CN105113783B - A kind of construction formwork and its construction method of gypsum cast-in-situ wall - Google Patents

A kind of construction formwork and its construction method of gypsum cast-in-situ wall Download PDF

Info

Publication number
CN105113783B
CN105113783B CN201510481093.9A CN201510481093A CN105113783B CN 105113783 B CN105113783 B CN 105113783B CN 201510481093 A CN201510481093 A CN 201510481093A CN 105113783 B CN105113783 B CN 105113783B
Authority
CN
China
Prior art keywords
template
interarea
pouring
bolt
gypsum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510481093.9A
Other languages
Chinese (zh)
Other versions
CN105113783A (en
Inventor
马保国
李显良
苏英
金子豪
张逸超
祝路
卢文达
贺行洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan University of Technology WUT
Original Assignee
Wuhan University of Technology WUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan University of Technology WUT filed Critical Wuhan University of Technology WUT
Priority to CN201510481093.9A priority Critical patent/CN105113783B/en
Publication of CN105113783A publication Critical patent/CN105113783A/en
Application granted granted Critical
Publication of CN105113783B publication Critical patent/CN105113783B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The present invention relates to a kind of construction formworks and its construction method of gypsum cast-in-situ wall, the template includes the interarea template for pouring gypsum base walling material, by the Side shuttering of interarea form for seal when pouring, bottom surface template for pouring waterproof course, the snap gauge of interarea template is limited when pouring, bolt and the internal position limited sleeve pipe that position-limiting action is sleeved on bolt and risen when pouring, the height of the bottom surface template is adapted with the height of waterproof bed course, the height of the height and wall of the interarea template and Side shuttering is adapted, the interarea template, the bolt hole for connecting and positioning is equipped in bottom surface template and Side shuttering.The template can carry out construction of waterproof layer and gypsum pouring construction successively, and gypsum pours primary completion, and construction efficiency is high, it is not easy to spillage, and gypsum wall bottom has obtained waterproofing protection.

Description

A kind of construction formwork and its construction method of gypsum cast-in-situ wall
Technical field
The invention belongs to the realm of building construction, and in particular to a kind of construction formwork and its construction party of gypsum cast-in-situ wall Method.
Background technology
Building materials of gypsum has the function of lightweight, fire prevention, temperature adjustment, damping etc., is Green energy-saving buildings material, cast-in-place using gypsum The construction method of wall carries out construction wall(Especially inner wall of building)Construction, it is not only efficient, labor intensity is small, but also have There is good construction quality, therefore, development potentiality is huge.
Current gypsum cast-in-situ wall is generally constructed using template, and patent 201110169048.1 discloses " a kind of Cast-in-situ gypsum hollow wall and preparation method thereof ", patent 201120210051.9 discloses one kind, and " cast-in-place gypsum wall is applied Work template system special ", above two construction method have the following problems:1. being not provided with waterproof bed course in work progress to apply Work is unfavorable for the waterproof of gypsum wall bottom;2. template is poured, construction effect in layer using the short template superposition of multilayer Rate is relatively low, it is important to be susceptible to spillage phenomenon in the contact position of adjacent template.
Invention content
For being not provided with construction of waterproof layer in the prior art and pour that the efficiency brought is low, is easy spillage by multilayer Problem should the object of the present invention is to provide a kind of construction formwork of gypsum cast-in-situ wall and based on the construction method of the template Template can carry out construction of waterproof layer and gypsum pouring construction successively, and gypsum pours primary completion, and construction efficiency is high, it is not easy to leak Slurry, and gypsum wall bottom has obtained waterproofing protection.
The technical solution adopted in the present invention is:
A kind of construction formwork of gypsum cast-in-situ wall, when including for pouring the interarea template of gypsum base walling material, pouring By the Side shuttering of interarea form for seal, bottom surface template for pouring waterproof course, pour when limit interarea template Snap gauge, bolt and while pouring, are sleeved on bolt and play the internal position limited sleeve pipe of position-limiting action, the height and waterproof of the bottom surface template The height of bed course is adapted, and the height of the height and wall of the interarea template and Side shuttering is adapted, the interarea template, The bolt hole for connecting and positioning is equipped in bottom surface template and Side shuttering.
Further, the both ends of the Side shuttering are bent to form rectangular channel to homonymy.
Further, the bottom surface template is equipped with the different altitude location hole of multiple height.
Further, the interarea template, bottom surface template and Side shuttering be thickness be 3mm-8mm aluminum alloy mould plate or Thickness is the plastic formwork of 6mm-12mm.
Further, the interarea template and the height of Side shuttering are 2.4m-2.7m.
Further, the snap gauge is in mountain font, can respectively be blocked by two open slots in the middle part of the font of mountain when pouring At the top of two interarea templates.
Further, the snap gauge is plastic material, thickness 6mm-12mm, width 5cm-10cm.
Further, the construction formwork of the gypsum cast-in-situ wall further includes that interarea template lateral surface is located at when pouring Reinforcing rib.
Further, the reinforcing rib is made of angle steel, and the angle steel thickness is 1mm-3mm.
A kind of construction method of the construction formwork based on above-mentioned gypsum cast-in-situ wall, step are:1. by bolt and interior Limit casing fixes bottom surface template, then closes bottom surface formwork sides;2. waterproof course is poured, after material hardening, Bottom surface template, bolt and internal position limited sleeve pipe are removed, there are bolts hole for waterproof bed course;3. installing interarea template, makes its bottom and prevent Water subfill bottom be aligned, be located at waterproof bed course part by bolt pass through waterproof bed course there are bolt hole carry out positioning and Fixed, the part higher than waterproof bed course is fixed by bolt and limit casing, with Side shuttering by interarea formwork sides Closing limits interarea template with snap gauge;Removed 4. pour gypsum base materials for wall, after material hardening interarea template, bolt and Internal position limited sleeve pipe.
The beneficial effects of the invention are as follows:
1. bottom surface template and interarea template can be installed to realize the step-by-step construction of waterproof bed course and gypsum wall step by step, The height of bottom surface template is adapted with the height of waterproof bed course, ensure that the construction quality of waterproof bed course;Side shuttering can nothing By interarea form for seal when beam column, ensure that the construction formwork various occasions adaptability;Interarea template and Side shuttering Height and the height of wall are adapted, and ensure that gypsum wall can be completed with one-time-concreting, it is not necessary to it pours step by step, it is efficient, no Easy spillage.
2. close interarea formwork sides, two interarea templates are placed in inside Side shuttering rectangular recess, are conducive to prevent Leak-stopping is starched.
3. the mountain font structure of snap gauge can not only limit two interarea template rectangle insides, but also can carry out external limit Position, it is simple in structure, it is at low cost.
4. behind some the altitude location hole for selecting good respective heights, remaining altitude location hole is blocked, you can anti-to adjust The height of water subfill, it is simple in structure, it is easy to operate.
Description of the drawings
Fig. 1 is the front view of interarea template in the present invention.
Fig. 2 is the front view of midsole face die plate of the present invention.
Fig. 3 is the vertical view of Side shuttering in the present invention.
Fig. 4 is the side view of Side shuttering in the present invention.
Fig. 5 is the schematic diagram of snap gauge in the present invention.
Fig. 6 is the construction drawing of bottom surface template when having beam column in the present invention.
Fig. 7 is the construction drawing of interarea template when having beam column in the present invention.
Fig. 8 is the construction drawing for increasing reinforcing rib when having beam column in the present invention in interarea template.
Fig. 9 be in the present invention without beam column when interarea template installation after vertical view.
In figure:1- interarea templates;2- bolts hole;The bottom surfaces 3- template;4- altitude locations hole;5- Side shutterings;6- snap gauges;7- Wall;8- reinforcing ribs;9- bolts;10- internal position limited sleeve pipes.
Specific implementation mode
The present invention is further illustrated with reference to the accompanying drawings and examples.
A kind of construction formwork of gypsum cast-in-situ wall, when including for pouring the interarea template 1 of gypsum base walling material, pouring By 1 closed Side shuttering 5 of interarea template, the bottom surface template 3 for pouring waterproof course, pour when limit interarea template 1 snap gauge 6, bolt 9 and while pouring, are sleeved on bolt 9 and rise the internal position limited sleeve pipe 10 of position-limiting action, the height of the bottom surface template 3 The height of degree and waterproof bed course is adapted(The height of bottom surface template 3 is slightly above the height of waterproof bed course), 1 He of interarea template The height of Side shuttering 5 and the height of wall are adapted(Interarea template 1 and the height of Side shuttering 5 are slightly below wall height, In the present embodiment, the height of the interarea template 1 and Side shuttering 5 is 2.4m-2.7m), the interarea template 1, bottom surface template 3 With the bolt hole 2 for connecting and positioning is equipped on Side shuttering 5.In the present embodiment, the interarea template 1, bottom surface mould Plate 3 and Side shuttering 5 be thickness be 3mm-8mm aluminum alloy mould plate or thickness be 6mm-12mm plastic formwork(It is easily fabricated And intensity is higher).
Bottom surface template 3 and interarea template 1 can be installed to realize the step-by-step construction of waterproof bed course and gypsum wall step by step, The height of bottom surface template 3 is adapted with the height of waterproof bed course, ensure that the construction quality of waterproof bed course;Side shuttering 5 can be with Interarea template 1 is closed when no beam column, ensure that the construction formwork various occasions adaptability;Interarea template 1 and side mould The height of plate 5 and the height of wall are adapted, and ensure that gypsum wall can be completed with one-time-concreting, it is not necessary to pour step by step, efficiency Height is not easy spillage.
As shown in figure 3, in the present embodiment, the both ends of the Side shuttering 5 are bent to form rectangular channel to homonymy.Closing When interarea 1 side of template, two interarea templates 1 are placed in inside 5 rectangular recess of Side shuttering, mortar leakage prevention is conducive to.
As shown in figure 5, in the present embodiment, the snap gauge 6 is in mountain font, can pass through two in the middle part of the font of mountain when pouring A open slot is stuck in the top of two interarea templates 1, and the snap gauge 6 is plastic material, thickness 6mm-12mm, width For 5cm-10cm.The mountain font structure of snap gauge 6 can not only limit two 1 rectangle insides of interarea template, but also can carry out outside Limit, it is simple in structure, it is at low cost.
As shown in Figure 2 and Figure 6, in the present embodiment, the bottom surface template 3 is equipped with the different height of multiple height Location hole 4.Behind some the altitude location hole 4 for selecting good respective heights, remaining altitude location hole 4 is blocked, you can anti-to adjust The height of water subfill, it is simple in structure, it is easy to operate.
The construction method of construction formwork based on above-mentioned gypsum cast-in-situ wall, step are:
1. bottom surface template 3 is fixed by bolt 9 and internal position limited sleeve pipe 10, then by 3 side-closed of bottom surface template;2. pouring Building waterproofing course(Waterproof course is rapid hardening high-strength material, and 2h intensity is i.e. up to 20MPa or more), after material hardening, Bottom surface template 3, bolt 9 and internal position limited sleeve pipe 10 are removed, there are bolts hole 2 for waterproof bed course;3. installing interarea template 1, make its bottom Portion is aligned with waterproof bed course bottom, be located at waterproof bed course part by bolt 9 pass through waterproof bed course there are bolt hole 2 into Row is positioned and is fixed, and the part higher than waterproof bed course is fixed by bolt 9 and limit casing, will be led with Side shuttering 5 1 side-closed of face die plate limits interarea template 1 with snap gauge 6(As shown in figure 8, in the present embodiment, it can be in master when pouring The lateral surface of face die plate 1 installs reinforcing rib 8, and to improve structural strength, which is made of angle steel, and the angle steel is thick Degree is 1mm-3mm);4. pouring gypsum base materials for wall, interarea template 1, bolt 9 and internal position limited sleeve pipe 10 are removed after material hardening .
It should be understood that for those of ordinary skills, it can be modified or changed according to the above description, And all these modifications and variations should all belong to the protection domain of appended claims of the present invention.

Claims (10)

1. a kind of construction formwork of gypsum cast-in-situ wall, it is characterised in that:It include the interarea mould for pouring gypsum base walling material Plate, when pouring by the Side shuttering of interarea form for seal, the bottom surface template for pouring waterproof course, pour when limit lead The snap gauge of face die plate, bolt and while pouring, are sleeved on bolt and rise the internal position limited sleeve pipe of position-limiting action, the height of the bottom surface template The height of degree and waterproof bed course is adapted, and the height of the height and wall of the interarea template and Side shuttering is adapted, described The bolt hole for connecting and positioning is equipped on interarea template, bottom surface template and Side shuttering;After removing bottom surface template, waterproof There are bolts hole for bed course, and when installing interarea template, interarea template bottom is aligned with waterproof bed course bottom, and interarea template is located at waterproof The part of bed course by bolt pass through waterproof bed course there are bolt hole positioned and fixed.
2. a kind of construction formwork of gypsum cast-in-situ wall as described in claim 1, it is characterised in that:The two of the Side shuttering It holds to homonymy and is bent to form rectangular channel.
3. a kind of construction formwork of gypsum cast-in-situ wall as described in claim 1, it is characterised in that:It is set in the bottom surface template There is the altitude location hole that multiple height are different.
4. a kind of construction formwork of gypsum cast-in-situ wall as described in claim 1, it is characterised in that:The interarea template, bottom Face die plate and Side shuttering be thickness be 3mm-8mm aluminum alloy mould plate or thickness be 6mm-12mm plastic formwork.
5. a kind of construction formwork of gypsum cast-in-situ wall as described in claim 1, it is characterised in that:The interarea template and side The height of face die plate is 2.4m-2.7m.
6. a kind of construction formwork of gypsum cast-in-situ wall as described in claim 1, it is characterised in that:The snap gauge is in mountain word Type can be stuck in the top of two interarea templates by two open slots in the middle part of the font of mountain when pouring.
7. a kind of construction formwork of gypsum cast-in-situ wall as claimed in claim 6, it is characterised in that:The snap gauge is plastics material Matter, thickness 6mm-12mm, width 5cm-10cm.
8. a kind of construction formwork of gypsum cast-in-situ wall as described in claim 1, it is characterised in that:The gypsum cast-in-place wall The construction formwork of body further includes the reinforcing rib that interarea template lateral surface is located at when pouring.
9. a kind of construction formwork of gypsum cast-in-situ wall as claimed in claim 8, it is characterised in that:The reinforcing rib is by angle steel Composition, the angle steel thickness is 1mm-3mm.
10. a kind of construction method of the construction formwork of gypsum cast-in-situ wall as described in claim 1 to 9 is any, feature exist In:Include the following steps, 1. are fixed bottom surface template by bolt and internal position limited sleeve pipe, then close bottom surface formwork sides; 2. pouring waterproof course, after material hardening, bottom surface template, bolt and internal position limited sleeve pipe are removed, there are bolts for waterproof bed course Hole;3. installing interarea template, its bottom is made to be aligned with waterproof bed course bottom, the part for being located at waterproof bed course is passed through by bolt Waterproof bed course there are bolt hole positioned and fixed, the part higher than waterproof bed course passes through bolt and limit casing and carries out It is fixed, interarea formwork sides are closed with Side shuttering, interarea template is limited with snap gauge;4. gypsum base materials for wall is poured, Interarea template, bolt and internal position limited sleeve pipe are removed after material hardening.
CN201510481093.9A 2015-08-07 2015-08-07 A kind of construction formwork and its construction method of gypsum cast-in-situ wall Expired - Fee Related CN105113783B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510481093.9A CN105113783B (en) 2015-08-07 2015-08-07 A kind of construction formwork and its construction method of gypsum cast-in-situ wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510481093.9A CN105113783B (en) 2015-08-07 2015-08-07 A kind of construction formwork and its construction method of gypsum cast-in-situ wall

Publications (2)

Publication Number Publication Date
CN105113783A CN105113783A (en) 2015-12-02
CN105113783B true CN105113783B (en) 2018-09-11

Family

ID=54661874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510481093.9A Expired - Fee Related CN105113783B (en) 2015-08-07 2015-08-07 A kind of construction formwork and its construction method of gypsum cast-in-situ wall

Country Status (1)

Country Link
CN (1) CN105113783B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105804392B (en) * 2016-05-11 2018-03-20 赵云川 A kind of construction technology of gypsum wall mould

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BE659676A (en) * 1964-02-12
ES2126444B1 (en) * 1993-01-27 1999-10-16 Bravo Roberto Just PROCEDURE FOR THE CONSTRUCTION OF PARTITIONS
AUPN317395A0 (en) * 1995-05-25 1995-06-22 Newtec Concrete Constructions Pty Limited Building methods and apparatus
CN202157533U (en) * 2011-06-21 2012-03-07 无锡市现代钢结构工程有限公司 Template system special for cast-in-place gypsum wall construction
CN202391102U (en) * 2011-12-07 2012-08-22 陈耀新 Split mounting type light heat-preservation cement wall body die structure
CN203175036U (en) * 2013-04-23 2013-09-04 葛洲坝集团第六工程有限公司 Asphalt-concrete core wall adjustable template device
US20150102204A1 (en) * 2013-10-10 2015-04-16 Allways Concrete, Llc Concrete form clip
CN104314305B (en) * 2014-10-15 2016-04-27 中铁四局集团有限公司 Integral moving formwork for straight wall concrete pouring and application thereof

Also Published As

Publication number Publication date
CN105113783A (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN108914965A (en) The continuous construction method of aluminum alloy mould plate for pipe gallery
CN207538350U (en) A kind of assembled cantilever stair
CN109322505A (en) A kind of roofing reserved opening concrete plugging device and preparation method thereof
CN203821688U (en) Building block with openings at two ends
CN203270627U (en) Construction joint structure of shear wall
CN104790435A (en) Post-subsidence pouring belt advancing waterstop impermeable concrete structure and construction technology thereof
CN105113783B (en) A kind of construction formwork and its construction method of gypsum cast-in-situ wall
CN205591555U (en) Processing apparatus of basement outer wall
CN215106098U (en) Prefabricated post connection structure
KR200469370Y1 (en) The pipe sleeve
CN206599990U (en) The one-time-concreting mould at underground structrue engineering exterior wall arc negative and positive angle
CN203961624U (en) A kind of prefabricated windowsill bears down on one
CN103696564A (en) Novel construction joint formwork
CN203213597U (en) Built-in type formwork for cast-in-situ fair-faced concrete stairs
CN106381883B (en) Bar Seepage method through walls
CN109518769A (en) A kind of method and structure using PVC waterstop joint installation sewer pipe
CN206205166U (en) It is a kind of can synchronous crossed construction outer wall of basement waterproofing protection structure
CN202090503U (en) Reinforced concrete ribbed porous decorating formwork
CN209082681U (en) A kind of prefabricated assembled bay window constructing structure of residential building
CN106592754A (en) Method for guaranteeing waterproof construction quality of deep foundation pit basement
CN210263452U (en) Waterproof structure of prefabricated external wall panel window hole
CN212078168U (en) Assembly type building pipeline embedded part
CN209443773U (en) A kind of embedded structure column template
CN209129413U (en) A kind of roofing reserved opening concrete plugging device
CN204738671U (en) High -rise building antiseep exterior window

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180911

Termination date: 20200807