CN105091682A - 钢筋混凝土柱轴向预埋炮孔及拆除爆破方法 - Google Patents
钢筋混凝土柱轴向预埋炮孔及拆除爆破方法 Download PDFInfo
- Publication number
- CN105091682A CN105091682A CN201510383378.9A CN201510383378A CN105091682A CN 105091682 A CN105091682 A CN 105091682A CN 201510383378 A CN201510383378 A CN 201510383378A CN 105091682 A CN105091682 A CN 105091682A
- Authority
- CN
- China
- Prior art keywords
- big gun
- gun hole
- buried
- buried big
- reinforced column
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000005422 blasting Methods 0.000 title claims abstract description 28
- 238000000034 method Methods 0.000 title claims abstract description 17
- 238000005266 casting Methods 0.000 title abstract 4
- 239000011150 reinforced concrete Substances 0.000 title abstract 3
- 239000000843 powder Substances 0.000 claims description 23
- 238000004880 explosion Methods 0.000 claims description 9
- 239000000463 material Substances 0.000 claims description 7
- 230000000903 blocking effect Effects 0.000 claims description 6
- 230000011218 segmentation Effects 0.000 claims description 6
- 239000002360 explosive Substances 0.000 abstract description 7
- 230000000694 effects Effects 0.000 abstract description 3
- 230000006378 damage Effects 0.000 abstract description 2
- 238000005553 drilling Methods 0.000 abstract description 2
- 230000003247 decreasing effect Effects 0.000 abstract 1
- 238000005474 detonation Methods 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 5
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 2
- 238000005452 bending Methods 0.000 description 2
- 230000009172 bursting Effects 0.000 description 2
- 239000000839 emulsion Substances 0.000 description 2
- 229910052760 oxygen Inorganic materials 0.000 description 2
- 239000001301 oxygen Substances 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 238000013467 fragmentation Methods 0.000 description 1
- 238000006062 fragmentation reaction Methods 0.000 description 1
- 239000000499 gel Substances 0.000 description 1
- 230000003014 reinforcing effect Effects 0.000 description 1
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510383378.9A CN105091682B (zh) | 2015-07-01 | 2015-07-01 | 钢筋混凝土柱轴向预埋炮孔及拆除爆破方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510383378.9A CN105091682B (zh) | 2015-07-01 | 2015-07-01 | 钢筋混凝土柱轴向预埋炮孔及拆除爆破方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105091682A true CN105091682A (zh) | 2015-11-25 |
CN105091682B CN105091682B (zh) | 2016-11-16 |
Family
ID=54572647
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510383378.9A Active CN105091682B (zh) | 2015-07-01 | 2015-07-01 | 钢筋混凝土柱轴向预埋炮孔及拆除爆破方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105091682B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105571418A (zh) * | 2016-02-23 | 2016-05-11 | 程大春 | 钢筋混凝土梁或柱水耦合装药爆破拆除方法 |
CN105587119A (zh) * | 2016-01-29 | 2016-05-18 | 武汉爆破有限公司 | 一种现浇混凝土预埋成孔装置及其现浇混凝土预埋成炮孔的方法 |
CN105627845A (zh) * | 2016-02-22 | 2016-06-01 | 叶建军 | 装药长袋及利用装药长袋对炮孔装药的方法 |
CN106049503A (zh) * | 2016-06-06 | 2016-10-26 | 武汉科技大学 | 一种基坑内钢筋混凝土支撑梁爆破拆除的预处理方法 |
CN109707118A (zh) * | 2019-01-18 | 2019-05-03 | 湖北工业大学 | 兼作拆除炮孔的落水管在建筑物周边柱中的预埋布置方式及方法 |
CN110284674A (zh) * | 2019-06-11 | 2019-09-27 | 湖北工业大学 | 钢筋混凝土楼梯预埋孔布置方式及安装扶手和爆破拆除的方法 |
CN112665474A (zh) * | 2020-12-22 | 2021-04-16 | 武汉爆破有限公司 | 一种混凝土水平支撑结构绿色施工工艺 |
CN113654423A (zh) * | 2021-08-31 | 2021-11-16 | 湖北工业大学 | 钢筋混凝土梁柱预埋孔机械切割与异地爆破绿色拆除方法 |
CN115045459A (zh) * | 2022-07-12 | 2022-09-13 | 河钢建筑工程有限公司 | 一种建筑装饰瓷砖、铺装和拆除方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1050424A (zh) * | 1989-09-21 | 1991-04-03 | 杨森 | 混凝土软化破碎方法 |
US20030019383A1 (en) * | 2001-03-20 | 2003-01-30 | Young-Jae Yoon | Method of blasting bench of rock with improved blasting efficiency and reduced blasting nuisance |
CN104215136A (zh) * | 2014-09-01 | 2014-12-17 | 武汉宏伟交通爆破工程有限公司 | 钢筋混凝土梁拆除爆破炮孔装药、堵塞和压渣结构及拆除爆破方法 |
CN104404965A (zh) * | 2014-11-05 | 2015-03-11 | 浙江海洋学院 | 基坑支护内钢筋混凝土支撑梁拆除方法 |
-
2015
- 2015-07-01 CN CN201510383378.9A patent/CN105091682B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1050424A (zh) * | 1989-09-21 | 1991-04-03 | 杨森 | 混凝土软化破碎方法 |
US20030019383A1 (en) * | 2001-03-20 | 2003-01-30 | Young-Jae Yoon | Method of blasting bench of rock with improved blasting efficiency and reduced blasting nuisance |
CN104215136A (zh) * | 2014-09-01 | 2014-12-17 | 武汉宏伟交通爆破工程有限公司 | 钢筋混凝土梁拆除爆破炮孔装药、堵塞和压渣结构及拆除爆破方法 |
CN104404965A (zh) * | 2014-11-05 | 2015-03-11 | 浙江海洋学院 | 基坑支护内钢筋混凝土支撑梁拆除方法 |
Cited By (13)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105587119A (zh) * | 2016-01-29 | 2016-05-18 | 武汉爆破有限公司 | 一种现浇混凝土预埋成孔装置及其现浇混凝土预埋成炮孔的方法 |
CN105627845A (zh) * | 2016-02-22 | 2016-06-01 | 叶建军 | 装药长袋及利用装药长袋对炮孔装药的方法 |
CN105627845B (zh) * | 2016-02-22 | 2018-08-24 | 叶建军 | 装药长袋及利用装药长袋对炮孔装药的方法 |
CN105571418B (zh) * | 2016-02-23 | 2018-01-16 | 程大春 | 钢筋混凝土梁或柱水耦合装药爆破拆除方法 |
CN105571418A (zh) * | 2016-02-23 | 2016-05-11 | 程大春 | 钢筋混凝土梁或柱水耦合装药爆破拆除方法 |
CN106049503A (zh) * | 2016-06-06 | 2016-10-26 | 武汉科技大学 | 一种基坑内钢筋混凝土支撑梁爆破拆除的预处理方法 |
CN106049503B (zh) * | 2016-06-06 | 2017-11-10 | 武汉科技大学 | 一种基坑内钢筋混凝土支撑梁爆破拆除的预处理方法 |
CN109707118A (zh) * | 2019-01-18 | 2019-05-03 | 湖北工业大学 | 兼作拆除炮孔的落水管在建筑物周边柱中的预埋布置方式及方法 |
CN110284674A (zh) * | 2019-06-11 | 2019-09-27 | 湖北工业大学 | 钢筋混凝土楼梯预埋孔布置方式及安装扶手和爆破拆除的方法 |
CN112665474A (zh) * | 2020-12-22 | 2021-04-16 | 武汉爆破有限公司 | 一种混凝土水平支撑结构绿色施工工艺 |
CN113654423A (zh) * | 2021-08-31 | 2021-11-16 | 湖北工业大学 | 钢筋混凝土梁柱预埋孔机械切割与异地爆破绿色拆除方法 |
CN115045459A (zh) * | 2022-07-12 | 2022-09-13 | 河钢建筑工程有限公司 | 一种建筑装饰瓷砖、铺装和拆除方法 |
CN115045459B (zh) * | 2022-07-12 | 2023-10-24 | 河北大河钢构科技有限公司 | 一种建筑装饰瓷砖、铺装和拆除方法 |
Also Published As
Publication number | Publication date |
---|---|
CN105091682B (zh) | 2016-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105091682A (zh) | 钢筋混凝土柱轴向预埋炮孔及拆除爆破方法 | |
CN104964624B (zh) | 钢筋混凝土梁轴向预埋炮孔及拆除爆破方法 | |
CN103321669B (zh) | 深孔定向预裂爆破低透气煤层增透的方法 | |
CN104964623B (zh) | 大面积或大体积混凝土预埋炮孔布置方式及拆除爆破方法 | |
CN105823386B (zh) | 一种基坑内钢筋混凝土支撑梁的爆破拆除方法 | |
CN108007285A (zh) | 一种岩石巷道深孔分阶分段高效掏槽爆破方法 | |
CN103924956A (zh) | 一种块煤开采用超前预裂方法 | |
CN101419040A (zh) | 大孔径复合掏槽中深孔爆破方法 | |
CN103953339B (zh) | 一种块煤开采用采煤机及煤层开采方法 | |
CN105387777B (zh) | 一种光面爆破间隔装药切缝管 | |
CN102808621B (zh) | 急倾斜厚矿体的爆破方法 | |
CN105571418A (zh) | 钢筋混凝土梁或柱水耦合装药爆破拆除方法 | |
CN102817633A (zh) | 深孔裂隙控制爆破的抽放瓦斯的装置及预裂方法 | |
CN111998742A (zh) | 一次爆破成深井的施工方法 | |
CN112161534A (zh) | 一种矿山井下上向进路一步骤回采控制爆破方法 | |
CN105387775A (zh) | 一种处理综采工作面过断层的方法及装置 | |
CN102374833A (zh) | 矿井平巷掘进爆破方法 | |
CN114183138A (zh) | 一种煤层末采钻孔预裂爆破方法 | |
CN111022051B (zh) | 一种工作面中央坚硬顶板强制放顶方法 | |
CN102927863B (zh) | 一种全岩巷道爆破施工的新方法 | |
CN111473701A (zh) | 一种适于高应力矿体超前聚能致裂爆破的方法 | |
CN212963058U (zh) | 地下采矿上向炮孔卡堵处理工具 | |
CN103175450B (zh) | 深孔爆破法 | |
CN1397783A (zh) | 一种爆破方法 | |
CN112611276A (zh) | 一种深孔分段爆破的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information | ||
CB03 | Change of inventor or designer information |
Inventor after: Ye Jianjun Inventor after: Yu Yifeng Inventor after: Chen Weiming Inventor after: Cheng Dachun Inventor after: Ming Jun Inventor before: Ye Jianjun Inventor before: Cheng Dachun Inventor before: Ming Jun |
|
TR01 | Transfer of patent right |
Effective date of registration: 20170822 Address after: 438700, 3, Simon Street, Wenquan Town, Yingshan County, Huanggang, Hubei Patentee after: HUBEI CHANG'AN CONSTRUCTION STOCK Co.,Ltd. Address before: 430068 Wuhan Province, Hongshan District, Hubei Province Li Road, No. 1 village, School of civil engineering, Hubei University of Technology, Department of geotechnical and road engineering Patentee before: Ye Jianjun |
|
TR01 | Transfer of patent right | ||
CP03 | Change of name, title or address |
Address after: No. 7 Yanhe West Road, Wenquan Town, Yingshan County, Huanggang City, Hubei Province 438700 Patentee after: Hubei Chang'an Construction Group Co.,Ltd. Address before: 438700 No. 3, Ximen street, Wenquan Town, Yingshan County, Huanggang City, Hubei Province Patentee before: HUBEI CHANG'AN CONSTRUCTION STOCK Co.,Ltd. |
|
CP03 | Change of name, title or address | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Axially embedded blast holes and demolition blasting methods for reinforced concrete columns Effective date of registration: 20230626 Granted publication date: 20161116 Pledgee: Industrial and Commercial Bank of China Limited Yingshan sub branch Pledgor: Hubei Chang'an Construction Group Co.,Ltd. Registration number: Y2023420000250 |
|
PE01 | Entry into force of the registration of the contract for pledge of patent right |