CN105024295A CN201510407658.9A CN201510407658A CN105024295A CN 105024295 A CN105024295 A CN 105024295A CN 201510407658 A CN201510407658 A CN 201510407658A CN 105024295 A CN105024295 A CN 105024295A
Authority
CN
China
Prior art keywords
equipment
electric equipment
topological
listing
remote control
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510407658.9A
Other languages
Chinese (zh)
Other versions
CN105024295B (en
Inventor
王巍巍
朱岩
陈琦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing SAC Automation Co Ltd
Original Assignee
Nanjing SAC Automation Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing SAC Automation Co Ltd filed Critical Nanjing SAC Automation Co Ltd
Priority to CN201510407658.9A priority Critical patent/CN105024295B/en
Publication of CN105024295A publication Critical patent/CN105024295A/en
Application granted granted Critical
Publication of CN105024295B publication Critical patent/CN105024295B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)

Abstract

The invention discloses a topology analysis-based intelligent transformer station tag hanging method, and includes: according to an acquired result of topology analysis, whether equipment is electrified is detected; if not, whether electrical equipment associated with the electrical equipment is electrified is detected; if a user chooses to hang a tag or a detection result of the electrical equipment associated with the electrical equipment is non-electrified, the user chooses a hang tag; after tag hanging is successful, remote control operation of the electrical equipment is performed if needed; whether a tag is hung on the equipment is judged, if no, whether after the remote control operation of the equipment, a topology analysis result of the equipment with a hang tag is influenced is judged and detected; if the topology analysis result of the equipment with the hang tag is influenced, the user insists remote control, or if the topology analysis result is not influenced, the user performs remote control; and after remote control is finished, topology analysis and calculation are performed again. According to the topology analysis-based intelligent transformer station tag hanging method, a plurality of operation interface prompts are provided, thereby reducing misoperation, other operation problems which are likely to influence the topology analysis result of the equipment with the hang tag are also considered, thereby preventing personal injury, and the method has good application prospects.

Description

Intelligent substation based on topological analysis is listed method
Technical field
The present invention relates to intelligent substation technical field, be specifically related to a kind of intelligent substation based on topological analysis and list method.
Background technology
At present, State Grid Corporation of China clearly proposes to build " has informationization, automation, interactive intelligent grid ", plan builds up unified intelligent grid to the year two thousand twenty comprehensively, intelligent substation is the critical facility of intelligent grid, a large amount of electric equipments is installed in it, electric equipment needs when overhauling to list to point out, to prevent maintainer's misoperation, equally, also to list to corresponding electric equipment in supervisory control system, overhauling to point out this electric equipment of operations staff or having people to carry out work at this equipment interval, prevent operation from bringing danger to maintainer.
In order to the electrically equipment of the electric equipment and operation of distinguishing maintenance, can list to repair apparatus, arbitrarily can not operate this equipment to point out maintainer's misoperation or operations staff, to confirm just can operate under safe and punctual prerequisite, so to needing the electric equipment of maintenance to list, forbid seeming particularly important to operate, because the electric equipment in intelligent substation is numerous, the processing mode of listing of existing intelligent substation is just pointed out on runnable interface, without any the safeguard measure preventing misoperation, if operations staff puts wrong equipment because of carelessness, there is unpredictable risk, and there is no the operational issue considering the electric equipment be associated with the electric equipment of listing.
Summary of the invention
The processing mode of listing that the object of the invention is to overcome existing intelligent substation is just pointed out on runnable interface, without any the safeguard measure preventing misoperation, does not also consider the problem of the electrical equipment operation be associated with the electric equipment of listing.
In order to achieve the above object, the technical solution adopted in the present invention is:
Intelligent substation based on topological analysis is listed a method, it is characterized in that: comprise the following steps,
Step (1), according to topological analysis, obtains the electriferous state of each electric equipment in intelligent substation, when carrying out listing operation to the electric equipment in intelligent substation, according to the result obtaining topological analysis, whether chargedly detects this equipment;
Step (2), if testing result is charged, then runnable interface provides the prompting that charging equipment does not allow to list, end of listing; If testing result is not charged, then whether chargedly detects the electric equipment associated with this electric equipment, and perform step (3);
Step (3), if the electric equipment testing result associated with this electric equipment is charged, then runnable interface provides the charged prompting whether confirming to list in electric equipment one end, if user selects not list, then end of listing; If user selects the electric equipment testing result listed or associate with this electric equipment for not charged, then runnable interface ejects window of listing, and selects board type to list for user;
Step (4), needs the electric equipment of listing to list successfully, if desired carries out straighforward operation to electric equipment each in intelligent substation, perform step (5);
Step (5), when carrying out straighforward operation to electric equipment each in intelligent substation, judges whether this equipment lists, if this equipment is listed, then runnable interface provide that equipment lists can not the prompting of remote control; If this equipment is not listed, then, after judging to detect the operation of this equipment remote-control, whether affect the topological analysis result of the equipment of listing;
Step (6), the topological analysis result of equipment if impact is listed, then runnable interface prompting user, and allow user be confirmed whether to carry out straighforward operation, if user selects not carry out remote control, then remote control terminates; If user selects to carry out remote control, then perform step (7); If do not affect the topological analysis result of the equipment of listing, then runnable interface prompting user carries out remote control;
Step (7), after remote control terminates, re-starting topological analysis and calculates, and return step (1), analyzing needing the electric equipment of listing operation in next intelligent substation.
The aforesaid intelligent substation based on topological analysis is listed method, it is characterized in that: step (1), according to topological analysis, obtains the electriferous state of each electric equipment in intelligent substation, comprises the following steps,
(101), after completing configuration state drafting primary connection circuit figure, carry out topology inspection, check establishment connected node storehouse correctly, and create topological analysis object, complete the foundation of configuration state topological relation;
(102), according to deciliter state of real-time state switch, disconnecting link, generating topological island, being combined into a topological island by there being the electric equipment of annexation;
(103), if having power supply in topological island, then in topological island, all electric equipments are charged; Otherwise all electric equipments are not charged in topological island.
The invention has the beneficial effects as follows: the intelligent substation based on topological analysis of the present invention is listed method, to list mode relative to traditional electric equipment, have the following advantages,
(1) listing of existing transformer station is just pointed out on runnable interface, without any the measure preventing misoperation, if operations staff puts wrong equipment because of carelessness, there is no precautionary measures, the present invention is based on topological analysis, obtain the electriferous state of electric equipment, and be provided with the prompting of multiple runnable interface, guarantee that operations staff can not carry out misoperation;
(2) the present invention not only considers the operational issue of the equipment of listing, and also contemplates the operational issue that other may affect the equipment of equipment topological analysis result of listing;
(3) operating accuracy of raising operations staff of the present invention, reduces misoperation, prevents personal injury.
Accompanying drawing explanation
Fig. 1 is that the intelligent substation based on topological analysis of the present invention is listed the flow chart of method.
Embodiment
Below in conjunction with Figure of description, the present invention is further illustrated.
Intelligent substation based on topological analysis of the present invention is listed method, based on topological analysis, obtains the electriferous state of electric equipment, be provided with the prompting of multiple runnable interface, guarantee that operations staff can not carry out misoperation, not only consider the operational issue of the equipment of listing, also contemplate the operational issue that other may affect the equipment of equipment topological analysis result of listing, improve the operating accuracy of operations staff, reduce misoperation, prevent personal injury, as shown in Figure 1, specifically comprise the following steps
Step (1), according to topological analysis, obtain the electriferous state of each electric equipment in intelligent substation, when carrying out listing operation to the electric equipment in intelligent substation, according to the result obtaining topological analysis, whether chargedly detect this equipment, obtain the electriferous state of each electric equipment in intelligent substation, detailed process is
(101), after completing configuration state drafting primary connection circuit figure, carry out topology inspection, check establishment connected node storehouse correctly, and create topological analysis object, complete the foundation of configuration state topological relation;
(102), according to deciliter state of real-time state switch, disconnecting link, generating topological island, being combined into a topological island by there being the electric equipment of annexation;
(103), if having power supply in topological island, then in topological island, all electric equipments are charged; Otherwise all electric equipments are not charged in topological island;
Step (2), if testing result is charged, then runnable interface provides the prompting that charging equipment does not allow to list, end of listing; If testing result is not charged, then whether chargedly detects the electric equipment associated with this electric equipment, and perform step (3);
Step (3), if the electric equipment testing result associated with this electric equipment is charged, then runnable interface provides the charged prompting whether confirming to list in electric equipment one end, if user selects not list, then end of listing; If user selects the electric equipment testing result listed or associate with this electric equipment for not charged, then runnable interface ejects window of listing, and selects board type to list for user;
Step (4), needs the electric equipment of listing to list successfully, if desired carries out straighforward operation to electric equipment each in intelligent substation, perform step (5);
Step (5), when carrying out straighforward operation to electric equipment each in intelligent substation, judges whether this equipment lists, if this equipment is listed, then runnable interface provide that equipment lists can not the prompting of remote control; If this equipment is not listed, then, after judging to detect the operation of this equipment remote-control, whether affect the topological analysis result of the equipment of listing;
Step (6), the topological analysis result of equipment if impact is listed, then runnable interface prompting user, and allow user be confirmed whether to carry out straighforward operation, if user selects not carry out remote control, then remote control terminates; If user selects to carry out remote control, then perform step (7); If do not affect the topological analysis result of the equipment of listing, then runnable interface prompting user carries out remote control;
Step (7), after remote control terminates, re-starting topological analysis and calculates, and return step (1), analyzing needing the electric equipment of listing operation in next intelligent substation.
Intelligent substation based on topological analysis of the present invention is listed method specific embodiment, when certain electric equipment of intelligent substation overhauls, first electric equipment can take safety prevention measure on the spot, place as the Sign Board such as " in this work ", " equipment live; quiescing ", " forbidding charged combined floodgate ", " overhaul of the equipments ", remind the running status of each equipment of operations staff, prevent operations staff from carrying out misoperation.Meanwhile, the picture of supervisory control system also to carry out corresponding listing operation, list on the equipment side of correspondence, to point out operations staff to have equipment in maintenance, can not arbitrarily operate; When listing to this electric equipment, be that first whether judgment device is charged, if charged, then forbids listing according to the result based on topological analysis; If not charged, judge that whether the equipment be associated with this equipment is charged further, then determine to list to equipment.
After this electric equipment is listed, if operations staff clicks the equipment of listing because of carelessness, supervisory control system can provide prompting, forbid that operations staff is to operate of listing, further, if the equipment that operations staff clicks is not listed, then can judge whether the state of this equipment can affect the electric equipment of having listed after changing based on topological analysis, if do not affect the electric equipment of having listed, then can operate; If affect the equipment of having listed, then provide prompting, determine whether proceed operation, substantially increase security performance by operations staff, reduce misoperation, prevent personal injury, have a good application prospect.
More than show and describe general principle of the present invention and principal character and advantage of the present invention.The technical staff of the industry should understand; the present invention is not restricted to the described embodiments; what describe in above-described embodiment and specification just illustrates principle of the present invention; without departing from the spirit and scope of the present invention; the present invention also has various changes and modifications, and these changes and improvements all fall in the claimed scope of the invention.Application claims protection range is defined by appending claims and equivalent thereof.

Claims (2)

1. to list method based on the intelligent substation of topological analysis, it is characterized in that: comprise the following steps,
Step (1), according to topological analysis, obtains the electriferous state of each electric equipment in intelligent substation, when carrying out listing operation to the electric equipment in intelligent substation, according to the result obtaining topological analysis, whether chargedly detects this equipment;
Step (2), if testing result is charged, then runnable interface provides the prompting that charging equipment does not allow to list, end of listing; If testing result is not charged, then whether chargedly detects the electric equipment associated with this electric equipment, and perform step (3);
Step (3), if the electric equipment testing result associated with this electric equipment is charged, then runnable interface provides the charged prompting whether confirming to list in electric equipment one end, if user selects not list, then end of listing; If user selects the electric equipment testing result listed or associate with this electric equipment for not charged, then runnable interface ejects window of listing, and selects board type to list for user;
Step (4), needs the electric equipment of listing to list successfully, if desired carries out straighforward operation to electric equipment each in intelligent substation, perform step (5);
Step (5), when carrying out straighforward operation to electric equipment each in intelligent substation, judges whether this equipment lists, if this equipment is listed, then runnable interface provide that equipment lists can not the prompting of remote control; If this equipment is not listed, then, after judging to detect the operation of this equipment remote-control, whether affect the topological analysis result of the equipment of listing;
Step (6), the topological analysis result of equipment if impact is listed, then runnable interface prompting user, and allow user be confirmed whether to carry out straighforward operation, if user selects not carry out remote control, then remote control terminates; If user selects to carry out remote control, then perform step (7); If do not affect the topological analysis result of the equipment of listing, then runnable interface prompting user carries out remote control;
Step (7), after remote control terminates, re-starting topological analysis and calculates, and return step (1), analyzing needing the electric equipment of listing operation in next intelligent substation.
2. the intelligent substation based on topological analysis according to claim 1 is listed method, it is characterized in that: step (1), according to topological analysis, obtains the electriferous state of each electric equipment in intelligent substation, comprises the following steps,
(101), after completing configuration state drafting primary connection circuit figure, carry out topology inspection, check establishment connected node storehouse correctly, and create topological analysis object, complete the foundation of configuration state topological relation;
(102), according to deciliter state of real-time state switch, disconnecting link, generating topological island, being combined into a topological island by there being the electric equipment of annexation;
(103), if having power supply in topological island, then in topological island, all electric equipments are charged; Otherwise all electric equipments are not charged in topological island.
CN201510407658.9A 2015-07-13 2015-07-13 Intelligent substation based on topological analysis is listed method Active CN105024295B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510407658.9A CN105024295B (en) 2015-07-13 2015-07-13 Intelligent substation based on topological analysis is listed method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510407658.9A CN105024295B (en) 2015-07-13 2015-07-13 Intelligent substation based on topological analysis is listed method

Publications (2)

Publication Number Publication Date
CN105024295A true CN105024295A (en) 2015-11-04
CN105024295B CN105024295B (en) 2017-06-23

Family

ID=54414085

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510407658.9A Active CN105024295B (en) 2015-07-13 2015-07-13 Intelligent substation based on topological analysis is listed method

Country Status (1)

Country Link
CN (1) CN105024295B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108490814A (en) * 2018-04-27 2018-09-04 国网山东省电力公司聊城供电公司 A kind of five anti-method of calibration of substation based on back brake principle

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1929241A (en) * 2006-09-18 2007-03-14 中国南方电网有限责任公司超高压输电公司 Zone control network topology five-preventing system for 500KV converting station
CN101819823A (en) * 2009-02-27 2010-09-01 中广核工程有限公司 Electronic hang tag system of nuclear power plant
CN102447305A (en) * 2010-10-11 2012-05-09 国电南瑞科技股份有限公司 Topological anti-misoperation system for power grid
CN102508059A (en) * 2011-10-18 2012-06-20 北京科东电力控制系统有限责任公司 Topology error-preventing checking method based on intelligent identification of state of equipment
WO2015047641A1 (en) * 2013-09-25 2015-04-02 Abb Technology Ag Methods, systems, and computer readable media for topology control and switching loads or sources between phases of a multi-phase power distribution system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1929241A (en) * 2006-09-18 2007-03-14 中国南方电网有限责任公司超高压输电公司 Zone control network topology five-preventing system for 500KV converting station
CN101819823A (en) * 2009-02-27 2010-09-01 中广核工程有限公司 Electronic hang tag system of nuclear power plant
CN102447305A (en) * 2010-10-11 2012-05-09 国电南瑞科技股份有限公司 Topological anti-misoperation system for power grid
CN102508059A (en) * 2011-10-18 2012-06-20 北京科东电力控制系统有限责任公司 Topology error-preventing checking method based on intelligent identification of state of equipment
WO2015047641A1 (en) * 2013-09-25 2015-04-02 Abb Technology Ag Methods, systems, and computer readable media for topology control and switching loads or sources between phases of a multi-phase power distribution system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
蒋宏图,袁岳,程伟: "智能变电站站控层在线防误的设计与实现", 《电力自动化设备》 *
陈光德: "配电网GIS中电网运行状态获取技术的研究与实现", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108490814A (en) * 2018-04-27 2018-09-04 国网山东省电力公司聊城供电公司 A kind of five anti-method of calibration of substation based on back brake principle
CN108490814B (en) * 2018-04-27 2020-06-23 国网山东省电力公司聊城供电公司 Switching principle-based transformer substation five-prevention verification method

Also Published As

Publication number Publication date
CN105024295B (en) 2017-06-23

Similar Documents

Publication Publication Date Title
CN103954883B (en) A kind of Secondary Connections of PTs inspection method and device
CN101789596B (en) Automatic detection method of power grid failure
CN105069697A (en) Intelligent transformer station maintenance strategy automatic identification system and method
CN103545786A (en) Leakage current protecting device
CN105514926A (en) Method for recovering power supply after stripping started by direct-current ground protection
CN105049282A (en) Intelligent relay protection device control overhauling method based on on-line monitoring information
CN104635712A (en) Safety guarantee method for full-automatic fault treatment of power distribution network
CN101609972A (en) Be used to guarantee the system and the control method of operating personnel's personal safety and proper operation
CN102723776A (en) Virtual debugging system with transformer substation protection measurement and control device
CN103969525B (en) A kind of power equipment networking quality flexible detection system and method
CN105024295A (en) Topology analysis-based intelligent transformer station tag hanging method
CN104977452A (en) Failure protection mutual inductor tail current detection method
CN105449857B (en) The anti-electric gas-tight lock system of ground control and method
CN203643557U (en) High-voltage insulation safety test system of insulating gloves and insulating boots
CN206292365U (en) Relay protection operation case actuating of relay characteristic tester and its automatic wire-changing device
CN103105843B (en) A kind of anti-error check module for supervisory system
CN111029914B (en) Active first-aid repair system based on ubiquitous Internet of things construction
CN204180088U (en) Current conversion station DC control and protection system CAN detection system
CN204789872U (en) Distribution system trouble on -line monitoring system
CN104614627A (en) Portable DC leakage detection positioning device and detection positioning method
CN203865752U (en) Elevator car roof water inlet automatic protection system
CN103412238A (en) Self-adaptive small current grounding line selection method
CN104280632B (en) Automatic detecting and early warning method for relay protection device and fault recorder
CN104348153B (en) Area power grid master-failure automatically turns power supply control and performs method
CN202880606U (en) Elevator dragging steel wire rope strand-breakage monitoring device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant