CN105091597B - A kind of bell of heating furnace - Google Patents

A kind of bell of heating furnace Download PDF

Info

Publication number
CN105091597B
CN105091597B CN201510540984.7A CN201510540984A CN105091597B CN 105091597 B CN105091597 B CN 105091597B CN 201510540984 A CN201510540984 A CN 201510540984A CN 105091597 B CN105091597 B CN 105091597B
Authority
CN
China
Prior art keywords
bell
top plate
heating furnace
chimney
heater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510540984.7A
Other languages
Chinese (zh)
Other versions
CN105091597A (en
Inventor
马志刚
吕峰
陈伟
钱怡
史大金
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taicang Jinma Intelligent Equipment Co Ltd
Original Assignee
Taicang Jinma Intelligent Equipment Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taicang Jinma Intelligent Equipment Co Ltd filed Critical Taicang Jinma Intelligent Equipment Co Ltd
Priority to CN201510540984.7A priority Critical patent/CN105091597B/en
Publication of CN105091597A publication Critical patent/CN105091597A/en
Application granted granted Critical
Publication of CN105091597B publication Critical patent/CN105091597B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Vertical, Hearth, Or Arc Furnaces (AREA)

Abstract

The present invention relates to a kind of bell of heating furnace, including bell body, the bell body has two top plates being obliquely installed in opposite directions, top plate described in two connects the top cover to form " ︿ " shape, the side plate of triangle is respectively connected between the ora terminalis of top plate described in two, surrounding edge is equipped with the side edge of top plate described in two and the edge of side plate described in two to enclose to form the vertical of rectangle, is vertically connected with the chimney that can be connected described in two on top plate.The bell of heating furnace of the present invention can make flue gas is smooth to be completely exhausted out body of heater, by setting two chimneys on bell body, add draft by setting the bell body of roof shape, can greatly increase the air into body of heater, it is ensured that the fuel in body of heater burns completely.

Description

A kind of bell of heating furnace
Technical field
The present invention relates to the bell on a kind of heating furnace, more particularly to a kind of heating furnace.
Background technology
In metallurgical industry, heating furnace is to be heated to be rolled into setting for forging temperature by material or workpiece (being usually metal) Standby (industrial furnace).Existing heating furnace is included in body of heater and the bell being arranged on body of heater, body of heater as burner hearth, and fuel is entered An exhaust opening is set on row burning, bell, air is sucked using the draft of exhaust opening while discharge flue gas, so that fuel is fired Burn.Because exhaust opening will complete work of the smoke evacuation with sucking air simultaneously, the air of suction can be caused not abundant enough, and influence combustion Material fully burning, fuel burn incompletely then discharges the flue gas containing carbon monoxide, environment is polluted.
In view of above-mentioned defect, the design people is actively subject to research and innovation, to found a kind of bell of heating furnace, Make it with more the value in industry.
The content of the invention
In order to solve the above technical problems, can suck sufficient air it is an object of the invention to provide one kind supplies fuel combustion Heating furnace bell.
The bell of the heating furnace of the present invention, including bell body, the bell body have two tops being obliquely installed in opposite directions Plate, top plate described in two connects the top cover to form " ︿ " shape, and the side plate of triangle is respectively connected between the ora terminalis of top plate described in two, Surrounding edge is equipped with the side edge of top plate described in two and the edge of side plate described in two to enclose to form the vertical of rectangle, described in two on top plate It is vertically connected with the chimney that can be connected.
Further, slide to be provided with top plate inwall described in two and can stop the damper of the chimney respectively.
Further, the vertical inwall that encloses is provided with the raised sealing ring of a circle.
Further, the chute slided for the damper is equipped with described in two on top plate inwall.
Further, the baffle plate that can be contacted with the inner wall of stack is equipped with the end of damper described in two.
Further, vertical place is additionally provided with some fixing holes.
By such scheme, the bell of heating furnace of the present invention can make flue gas suitable by setting the bell body of roof shape Body of heater freely is completely exhausted out, by setting two chimneys on bell body, draft is added, the sky into body of heater can be greatly increased Gas, it is ensured that the fuel in body of heater burns completely.
Described above is only the general introduction of technical solution of the present invention, in order to better understand the technological means of the present invention, And can be practiced according to the content of specification, below with presently preferred embodiments of the present invention and coordinate accompanying drawing describe in detail as after.
Brief description of the drawings
Fig. 1 is the structural representation of the present invention;
Fig. 2 is the structural representation of top plate in the present invention.
Embodiment
With reference to the accompanying drawings and examples, the embodiment to the present invention is described in further detail.Implement below Example is used to illustrate the present invention, but is not limited to the scope of the present invention.
Referring to Fig. 1 and Fig. 2, a kind of bell of heating furnace described in a preferred embodiment of the present invention, including bell body, stove Lid body has two top plates 10 being obliquely installed in opposite directions, and the connection of two top plates 10 forms the top cover of " ︿ " shape, at the end of two top plates 10 It is respectively connected between edge on the side plate 20 of triangle, the side edge of two top plates 10 and the edge of biside plate 20 and is equipped with surrounding edge with shape Rectangular vertical enclose is equipped with the chimney 40 that can be connected on 30, two top plates 10.Bell body is set to room in the present invention Shape is pushed up, and two chimneys 40 communicated are set, during heating furnace burning fuel is heated, flue gas can be along inclined top Plate 10, which is taken advantage of a situation, reaches chimney 40, is emitted through chimney 40, compared to the conventional upper for keeping flat setting, 10, the top plate being obliquely installed To the effect of flue gas water conservancy diversion, if keeping flat the top plate of setting, flue gas can produce delay, and the flue gas for also not coming and emitting is rear When continuous flue gas comes up, produce vortex and be trapped in bell, then reduce the entrance of air, cause non-complete combustion of fuel;And The bell of the present invention is when discharging flue gas, flue gas reaches chimney along the top plate 10 that is obliquely installed, even if partial fume is not remembered also It must discharge, when follow-up flue gas comes up, flue gas above can only be rushed out, be not detained in bell, it is ensured that fuel can Burning completely.
The present invention adds smoke discharge amount, while also increasing by setting two chimneys 40 on the bell of roof shape Draft is added, more air can be pumped into and entered in bell, to ensure that fuel burns completely.Because top plate 10 is to tilt to set Put, chimney 40 is vertically set on top plate in the present invention, chimney 40 is also inclined, chimney 40 is empty when being pumped into air Gas is with flue gas formation convection current, and the air that two chimneys 40 are pumped into radially is acted on to fuel after merging in bell so that combustion Material fully burning.It can be seen that, make two chimneys 40 inclined, so as to the air interflow that two chimneys 40 are sucked, inclined top plate 10 So that the air radiation behind interflow is acted on fuel.
Further, slided provided with the damper 50 of chimney 40 can be stopped respectively, specifically on the inwall of two top plate 10 A through hole 12 is opened on top plate 10, chimney 40 is connected on through hole 12, chute 11 is set on the inwall of top plate 10, flue is kept off Plate 50 is slidably connected with chute 11, by sliding damper 50, and through hole 12 is blocked, so that the mouth of chimney 40 is stopped, In the case that heating furnace is stopped, stop chimney 40, prevent foreign matter from entering from chimney 40 in heating furnace.
It is preferred that, the baffle plate 51 that can be contacted with the inwall of chimney 40 is equipped with the end of two dampers 50, by cigarette Road baffle plate 50 slip away through hole 12 when, eliminate stop to chimney 40, chimney 40 is connected with bell inside, using baffle plate 51 by cigarette Road baffle plate 50 is hung on chimney 40, it is to avoid damper 50 hangs over damper 50 on chute 11 completely into chute 11, When needing to cover through hole 12, baffle plate 51 is lifted.
Further, stand and enclose 30 inwalls provided with the raised sealing ring 31 of a circle, be installed to by bell body on body of heater When, using sealing ring 31 bell body can be made closely to be connected with body of heater, prevent the flue gas in body of heater from spilling.
Installed for convenience of bell body with body of heater, some fixing holes 32 can be set on 30 in vertical enclose, be passed through and fixed using bolt Bell body is arranged on body of heater by hole 32.
The bell of the heating furnace of the present invention can make flue gas is smooth to be completely exhausted out stove by setting the bell body of roof shape Body, by setting two chimneys on bell body, adds draft, can greatly increase the air into body of heater, it is ensured that in body of heater Fuel burn completely.
Described above is only the preferred embodiment of the present invention, is not intended to limit the invention, it is noted that for this skill For the those of ordinary skill in art field, without departing from the technical principles of the invention, can also make it is some improvement and Modification, these improvement and modification also should be regarded as protection scope of the present invention.

Claims (6)

1. a kind of bell of heating furnace, it is characterised in that:Including bell body, the bell body has two to be obliquely installed in opposite directions Top plate, top plate described in two connects the top cover to form " ︿ " shape, triangle is respectively connected between the ora terminalis of top plate described in two Surrounding edge is equipped with side plate, the side edge of top plate described in two and the edge of side plate described in two to enclose to form the vertical of rectangle, is pushed up described in two The chimney that can be connected is vertically connected with plate.
2. the bell of heating furnace according to claim 1, it is characterised in that:Slided on top plate inwall described in two and be provided with energy Enough dampers for stopping the chimney respectively.
3. the bell of heating furnace according to claim 1, it is characterised in that:The vertical inwall that encloses is provided with a circle projection Sealing ring.
4. the bell of heating furnace according to claim 2, it is characterised in that:It is equipped with described in two on top plate inwall for described The chute that damper is slided.
5. the bell of heating furnace according to claim 4, it is characterised in that:It is equipped with the end of damper described in two The baffle plate that can be contacted with the inner wall of stack.
6. the bell of heating furnace according to claim 3, it is characterised in that:Vertical place is additionally provided with some fixing holes.
CN201510540984.7A 2015-08-28 2015-08-28 A kind of bell of heating furnace Active CN105091597B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510540984.7A CN105091597B (en) 2015-08-28 2015-08-28 A kind of bell of heating furnace

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510540984.7A CN105091597B (en) 2015-08-28 2015-08-28 A kind of bell of heating furnace

Publications (2)

Publication Number Publication Date
CN105091597A CN105091597A (en) 2015-11-25
CN105091597B true CN105091597B (en) 2017-10-03

Family

ID=54572566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510540984.7A Active CN105091597B (en) 2015-08-28 2015-08-28 A kind of bell of heating furnace

Country Status (1)

Country Link
CN (1) CN105091597B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106370012A (en) * 2016-11-15 2017-02-01 天津林立感应加热电炉制造有限公司 Novel rotary furnace lid

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2323969A1 (en) * 1975-09-12 1977-04-08 Dupeux M Sa Intermittently operating furnace, esp. with mobile hearth - has flues improving thermal characteristics at ends of chamber
CN202813405U (en) * 2012-08-22 2013-03-20 河北大唐国际丰润热电有限责任公司 Chimney smoke isolation device
CN203586239U (en) * 2013-12-16 2014-05-07 倪鸣 Improved structure of chimney
CN203687617U (en) * 2014-02-11 2014-07-02 金坛市六九钛业科技有限公司 High-temperature furnace with outstanding heat insulation function and furnace cover thereof
CN203908318U (en) * 2014-06-23 2014-10-29 莱芜钢铁集团有限公司 Heating furnace and composite furnace door thereof
CN205079610U (en) * 2015-08-28 2016-03-09 太仓金马金属构件有限公司 Bell of heating furnace

Also Published As

Publication number Publication date
CN105091597A (en) 2015-11-25

Similar Documents

Publication Publication Date Title
RU77940U1 (en) FURNACE FURNACE DEVICE
WO2021088709A1 (en) Anode furnace feeding device
EP3333487A2 (en) Wood-burning appliance
CN105091597B (en) A kind of bell of heating furnace
CN205079610U (en) Bell of heating furnace
CN210533021U (en) Energy-saving fuel gas zinc alloy smelting furnace
CN204880693U (en) Unload convenient energy -conserving boiler of sediment
JP2016090168A (en) Firewood stove
CN202158655U (en) Straight-seam hot blast furnace provided with smoke dust settling chamber
CN204717749U (en) A kind of movable upper lower flue biomass semi-gasification radiator
CN206469294U (en) Efficient complete combustion furnace
CN205447835U (en) Energy -efficient reborner
CN105964870B (en) A kind of forge furnace
CN211400772U (en) Improved energy-saving briquette kiln
CN206127377U (en) Old and useless printed circuit board's of resourceful treatment kiln
CN200996633Y (en) Smokeless and dustless internally-roasting water-heating stove
CN206771433U (en) A kind of civil heating stove for being easy to ash disposal
CN218001829U (en) Wall-mounted furnace smoke collecting hood
CN203810461U (en) Energy-saving burner
CN203784908U (en) Novel boiler for combustion of biomass pressing block
CN106765320A (en) A kind of flue gas recirculation is reburned formula smokeless heating furnace
CN210601626U (en) Sinking type garbage pyrolysis furnace
CN213873861U (en) Heat source supply device
CN106556038A (en) A kind of exhaust system of the dining room kitchen range top
CN209116782U (en) High temperature residual gas processing system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 215400 new Mao power station village, Chengxiang Town, Jiangsu, Taicang

Applicant after: Taicang Jinma Intelligent Equipment Co., Ltd.

Address before: 215400 Taicang, Suzhou, Chengxiang City, the new town of Mao Village

Applicant before: TAICANG GOLDENMA METAL STRUCTURE CO., LTD.

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Ma Zhigang

Inventor after: Lv Feng

Inventor after: Chen Wei

Inventor after: Qian Yi

Inventor after: Shi Dajin

Inventor before: Ma Zhigang

Inventor before: Zhan Feng

Inventor before: Chen Wei

Inventor before: Qian Yi

Inventor before: Shi Dajin

GR01 Patent grant
GR01 Patent grant