CN104963497A - Scaffold connecting rod - Google Patents
Scaffold connecting rod Download PDFInfo
- Publication number
- CN104963497A CN104963497A CN201510318006.8A CN201510318006A CN104963497A CN 104963497 A CN104963497 A CN 104963497A CN 201510318006 A CN201510318006 A CN 201510318006A CN 104963497 A CN104963497 A CN 104963497A
- Authority
- CN
- China
- Prior art keywords
- connecting rod
- scaffold
- rod
- connecting portion
- head rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The invention provides a scaffold connecting rod. The scaffold connecting rod comprises a first connecting rod and a second connecting rod arranged on the first connecting rod. A first connecting rod body is provided with a connecting part. The second connecting rod is connected with the first connecting rod through the connecting part. The second connecting rod can rotate with the connecting part as the circle center. The first connecting rod is in a U shape and comprises two first vertical rods fixedly connected with the ground, and a first cross rod arranged between the two first vertical rods. Compared with the prior art, the scaffold connecting rod has the technical advantages that after the second connecting rod is rotated to a set angle, a work platform erected by a scaffold can be extended, operation is easy and convenient, and the construction efficiency is greatly improved while the extendibility of the scaffold platform is improved.
Description
Technical field
The present invention relates to building implement field, particularly relate to the scaffold connecting rod used in a kind of building operations.
Background technology
Scaffold refers to that job site is the various supports that operative also solves vertically and horizontal transport is set up.The generic term on building circle, refers to building site be used in the higher place that cannot directly construct of exterior wall, interior decoration or floor height.Mainly for constructor works or the maintenance of perimeter security net and high-altitude installation component etc. up and down, be exactly plainly build a framework, scaffold makes material to be had usually: bamboo and wood, steel pipe or synthetic materials etc.Some engineering is also worked as template with scaffold and is used, and the department such as this external advertising, municipal administration, traffic road and bridge, mine is also extensively used.
In prior art, before total body construction starts, need to set up multiple scaffold, more multiple scaffold is coupled together formation working platform.But scaffolding structure of the prior art is single, the ductility of single support is poor, so in time there is construction problem, need again to set up scaffold, be connected with original scaffold again, considerably increase difficulty of construction and construction period, have impact on efficiency of construction.
In view of this, a kind of follow-on scaffold should be provided, to solve the problems of the technologies described above.
Summary of the invention
The object of the present invention is to provide a kind of scaffold connecting rod that can extend.
To achieve these goals, the invention provides a kind of scaffold connecting rod.Comprise head rod and be arranged at the second connecting rod on head rod, the head rod body of rod is provided with connecting portion, second connecting rod is connected with head rod by connecting portion, and the second connecting rod can be that the center of circle is rotated with connecting portion, head rod is " recessed " font, comprise two the first vertical bars be fixedly connected with ground and the first cross bar be arranged between two first vertical bars, connecting portion comprises attaching nut and attachment screw, and connecting portion is in the middle and upper part of the first vertical club shaft.
Scaffold connecting rod of the present invention compared with prior art, have the following advantages: after the second connecting rod rotates to first retainer, the working platform of the scaffold building that can extend, easy and simple to handle, while improve the ductility of scaffolding platform, substantially increase the efficiency of construction.
Accompanying drawing explanation
Fig. 1 is the structural representation of one embodiment of the present invention scaffold connecting rod.
Detailed description of the invention
Explanation that the present invention is described in further detail below in conjunction with drawings and the specific embodiments.
Show to the schematic property of Fig. 1 scaffold connecting rod according to an embodiment of the present invention.As shown in the figure, scaffold connecting rod comprises head rod 10 and is arranged at the second connecting rod 20 on head rod 10.Head rod 10 is " recessed " font, comprises two the first vertical bars 101 be fixedly connected with ground and the first cross bar 103 be arranged between two first vertical bars 101.
All be provided with connecting portion 105 in the middle part of the body of rod of two symmetrically arranged first vertical bars 101, connecting portion 105 comprises an attaching nut 107.Connecting portion 105 is connected with the second connecting rod 20 by attachment screw.Second connecting rod 20 is fixedly connected with connecting portion 105 by attachment screw, when needs extend, can unclamp screw, then the second connecting rod 20 can connecting portion 105 be center of circle rotation.After the second connecting rod 20 rotates to first retainer, screw the location that attaching nut 107 can complete the second connecting rod 20.When not needing to use, the second connecting rod 20 can rotate to and is set on head rod 10, and parallel with the first cross bar 103 in vertical direction.
Compared with prior art, Advantageous Effects of the present invention is, after the second connecting rod rotates to first retainer, can be extended the working platform of scaffold building, easy and simple to handle, while improve the ductility of scaffolding platform, substantially increase the efficiency of construction.
Be to be understood that, although this manual is described according to embodiment, but not each embodiment only comprises an independently technical scheme, this narrating mode of manual is only for clarity sake, those skilled in the art should by manual integrally, technical scheme in each embodiment also through appropriately combined, can form other embodiments that it will be appreciated by those skilled in the art that.
A series of detailed description listed is above only illustrating for possible embodiments of the present invention; they are also not used to limit the scope of the invention, all do not depart from Equivalent embodiments of the present invention or change all should be included within protection scope of the present invention.
Claims (1)
1. scaffold connecting rod, it is characterized in that, comprise head rod (10) and be arranged at the second connecting rod (20) on described head rod (10), described head rod (10) body of rod is provided with connecting portion (105), described second connecting rod (20) is connected with described head rod (10) by described connecting portion (105), and described second connecting rod (20) can with described connecting portion (105) for the center of circle be rotated, described head rod (10) is " recessed " font, comprise two the first vertical bars (101) be fixedly connected with ground and the first cross bar (103) be arranged at described in two between first vertical bar (101), described connecting portion (105) comprises attaching nut (107) and attachment screw (109), described connecting portion (105) is positioned at the middle and upper part of described first vertical bar (101) body of rod.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510318006.8A CN104963497A (en) | 2015-06-05 | 2015-06-05 | Scaffold connecting rod |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510318006.8A CN104963497A (en) | 2015-06-05 | 2015-06-05 | Scaffold connecting rod |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104963497A true CN104963497A (en) | 2015-10-07 |
Family
ID=54217562
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510318006.8A Pending CN104963497A (en) | 2015-06-05 | 2015-06-05 | Scaffold connecting rod |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104963497A (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08333884A (en) * | 1995-06-08 | 1996-12-17 | Ohbayashi Corp | Structure of connecting board for jumping scaffolding in building construction |
JP2594530B2 (en) * | 1994-12-28 | 1997-03-26 | 中央ビルト工業株式会社 | Railing frame for scaffolding |
CN1796703A (en) * | 2004-12-20 | 2006-07-05 | 久纳利彦 | Working surface construction system of slope, working surface construction apparatus and working panel |
CN203175015U (en) * | 2012-08-19 | 2013-09-04 | 赵建山 | Indoor/outdoor universal door-type scaffold |
CN203729567U (en) * | 2013-12-03 | 2014-07-23 | 郝绍菊 | Scaffold connecting rod |
-
2015
- 2015-06-05 CN CN201510318006.8A patent/CN104963497A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2594530B2 (en) * | 1994-12-28 | 1997-03-26 | 中央ビルト工業株式会社 | Railing frame for scaffolding |
JPH08333884A (en) * | 1995-06-08 | 1996-12-17 | Ohbayashi Corp | Structure of connecting board for jumping scaffolding in building construction |
CN1796703A (en) * | 2004-12-20 | 2006-07-05 | 久纳利彦 | Working surface construction system of slope, working surface construction apparatus and working panel |
CN203175015U (en) * | 2012-08-19 | 2013-09-04 | 赵建山 | Indoor/outdoor universal door-type scaffold |
CN203729567U (en) * | 2013-12-03 | 2014-07-23 | 郝绍菊 | Scaffold connecting rod |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204876508U (en) | Portable height -adjustable scaffold | |
CN204126230U (en) | Assembly scaffold unit | |
CN103104092A (en) | Support composite structure of beam and slab | |
CN204266609U (en) | Assembled architecture faces limit horizontal protective and chooses net system | |
CN204199651U (en) | Foldable mobile scaffold | |
CN203834926U (en) | Formwork erecting structure for bare concrete basement exterior wall | |
CN203729567U (en) | Scaffold connecting rod | |
CN104963497A (en) | Scaffold connecting rod | |
CN104018655B (en) | A kind of assembly type monomer bracing frame | |
CN104164889A (en) | Demountable tower crane foundation | |
CN104328900A (en) | Gantry type scaffold | |
CN207362706U (en) | Load carrying type hanging basket operating platform | |
CN205444451U (en) | An H-shaped steel combined base for light house | |
CN204212273U (en) | A kind of composite steel concrete column and box concrete filled steel tube cant beam switching node | |
CN210369827U (en) | Scaffold for building external wall construction | |
CN203977844U (en) | A kind of for the fixing steel pipe iron wire fastener of building trade | |
CN203795824U (en) | Suspension type fastener scaffold erecting device | |
CN103195079A (en) | Installation type templates, installation type template group and set of installation type template devices | |
CN206267039U (en) | A kind of jack support platform of hollow slab girder jack-up construction | |
CN204174919U (en) | Scaffold | |
CN204435813U (en) | Care-supporting movable Scaffold protected by a kind of band | |
CN203878952U (en) | Simple telescopic scaffold | |
CN210459952U (en) | Scaffold frame that building engineering construction operation was used | |
CN204418696U (en) | Vertical reinforcement spreading lifting assistor | |
CN211572533U (en) | Pre-buried connecting device of concrete building scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20151007 |