CN104818858B - Indoor heavy electrical cabinet hanging method - Google Patents

Indoor heavy electrical cabinet hanging method Download PDF

Info

Publication number
CN104818858B
CN104818858B CN201510190928.5A CN201510190928A CN104818858B CN 104818858 B CN104818858 B CN 104818858B CN 201510190928 A CN201510190928 A CN 201510190928A CN 104818858 B CN104818858 B CN 104818858B
Authority
CN
China
Prior art keywords
electrical cabinet
heavy electrical
suspension ring
platform
steel wire
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510190928.5A
Other languages
Chinese (zh)
Other versions
CN104818858A (en
Inventor
江龙
孙亮
杨明
陈忠保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201510190928.5A priority Critical patent/CN104818858B/en
Publication of CN104818858A publication Critical patent/CN104818858A/en
Application granted granted Critical
Publication of CN104818858B publication Critical patent/CN104818858B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of indoor heavy electrical cabinet hanging method, including following construction procedure;It is carried to heavy electrical cabinet lift region, aisle, protective demolition electric panel room doorway platform guardrail;4 suspension ring are respectively penetrated in 4 hangers of heavy electrical cabinet, 4 suspension ring are divided into two groups, cabinet top top view is rectangle, two summits of rectangle every minor face are one group, it is divided into two groups, one of which suspension ring respectively penetrate 1 root length steel wire rope, and another group suspension ring respectively penetrate 1 strap, and the hook of 1 chain block tangles the other end of 2 straps.The invention have the advantage that compared with routine work method, be not required to set up, remove scaffold lifting operation platform, be not required to operation on scaffold lifting operation platform, it is to avoid the danger that work high above the ground brings, improve the safety of operation;Use this method can save scaffold and take the turnover trucking expenses of labour cost, fee of material and the material torn open.

Description

Indoor heavy electrical cabinet hanging method
Technical field
The present invention relates to a kind of industrial equipment construction method of installation, in particular, relate to a kind of indoor heavy electrical Cabinet hanging method.
Background technology
In metallurgical, power ampere packing technique field, some heavy electrical cabinets such as frequency conversion tank need to be arranged in electric panel room.Typically In the case of, second floor and above electric panel room doorway are aisle platform, owing to there being last layer aisle platform to stop, no above the platform of aisle Meet the condition of directly lifting.Routine work method is before lifting, sets up scaffold lifting outside the platform of electric panel room aisle Platform, then by heavy electrical cabinet lifting to hoisting platform, is finally pushed heavy electrical cabinet in electric panel room by hoisting platform Install.This hanging method not only needs to spend substantial amounts of manpower and materials to carry out setting up of scaffold hoisting platform, Er Qie Needing after having lifted to remove scaffold hoisting platform, there is bigger potential safety hazard, be unfavorable for the raising of working performance, impact is executed Work progress.
Summary of the invention
The present invention is directed to the deficiencies in the prior art, and a kind of working performance that improves is provided, save expense, it is to avoid scaffold hangs Assembling platform is set up, is removed and the hidden danger of operation on scaffold hoisting platform, and the indoor heavy electrical cabinet reducing construction cost hangs Dress method.
A kind of indoor heavy electrical cabinet hanging method of the present invention, including following construction procedure:
Heavy electrical cabinet is carried to lift region, aisle, protective demolition electric panel room doorway platform guardrail by step 1;
4 suspension ring are respectively penetrated in 4 hangers of heavy electrical cabinet by step 2, and 4 suspension ring are divided into two groups, bow in cabinet top View is rectangle, and two summits of rectangle every minor face are one group, are divided into two groups, and each suspension ring of one group of suspension ring all penetrate 1 Root length steel wire rope, another group suspension ring each suspension ring all penetrate 1 strap, the hook of 1 chain block is tangled 2 short The other end of steel wire rope;
The step 3 aisle platform 2 channel-section steels of laying on electric panel room doorway are as guide rail, and 4 steel pipes are laid on guide rail On, truck crane is in place, and hook and the 2 root length steel wire ropes of chain block is linked in truck crane suspension hook;
Carry out examination before step 4 lifting to hang, adjust chain block and guarantee heavy electrical cabinet holding level in hoisting process;
By the rope made of hemp, (at heavy electrical cashier's office in a shop, truck crane formally lifts by crane step 5 in colligation, is hoisted to electrically by heavy electrical cabinet The aisle platform on doorway, room;
Step 6 is on the premise of ensureing job safety, and one end of the rope made of hemp is dragged to the platform of aisle by operating personnel, simultaneously It is drawn to chain block side, adjust the sling height of truck crane, by the one of heavy electrical cabinet by heavy electrical cabinet by the rope made of hemp While be placed on the steel pipe laid;
Step 7 is under the guiding of crane, and relax 200mm by the chain lock length of chain block, more slowly lifts by crane, and pulls Ground is first left, when ground is left in long steel wire rope side in the long steel wire rope side making heavy electrical cabinet by the calabash 200mm that relaxes During 50mm~80mm, by rope made of hemp traction by heavy electrical cabinet toward layback in the platform of aisle, treat that truck crane hoist cable is in vertical position Postponing, now continue chain lock length 200mm of lax chain block, more slowly lift by crane, the rope made of hemp draws heavy electrical cabinet toward walking Layback in road platform;
Step 8 relaxes chain lock length 500mm of chain block, more slowly lifts by crane, when the one of the long steel wire rope of heavy electrical cabinet When ground 50mm~80mm is left in side, the rope made of hemp draws heavy electrical cabinet toward layback in the platform of aisle, until by whole heavy electricity Gas holder is drawn into aisle platform, is then removed by 4 suspension ring, then heavy electrical cabinet is pushed electric panel room installs;Lifting completes Rear recovery removes guardrail.
The length of described strap is not less than 500mm.The length of described long steel wire rope is not less than 1m.Described strap A length of 600mm.The a length of 1.2m of described long steel wire rope.
The invention has the beneficial effects as follows: (1) is safe and reliable: compared with routine work method, be not required to set up, remove scaffold Lifting operation platform, be not required to operation on scaffold lifting operation platform, it is to avoid the danger that work high above the ground brings, and improves operation Safety;(2) high financial profit: use this method can save scaffold and take labour cost, fee of material and the material torn open Turnover trucking expenses;(3) accelerating construction progress: be not required to take a significant amount of time before operation carry out the materials such as scaffold carrying, The setting up of scaffold lifting operation platform, operation complete after the dismounting of scaffold, improve working performance.
Accompanying drawing explanation
Fig. 1 is that the inventive method lifts top view;
Fig. 2 is the inventive method implementation process schematic diagram one;
Fig. 3 is the inventive method implementation process schematic diagram two;
Fig. 4 is the inventive method implementation process schematic diagram three;
Fig. 5 is the inventive method implementation process schematic diagram four;
In figure: aisle platform 1, heavy electrical cabinet 2, truck crane 3, suspension ring 4, long steel wire rope 5, strap 6, chain block 7, channel-section steel 8, steel pipe 9, the rope made of hemp 10, aisle platform guardrail 11.
Detailed description of the invention
The invention will be further described below in conjunction with the accompanying drawings.
In the drawings, a kind of indoor heavy electrical cabinet hanging method of the present invention, including following construction procedure:
Heavy electrical cabinet 2 is carried to lift region, aisle, protective demolition electric panel room doorway platform guardrail 11 by step 1;
4 suspension ring 4 are respectively penetrated in 4 hangers of heavy electrical cabinet 2 by step 2,4 suspension ring 4 are divided into two groups, cabinet Top top view is rectangle, and two summits of rectangle every minor face are one group, are divided into two groups, and each suspension ring of one group of suspension ring 4 are equal Penetrating 1 root length steel wire rope 5, each suspension ring of another group suspension ring 4 all penetrate 1 strap 6, by the extension of 1 chain block 7 Hook the other end of 2 straps 6;
The step 3 aisle platform 1 on electric panel room doorway lays 2 channel-section steels 8 as guide rail, and is laid on by 4 steel pipes 9 On guide rail, truck crane 3 is in place, and hook and the 2 root length steel wire ropes 5 of chain block 7 is linked in truck crane 3 suspension hook;
Carry out examination before step 4 lifting to hang, adjust chain block 7 and guarantee that heavy electrical cabinet 2 keeps water in hoisting process Flat;
Step 5 is by the rope made of hemp 10 colligation on heavy electrical cabinet 2, and truck crane 3 formally lifts by crane, and is hoisted to by heavy electrical cabinet 2 The aisle platform 1 on electric panel room doorway;
Step 6 is on the premise of ensureing job safety, and one end of the rope made of hemp 10 is dragged to aisle platform 1 by operating personnel, with Time by the rope made of hemp 10 heavy electrical cabinet 2 is drawn to chain block 7 side, adjust the sling height of truck crane 3, by heavy electrical Cabinet 2 while being placed on the steel pipe 9 laid;
Step 7 is under the guiding of crane, and relax 200mm by the chain lock length of chain block 7, more slowly lifts by crane, and pulls Ground is first left, when ground is left in long steel wire rope 5 side in long steel wire rope 5 side making heavy electrical cabinet 2 by calabash 7 200mm that relaxes During the 60mm of face, drawn heavy electrical cabinet 2 toward layback in aisle platform 1 by the rope made of hemp 10, treat that truck crane 3 hoist cable is in vertical position Postponing, now continue chain lock length 200mm of lax chain block 7, more slowly lift by crane, the rope made of hemp 10 draws heavy electrical cabinet 2 Layback in aisle platform 1;
Step 8 relaxes chain lock length 500mm of chain block 7, more slowly lifts by crane, when the long steel wire rope of heavy electrical cabinet 25 Side when leaving ground 60mm, the rope made of hemp 10 draws heavy electrical cabinet 2 toward layback in aisle platform 1, until by whole heavy type Regulator cubicle 2 is drawn into aisle platform 1, is then removed by 4 suspension ring 4, then heavy electrical cabinet 2 is pushed electric panel room installs;Hang Recover after installing into remove guardrail 11.
The a length of 600mm of described strap 6.The a length of 1.2m of described long steel wire rope 5.

Claims (5)

1. an indoor heavy electrical cabinet hanging method, it is characterised in that include following construction procedure:
Heavy electrical cabinet (2) is carried to lift region, aisle, protective demolition electric panel room doorway platform guardrail (11) by step 1;
4 suspension ring (4) are respectively penetrated in 4 hangers of heavy electrical cabinet (2) by step 2, and 4 suspension ring (4) are divided into two groups, Cabinet top top view is rectangle, and two summits of rectangle every minor face are one group, are divided into two groups, one of which suspension ring (4) every Individual suspension ring all penetrate 1 root length steel wire rope (5), and each suspension ring of another group suspension ring (4) all penetrate 1 strap (6), by 1 The hook of chain block (7) tangles the other end of 2 straps (6);
The step 3 aisle platform (1) 2 channel-section steels (8) of laying on electric panel room doorway are as guide rail, and 4 steel pipes (9) laid On guide rail, truck crane (3) is in place, and hook and the 2 root length steel wire ropes (5) of chain block (7) are linked into truck crane (3) suspension hook In;
Carry out examination before step 4 lifting to hang, adjust chain block (7) and guarantee that heavy electrical cabinet (2) keeps water in hoisting process Flat;
Step 5 is by the rope made of hemp (10) colligation on heavy electrical cabinet (2), and truck crane (3) formally lifts by crane, and is hung by heavy electrical cabinet (2) It is transported to the aisle platform (1) on electric panel room doorway;
Step 6 is on the premise of ensureing job safety, and one end of the rope made of hemp (10) is dragged to aisle platform (1) by operating personnel, with Time by the rope made of hemp (10) heavy electrical cabinet (2) is drawn to chain block (7) side, adjust the sling height of truck crane (3), will Heavy electrical cabinet (2) while being placed on the steel pipe (9) laid;
Step 7 is under the guiding of crane, and relax 200mm by the chain lock length of chain block (7), more slowly lifts by crane, and pulls calabash Ground is first left, when long steel wire rope (5) side in long steel wire rope (5) side making heavy electrical cabinet (2) by the lax 200mm of reed (7) When leaving ground 50mm~80mm, by the rope made of hemp (10) traction by heavy electrical cabinet (2) toward aisle platform (1) interior layback, treat vapour Car hang (3) hoist cable in vertical position after, now continue chain lock length 200mm of lax chain block (7), more slowly lift by crane, The rope made of hemp (10) draws heavy electrical cabinet (2) toward aisle platform (1) interior layback;
Step 8 relaxes chain lock length 500mm of chain block (7), more slowly lifts by crane, when heavy electrical cabinet (2) long steel wire rope (5), when ground 50mm~80mm is left in side, the rope made of hemp (10) draws heavy electrical cabinet (2) toward aisle platform (1) interior layback, Until whole heavy electrical cabinet (2) to be drawn into aisle platform (1), then 4 suspension ring (4) are removed, then by heavy electrical cabinet (2) Push electric panel room to install;Recover after having lifted to remove guardrail (11).
Indoor heavy electrical cabinet hanging method the most according to claim 1, it is characterised in that described strap (6) Length is not less than 500mm.
Indoor heavy electrical cabinet hanging method the most according to claim 1, it is characterised in that described long steel wire rope (5) Length is not less than 1m.
Indoor heavy electrical cabinet hanging method the most according to claim 2, it is characterised in that described strap (6) A length of 600mm.
Indoor heavy electrical cabinet hanging method the most according to claim 3, it is characterised in that described long steel wire rope (5) A length of 1.2m.
CN201510190928.5A 2015-04-22 2015-04-22 Indoor heavy electrical cabinet hanging method Active CN104818858B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510190928.5A CN104818858B (en) 2015-04-22 2015-04-22 Indoor heavy electrical cabinet hanging method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510190928.5A CN104818858B (en) 2015-04-22 2015-04-22 Indoor heavy electrical cabinet hanging method

Publications (2)

Publication Number Publication Date
CN104818858A CN104818858A (en) 2015-08-05
CN104818858B true CN104818858B (en) 2016-10-05

Family

ID=53729318

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510190928.5A Active CN104818858B (en) 2015-04-22 2015-04-22 Indoor heavy electrical cabinet hanging method

Country Status (1)

Country Link
CN (1) CN104818858B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106185599B (en) * 2016-08-30 2017-11-24 大唐黄岛发电有限责任公司 A kind of hydrogen-cooled device maintenance special purpose device of generator
CN108675105A (en) * 2018-05-22 2018-10-19 山西省工业设备安装集团有限公司 A kind of condenser hanging apparatus and its construction technology
CN109761146A (en) * 2019-03-07 2019-05-17 中国十七冶集团有限公司 A kind of transformer installation method of no hoisting platform
CN112390207A (en) * 2020-11-19 2021-02-23 深圳供电局有限公司 Power equipment operation maintenance device and operation method thereof
CN115092845A (en) * 2022-06-15 2022-09-23 中建三局安装工程有限公司 Method for hoisting equipment

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1396529A (en) * 1964-03-13 1965-04-23 Handling device for lifting operations
FR2253901A1 (en) * 1975-01-03 1975-07-04 Compensation Ste Gle Method of transferring shuttering - involves using three axle carriage not pivoting when lifted by slings
CN201276399Y (en) * 2008-09-11 2009-07-22 上海市安装工程有限公司 Apparatus hoisting mechanism for tall building floor non-steel platform
CN102190254B (en) * 2010-03-03 2014-10-01 五冶集团上海有限公司 Hoisting method for equipment installation in in-between hollow space of multilayer concrete platforms
CN102190249B (en) * 2010-03-17 2014-10-01 五冶集团上海有限公司 Method for hoisting equipment positioned at bottom of multilayer frame platform
CN102635225A (en) * 2012-04-05 2012-08-15 广东省工业设备安装公司 Equipment hoisting platform and method for super high-rise buildings

Also Published As

Publication number Publication date
CN104818858A (en) 2015-08-05

Similar Documents

Publication Publication Date Title
CN104818858B (en) Indoor heavy electrical cabinet hanging method
CN205955236U (en) Container formula of taking pulley platform of unloading of encorbelmenting
CN205953370U (en) Perpendicular transport means of unitized curtain wall
CN104895337B (en) The installation method of large-size horizontal equipment in concrete frame
CN102409838B (en) Moveable operating platform and method for constructing suspended ceiling of roof by using same
CN206502579U (en) Power pole hoisting device
CN105019664B (en) The air translation Method for Installation of case room formula electric panel room
CN105460759B (en) A kind of method that main shaft winch tail rope is changed
CN204689430U (en) To Construction of Silo movable hoisting device
CN106315426B (en) A kind of assembling flat-top tower crane for building is installed, jacking method
CN108675170A (en) Roofing monorail crane and its construction method
CN106144929A (en) One population hoist device and construction method
CN106276602B (en) A kind of across high ferro Business Line beam body hangs method
CN108797339A (en) A kind of safe construction method of cast-in-situ steel reinforced concrete anticollision barrier
CN208732486U (en) Roofing monorail crane
CN207312995U (en) One kind self-control bridge-collision-avoidance wall form hanging device
CN203143964U (en) Device for quickly changing blast furnace air-tight box
CN202594676U (en) Bridge deck system shielding plate installation gantry crane for passenger dedicated railway line
CN104344075B (en) Shaft construction hangs the quick handling of interim edema due to wind pathogen pipeline and installation method using the borehole wall
CN205407131U (en) Cable laying device
CN209959289U (en) Mining hydraulic hoisting-free loading platform
CN103407903A (en) Automatic traction system for large-size tower crane mounting and dismounting standard knot and traction method thereof
CN208517821U (en) A kind of simple hoisting apparatus for removing box beam beret slice
CN205802821U (en) A kind of heating furnace water beam is lifted the device having bad luck
CN205114861U (en) Hoist and mount lacing device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant