CN104947602B - A kind of Novel rhombus false work - Google Patents

A kind of Novel rhombus false work Download PDF

Info

Publication number
CN104947602B
CN104947602B CN201510384143.1A CN201510384143A CN104947602B CN 104947602 B CN104947602 B CN 104947602B CN 201510384143 A CN201510384143 A CN 201510384143A CN 104947602 B CN104947602 B CN 104947602B
Authority
CN
China
Prior art keywords
iron
steel
side plate
reinforced sheet
metal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510384143.1A
Other languages
Chinese (zh)
Other versions
CN104947602A (en
Inventor
求才军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Changqing Construction Products Co., Ltd.
Original Assignee
Shizuishan Hongyu Electronic Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shizuishan Hongyu Electronic Technology Co Ltd filed Critical Shizuishan Hongyu Electronic Technology Co Ltd
Priority to CN201510384143.1A priority Critical patent/CN104947602B/en
Priority to CN201610677525.8A priority patent/CN106284101A/en
Publication of CN104947602A publication Critical patent/CN104947602A/en
Application granted granted Critical
Publication of CN104947602B publication Critical patent/CN104947602B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)
  • Bending Of Plates, Rods, And Pipes (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The invention discloses a kind of Novel rhombus false work, including connecting box, connecting rod, described connection box includes the first connection box, second connects box, 3rd connects box and the 4th connects box, described connecting rod includes head rod, second connecting rod, 3rd connecting rod, 4th connecting rod and the 5th connecting rod, described head rod two end is respectively arranged on the first connection box and the 4th and connects on box, the second described connecting rod two end is respectively arranged on the first connection box and second and connects on box, the 3rd described connecting rod two end is respectively arranged on the first connection box and the 3rd and connects on box, the 4th described connecting rod two end is respectively arranged on the 3rd connection box and the 4th and connects on box, the 5th described connecting rod two end is respectively arranged on the second connection box and the 3rd and connects on box.

Description

A kind of Novel rhombus false work
Technical field
The present invention relates to a kind of rhombus false work, a kind of main truss cradle rhombus false work for bridge construction.
Technical background
The main truss cradle of bridge construction is to connect box by rhombus false work to form with connecting casing connecting rod, but some the rhombus false works on existing market are with connecting box at present, design unreasonable, after connecting each parts of main truss cradle, to re-use if disassembled, its connecting hole (through hole) can destroy, and rhombus false work connection box mostly is a steel body structure, Heavy Weight, cost is high, time fixing, multiple workmans are wanted to lift, assemble inconvenience, and when installing main truss cradle, it is all in high-altitude, the parts of Heavy Weight, cause the workman of installation abnormally dangerous, imprudence falls down, will result in considerable safety thing.
Summary of the invention
The invention provides a kind of Novel rhombus false work.
Present invention aim to address some the rhombus false works on existing market, design unreasonable, after connecting each parts of main truss cradle, to utilize from new if disassembled, its connecting hole (through hole) can destroy, and rhombus false work connection box mostly is a steel body structure, Heavy Weight, cost is high, time fixing, multiple workmans to lift, assemble inconvenience, and when installing main truss cradle, it is all in high-altitude, the parts of Heavy Weight, cause the workman of installation abnormally dangerous, imprudence falls down, the problem that will result in serious accident.
nullThe technical solution adopted for the present invention to solve the technical problems is: the present invention includes connecting box、Connecting rod,Described connection box includes the first connection box、Second connects box、3rd connects box and the 4th connects box,Described connecting rod includes head rod、Second connecting rod、3rd connecting rod、4th connecting rod and the 5th connecting rod,Described head rod two end is respectively arranged on the first connection box and the 4th and connects on box,The second described connecting rod two end is respectively arranged on the first connection box and second and connects on box,The 3rd described connecting rod two end is respectively arranged on the first connection box and the 3rd and connects on box,The 4th described connecting rod two end is respectively arranged on the 3rd connection box and the 4th and connects on box,The 5th described connecting rod two end is respectively arranged on the second connection box and the 3rd and connects on box,The first described connection box includes side plate、Base plate、Reinforcing plate、Reinforced sheet and dividing plate,Described side plate includes the first side plate and the second side plate,Described reinforcing plate includes the first reinforcing plate、Second reinforcing plate、3rd reinforcing plate、4th reinforcing plate、5th reinforcing plate and the 6th reinforcing plate,The first described side plate and the second side plate are located on base plate dual side-edge,The first described reinforcing plate、Second reinforcing plate and the 3rd reinforcing plate are respectively arranged between the first side plate outside and base plate;nullThe 4th described reinforcing plate、5th reinforcing plate and the 6th reinforcing plate are respectively arranged between the second side plate outside and base plate,Described reinforced sheet includes the first reinforced sheet、Second reinforced sheet、3rd reinforced sheet、4th reinforced sheet、5th reinforced sheet、6th reinforced sheet、7th reinforced sheet and the 8th reinforced sheet,The first described reinforced sheet、Second reinforced sheet、3rd reinforced sheet and the 4th reinforced sheet are respectively arranged on outside the first side plate,The 5th described reinforced sheet、6th reinforced sheet、7th reinforced sheet and the 8th reinforced sheet are respectively arranged on outside the second side plate,Described dividing plate includes the first dividing plate、Second partition、3rd dividing plate、4th dividing plate and the 5th dividing plate,The first described dividing plate、Second partition、3rd dividing plate、4th dividing plate and the 5th dividing plate are respectively arranged between the first side plate and the second side plate,The first described dividing plate and second partition longitudinally vertical being located between the first side plate and the second side plate,The 3rd described dividing plate transverse horizontal is located on the left of the first dividing plate,The 4th described dividing plate transverse horizontal is located on the right side of second partition,The 5th described dividing plate is the most vertically located between the 3rd dividing plate horizontal stroke and base plate;nullThe 4th described connection box includes metal side plate、Metal base plate、Metal reinforcement strip and metal partion (metp),Described metal side plate includes the first metal side plate and the second metal side plate,The first described metal side plate and the second metal side plate are located on metal base plate dual side-edge,Described metal reinforcement strip includes the first metal reinforcement strip、Second metal reinforcement strip、3rd metal reinforcement strip、4th metal reinforcement strip、Fifth metal reinforced sheet and the 6th metal reinforcement strip,The first described metal reinforcement strip、Second metal reinforcement strip、3rd metal reinforcement strip is respectively arranged on outside the first metal side plate,The 4th described metal reinforcement strip、Fifth metal reinforced sheet、6th metal reinforcement strip is respectively arranged on outside the second metal side plate,Described metal partion (metp) includes the first metal partion (metp)、Second metal partion (metp) and the 3rd metal partion (metp),The first described metal partion (metp)、Second metal partion (metp) and the 3rd metal partion (metp) are respectively arranged between the first metal side plate and the second metal side plate,The first described metal partion (metp) transverse horizontal is located between the first metal side plate and the second metal side plate,Between the second described metal partion (metp) and the most longitudinally perpendicular the first metal side plate being located at the first metal partion (metp) top of the 3rd metal partion (metp) and the second metal side plate;Being respectively equipped with a through hole on described the first metal reinforcement strip, the second metal reinforcement strip, the 3rd metal reinforcement strip, the 4th metal reinforcement strip, fifth metal reinforced sheet and the 6th metal reinforcement strip, the first metal side plate of its correspondence position is provided with the corresponding through hole connected with the second metal side plate;The first described metal side plate and the second metal side plate top are provided with cover plate;Described metal base plate be shorter in length than the first metal side plate and the length of the second metal side plate;nullThe second described connection box includes iron and steel side plate、Iron and steel top board、Iron and steel reinforcing plate、Iron and steel reinforced sheet and iron and steel dividing plate,Described iron and steel side plate includes the first iron and steel side plate and the second iron and steel side plate,Described iron and steel reinforcing plate includes the first iron and steel reinforcing plate and the second iron and steel reinforcing plate,The first described iron and steel side plate and the second iron and steel side plate are located on iron and steel dividing plate dual side-edge outside,The first described iron and steel reinforcing plate、Second iron and steel reinforcing plate is respectively arranged on iron and steel the lower partition,Described iron and steel reinforced sheet includes the first iron and steel reinforced sheet、Second adds the strong sheet of iron and steel、3rd iron and steel reinforced sheet、4th iron and steel reinforced sheet、5th iron and steel reinforced sheet、6th iron and steel reinforced sheet and the 7th iron and steel reinforced sheet,The first described iron and steel reinforced sheet、Second iron and steel reinforced sheet and the 3rd iron and steel reinforced sheet are respectively arranged on outside the first iron and steel side plate,The 4th described iron and steel reinforced sheet、5th iron and steel reinforced sheet and the 6th iron and steel reinforced sheet are respectively arranged on outside the second iron and steel side plate,The 7th described iron and steel reinforced sheet is located on the side of the first iron and steel reinforcing plate,Described iron and steel top board is located at the first iron and steel side plate and the second iron and steel side plate top;The first described iron and steel side plate and the second iron and steel lateral plate structure are identical;Described first adds and is respectively equipped with a through hole on the strong sheet of iron and steel, the second iron and steel reinforced sheet, the 3rd iron and steel reinforced sheet, the 4th iron and steel reinforced sheet, the 5th iron and steel reinforced sheet, the 6th iron and steel reinforced sheet and the 7th iron and steel reinforced sheet, and the first iron and steel side plate of its correspondence position, the second iron and steel side plate and the first iron and steel reinforcing plate are provided with the through hole of corresponding connection.
The first described side plate and the second lateral plate structure are identical, it is respectively equipped with the first angle of chamfer and the second angle of chamfer at the first described side plate and the second side plate top, being provided with the 3rd angle of chamfer on the right side of the first described side plate bottom, the second described angle of chamfer and the 3rd angle of chamfer constitute an obtuse angle.
Being respectively equipped with a through hole on described the first reinforced sheet, the second reinforced sheet, the 3rd reinforced sheet, the 4th reinforced sheet, the 5th reinforced sheet, the 6th reinforced sheet, the 7th reinforced sheet and the 8th reinforced sheet, the first side plate of its correspondence position and the second side plate are provided with the through hole of corresponding connection.
The invention has the beneficial effects as follows: present configuration is reasonable in design, being particularly suitable for the connection of each parts of bridge hanging basket main truss, recycling rate of waterused is high.
Accompanying drawing explanation
Fig. 1 is present configuration schematic diagram.
Fig. 2 is the structural representation that the present invention first connects box.
Fig. 3 is the plan structure schematic diagram of Fig. 2.
Fig. 4 is the A-A structural representation of Fig. 2.
Fig. 5 is that the present invention the 4th connects box structural representation.
Fig. 6 is the A-A structural representation of Fig. 5.
Fig. 7 is the B-B structural representation of Fig. 5.
Fig. 8 is that the present invention second connects box structural representation.
Fig. 9 is the A-A structural representation of Fig. 8.
Figure 10 is the B-B structural representation of Fig. 8.
Figure 11 is the C-C structural representation of Fig. 8.
Figure 12 is the D-D structural representation of Fig. 8.
Detailed description of the invention
The present invention is further described with embodiment below in conjunction with the accompanying drawings:
nullAs shown in the figure,The present invention includes connecting box、Connecting rod,Described connection box includes the first connection box 211、Second connects box 212、3rd connects box 213 and the 4th connects box 214,Described connecting rod includes head rod 311、Second connecting rod 312、3rd connecting rod 313、4th connecting rod 314 and the 5th connecting rod 315,Described head rod 311 2 end is respectively arranged on the first connection box 211 and the 4th and connects on box 214,The second described connecting rod 312 2 end is respectively arranged on the first connection box 211 and second and connects on box 212,The 3rd described connecting rod 313 2 end is respectively arranged on the first connection box 211 and the 3rd and connects on box 213,The 4th described connecting rod 314 2 end is respectively arranged on the 3rd connection box 213 and the 4th and connects on box 214,The 5th described connecting rod 315 2 end is respectively arranged on the second connection box 212 and the 3rd and connects on box 213,The first described connection box 211 includes side plate、Base plate 16、Reinforcing plate、Reinforced sheet and dividing plate,Described side plate includes the first side plate 1 and the second side plate 15,Described reinforcing plate includes the first reinforcing plate 12、Second reinforcing plate 10、3rd reinforcing plate 8、4th reinforcing plate 22、5th reinforcing plate 20 and the 6th reinforcing plate 18,The first described side plate 1 and the second side plate 15 are located on base plate 16 dual side-edge,The first described reinforcing plate 12、Second reinforcing plate 10 and the 3rd reinforcing plate 8 are respectively arranged between the first side plate 1 outside and base plate 16;nullThe 4th described reinforcing plate 22、5th reinforcing plate 20 and the 6th reinforcing plate 18 are respectively arranged between the second side plate 15 outside and base plate 16,Described reinforced sheet includes the first reinforced sheet 11、Second reinforced sheet 3、3rd reinforced sheet 9、4th reinforced sheet 5、5th reinforced sheet 21、6th reinforced sheet 19、7th reinforced sheet and the 8th reinforced sheet 17,The first described reinforced sheet 11、Second reinforced sheet 3、It is outside that 3rd reinforced sheet 9 and the 4th reinforced sheet 5 are respectively arranged on the first side plate 1,The 5th described reinforced sheet 21、6th reinforced sheet 19、It is outside that 7th reinforced sheet and the 8th reinforced sheet 17 are respectively arranged on the second side plate 15,Described dividing plate includes the first dividing plate 3、Second partition 4、3rd dividing plate 13、4th dividing plate 6 and the 5th dividing plate 7,The first described dividing plate 3、Second partition 4、3rd dividing plate 13、4th dividing plate 6 and the 5th dividing plate 7 are respectively arranged between the first side plate 1 and the second side plate 15,The first described dividing plate 3 and second partition 4 longitudinally vertical being located between the first side plate 1 and the second side plate 15,The 3rd described dividing plate 13 transverse horizontal is located on the left of the first dividing plate 3,The 4th described dividing plate 6 transverse horizontal is located on the right side of second partition 4,The 5th described dividing plate horizontal stroke 7 is to being vertically located between the 3rd dividing plate horizontal 6 and base plate 16.nullThe 4th described connection box 214 includes metal side plate、Metal base plate 118、Metal reinforcement strip and metal partion (metp),Described metal side plate includes the first metal side plate 111 and the second metal side plate 121,The first described metal side plate 111 and the second metal side plate 121 are located on metal base plate 118 dual side-edge,Described metal reinforcement strip includes the first metal reinforcement strip 117、Second metal reinforcement strip 119、3rd metal reinforcement strip 116、4th metal reinforcement strip 120、Fifth metal reinforced sheet 123 and the 6th metal reinforcement strip 125,The first described metal reinforcement strip 117、Second metal reinforcement strip 119、It is outside that 3rd metal reinforcement strip 116 is respectively arranged on the first metal side plate 111,The 4th described metal reinforcement strip 120、Fifth metal reinforced sheet 123、It is outside that 6th metal reinforcement strip 125 is respectively arranged on the second metal side plate 121,Described metal partion (metp) includes the first metal partion (metp) 114、Second metal partion (metp) 113 and the 3rd metal partion (metp) 115,The first described metal partion (metp) 114、Second metal partion (metp) 113 and the 3rd metal partion (metp) 115 are respectively arranged between the first metal side plate 111 and the second metal side plate 121,The first described metal partion (metp) 114 transverse horizontal is located between the first metal side plate 111 and the second metal side plate 121,Between the second described metal partion (metp) 113 and the most longitudinally perpendicular the first metal side plate 111 and the second metal side plate 121 being located at the first metal partion (metp) 114 top of the 3rd metal partion (metp) 114.Being respectively equipped with a through hole 122 on described first metal reinforcement strip the 117, second metal reinforcement strip the 119, the 3rd metal reinforcement strip the 116, the 4th metal reinforcement strip 120, fifth metal reinforced sheet 123 and the 6th metal reinforcement strip 125, the first metal side plate 111 of its correspondence position is provided with the corresponding through hole 122 connected with the second metal side plate 121.The first described metal side plate 111 and the second metal side plate 121 top are provided with cover plate 112.Described metal base plate 118 be shorter in length than the first metal side plate 111 and length of the second metal side plate 121;nullThe second described connection box includes iron and steel side plate、Iron and steel top board 132、Iron and steel reinforcing plate、Iron and steel reinforced sheet and iron and steel dividing plate 135,Described iron and steel side plate includes the first iron and steel side plate 131 and the second iron and steel side plate 1313,Described iron and steel reinforcing plate includes the first iron and steel reinforcing plate 138 and the second iron and steel reinforcing plate 136,The first described iron and steel side plate 131 and the second iron and steel side plate 1313 are located on iron and steel dividing plate 135 dual side-edge outside,The first described iron and steel reinforcing plate 138、Second iron and steel reinforcing plate 136 is respectively arranged on iron and steel dividing plate 135 bottom,Described iron and steel reinforced sheet includes the first iron and steel reinforced sheet 139、Second adds the strong sheet of iron and steel 133、3rd iron and steel reinforced sheet 134、4th iron and steel reinforced sheet 1314、5th iron and steel reinforced sheet 1310、6th iron and steel reinforced sheet 1312 and the 7th iron and steel reinforced sheet 137,The first described iron and steel reinforced sheet 139、It is outside that second iron and steel reinforced sheet 133 and the 3rd iron and steel reinforced sheet 134 are respectively arranged on the first iron and steel side plate 131,The 4th described iron and steel reinforced sheet 1314、It is outside that 5th iron and steel reinforced sheet 1310 and the 6th iron and steel reinforced sheet 1312 are respectively arranged on the second iron and steel side plate 1313,The 7th described iron and steel reinforced sheet 137 is located on the side of the first iron and steel reinforcing plate 138,Described iron and steel top board 132 is located on the first iron and steel side plate 131 and the second iron and steel side plate 1313;The first described iron and steel side plate 131 is identical with the second iron and steel side plate 1313 structure;Described first adds and is respectively equipped with a through hole 1311 on the strong sheet of iron and steel, the second iron and steel reinforced sheet, the 3rd iron and steel reinforced sheet, the 4th iron and steel reinforced sheet, the 5th iron and steel reinforced sheet, the 6th iron and steel reinforced sheet and the 7th iron and steel reinforced sheet, and the first iron and steel side plate of its correspondence position, the second iron and steel side plate and the first iron and steel reinforcing plate are provided with the through hole 1311 of corresponding connection.
The first described side plate 1 is identical with the second side plate 16 structure, it is respectively equipped with the first angle of chamfer and the second angle of chamfer at the first described side plate 1 and the second side plate 16 top, being provided with the 3rd angle of chamfer on the right side of the first described side plate bottom, the second described angle of chamfer and the 3rd angle of chamfer constitute an obtuse angle.
Being respectively equipped with a through hole 14 on first described reinforced sheet the 11, second reinforced sheet the 3, the 3rd reinforced sheet the 9, the 4th reinforced sheet the 5, the 5th reinforced sheet the 21, the 6th reinforced sheet the 19, the 7th reinforced sheet and the 8th reinforced sheet 17, the first side plate 1 of its correspondence position is provided with the corresponding through hole 14 connected with the second side plate 15.

Claims (3)

  1. null1. a Novel rhombus false work,It is characterized in that including connecting box、Connecting rod,Described connection box includes the first connection box、Second connects box、3rd connects box and the 4th connects box,Described connecting rod includes head rod、Second connecting rod、3rd connecting rod、4th connecting rod and the 5th connecting rod,Described head rod two end is respectively arranged on the first connection box and the 4th and connects on box,The second described connecting rod two end is respectively arranged on the first connection box and second and connects on box,The 3rd described connecting rod two end is respectively arranged on the first connection box and the 3rd and connects on box,The 4th described connecting rod two end is respectively arranged on the 3rd connection box and the 4th and connects on box,The 5th described connecting rod two end is respectively arranged on the second connection box and the 3rd and connects on box,The first described connection box includes side plate、Base plate、Reinforcing plate、Reinforced sheet and dividing plate,Described side plate includes the first side plate and the second side plate,Described reinforcing plate includes the first reinforcing plate、Second reinforcing plate、3rd reinforcing plate、4th reinforcing plate、5th reinforcing plate and the 6th reinforcing plate,The first described side plate and the second side plate are located on base plate dual side-edge,The first described reinforcing plate、Second reinforcing plate and the 3rd reinforcing plate are respectively arranged between the first side plate outside and base plate;nullThe 4th described reinforcing plate、5th reinforcing plate and the 6th reinforcing plate are respectively arranged between the second side plate outside and base plate,Described reinforced sheet includes the first reinforced sheet、Second reinforced sheet、3rd reinforced sheet、4th reinforced sheet、5th reinforced sheet、6th reinforced sheet、7th reinforced sheet and the 8th reinforced sheet,The first described reinforced sheet、Second reinforced sheet、3rd reinforced sheet and the 4th reinforced sheet are respectively arranged on outside the first side plate,The 5th described reinforced sheet、6th reinforced sheet、7th reinforced sheet and the 8th reinforced sheet are respectively arranged on outside the second side plate,Described dividing plate includes the first dividing plate、Second partition、3rd dividing plate、4th dividing plate and the 5th dividing plate,The first described dividing plate、Second partition、3rd dividing plate、4th dividing plate and the 5th dividing plate are respectively arranged between the first side plate and the second side plate,The first described dividing plate and second partition longitudinally vertical being located between the first side plate and the second side plate,The 3rd described dividing plate transverse horizontal is located on the left of the first dividing plate,The 4th described dividing plate transverse horizontal is located on the right side of second partition,The 5th described dividing plate is the most vertically located between the 3rd dividing plate horizontal stroke and base plate;nullThe 4th described connection box includes metal side plate、Metal base plate、Metal reinforcement strip and metal partion (metp),Described metal side plate includes the first metal side plate and the second metal side plate,The first described metal side plate and the second metal side plate are located on metal base plate dual side-edge,Described metal reinforcement strip includes the first metal reinforcement strip、Second metal reinforcement strip、3rd metal reinforcement strip、4th metal reinforcement strip、Fifth metal reinforced sheet and the 6th metal reinforcement strip,The first described metal reinforcement strip、Second metal reinforcement strip、3rd metal reinforcement strip is respectively arranged on outside the first metal side plate,The 4th described metal reinforcement strip、Fifth metal reinforced sheet、6th metal reinforcement strip is respectively arranged on outside the second metal side plate,Described metal partion (metp) includes the first metal partion (metp)、Second metal partion (metp) and the 3rd metal partion (metp),The first described metal partion (metp)、Second metal partion (metp) and the 3rd metal partion (metp) are respectively arranged between the first metal side plate and the second metal side plate,The first described metal partion (metp) transverse horizontal is located between the first metal side plate and the second metal side plate,Between the second described metal partion (metp) and the most longitudinally perpendicular the first metal side plate being located at the first metal partion (metp) top of the 3rd metal partion (metp) and the second metal side plate;Being respectively equipped with a through hole on described the first metal reinforcement strip, the second metal reinforcement strip, the 3rd metal reinforcement strip, the 4th metal reinforcement strip, fifth metal reinforced sheet and the 6th metal reinforcement strip, the first metal side plate of its correspondence position is provided with the corresponding through hole connected with the second metal side plate;The first described metal side plate and the second metal side plate top are provided with cover plate;Described metal base plate be shorter in length than the first metal side plate and the length of the second metal side plate;nullThe second described connection box includes iron and steel side plate、Iron and steel top board、Iron and steel reinforcing plate、Iron and steel reinforced sheet and iron and steel dividing plate,Described iron and steel side plate includes the first iron and steel side plate and the second iron and steel side plate,Described iron and steel reinforcing plate includes the first iron and steel reinforcing plate and the second iron and steel reinforcing plate,The first described iron and steel side plate and the second iron and steel side plate are located on iron and steel dividing plate dual side-edge outside,The first described iron and steel reinforcing plate、Second iron and steel reinforcing plate is respectively arranged on iron and steel the lower partition,Described iron and steel reinforced sheet includes the first iron and steel reinforced sheet、Second adds the strong sheet of iron and steel、3rd iron and steel reinforced sheet、4th iron and steel reinforced sheet、5th iron and steel reinforced sheet、6th iron and steel reinforced sheet and the 7th iron and steel reinforced sheet,The first described iron and steel reinforced sheet、Second iron and steel reinforced sheet and the 3rd iron and steel reinforced sheet are respectively arranged on outside the first iron and steel side plate,The 4th described iron and steel reinforced sheet、5th iron and steel reinforced sheet and the 6th iron and steel reinforced sheet are respectively arranged on outside the second iron and steel side plate,The 7th described iron and steel reinforced sheet is located on the side of the first iron and steel reinforcing plate,Described iron and steel top board is located at the first iron and steel side plate and the second iron and steel side plate top;The first described iron and steel side plate and the second iron and steel lateral plate structure are identical;Described first adds and is respectively equipped with a through hole on the strong sheet of iron and steel, the second iron and steel reinforced sheet, the 3rd iron and steel reinforced sheet, the 4th iron and steel reinforced sheet, the 5th iron and steel reinforced sheet, the 6th iron and steel reinforced sheet and the 7th iron and steel reinforced sheet, and the first iron and steel side plate of its correspondence position, the second iron and steel side plate and the first iron and steel reinforcing plate are provided with the through hole of corresponding connection.
  2. Novel rhombus false work the most according to claim 1, it is characterized in that the first described side plate and the second lateral plate structure are identical, it is respectively equipped with the first angle of chamfer and the second angle of chamfer at the first described side plate and the second side plate top, being provided with the 3rd angle of chamfer on the right side of the first described side plate bottom, the second described angle of chamfer and the 3rd angle of chamfer constitute an obtuse angle.
  3. Novel rhombus false work the most according to claim 1, it is characterized in that being respectively equipped with a through hole on described the first reinforced sheet, the second reinforced sheet, the 3rd reinforced sheet, the 4th reinforced sheet, the 5th reinforced sheet, the 6th reinforced sheet, the 7th reinforced sheet and the 8th reinforced sheet, the first side plate of its correspondence position and the second side plate are provided with the through hole of corresponding connection.
CN201510384143.1A 2015-07-03 2015-07-03 A kind of Novel rhombus false work Active CN104947602B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN201510384143.1A CN104947602B (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work
CN201610677525.8A CN106284101A (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510384143.1A CN104947602B (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN201610677525.8A Division CN106284101A (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work

Publications (2)

Publication Number Publication Date
CN104947602A CN104947602A (en) 2015-09-30
CN104947602B true CN104947602B (en) 2016-12-07

Family

ID=54162627

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201610677525.8A Pending CN106284101A (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work
CN201510384143.1A Active CN104947602B (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work

Family Applications Before (1)

Application Number Title Priority Date Filing Date
CN201610677525.8A Pending CN106284101A (en) 2015-07-03 2015-07-03 A kind of Novel rhombus false work

Country Status (1)

Country Link
CN (2) CN106284101A (en)

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4928342B2 (en) * 2007-04-27 2012-05-09 株式会社ピーエス三菱 Corrugated steel web bridge erection device and corrugated steel web bridge erection method
CN101586330B (en) * 2008-05-22 2011-01-26 中铁十一局集团第一工程有限公司 Receding construction method of cradle of continuous girder bridge made of prestressing concrete
CN201695346U (en) * 2010-06-25 2011-01-05 中铁五局(集团)有限公司 Combination device adopting hydraulic jack mobile walking suspended cradle
CN201990949U (en) * 2011-03-15 2011-09-28 中国建筑股份有限公司 Axle type advancing device for hanging basket formwork
CN202132663U (en) * 2011-05-20 2012-02-01 陈耀兴 Metal support
CN102352604B (en) * 2011-08-05 2014-01-15 中铁大桥局股份有限公司 Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof
CN202595625U (en) * 2012-03-30 2012-12-12 浙江兴土桥梁建设有限公司 Hanging basket main truss for bridge
JP5546598B2 (en) * 2012-08-31 2014-07-09 今治造船株式会社 Floating body unit, floating body structure assembled by floating body unit, and assembling method of floating body structure
CN203065974U (en) * 2012-12-18 2013-07-17 中国建筑第七工程局有限公司 Walking device of cantilever suspended basket
JP5956967B2 (en) * 2013-09-13 2016-07-27 株式会社安部日鋼工業 Curing method for concrete bridge girder
CN204780636U (en) * 2015-07-03 2015-11-18 金少平 Novel rhombus false work

Also Published As

Publication number Publication date
CN106284101A (en) 2017-01-04
CN104947602A (en) 2015-09-30

Similar Documents

Publication Publication Date Title
CN104088227A (en) Rear pull rod
CN104099877A (en) Connecting bar
CN203834915U (en) Adjustable steel beam suspension operation platform
CN104947602B (en) A kind of Novel rhombus false work
CN204780636U (en) Novel rhombus false work
CN204780637U (en) Novel rhombus false work
CN204780621U (en) Rhombus false work
CN204753401U (en) Rhombus is connecting box for false work
CN204875557U (en) Rhombus false work
CN204780620U (en) Rhombus is connecting box for false work
CN204780619U (en) Rhombus connecting box for false work for bridge
CN204940119U (en) Bridge rhombus false work
CN104963297A (en) Novel rhombic building rack
CN202337339U (en) Scaffold structure for hatch coaming
CN104947596A (en) Rhombic building frame
CN204311356U (en) Connecting rod
CN204311353U (en) A kind of connecting rod
CN204311361U (en) A kind of hanger device
CN105002827A (en) Connecting box for rhombic construction frame
CN104947594A (en) Rhombic construction frame
CN204847843U (en) Hoist traveling carriage bearing structure
CN204311354U (en) Hanger box
CN204311357U (en) A kind of connecting rod side plate
CN204311362U (en) hanger device
CN204325925U (en) A kind of suspension bracket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
CB03 Change of inventor or designer information

Inventor after: Qiu Caijun

Inventor before: Jin Shaoping

COR Change of bibliographic data
TA01 Transfer of patent application right

Effective date of registration: 20161014

Address after: 753000 the Ningxia Hui Autonomous Region Shizuishan District of Dawukou City Hengyuan District 1 Building No. 5 operating room

Applicant after: Shizuishan Hongyu Electronic Technology Co., Ltd.

Address before: No. 52 Qianjin village 314200 Zhejiang province Pinghu city Dushan port Huanggu town

Applicant before: Jin Shaoping

C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191202

Address after: 239300 South of Construction Road and West of Six Road in Tianchang Economic Development Zone, Chuzhou City, Anhui Province

Patentee after: Anhui Changqing Construction Products Co., Ltd.

Address before: 753000 the Ningxia Hui Autonomous Region Shizuishan District of Dawukou City Hengyuan District 1 Building No. 5 operating room

Patentee before: Shizuishan Hongyu Electronic Technology Co., Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Novel rhombic scaffold

Effective date of registration: 20200720

Granted publication date: 20161207

Pledgee: Tianchang vibration financing Company limited by guarantee

Pledgor: ANHUI CHANGQING BUILDING PRODUCTS Co.,Ltd.

Registration number: Y2020980004207

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20210618

Granted publication date: 20161207

Pledgee: Tianchang vibration financing Company limited by guarantee

Pledgor: ANHUI CHANGQING BUILDING PRODUCTS Co.,Ltd.

Registration number: Y2020980004207

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: A new diamond frame

Effective date of registration: 20210629

Granted publication date: 20161207

Pledgee: Tianchang vibration financing Company limited by guarantee

Pledgor: ANHUI CHANGQING BUILDING PRODUCTS Co.,Ltd.

Registration number: Y2021980005477