CN105040929B - Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface - Google Patents

Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface Download PDF

Info

Publication number
CN105040929B
CN105040929B CN201510575939.5A CN201510575939A CN105040929B CN 105040929 B CN105040929 B CN 105040929B CN 201510575939 A CN201510575939 A CN 201510575939A CN 105040929 B CN105040929 B CN 105040929B
Authority
CN
China
Prior art keywords
putty
wall surface
metope
batch
glue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510575939.5A
Other languages
Chinese (zh)
Other versions
CN105040929A (en
Inventor
仇毓新
王文新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Co Ltd Is Built In Suzhou Land Of Woods And Waters Design
Original Assignee
Co Ltd Is Built In Suzhou Land Of Woods And Waters Design
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Co Ltd Is Built In Suzhou Land Of Woods And Waters Design filed Critical Co Ltd Is Built In Suzhou Land Of Woods And Waters Design
Priority to CN201510575939.5A priority Critical patent/CN105040929B/en
Publication of CN105040929A publication Critical patent/CN105040929A/en
Application granted granted Critical
Publication of CN105040929B publication Critical patent/CN105040929B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)
  • Paints Or Removers (AREA)
  • Application Of Or Painting With Fluid Materials (AREA)

Abstract

The invention discloses a construction method for strengthening bottom-painting putty via glue immersion on a building pain wall surface. The construction method comprises steps of first, modularizing bottom-painting paint putty loosened after drying, then painting putty, second, grinding and flattening after wall surface putty dries, third, rolling-painting glue relapsed by water on the grinded and flattened wall surface via a wool roller cylinder and then penetrating glue into the putty painted on the wall surface for drying, fourth, conducting further grinding process for the putty strengthened due to immersed of glue and dried, and fifth, finally painting on the bottom-painted wall surface. By the use of the construction method, putty dries and solidifies, so the wall surface can be grinded and flattened; glue is immersed to strengthen the putty after grinding and flattening; a paint bottom-paint layer with high hardness is achieved at last; and paint can be easily attached to the wall surface; and problems of crack, bulge and wrapping of the paint surface layer due to looseness of the putty painted on the bottom can be effectively prevented.

Description

Batch bottom putty strike-through reinforcing construction method of building coating metope
Technical field
The present invention relates to a kind of surface-veneer engineered construction technology of interior decoration, and in particular to a kind of building coating metope batch Bottom putty strike-through reinforcing construction method.
Background technology
At present building coating metope carried out putty batch bottom operation to obtain entering for coating bottom surface before coating is done in technology One step is smooth, while be the important prerequisite for determining coating metope planarization effects, for the putty modulation at batch bottom, if modulation is greasy It is excessively loose after sub- dry solidification, though the smooth polishing for being easy to rubber is unfavorable for the stickup adhesive force of coating, it is easy to produce painting The minute crack on material surface, can ftracture if metope makes moist, play the major defects such as drum, volume skin.If the putty of modulation is done It is overly hard after dry solidification, though for coating has stronger adhesive force, increased the difficulty that rubber polishes flat, its batch of bottom Planarization effects are difficult to.
The content of the invention
It is an object of the invention to provide a kind of batch bottom putty strike-through of building coating metope strengthens construction method, putty is done It is easy to polish flat after dry solidification, and strike-through reinforcing is carried out on the basis of smooth polishing is easy to, final acquisition higher hardness Charge bottom is applied, is conducive to the attachment of coating, effectively prevented the cracking of the loose paint topcoat for causing because of batch bottom putty, rise The phenomenons such as drum, volume skin.
For achieving the above object, the technical scheme is that a kind of batch bottom putty strike-through of building coating metope of design is strong Change construction method, comprise the steps:
1)More loose painting charge bottom putty after modulation dry solidification, with batch knife by the putty batch in needing coating finish Metope, reaches substantially smooth, solidification to be dried;
2)After wall surface putty is dried, the process that polishes flat is carried out to loose wall surface putty using rubber, it is smooth to reach Require;
3)Using the water soluble adhesive that water is no longer dissolve in after drying, carry out being watered dilution, the glue after dilution will be watered Roller coating is carried out in the metope for having polished flat with hair cylinder, glue is penetrated in batch putty of upper metope, it is to be dried;
4)After the putty dry solidification of strike-through reinforcing, then further rubber grinding process is done, it is higher smooth to obtain Batch bottom metope of precision;
5)Implement coating finish in batch bottom metope.
Preferably, the water soluble adhesive that water is no longer dissolve in after the drying is white glue with vinyl.
The advantages of the present invention are:A kind of batch bottom putty strike-through reinforcing construction of building coating metope is provided Method, is easy to polish flat after putty dry solidification, and strike-through reinforcing is carried out on the basis of smooth polishing is easy to, final to obtain The painting charge bottom of higher hardness, is conducive to the attachment of coating, effectively prevents because of the loose painting charge level for causing of batch bottom putty The phenomenons such as the cracking of layer, a drum, volume skin.
Construction method of the present invention only increases strike-through technique in batch bottom polishing subitem work post of prior art, solves because applying The loose paint topcoat cracking for causing of charge bottom putty, the phenomenon for playing drum, rolling up skin, particularly metope is even more serious after making moist, batch Bottom putty is hard and is difficult to the contradiction that polishes flat, simple, practical.
Specific embodiment
With reference to embodiment, the specific embodiment of the present invention is further described.Following examples are only used for more Plus technical scheme is clearly demonstrated, and can not be limited the scope of the invention with this.
The technical scheme that the present invention is embodied as is:
A kind of batch bottom putty strike-through reinforcing construction method of building coating metope, comprises the steps:
1)Modulation painting charge bottom putty loose after being dried, with batch knife by the putty batch in the metope for needing coating finish, Reach substantially smooth, solidification to be dried;
2)After wall surface putty is dried, the process that polishes flat is carried out to loose wall surface putty using rubber, it is smooth to reach Require;
3)Using the water soluble adhesive that water is no longer dissolve in after drying, carry out being watered dilution, the glue after dilution will be watered Roller coating is carried out in the metope for having polished flat with hair cylinder, glue is penetrated in batch putty of upper metope, it is to be dried;
4)After the putty dry solidification of strike-through reinforcing, then further rubber grinding process is done, it is higher smooth to obtain Batch bottom metope of precision;
5)Implement coating finish in batch bottom metope.
The water soluble adhesive that water is no longer dissolve in after above-mentioned drying may be selected white glue with vinyl.
The above is only the preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, on the premise of without departing from the technology of the present invention principle, some improvements and modifications can also be made, these improvements and modifications Also should be regarded as protection scope of the present invention.

Claims (2)

1. batch bottom putty strike-through of building coating metope strengthens construction method, it is characterised in that comprise the steps:
1)Modulation painting charge bottom putty loose after being dried, is reached the putty batch in the metope for needing coating finish with batch knife It is substantially smooth, solidification to be dried;
2)After wall surface putty is dried, the process that polishes flat is carried out to loose wall surface putty using rubber, to reach level requirements;
3)Using the water soluble adhesive that water is no longer dissolve in after drying, carry out being watered dilution, the glue hair after dilution will be watered Cylinder carries out roller coating in the metope for having polished flat, glue is penetrated in batch putty of upper metope, to be dried;
4)After the putty dry solidification of strike-through reinforcing, then further rubber grinding process is done, to obtain higher smooth precision Batch bottom metope;
5)Implement coating finish in batch bottom metope.
2. batch bottom putty strike-through of building coating metope according to claim 1 strengthens construction method, it is characterised in that institute State be dried after be no longer dissolve in water water soluble adhesive be white glue with vinyl.
CN201510575939.5A 2015-09-11 2015-09-11 Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface Active CN105040929B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510575939.5A CN105040929B (en) 2015-09-11 2015-09-11 Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510575939.5A CN105040929B (en) 2015-09-11 2015-09-11 Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface

Publications (2)

Publication Number Publication Date
CN105040929A CN105040929A (en) 2015-11-11
CN105040929B true CN105040929B (en) 2017-05-03

Family

ID=54447871

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510575939.5A Active CN105040929B (en) 2015-09-11 2015-09-11 Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface

Country Status (1)

Country Link
CN (1) CN105040929B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09279804A (en) * 1996-04-18 1997-10-28 Takeya Kagaku Kenkyusho:Kk Trowel coating wall material and wall coating method thereof
JPH10159292A (en) * 1996-11-27 1998-06-16 Sato Kogyo Kk Structure of building wall surface using board for construction
CN1414196A (en) * 2001-10-25 2003-04-30 云南建工装饰工程有限公司 External wall magnetic surface whitewash technology
CN101363269A (en) * 2008-08-13 2009-02-11 中建五局第三建设有限公司 Construction method of plastering-free concrete structure wall putty
CN102477797A (en) * 2010-11-24 2012-05-30 五冶集团上海有限公司 Construction method for preventing crack of infilled wall
CN102704635A (en) * 2012-06-19 2012-10-03 无锡市康顺节能材料科技有限公司 Paint brushing construction method
CN102828588A (en) * 2011-12-31 2012-12-19 常熟古建园林建设集团有限公司 Method for improving construction quality of exterior wall coating

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09279804A (en) * 1996-04-18 1997-10-28 Takeya Kagaku Kenkyusho:Kk Trowel coating wall material and wall coating method thereof
JPH10159292A (en) * 1996-11-27 1998-06-16 Sato Kogyo Kk Structure of building wall surface using board for construction
CN1414196A (en) * 2001-10-25 2003-04-30 云南建工装饰工程有限公司 External wall magnetic surface whitewash technology
CN101363269A (en) * 2008-08-13 2009-02-11 中建五局第三建设有限公司 Construction method of plastering-free concrete structure wall putty
CN102477797A (en) * 2010-11-24 2012-05-30 五冶集团上海有限公司 Construction method for preventing crack of infilled wall
CN102828588A (en) * 2011-12-31 2012-12-19 常熟古建园林建设集团有限公司 Method for improving construction quality of exterior wall coating
CN102704635A (en) * 2012-06-19 2012-10-03 无锡市康顺节能材料科技有限公司 Paint brushing construction method

Also Published As

Publication number Publication date
CN105040929A (en) 2015-11-11

Similar Documents

Publication Publication Date Title
CN103225383B (en) Manufacture method for anti-scraping and wear-resistant paint wood floor
CN103769353B (en) Transfer printing coating method for decorating plate
CN103537420B (en) Coating agent brushing and spraying process for wooden door
CN102352677A (en) Construction method for as-cast finish concrete transparent protective layer
CN102294322A (en) Method for painting paint face of piano
CN102085629A (en) Process for treating wood grain on surface of wood floor board
CN104386950A (en) Exterior wall brick-imitating elastic texture coating and application process thereof
CN104371409B (en) A kind of glaze and continuous American and European style technique modelled after an antique thereof
CN102794800A (en) Wood surface processing method
CN105040929B (en) Construction method for strengthening bottom-painting putty via glue immersion on building pain wall surface
CN104549968A (en) Mahogany furniture painting process
CN106217568B (en) A kind of woodwork does old technology
CN105499106A (en) Coating construction process for elastic UV (ultraviolet) primer for veneers
CN109944455A (en) A kind of building masonry wall method for repairing crack
CN104294596A (en) Coating finishing process
CN105772375A (en) Semi-open type UV coating and applying technology of edge sealing strip veneer elastic primer
CN102886345A (en) Paint archaized coating process for furniture
CN106602815A (en) Surface treatment method for upper cover of variable-frequency motor
CN103233571B (en) A kind of elasticity lacquer painting wood flooring manufacture method and wood flooring
CN104441151A (en) Wood plate antique finishing method
CN107511308A (en) A kind of high efficiency high-performance seal coat UV coating construction process
CN103291046A (en) Floor tile processing technology
CN205134855U (en) Wall brick laminating structure
CN202039535U (en) Composite floor sheet
CN108571145A (en) A kind of interior colour ground curing agent construction technology

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant