CN104993419B - Transmission line of electricity payingoff construction guide rope point rope technique - Google Patents
Transmission line of electricity payingoff construction guide rope point rope technique Download PDFInfo
- Publication number
- CN104993419B CN104993419B CN201510304100.8A CN201510304100A CN104993419B CN 104993419 B CN104993419 B CN 104993419B CN 201510304100 A CN201510304100 A CN 201510304100A CN 104993419 B CN104993419 B CN 104993419B
- Authority
- CN
- China
- Prior art keywords
- traction
- block
- rope
- construction
- pay
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
- Electric Cable Installation (AREA)
Abstract
本发明涉及一种输电线路放线施工导引绳分绳工艺,具体施工工艺如下:⑴根据分线施工工艺布置铁塔;⑵放线滑车下降,牵引走板由原来的竖直吊装位置渐渐倾斜;⑶牵引前进,放线滑车下端挂钩开启,放线滑车与牵引走板脱离,启动牵引设备使牵引绳拉动牵引走板横向移动;⑷直到牵引走板被到达下一个铁塔位置,重复上述步骤⑴至步骤⑶,逐级铁塔进行施工,将导引绳自动分置搁放在对应的线缆安装位置。本发明输电线路放线施工导引绳分绳工艺改变了传统的放线工艺,将原先分绳是牵引绳改为轻质、耐热绝缘绳进行分绳,然后由分别替代成牵引绳进行导线牵引,减少施工对张力放线机及绞磨等设备的使用数量,简化施工步骤,降低施工成本,提升施工效率。
The present invention relates to a technique of separating guide ropes for the setting-out construction of transmission lines. The specific construction techniques are as follows: (1) Arrange iron towers according to the line-dividing construction technique; (2) The setting-out block is lowered, and the traction board is gradually inclined from the original vertical hoisting position; ⑶The traction moves forward, the hook at the lower end of the pay-off block is opened, the pay-off block is separated from the traction pallet, and the traction equipment is started to make the traction rope pull the traction pallet to move laterally; ⑷Until the traction pallet reaches the next iron tower position, repeat the above steps from ⑴ to Step ⑶, the construction is carried out step by step, and the guide ropes are automatically separated and placed in the corresponding cable installation positions. The rope separation process of the guide rope for the laying-out construction of the transmission line in the present invention changes the traditional laying-out process, and changes the original rope separation from the traction rope to a light, heat-resistant insulating rope for separation, and then replaces it with traction ropes for conducting wires. Traction reduces the number of equipment used in construction such as tension pay-off machines and winch mills, simplifies construction steps, reduces construction costs, and improves construction efficiency.
Description
技术领域technical field
本发明属于电力施工领域,涉及铁塔间高空放线技术,尤其是一种输电线路放线施工导引绳分绳工艺。The invention belongs to the field of electric power construction, and relates to high-altitude wire-laying technology between iron towers, in particular to a guide rope separation process for wire-laying construction of power transmission lines.
背景技术Background technique
目前,输电线路施工工艺为铺放式展放牵引绳,施工过程中极易受外协干扰,再进行一牵四带牵引绳,展放过程且在分绳入滑车过程中需要用到张力放线机和逐级铁塔都需2台以上绞磨进行。At present, the construction technology of transmission lines is laying and laying out traction ropes. During the construction process, it is very easy to be interfered by external cooperation. Then, one pull and four belt traction ropes are carried out. Both the wire machine and the step-by-step iron tower need more than 2 winching mills.
经过检索,发现以下相近技术领域的专利文献:After searching, the following patent documents in similar technical fields were found:
一种大截面导线“一牵二”展放施工工艺(CN102593759A),其特征在于包括以下步骤:①、施工准备:进行导线、地线的压接试验、设置张力场和牵引场场地、清理施工通道;②、悬挂滑车;③、跨越施工;④、张力放线,展放地线、导线,及时临锚;⑤、压接导线,进行紧线、观测弛度、挂线,完成整个施工。本发明保证了同相各子导线有相同的放线张力,保证了架线施工质量;而且优化了放线滑车悬挂、导线引绳和牵引绳展放、导线展放、紧线、附件安装等施工工艺,有效提高张力放线施工效率;减小了人力、时间的浪费,并且需要设备数量少,占地面积小,具有较高的社会经济性。A large cross-section wire "one pull two" construction technology (CN102593759A), characterized in that it includes the following steps: 1. Construction preparation: conduct crimping tests on wires and ground wires, set tension fields and traction fields, and clean up the construction Channel; ②, Suspension block; ③, Spanning construction; ④, Tension setting out, laying out the ground wire, wire, and anchoring in time; ⑤, Crimp wire, tighten the wire, observe the slack, hang the wire, and complete the entire construction. The invention ensures that each sub-conductor in the same phase has the same pay-off tension, and ensures the construction quality of the stringing construction; moreover, it optimizes the suspension of the pay-off block, the deployment of the wire guide rope and the traction rope, the deployment of the wire, the tightening of the wire, and the installation of accessories. The technology can effectively improve the construction efficiency of tension setting-out; reduce the waste of manpower and time, and require less equipment, occupy a small area, and have high socio-economic benefits.
一种放线张力机操控装置(CN203269220U),有控制放线张力机运作的远程操控箱,远程操控箱同时与所有放线张力机上的继电器连接,通过远程操控箱的操控系统对各放线张力机进行控制,只需一个即可同时操控多台机器,降低人员成本;同时,单人操作避免多人配合所产生的困难和麻烦。远程操控箱与放线张力机间有较远的距离,一方面可避免放线张力机旁产生的巨大噪音和大量灰尘,避免操作人员的健康受到影响;另一方面,操作人员可选择适当距离进行操控,视线不会因在放线张力机旁受到阻碍,而更便于操作人员对放线施工现场的观察和控制。A pay-off tension machine control device (CN203269220U), which has a remote control box for controlling the operation of the pay-off tension machine. Only one machine is needed to control multiple machines at the same time, reducing personnel costs; at the same time, single-person operation avoids the difficulties and troubles caused by the cooperation of multiple people. There is a long distance between the remote control box and the pay-off tension machine. On the one hand, it can avoid the huge noise and a lot of dust generated by the pay-off tension machine, and avoid the health of the operator from being affected; on the other hand, the operator can choose an appropriate distance. Controlling, the line of sight will not be hindered by the pay-off tension machine, and it is more convenient for the operator to observe and control the pay-off construction site.
对比分析,以上已公开的现有技术与本申请所要求保护的技术内容相比,其所要解决的技术问题、采用的技术手段均存在较大不同。Comparative analysis shows that the technical problems to be solved and the technical means adopted are quite different between the prior art disclosed above and the technical content claimed in this application.
发明内容Contents of the invention
本发明的目的在于克服现有技术的不足之处,提供一种结构简单、设计合理、使用方便、工艺可靠的输电线路放线施工导引绳分绳工艺。The purpose of the present invention is to overcome the disadvantages of the prior art, and provide a simple structure, reasonable design, convenient use, and reliable process of the guide rope separation process for the construction of power transmission lines.
本发明解决其技术问题是采取以下技术方案实现的:The present invention solves its technical problem and realizes by taking the following technical solutions:
一种输电线路放线施工导引绳分绳工艺,其特征在于:全部施工都在高空进行,即在塔上进行分线施工,具体施工工艺如下:A technique for separating the guide ropes in the setting-out construction of transmission lines, characterized in that all the construction is carried out at high altitude, that is, the line-dividing construction is carried out on the tower, and the specific construction process is as follows:
⑴根据分线施工工艺布置铁塔,在铁塔1的上端中部安装有手扳葫芦,铁塔上端外沿位置吊装有起重滑车,手扳葫芦通过该起重滑车连接有一放线滑车,手扳葫芦控制放线滑车上、下移动;⑴The iron tower is arranged according to the branch line construction process. A lever block is installed in the middle of the upper end of the iron tower 1, and a hoisting block is hoisted at the outer edge of the upper end of the iron tower. The hand block is connected to a pay-off block through the lifting block. The pay-off tackle moves up and down;
在放线滑车上穿装有牵引绳,该牵引绳的一端连接一牵引走板的前端,该牵引绳的另一端向待布设电缆的方向延伸并连接到用于牵引收线的牵引设备;牵引走板的后端间隔均布连接多条导引绳,A traction rope is worn on the pay-off block, one end of the traction rope is connected to the front end of a traction walking board, and the other end of the traction rope extends in the direction of the cable to be laid and is connected to the traction equipment for traction and take-up; traction The rear end of the walking board is evenly spaced to connect multiple guide ropes,
在放线滑车斜下方对应的铁塔上间隔安装有多个朝天滑车,朝天滑车用于限位支撑导引绳,朝天滑车与导引绳一一对应,可以根据施工需要增减朝天滑车的数量;A plurality of sky blocks are installed at intervals on the corresponding iron tower below the pay-off block. The sky blocks are used to limit the support of the guide rope. The sky blocks correspond to the guide ropes one by one. The number of sky blocks can be increased or decreased according to the construction needs;
导引绳向地面延伸,连接到线缆,导引绳牵引线缆前进,线缆被牵引上升到铁塔上并限位在朝天滑车上;The guide rope extends to the ground and is connected to the cable. The guide rope pulls the cable forward, and the cable is pulled up to the iron tower and limited on the sky block;
⑵放线滑车下降,手扳葫芦运行将放线滑车向下放松,放线滑车下降直至牵引走板的高度低于朝天滑车,此时导引绳的重量压在朝天滑车上,导引绳横向拉扯牵引走板,牵引走板由原来的竖直吊装位置渐渐倾斜,放线滑车下降过程保持匀速稳定;⑵The pay-off block is lowered, and the hand block is running to loosen the pay-off block, and the pay-off block is lowered until the height of the traction running board is lower than the upward block. At this time, the weight of the guide rope is pressed on the upward block. Pull the traction board, the traction board gradually tilts from the original vertical hoisting position, and the pay-off block maintains a constant speed and stability during the descent process;
⑶牵引前进,放线滑车下端挂钩开启,放线滑车与牵引走板脱离,启动牵引设备使牵引绳拉动牵引走板横向移动;⑶ Pulling forward, the hook at the lower end of the pay-off block is opened, the pay-off block is separated from the traction pallet, and the traction equipment is started to make the traction rope pull the traction pallet to move laterally;
牵引设备持续工作,牵引绳带动牵引走板,牵引走板带动多条导引线同步向待施工方向的下一个铁塔移动;The traction equipment continues to work, the traction rope drives the traction board, and the traction board drives multiple guide lines to move synchronously to the next iron tower in the direction of construction;
⑷牵引走板到达下一个铁塔位置,下一个铁塔上的放线滑车挂接牵引走板的前端而后上升到达步骤⑴的初始位置,重复上述步骤⑴至步骤⑶,逐级铁塔进行施工,将导引绳自动分置搁放在对应的线缆安装位置,施工在高空中连续进行。⑷The traction board reaches the position of the next iron tower, and the pay-off block on the next iron tower is hooked to the front end of the traction board and then rises to the initial position of step 1. Repeat the above steps 1 to 3, and carry out construction step by step. The guide ropes are automatically separated and placed in the corresponding cable installation positions, and the construction is carried out continuously at high altitude.
而且,所述工艺中牵引走板采用轻质、耐热绝缘材料制成的轻型导引绳牵引走板,导引绳分另定制成不同颜色。Moreover, in the described process, light-duty guide ropes made of light-weight, heat-resistant insulating materials are used for traction and movement of the boards, and the guide ropes are separately customized into different colors.
而且,所述牵引走板连接四条导引绳,导引绳采用轻质、耐热、绝缘导引绳。Moreover, the traction walking board is connected with four guide ropes, and the guide ropes are light, heat-resistant and insulating guide ropes.
本发明的优点和积极效果是:Advantage and positive effect of the present invention are:
1、本工艺结合入放线滑车的开闭工艺,实现在避免采用机械的情况下,将导引绳分置各放线滑车中。1. This process is combined with the opening and closing process of the pay-off block, so that the guide rope can be separated into each pay-off block while avoiding the use of machinery.
2、本工艺全部施工都在高空进行,极大避免了外协干扰,大大地缩短了放线工期。2. All the construction of this process is carried out at high altitude, which greatly avoids the interference of external cooperation and greatly shortens the construction period of setting out.
3、本工艺节省了大型机械和各铁塔的机械使用数量,效果极其明显。3. This process saves the number of large machines and the number of machines used for each iron tower, and the effect is extremely obvious.
4、本工艺节省了施工人员高空作业人员的投入,减少高空作业风险,增强施工人员的安全性。4. This process saves the investment of construction workers working at heights, reduces the risk of working at heights, and enhances the safety of construction workers.
5、本工艺由于采用的轻质、耐热、绝缘导引绳,施工过程中,人身安全和意外断线等安全危险程度大大降低。5. Due to the light weight, heat-resistant and insulated guide rope used in this process, the degree of safety hazards such as personal safety and accidental disconnection during the construction process is greatly reduced.
6、本发明输电线路放线施工导引绳分绳工艺改变了传统的放线工艺,将原先分绳是牵引绳改为轻质、耐热绝缘绳进行分绳,然后由分别替代成牵引绳进行导线牵引,减少施工对张力放线机及绞磨等设备的使用数量,简化施工步骤,降低施工成本,提升施工效率。6. The rope separation process of the guide rope for the laying-out construction of the transmission line of the present invention has changed the traditional laying-out process, changing the original rope separation from the traction rope to a light, heat-resistant insulating rope for separation, and then replacing it with traction ropes Conduct wire traction, reduce the number of equipment used in construction such as tension pay-off machines and winch mills, simplify construction steps, reduce construction costs, and improve construction efficiency.
附图说明Description of drawings
图1为本发明施工步骤一;Fig. 1 is construction step one of the present invention;
图2为本发明施工步骤二;Fig. 2 is construction step two of the present invention;
图3为本发明施工步骤三。Fig. 3 is the third construction step of the present invention.
具体实施方式Detailed ways
下面结合附图并通过具体实施例对本发明作进一步详述,以下实施例只是描述性的,不是限定性的,不能以此限定本发明的保护范围。The present invention will be further described in detail below in conjunction with the accompanying drawings and through specific embodiments. The following embodiments are only descriptive, not restrictive, and cannot limit the protection scope of the present invention.
一种输电线路放线施工导引绳分绳工艺,具体施工工艺如下:A technique for separating the guide ropes in the setting-out construction of transmission lines, the specific construction techniques are as follows:
施工步骤一,根据分线施工工艺布置铁塔,参见附图1,在铁塔1的上端中部安装有手扳葫芦2,铁塔上端外沿位置吊装有起重滑车3,手扳葫芦通过该起重滑车连接有一放线滑车4,手扳葫芦控制放线滑车上、下移动;Construction step 1: Arrange the iron tower according to the construction process of the sub-line, see attached drawing 1, a lever block 2 is installed in the middle of the upper end of the iron tower 1, and a lifting block 3 is hoisted on the outer edge of the upper end of the iron tower, and the lever block passes through the lifting block Connected with a pay-off tackle 4, the lever block controls the up and down movement of the pay-off tackle;
在放线滑车上穿装有牵引绳5,该牵引绳的一端连接一牵引走板6的前端,本工艺中牵引走板采用轻质、耐热绝缘材料制成的轻型导引绳牵引走板,该牵引绳的另一端向待布设电缆的方向延伸并连接到用于牵引收线的牵引设备(图中未示出);A traction rope 5 is installed on the pay-off block, and one end of the traction rope is connected to the front end of a traction pallet 6. In this process, the traction pallet adopts a light guide rope made of light-weight, heat-resistant insulating material to pull the pallet , the other end of the traction rope extends to the direction of the cable to be laid and is connected to a traction device (not shown) for traction take-up;
牵引走板的后端间隔均布连接多条导引绳,本实施例中的常用施工工艺中是连接四条导引绳,导引绳采用轻质、耐热、绝缘导引绳,导引绳的规格根据实际施工要求进行计算获得,The rear end of the traction board is connected with multiple guide ropes evenly distributed at intervals. In the common construction process in this embodiment, four guide ropes are connected. The guide ropes are light, heat-resistant and insulated guide ropes. The specifications are calculated according to the actual construction requirements,
为了便于区分相序,导引绳分另定制成不同颜色,有效提高施工效率,避免接线错误。In order to easily distinguish the phase sequence, the guide ropes are separately customized into different colors, which can effectively improve the construction efficiency and avoid wiring errors.
在放线滑车斜下方对应的铁塔上间隔安装有多个朝天滑车7,朝天滑车用于限位支撑导引绳,朝天滑车与导引绳一一对应,可以根据施工需要增减朝天滑车的数量;A plurality of sky blocks 7 are installed at intervals on the corresponding iron tower below the pay-off block. The sky blocks are used to limit the support of the guide rope. The sky blocks correspond to the guide ropes one by one. The number of sky blocks can be increased or decreased according to construction needs. ;
导引绳向地面延伸,连接到线缆,导引绳牵引线缆前进,线缆被牵引上升到铁塔上并限位在朝天滑车上;The guide rope extends to the ground and is connected to the cable. The guide rope pulls the cable forward, and the cable is pulled up to the iron tower and limited on the sky block;
施工步骤二,放线滑车下降,参见附图2,手扳葫芦运行将放线滑车向下放松,放线滑车下降直至牵引走板的高度低于朝天滑车,此时导引绳的重量压在朝天滑车上,导引绳横向拉扯牵引走板,牵引走板由原来的竖直吊装位置渐渐倾斜,放线滑车下降过程保持匀速稳定;Construction step 2, the pay-off block is lowered, see attached drawing 2, the hand block is running to loosen the pay-off block, and the pay-off block is lowered until the height of the traction board is lower than the sky block. At this time, the weight of the guide rope is on On the sky block, the guide rope pulls the traction board horizontally, the traction board gradually tilts from the original vertical hoisting position, and the pay-off block maintains a constant speed and stability during its descent;
施工步骤三,牵引前进,参见附图3,放线滑车下端挂钩开启,放线滑车与牵引走板脱离,启动牵引设备使牵引绳拉动牵引走板横向移动;Construction step 3, traction forward, see attached drawing 3, the hook at the lower end of the pay-off block is opened, the pay-off block is separated from the traction pallet, and the traction equipment is started to make the traction rope pull the traction pallet to move laterally;
牵引设备持续工作,牵引绳带动牵引走板,牵引走板带动多条导引线同步向待施工方向的下一个铁塔移动;The traction equipment continues to work, the traction rope drives the traction board, and the traction board drives multiple guide lines to move synchronously to the next iron tower in the direction of construction;
直到牵引走板到达下一个铁塔位置,下一个铁塔上的放线滑车挂接牵引走板的前端而后上升到达步骤一的初始位置,重复上述步骤一至步骤三,逐级铁塔进行施工,将导引绳自动分置搁放在对应的线缆安装位置,施工在高空中连续进行,显著提升施工效率。Until the traction board reaches the position of the next iron tower, the pay-off block on the next tower is hooked to the front end of the traction board and then rises to the initial position of step 1. Repeat the above steps 1 to 3, and carry out construction step by step. The ropes are automatically separated and placed in the corresponding cable installation positions, and the construction is carried out continuously at high altitude, which significantly improves the construction efficiency.
本发明在描述上仅体现为牵引绳使用位置和数量的变化,但这样的变化是克服了多年来行业传统施工工艺的技术创新,而且其效果非常显著,适于在本领域内进行广泛推广应用。The description of the present invention is only reflected in the change of the position and quantity of the traction rope, but such a change is a technical innovation that overcomes the traditional construction technology of the industry for many years, and its effect is very significant, suitable for wide application in this field .
尽管为说明目的公开了本发明的实施例和附图,但是本领域的技术人员可以理解:在不脱离本发明及所附权利要求的精神和范围内,各种替换、变化和修改都是可能的,因此,本发明的范围不局限于实施例和附图所公开的内容。Although the embodiments and drawings of the present invention are disclosed for the purpose of illustration, those skilled in the art can understand that various replacements, changes and modifications are possible without departing from the spirit and scope of the present invention and the appended claims Therefore, the scope of the present invention is not limited to what is disclosed in the embodiments and drawings.
Claims (3)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510304100.8A CN104993419B (en) | 2015-06-05 | 2015-06-05 | Transmission line of electricity payingoff construction guide rope point rope technique |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510304100.8A CN104993419B (en) | 2015-06-05 | 2015-06-05 | Transmission line of electricity payingoff construction guide rope point rope technique |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN104993419A CN104993419A (en) | 2015-10-21 |
| CN104993419B true CN104993419B (en) | 2018-04-03 |
Family
ID=54305194
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510304100.8A Active CN104993419B (en) | 2015-06-05 | 2015-06-05 | Transmission line of electricity payingoff construction guide rope point rope technique |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104993419B (en) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110752550B (en) * | 2019-10-25 | 2020-11-06 | 四川电力送变电建设有限公司 | Multi-pulley arrangement method for steering field |
| CN115241798B (en) * | 2022-08-26 | 2024-01-19 | 国网山东省电力公司潍坊供电公司 | A ground conductor pay-off pulley structure |
| CN119297838B (en) * | 2024-10-25 | 2025-11-14 | 安徽送变电工程有限公司 | A method for constructing traction ropes and calculating anchor rope specifications for cable laying. |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU997158A1 (en) * | 1981-04-29 | 1983-02-15 | Проектно-Конструкторское Бюро Главстроймеханизации Министерства Транспортного Строительства | Wire uncoiling device |
| JPH01248914A (en) * | 1988-03-28 | 1989-10-04 | Kyushu Denki Kensetsu Koji Kk | Snatch block device for wire extension |
| CN101436764A (en) * | 2008-11-13 | 2009-05-20 | 江苏省电力公司宜兴市供电公司 | Crossover stringing method for overhead line and stringing sheave pulley |
| CN201388013Y (en) * | 2009-03-06 | 2010-01-20 | 辽宁省电力有限公司盘锦供电公司 | multi-purpose pulley |
| CN101697403A (en) * | 2009-10-23 | 2010-04-21 | 江苏省电力公司句容市供电公司 | Construction method for spreading lead wire and earth wire in transmission line |
| CN102593759A (en) * | 2012-02-16 | 2012-07-18 | 湖北省输变电工程公司 | One-pulling-two expansion and construction process of large-section lead |
| CN103663237A (en) * | 2014-01-24 | 2014-03-26 | 国家电网公司 | Supporting and orientating guide pulley which can rise and fall and has smoothing function |
-
2015
- 2015-06-05 CN CN201510304100.8A patent/CN104993419B/en active Active
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| SU997158A1 (en) * | 1981-04-29 | 1983-02-15 | Проектно-Конструкторское Бюро Главстроймеханизации Министерства Транспортного Строительства | Wire uncoiling device |
| JPH01248914A (en) * | 1988-03-28 | 1989-10-04 | Kyushu Denki Kensetsu Koji Kk | Snatch block device for wire extension |
| CN101436764A (en) * | 2008-11-13 | 2009-05-20 | 江苏省电力公司宜兴市供电公司 | Crossover stringing method for overhead line and stringing sheave pulley |
| CN201388013Y (en) * | 2009-03-06 | 2010-01-20 | 辽宁省电力有限公司盘锦供电公司 | multi-purpose pulley |
| CN101697403A (en) * | 2009-10-23 | 2010-04-21 | 江苏省电力公司句容市供电公司 | Construction method for spreading lead wire and earth wire in transmission line |
| CN102593759A (en) * | 2012-02-16 | 2012-07-18 | 湖北省输变电工程公司 | One-pulling-two expansion and construction process of large-section lead |
| CN103663237A (en) * | 2014-01-24 | 2014-03-26 | 国家电网公司 | Supporting and orientating guide pulley which can rise and fall and has smoothing function |
Also Published As
| Publication number | Publication date |
|---|---|
| CN104993419A (en) | 2015-10-21 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN101582572B (en) | Method of extra-high voltage tension stringing | |
| CN102354926A (en) | Large-section conductor tension stringing construction method | |
| CN201708479U (en) | Cable stretching construction cross pulley | |
| CN102290742A (en) | Tension stringing construction technology | |
| CN104993419B (en) | Transmission line of electricity payingoff construction guide rope point rope technique | |
| CN204230769U (en) | Climb type steel cable ladder | |
| CN107834434A (en) | Crossing method for the construction of transmission line of electricity tension stringing | |
| CN202423978U (en) | Overhead wire crossing frame | |
| CN104410005A (en) | Operation method for replacing overhead conductor and ground wire | |
| CN201785175U (en) | Hoisting basket for high-voltage steel tower | |
| CN211456516U (en) | Electrified wire feeding and discharging device of high-voltage overhead bare conductor insulation rubber coating robot | |
| CN103663301A (en) | Inward-inclined type hanging basket device | |
| CN201742028U (en) | Pulley used for overhaul of overhead power transmission lines | |
| CN102237654A (en) | Tool and method for replacing jumper string at double angle hanging point | |
| CN103708371A (en) | Cable-driving rope replacing mechanism | |
| CN102593759A (en) | One-pulling-two expansion and construction process of large-section lead | |
| CN205318933U (en) | Enameled wire collection device | |
| CN205985948U (en) | Tension formula line protection | |
| CN106300128A (en) | A kind of double bundle conductor conductor spacer of changing puies forward the Line tool and using method | |
| CN201285999Y (en) | Soft ladder for high voltage line maintenance | |
| CN110212324A (en) | A kind of hanging device and method of voltage levels temporary ground wire | |
| CN203774686U (en) | Multi-wheel pulley set tension line laying apparatus | |
| CN214934920U (en) | Auxiliary device for cable processing | |
| CN104724615A (en) | Penetrating and winding method of large-diameter variable-amplitude steel wire rope of large moving-arm type tower crane | |
| CN117166369A (en) | A lifting device for HDPE outer casing of steel strand cable-stayed cables and its use method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |