CN105040829B - 一种预制混凝土主次梁连接结构及其施工方法 - Google Patents

一种预制混凝土主次梁连接结构及其施工方法 Download PDF

Info

Publication number
CN105040829B
CN105040829B CN201510359892.9A CN201510359892A CN105040829B CN 105040829 B CN105040829 B CN 105040829B CN 201510359892 A CN201510359892 A CN 201510359892A CN 105040829 B CN105040829 B CN 105040829B
Authority
CN
China
Prior art keywords
main beam
precast main
secondary beam
prefabricated
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510359892.9A
Other languages
English (en)
Other versions
CN105040829A (zh
Inventor
吴敦军
王流金
刘亮
许小俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Yangtze River Urban Architectural Design Co Ltd
Original Assignee
Nanjing Yangtze River Urban Architectural Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Yangtze River Urban Architectural Design Co Ltd filed Critical Nanjing Yangtze River Urban Architectural Design Co Ltd
Priority to CN201510359892.9A priority Critical patent/CN105040829B/zh
Publication of CN105040829A publication Critical patent/CN105040829A/zh
Application granted granted Critical
Publication of CN105040829B publication Critical patent/CN105040829B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Rod-Shaped Construction Members (AREA)

Abstract

本发明公开了一种预制混凝土主次梁连接结构及其施工方法,包括预制主梁和预制次梁,预制主梁上设置后浇段,且预制主梁的主梁底部受力钢筋在后浇段贯通连续,预制主梁的后浇段内预留主梁箍筋,预制次梁伸入预制主梁的后浇段内,预制次梁的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁上,预制主梁上部的叠合层内铺设通长受力钢筋,通长受力钢筋穿过预制次梁上部,支模浇筑形成后浇段。与现有技术相比,本发明的有益效果是:通过改进预制主梁和预制次梁的连接方式,方便预制构件的吊装及连接,使预制主梁和预制次梁连接性能达到等同于现浇结构的效果,节点连接牢靠,无需水平套筒灌浆连接,节省材料,降低造价,施工简单快捷。

Description

一种预制混凝土主次梁连接结构及其施工方法
技术领域
本发明属于土木工程领域,涉及一种预制混凝土主次梁连接结构及其施工方法。
背景技术
预制装配整体式框架结构的关键是如何将在工厂制作的预制构件现场吊装后有效地连接形成一个整体结构体系。连接节点区域构件的安装难易程度与混凝土浇筑质量会直接影响工程的施工进度与质量。因此,在保证结构安全的前提下,寻求尽可能简便的预制装配整体式框架节点连接方法,是目前工程界亟需解决的问题。
预制混凝土主次梁连接可采用灌浆套筒水平连接受力钢筋等连接方式。但采用上述连接方式,造价高,施工麻烦。
发明内容
本发明需要解决的上述问题是针对上述现有技术中采用灌浆套筒水平连接受力钢筋等连接方式,造价高,施工麻烦的不足,而提供一种降低造价,施工简单快捷的预制混凝土主次梁连接结构及其施工方法。
为解决上述技术问题,本发明采用的技术方案是:
一种预制混凝土主次梁连接结构,包括预制主梁和预制次梁,预制主梁上搭接预制次梁处设置后浇段,且预制主梁的主梁底部受力钢筋在后浇段贯通连续,预制主梁的后浇段内预留主梁箍筋,预制次梁伸入预制主梁的后浇段内,预制次梁的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁上,且锚固长度大于等于12d,预制主梁及预制次梁上部的叠合层内铺设通长受力钢筋,通长受力钢筋穿过预制次梁上部,需要绑扎的钢筋进行绑扎处理,支模浇筑形成后浇段。
预制次梁伸入预制主梁的后浇段内的长度大于等于10mm。
预制主梁的一侧或两侧分别搭接预制次梁,两预制次梁的次梁底部纵筋采用高度上下错开锚固的方式分别与预制主梁锚固。
预制主梁、预制次梁端部分别设置抗剪凹槽。
后浇段的两端分别伸出主梁腰筋,增设等直径的附加腰筋分别与两根主梁腰筋焊接连接。
预制混凝土主次梁连接结构的施工方法,包括以下步骤:
(1)、制造预制主梁和预制次梁,预制主梁上搭接预制次梁处设置后浇段,且预制主梁的主梁底部受力钢筋在后浇段贯通连续,预制主梁的后浇段内预留主梁箍筋;
(2)、吊装预制主梁和预制次梁,将预制次梁伸入预制主梁的后浇段内,预制次梁的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁上,且锚固长度大于等于12d;
(3)、预制主梁及预制次梁上部的叠合层内铺设通长受力钢筋,通长受力钢筋穿过预制次梁上部;
(4)、支模板,在预制主梁的侧边、预制次梁的侧边及预制主梁的底部设置模板;
(5)、对需要绑扎的钢筋进行绑扎处理;
(6)、浇筑后浇段;使预制主梁和预制次梁形成整体。
与现有技术相比,本发明的有益效果是:通过改进预制主梁和预制次梁的连接方式,方便预制构件的吊装及连接,使预制主梁和预制次梁连接性能达到等同于现浇结构的效果,节点连接牢靠,无需水平套筒灌浆连接,节省材料,降低造价,施工简单快捷。
附图说明
图1是本发明的预制混凝土主次梁连接结构的俯视图;
图2是预制混凝土主次梁连接结构的A-A剖视图;
图3是预制混凝土主次梁连接结构的B-B剖视图。
其中,1、预制主梁,2、预制次梁,3、后浇段,4、叠合层,5、主梁箍筋,6、通长受力钢筋,7、抗剪凹槽,8、主梁腰筋,9、附加腰筋。
具体实施方式
现在结合附图对本发明作进一步详细的说明。这些附图均为简化的示意图,仅以示意方式说明本发明的基本结构,因此其仅显示与本发明有关的构成。
如图1所示,一种预制混凝土主次梁连接结构,包括预制主梁1和预制次梁2,预制主梁1上搭接预制次梁2处设置后浇段3,且预制主梁1的主梁底部受力钢筋在后浇段3贯通连续,预制主梁1的后浇段3内预留主梁箍筋5,预制次梁2伸入预制主梁1的后浇段3内,预制次梁2的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁1上,且锚固长度大于等于12d,预制主梁1及预制次梁2上部的叠合层4内铺设通长受力钢筋6,通长受力钢筋6穿过预制次梁2上部,需要绑扎的钢筋进行绑扎处理,支模浇筑形成后浇段3。
预制次梁2伸入预制主梁1的后浇段3内的长度大于等于10mm。
预制主梁1的一侧或两侧分别搭接预制次梁2,两预制次梁2的次梁底部纵筋采用高度上下错开锚固的方式分别与预制主梁1锚固。
预制主梁1、预制次梁2端部分别设置抗剪凹槽7。
后浇段3的两端分别伸出主梁腰筋8,增设等直径的附加腰筋9分别与两根主梁腰筋8焊接连接。
预制混凝土主次梁连接结构的施工方法,包括以下步骤:
(1)、制造预制主梁1和预制次梁2,预制主梁1上搭接预制次梁2处设置后浇段3,且预制主梁1的主梁底部受力钢筋在后浇段3贯通连续,预制主梁1的后浇段3内预留主梁箍筋5;
(2)、吊装预制主梁1和预制次梁2,将预制次梁2伸入预制主梁1的后浇段3内,预制次梁2的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁1上,且锚固长度大于等于12d;
(3)、预制主梁1及预制次梁2上部的叠合层4内铺设通长受力钢筋6,通长受力钢筋6穿过预制次梁2上部;
(4)、支模板,在预制主梁1的侧边、预制次梁2的侧边及预制主梁1的底部设置模板;
(5)、对需要绑扎的钢筋进行绑扎处理;
(6)、浇筑后浇段3,使预制主梁1和预制次梁2形成整体。
与现有技术相比,本发明的有益效果是:通过改进预制主梁和预制次梁的连接方式,方便预制构件的吊装及连接,使预制主梁和预制次梁连接性能达到等同于现浇结构的效果,节点连接牢靠,无需水平套筒灌浆连接,节省材料,降低造价,施工简单快捷。
以上对本发明的较佳实施例进行了描述。需要理解的是,本发明并不局限于上述特定实施方式,其中未尽详细描述的设备和结构应该理解为用本领域中的普通方式予以实施;任何熟悉本领域的技术人员,在不脱离本发明技术方案范围情况下,都可利用上述揭示的方法和技术内容对本发明技术方案作出许多可能的变动和修饰,或修改为等同变化的等效实施例,这并不影响本发明的实质内容。因此,凡是未脱离本发明技术方案的内容,依据本发明的技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均仍属于本发明技术方案保护的范围内。

Claims (1)

1.一种预制混凝土主次梁连接结构,包括预制主梁和预制次梁,其特征在于:预制主梁上搭接预制次梁处设置后浇段,且预制主梁的主梁底部受力钢筋在后浇段贯通连续,预制主梁的后浇段内预留主梁箍筋,预制次梁伸入预制主梁的后浇段内,预制次梁的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁上,且锚固长度大于等于12d,预制主梁及预制次梁上部的叠合层内铺设通长受力钢筋,通长受力钢筋穿过预制次梁上部,需要绑扎的钢筋进行绑扎处理,支模浇筑形成后浇段;预制次梁伸入预制主梁的后浇段内的长度大于等于10mm;预制主梁的一侧或两侧分别搭接预制次梁,两预制次梁的次梁底部纵筋采用高度上下错开锚固的方式分别与预制主梁锚固;预制主梁、预制次梁端部分别设置抗剪凹槽;后浇段的两端分别伸出主梁腰筋,增设等直径的附加腰筋分别与两根主梁腰筋焊接连接;
预制混凝土主次梁连接结构的施工方法,包括以下步骤:
(1)、制造预制主梁和预制次梁,预制主梁上搭接预制次梁处设置后浇段,且预制主梁的主梁底部受力钢筋在后浇段贯通连续,预制主梁的后浇段内预留主梁箍筋;
(2)、吊装预制主梁和预制次梁,将预制次梁伸入预制主梁的后浇段内,预制次梁的次梁底部纵筋直接锚固或通过附加钢筋锚固于预制主梁上,且锚固长度大于等于12d;
(3)、预制主梁及预制次梁上部的叠合层内铺设通长受力钢筋,通长受力钢筋穿过预制次梁上部;
(4)、支模板,在预制主梁的侧边、预制次梁的侧边及预制主梁的底部设置模板;
(5)、对需要绑扎的钢筋进行绑扎处理;
(6)、浇筑后浇段;使预制主梁和预制次梁形成整体。
CN201510359892.9A 2015-06-26 2015-06-26 一种预制混凝土主次梁连接结构及其施工方法 Active CN105040829B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510359892.9A CN105040829B (zh) 2015-06-26 2015-06-26 一种预制混凝土主次梁连接结构及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510359892.9A CN105040829B (zh) 2015-06-26 2015-06-26 一种预制混凝土主次梁连接结构及其施工方法

Publications (2)

Publication Number Publication Date
CN105040829A CN105040829A (zh) 2015-11-11
CN105040829B true CN105040829B (zh) 2017-11-03

Family

ID=54447771

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510359892.9A Active CN105040829B (zh) 2015-06-26 2015-06-26 一种预制混凝土主次梁连接结构及其施工方法

Country Status (1)

Country Link
CN (1) CN105040829B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111005446A (zh) * 2019-12-23 2020-04-14 三一筑工科技有限公司 预制柱节点连接结构及施工方法

Families Citing this family (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105297893B (zh) * 2015-12-02 2017-09-19 上海欧本钢结构有限公司 榫卯式混凝土叠合梁交叉连接结构及其施工方法
CN105297892B (zh) * 2015-12-02 2017-09-19 上海欧本钢结构有限公司 一种设有张拉钢筋的混凝土梁交叉连接结构的施工方法
CN105926820B (zh) * 2016-05-03 2020-06-26 台州远信建设工程有限公司 一种预制梁钢承板电阻网片组合楼面的施工工法
CN109098279A (zh) * 2018-09-28 2018-12-28 福州大学 装配式预制主梁与次梁的连接构造及施工方法
CN109680807A (zh) * 2019-01-25 2019-04-26 华汇工程设计集团股份有限公司 先张法预制叠合梁钢绞线在梁柱节点的锚固结构及方法
CN110130487B (zh) * 2019-05-24 2024-01-16 广东中建新型建筑构件有限公司 一种预制主次梁连接节点及连接方法
CN110331817A (zh) * 2019-07-11 2019-10-15 江西建工第二建筑有限责任公司 一种装配式组合梁次梁构造
CN110512730B (zh) * 2019-08-07 2022-08-12 泰州职业技术学院 一种装配式混凝土主次梁连接结构
CN110439180A (zh) * 2019-08-20 2019-11-12 长沙远大住宅工业安徽有限公司 一种交叉梁及施工方法
CN110725399A (zh) * 2019-10-15 2020-01-24 广州瀚阳工程咨询有限公司 一种装配式建筑纵横梁连接节点的实施方法
CN112411746A (zh) * 2020-11-27 2021-02-26 湖南建工五建建筑工业化有限公司 一种主次梁十字搭接连接结构及其连接方法
CN114541576B (zh) * 2022-02-16 2024-07-02 浙江大学建筑设计研究院有限公司 装配式钢筋混凝土主梁与次梁的连接结构及施工方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073448A (ja) * 1998-08-28 2000-03-07 Dai Nippon Construction プレキャストコンクリート梁と柱の接合方法および接合構造
CN2637592Y (zh) * 2003-09-04 2004-09-01 张英保 建筑外墙墙板与现浇混凝土楼板的连接结构
CN101660327A (zh) * 2008-08-29 2010-03-03 万科企业股份有限公司 预制混凝土次梁与主梁的连接结构、施工方法及建筑
CN102587554A (zh) * 2012-02-29 2012-07-18 黑龙江宇辉新型建筑材料有限公司 跨度内应用钢筋180°弯锚连接的混凝土叠合板及连接方法
CN102677784A (zh) * 2012-05-21 2012-09-19 天津大学 一种预制混凝土管柱钢筋混凝土梁节点结构及其施工方法
CN204098221U (zh) * 2014-07-28 2015-01-14 南京长江都市建筑设计股份有限公司 一种包含t型抗剪钢板的预制主次梁连接节点
CN204728484U (zh) * 2015-06-26 2015-10-28 南京长江都市建筑设计股份有限公司 一种预制混凝土主次梁连接结构

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000073448A (ja) * 1998-08-28 2000-03-07 Dai Nippon Construction プレキャストコンクリート梁と柱の接合方法および接合構造
CN2637592Y (zh) * 2003-09-04 2004-09-01 张英保 建筑外墙墙板与现浇混凝土楼板的连接结构
CN101660327A (zh) * 2008-08-29 2010-03-03 万科企业股份有限公司 预制混凝土次梁与主梁的连接结构、施工方法及建筑
CN102587554A (zh) * 2012-02-29 2012-07-18 黑龙江宇辉新型建筑材料有限公司 跨度内应用钢筋180°弯锚连接的混凝土叠合板及连接方法
CN102677784A (zh) * 2012-05-21 2012-09-19 天津大学 一种预制混凝土管柱钢筋混凝土梁节点结构及其施工方法
CN204098221U (zh) * 2014-07-28 2015-01-14 南京长江都市建筑设计股份有限公司 一种包含t型抗剪钢板的预制主次梁连接节点
CN204728484U (zh) * 2015-06-26 2015-10-28 南京长江都市建筑设计股份有限公司 一种预制混凝土主次梁连接结构

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111005446A (zh) * 2019-12-23 2020-04-14 三一筑工科技有限公司 预制柱节点连接结构及施工方法

Also Published As

Publication number Publication date
CN105040829A (zh) 2015-11-11

Similar Documents

Publication Publication Date Title
CN105040829B (zh) 一种预制混凝土主次梁连接结构及其施工方法
CN105735464B (zh) 一种装配式组合结构及其安装方法
CN106013172B (zh) 双排桩与斜撑组合软土深基坑支护结构及施工方法
CN105863111B (zh) 内嵌预制混凝土剪力墙同时抗弯的钢框架构造
KR100958014B1 (ko) 강합성 거더교 시공방법
CN104775545B (zh) 装配式混凝土框架-剪力墙拆分构件的连接方法
CN208280325U (zh) 建筑结构的预制装配式主次梁连接节点
CN104563305B (zh) 一种混凝土叠合梁与钢管混凝土柱连接节点及施工方法
CN106555453A (zh) 一种预应力预制叠合空心板及其施工方法
CN208486364U (zh) 框架结构体系
CN107090908B (zh) 一种竖向预制构件节点连接方法
CN107245953B (zh) 一种多层桥梁结构的交叉施工方法
CN107130715A (zh) 一种后浇齿槽连接装配式楼屋盖的施工方法
CN108532445A (zh) 一种预制盖梁与预制墩柱的连接构造及其施工方法
CN106223183A (zh) 装配式矩形钢管混凝土组合桁梁桥及施工方法
CN107130716A (zh) 后浇齿槽连接装配式楼屋盖
CN108660912A (zh) 预制桥墩、轨道支撑组件及其制造安装方法
CN106012851A (zh) 钢箱梁与混凝土墩柱同步施工方法
CN107806101A (zh) 条形基坑现浇混凝土对撑预制连系梁的施工方法
CN106436732A (zh) 一种条形基础置换成筏板基础的加固方法及加固结构
CN209653108U (zh) 预制钢筋混凝土柱连接结构
CN108301425A (zh) 预制快装型格构梁体系及其施工方法
CN205531016U (zh) 一种预制混凝土柱构件及连接节点
CN107246109A (zh) 实复式钢管混凝土组合柱组合梁构成的框架及其施工方法
CN206769150U (zh) 后浇齿槽连接装配式楼屋盖

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant