三轴搅拌桩3的一侧设置一排围护桩2;深基坑内设置若干立柱桩5,每个立柱桩5上连接一格构柱4组成内支撑的竖向承力结构;在围护桩2内设置若干道钢筋混凝土内支撑6,各内支撑6之间通过对应格构柱4承载组成深基坑的内支撑形式。
利用所述的大面积深基坑分区顺逆工况下的支撑体系的施工方法,其特征在于按以下步骤进行:(1)在深基坑外侧由TRD止水帷幕1形成封闭止水墙,TRD止水帷幕1的内侧设置一排围护桩2作为深基坑的支护体系;在深基坑的中部设置一道三轴搅拌桩3将深基坑分成两个区域,并在三轴搅拌桩3的一侧设置一排围护桩2;深基坑内设置若干立柱桩5,每个立柱桩5上连接一格构柱4组成内支撑的竖向承力结构;在围护桩2内设置若干道钢筋混凝土内支撑6,各内支撑6之间通过对应格构柱4承载组成深基坑的内支撑形式;(2)先对一个区域的土方开挖和钢筋混凝土支撑施工,并进行钢筋混凝土内支撑6的拆除和地下室结构层10及换撑板带7的施工,从基础底板9开始向上进行结构施工,每拆除一钢筋混凝土内支撑6同时建好一地下室结构层10和换撑板带7,换撑板带7一端固定在围护桩2上另一端与地下室结构层10固定,地下室结构层10另一端与对应的围护桩2固定,待一个区域施工至地下室负一层时,在进行型钢斜撑换撑8施工,型钢斜撑换撑8一端固定在地下室结构层10上,另一端固定在对应的围护桩2上;(3)按步骤(2)进行另一个区域的施工。
本发明一个区域由下向上进行结构层施工时,另一个区域由上向下进行土方开挖;待另一个区域的地下室结构施工完成后,进行深基坑分区界处的围护桩2破除,并将两个区的结构梁板连接起来形成整个地下室结构。
本发明的有益效果是,可以减少整个深基坑的长度距离,缩短每次支撑施工和每层结构施工的流水时间,减少整个深基坑在长度和宽度上大距离的整体暴露时间,达到减小内支撑在轴力方向上的徐变值的效果,从而减小对周边道路、管线和建筑物的沉降。

Claims (3)

1.一种大面积深基坑分区顺逆工况下的支撑体系,包括TRD止水帷幕、围护桩、三轴搅拌桩、格构柱、立柱桩、钢筋混凝土内支撑,其特征在于:由TRD止水帷幕形成深基坑外侧封闭止水墙;TRD止水帷幕的内侧设置一排围护桩作为深基坑的支护体系;在深基坑的中部设置一道三轴搅拌桩将深基坑分成两个区域,并在三轴搅拌桩的一侧设置一排围护桩;深基坑内设置若干立柱桩,每个立柱桩上连接一格构柱组成内支撑的竖向承力结构;在围护桩内设置若干道钢筋混凝土内支撑,各内支撑之间通过对应格构柱承载组成深基坑的内支撑形式。
2.利用根据权利要求1所述的大面积深基坑分区顺逆工况下的支撑体系的施工方法,其特征在于按以下步骤进行:(1)在深基坑外侧由TRD止水帷幕1形成封闭止水墙,TRD止水帷幕的内侧设置一排围护桩作为深基坑的支护体系;在深基坑的中部设置一道三轴搅拌桩将深基坑分成两个区域,并在三轴搅拌桩的一侧设置一排围护桩;深基坑内设置若干立柱桩,每个立柱桩上连接一格构柱组成内支撑的竖向承力结构;在围护桩内设置若干道钢筋混凝土内支撑,各内支撑之间通过对应格构柱承载组成深基坑的内支撑形式;(2)先对一个区域的土方开挖和钢筋混凝土支撑施工,并进行钢筋混凝土内支撑的拆除和地下室结构层及换撑板带的施工,从基础底板开始向上进行结构施工,每拆除一钢筋混凝土内支撑同时建好一地下室结构层和换撑板带,换撑板带一端固定在围护桩上另一端与地下室结构层固定,地下室结构层另一端与对应的围护桩固定,待一个区域施工至地下室负一层时,在进行型钢斜撑换撑施工,型钢斜撑换撑一端固定在地下室结构层上,另一端固定在对应的围护桩上;(3)按步骤(2)进行另一个区域的施工。
3.根据权利要求2所述的大面积深基坑分区顺逆工况下的支撑体系的施工方法,其特征在于:一个区域由下向上进行结构层施工时,另一个区域由上向下进行土方开挖;待另一个区域的地下室结构施工完成后,进行深基坑分区界处的围护桩破除,并将两个区的结构梁板连接起来形成整个地下室结构。
CN201510340434.0A 2015-06-18 2015-06-18 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法 Active CN105155549B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510340434.0A CN105155549B (zh) 2015-06-18 2015-06-18 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510340434.0A CN105155549B (zh) 2015-06-18 2015-06-18 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法

Publications (2)

Publication Number Publication Date
CN105155549A true CN105155549A (zh) 2015-12-16
CN105155549B CN105155549B (zh) 2017-05-10

Family

ID=54796567

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510340434.0A Active CN105155549B (zh) 2015-06-18 2015-06-18 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法

Country Status (1)

Country Link
CN (1) CN105155549B (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894422A (zh) * 2017-02-28 2017-06-27 南通华荣建设集团有限公司 复杂环境深基坑支护施工方法
CN110306557A (zh) * 2019-07-10 2019-10-08 武汉立诚岩土工程有限公司 基于地下室深基坑工程的土方开挖方法
CN111335321A (zh) * 2020-03-12 2020-06-26 广东省建筑构件工程有限公司 一种地铁隧道上方的深基坑结构及其施工方法
CN111424676A (zh) * 2020-03-31 2020-07-17 中国一冶集团有限公司 一种主体框架梁换撑结构及施工方法
CN111648376A (zh) * 2020-06-10 2020-09-11 深圳市市政工程总公司 一种采用深基坑撑锚结构支护的施工方法
CN112575812A (zh) * 2020-12-01 2021-03-30 中国建筑第二工程局有限公司 一种应用于拆除改造工程的内支撑转换体系及其施工方法
CN112982498A (zh) * 2021-01-20 2021-06-18 广州地铁设计研究院股份有限公司 一种大型基坑的施工方法
CN113216205A (zh) * 2021-05-08 2021-08-06 中国建筑第四工程局有限公司 一种深基坑分基坑施工中隔墙支撑转换方法
CN114411757A (zh) * 2022-02-08 2022-04-29 中建八局南方建设有限公司 深基坑的内支撑分区早拆施工方法
CN114561957A (zh) * 2022-03-15 2022-05-31 中铁四院集团工程建设有限责任公司 邻近既有建筑物的基坑支护系统和施工方法
CN114961335A (zh) * 2022-06-24 2022-08-30 广东省第四建筑工程有限公司 一种大跨度钢筋混凝土支撑梁的拆除施工方法
CN115094912A (zh) * 2022-08-01 2022-09-23 上海建工一建集团有限公司 一种超大型软土基坑上部建筑跨分区顺逆结合施工方法
CN115506405A (zh) * 2022-10-18 2022-12-23 中国建筑第八工程局有限公司 用于超大深基坑的地下室结构半逆作施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090043625A (ko) * 2007-10-30 2009-05-07 이호찬 변단면 철골보를 이용한 지하층의 슬래브 시공 방법
CN103590406A (zh) * 2013-11-29 2014-02-19 中船第九设计研究院工程有限公司 一种超大型深基坑分区同步开挖的施工方法
CN204282370U (zh) * 2014-11-26 2015-04-22 江苏鸿基科技有限公司 一种刚性出土平台基坑内支撑结构
CN204343301U (zh) * 2014-12-13 2015-05-20 中铁二十局集团第三工程有限公司 一种地铁车站基坑开挖支护结构
CN204715366U (zh) * 2015-06-18 2015-10-21 中建三局第二建设工程有限责任公司 一种大面积深基坑分区顺逆工况下的支撑体系

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090043625A (ko) * 2007-10-30 2009-05-07 이호찬 변단면 철골보를 이용한 지하층의 슬래브 시공 방법
CN103590406A (zh) * 2013-11-29 2014-02-19 中船第九设计研究院工程有限公司 一种超大型深基坑分区同步开挖的施工方法
CN204282370U (zh) * 2014-11-26 2015-04-22 江苏鸿基科技有限公司 一种刚性出土平台基坑内支撑结构
CN204343301U (zh) * 2014-12-13 2015-05-20 中铁二十局集团第三工程有限公司 一种地铁车站基坑开挖支护结构
CN204715366U (zh) * 2015-06-18 2015-10-21 中建三局第二建设工程有限责任公司 一种大面积深基坑分区顺逆工况下的支撑体系

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106894422B (zh) * 2017-02-28 2019-03-12 南通华荣建设集团有限公司 复杂环境深基坑支护施工方法
CN106894422A (zh) * 2017-02-28 2017-06-27 南通华荣建设集团有限公司 复杂环境深基坑支护施工方法
CN110306557A (zh) * 2019-07-10 2019-10-08 武汉立诚岩土工程有限公司 基于地下室深基坑工程的土方开挖方法
CN110306557B (zh) * 2019-07-10 2021-04-13 武汉立诚岩土工程有限公司 基于地下室深基坑工程的土方开挖方法
CN111335321B (zh) * 2020-03-12 2021-11-23 广东省构建工程建设有限公司 一种地铁隧道上方的深基坑结构及其施工方法
CN111335321A (zh) * 2020-03-12 2020-06-26 广东省建筑构件工程有限公司 一种地铁隧道上方的深基坑结构及其施工方法
CN111424676A (zh) * 2020-03-31 2020-07-17 中国一冶集团有限公司 一种主体框架梁换撑结构及施工方法
CN111424676B (zh) * 2020-03-31 2022-05-10 中国一冶集团有限公司 一种主体框架梁换撑结构及施工方法
CN111648376A (zh) * 2020-06-10 2020-09-11 深圳市市政工程总公司 一种采用深基坑撑锚结构支护的施工方法
CN112575812A (zh) * 2020-12-01 2021-03-30 中国建筑第二工程局有限公司 一种应用于拆除改造工程的内支撑转换体系及其施工方法
CN112575812B (zh) * 2020-12-01 2022-05-24 中国建筑第二工程局有限公司 一种应用于拆除改造工程的内支撑转换体系及其施工方法
CN112982498A (zh) * 2021-01-20 2021-06-18 广州地铁设计研究院股份有限公司 一种大型基坑的施工方法
CN113216205A (zh) * 2021-05-08 2021-08-06 中国建筑第四工程局有限公司 一种深基坑分基坑施工中隔墙支撑转换方法
CN114411757A (zh) * 2022-02-08 2022-04-29 中建八局南方建设有限公司 深基坑的内支撑分区早拆施工方法
CN114561957A (zh) * 2022-03-15 2022-05-31 中铁四院集团工程建设有限责任公司 邻近既有建筑物的基坑支护系统和施工方法
CN114561957B (zh) * 2022-03-15 2024-06-07 中铁四院集团工程建设有限责任公司 邻近既有建筑物的基坑支护系统及其施工方法
CN114961335A (zh) * 2022-06-24 2022-08-30 广东省第四建筑工程有限公司 一种大跨度钢筋混凝土支撑梁的拆除施工方法
CN114961335B (zh) * 2022-06-24 2023-08-15 广东省第四建筑工程有限公司 一种大跨度钢筋混凝土支撑梁的拆除施工方法
CN115094912A (zh) * 2022-08-01 2022-09-23 上海建工一建集团有限公司 一种超大型软土基坑上部建筑跨分区顺逆结合施工方法
CN115094912B (zh) * 2022-08-01 2023-11-28 上海建工一建集团有限公司 一种超大型软土基坑上部建筑跨分区顺逆结合施工方法
CN115506405A (zh) * 2022-10-18 2022-12-23 中国建筑第八工程局有限公司 用于超大深基坑的地下室结构半逆作施工方法

Also Published As

Publication number Publication date
CN105155549B (zh) 2017-05-10

Similar Documents

Publication Publication Date Title
CN105155549A (zh) 一种大面积深基坑分区顺逆工况下的支撑体系及施工方法
CN105089061B (zh) 一种超深基坑支护方法
CN102182325B (zh) 一种框架结构独立基础既有建筑物地下室增层方法
CN205776347U (zh) 用于地铁车站的新型盖挖逆作结构体系
CN105155554B (zh) 一种拱形支护体系的深基坑
CN204715366U (zh) 一种大面积深基坑分区顺逆工况下的支撑体系
CN104131565B (zh) 一种逆作土方正作开挖的施工方法
CN203654294U (zh) 一种逆作法中基坑的支护结构
KR100967497B1 (ko) 지하 구조물 구축공법
CN104264685B (zh) 一种中隔墙区域结构合拢的施工方法
CN105089670B (zh) 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法
CN100510281C (zh) 超大直径、超埋深度调蓄池的半逆作施工方法
CN103938634A (zh) 一种深基坑支护结构及施工方法
CN109505298A (zh) 一种自平衡基坑围护方法
CN104632250A (zh) 圆形基坑倒挂管片装配式衬砌结构及其施工方法
CN104631469B (zh) 用于深大基坑的无柱钢筋混凝土支撑构架及其搭建方法
CN103104102A (zh) 一种地下增层改造施工方法
CN101498133B (zh) 增大地下室逆作法土方开挖空间的方法和支护结构
CN207452911U (zh) 一种多线立体交叉异型深基坑支护结构
CN204282399U (zh) 一种地铁围护结构
CN102493488A (zh) 基坑工程逆梁顺板施工方法
CN112096425A (zh) 一种马头门位置的横通道支护系统及其施工方法
CN204174854U (zh) 一种垂直分段组合式旋转爬梯
CN203821399U (zh) 一种深基坑支护结构
KR101522300B1 (ko) 기둥의 셀프 포지셔닝 구조 및 이를 이용한 모듈러 적층공법

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20221226

Address after: Room 2105, 21st Floor, Tongda Plaza, No. 111 Wenhua Avenue, Jiangxia District, Wuhan City, Hubei Province 430000

Patentee after: THE SECOND CONSTRUCTION Co.,Ltd. OF CHINA CONSTRUCTION THIRD ENGINEERING BUREAU

Patentee after: China Construction Third Engineering Bureau Group (Jiangsu) Co.,Ltd.

Patentee after: China Construction Third Engineering Bureau second construction and installation Co.,Ltd.

Patentee after: CHINA CONSTRUCTION THIRD ENGINEERING BUREAU GREEN INDUSTRY INVESTMENT Co.,Ltd.

Address before: 430074 No. 306 Lu Lu, Hongshan District, Hubei, Wuhan

Patentee before: THE SECOND CONSTRUCTION Co.,Ltd. OF CHINA CONSTRUCTION THIRD ENGINEERING BUREAU

TR01 Transfer of patent right