CN203065974U - Walking device of cantilever suspended basket - Google Patents

Walking device of cantilever suspended basket Download PDF

Info

Publication number
CN203065974U
CN203065974U CN 201220701501 CN201220701501U CN203065974U CN 203065974 U CN203065974 U CN 203065974U CN 201220701501 CN201220701501 CN 201220701501 CN 201220701501 U CN201220701501 U CN 201220701501U CN 203065974 U CN203065974 U CN 203065974U
Authority
CN
China
Prior art keywords
hanging basket
jack
steel strand
walking device
reaction frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201220701501
Other languages
Chinese (zh)
Inventor
陈磊
史少博
张煜
李阳
周支军
陈致昂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN 201220701501 priority Critical patent/CN203065974U/en
Application granted granted Critical
Publication of CN203065974U publication Critical patent/CN203065974U/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a walking device of a cantilever suspended basket. The walking device of the cantilever suspended basket comprises the suspended basket, a horizontally arranged guide rail is arranged at a hanging basket support leg of the lower portion of the hanging basket, and a counterforce frame is arranged at the front end of the guide rail. The counterforce frame reversely buckles the front end of the guide rail, and a through hole is arranged in the counterforce frame. A jack is arranged at the hanging basket support leg and hung on the hanging basket support leg, and the jack is connected with a hydraulic oil pump through an oil pipe. A steel strand is arranged between the counterforce frame and the jack, one end of the steel strand is extruded and fixed by an extrusion sleeve, and the other end of the steel strand sequentially penetrates through the counterforce frame, the hanging basket support leg and the jack. According to the walking device of the cantilever suspended basket, the hydraulic jack is used for dragging the hanging basket to walk, the structure is simple, stress is definite, operation is simple and convenient, and the walking device is safe and reliable. Time consumption in walking is low, labor force is saved, labor intensity is relieved, working efficiency is improved, use cost is reduced, and a construction period can be shortened.

Description

Cantilever Hanging Basket running gear
Technical field
The utility model relates to a kind of cantilever Hanging Basket running gear.
Background technology
The cantilever cradle construction has been widely used in firm structure concrete continuous girder bridge, in Hanging Basket cantilever pouring work progress, Hanging Basket need run to next beam section after a beam section was finished in every construction, traditional construction technology adopts the walking of artificial Chain block traction Hanging Basket, every Hanging Basket walking needs to be equipped with Chain block and 8 workmans of 2 10T, not only labour's input is bigger, inefficiency, and also walking process is consuming time longer.
Summary of the invention
The purpose of this utility model is to provide a kind of employing hydraulic jack to replace the walking of artificial Chain block traction Hanging Basket, effectively alleviated labour intensity, reduced construction cost and alleviated because of artificial Chain block inefficiency to the influence of overall duration of engineering.
The utility model is achieved through the following technical solutions:
A kind of cantilever Hanging Basket running gear comprises Hanging Basket, and the Hanging Basket supporting leg place of described Hanging Basket bottom is provided with horizontally disposed track, and the front end of track is provided with reaction frame, and described reaction frame is the front end of left-hand thread track, and reaction frame is provided with through hole; The place is provided with jack at the Hanging Basket supporting leg, and this jack withstands on the Hanging Basket supporting leg, and is connected with hydraulic oil pump by oil pipe; Be provided with steel strand between reaction frame and jack, an end of steel strand is firm with the extruded sleeve extruding, and the other end passes reaction frame, Hanging Basket supporting leg and jack successively.
The utility model has the advantages that: the utility model is simple, stressed clear and definite, easy and simple to handle, safe and reliable by hydraulic jack traction Hanging Basket walking structure; Walking process less, labor savings consuming time, reduce labor intensity; Increase work efficiency, reduce use cost, can the reduction of erection time; By Pump Control, truss walking in the left and right sides can be carried out synchronously in the walking process; This job practices is comparatively simple, reasonable, control, and efficient height easily.
Description of drawings
Fig. 1 is the structural representation of the utility model reality.
The specific embodiment
Embodiment: cantilever Hanging Basket running gear as shown in the figure, comprise Hanging Basket 7, Hanging Basket supporting leg 3 places of described Hanging Basket 7 bottoms are provided with horizontally disposed track 4, and the front end of track 4 is provided with reaction frame 6, described reaction frame 6 is front ends of left-hand thread track 4, and reaction frame 6 is provided with through hole; 3 places are provided with jack 1 at the Hanging Basket supporting leg, and this jack 1 withstands on the Hanging Basket supporting leg 3, and are connected with hydraulic oil pump 2 by oil pipe 8; Be provided with steel strand 5 between reaction frame 6 and jack 1, an end of steel strand 5 is firm with the extruded sleeve extruding, and the other end passes reaction frame 6, Hanging Basket supporting leg 3 and jack 1 successively.
In Hanging Basket 7 cantilever pouring work progresss, Hanging Basket 7 walkings adopt steel strand 5 one ends to be fixed on the reaction frame 6 of Hanging Basket 7 walking tracks 4 leading portions, make reaction frame 6 left-hand threads moderate at Hanging Basket 7 walking tracks 4 front ends, be unlikely to that the too little left-hand thread of size does not get on or size comes off very much greatly easily.Steel strand 5 cutting lengths need to determine according to Hanging Basket 7 travel distances and Hanging Basket supporting leg 3 positions.Walk forward thereby jack 1 stretch-draw steel strand 5 draw Hanging Basket supporting legs 3 and drive Hanging Basket 7 truss, can reduce labour's input, reduce labor intensity, increase work efficiency, can when guaranteeing construction safety, accelerate speed of application.Track 4 surface layers also can be smeared a little butter, to reduce Hanging Basket supporting leg and interorbital frictional force in Hanging Basket 7 walking processes.Start oil pump, the jack tension steel strand make steel strand traction Hanging Basket supporting leg 3 drive the Hanging Basket truss and walk forward, about traction should keep the speed unanimity by hydraulic oil pump 2 controls, with moved further Hanging Basket 7 and template system to next beam section.Walking process is easy and simple to handle, and only needing to drop into 2, each is artificial, and the overall process time spent was less than 1 hour.
Hanging Basket 7 runs to the suspension rod that forward and backward lower transverse beam is installed behind the assigned address, removes the 5t cucurbit.Suspension is installed, is removed the guide box pulley and it is moved on to next case Liang Yuliukongdongchu and reinstall again.Debugging Hanging Basket 7 and template are installed, and press drawing then and lay reinforcing bar, place built-in fitting and arrange preformed hole, finish the concrete cast.

Claims (1)

1. a cantilever Hanging Basket running gear comprises Hanging Basket, it is characterized in that: the Hanging Basket supporting leg place of described Hanging Basket bottom is provided with horizontally disposed track, and the front end of track is provided with reaction frame, and described reaction frame is the front end of left-hand thread track, and reaction frame is provided with through hole; The place is provided with jack at the Hanging Basket supporting leg, and this jack withstands on the Hanging Basket supporting leg, and is connected with hydraulic oil pump by oil pipe; Be provided with steel strand between reaction frame and jack, an end of steel strand is firm with the extruded sleeve extruding, and the other end passes reaction frame, Hanging Basket supporting leg and jack successively.
CN 201220701501 2012-12-18 2012-12-18 Walking device of cantilever suspended basket Expired - Fee Related CN203065974U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201220701501 CN203065974U (en) 2012-12-18 2012-12-18 Walking device of cantilever suspended basket

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201220701501 CN203065974U (en) 2012-12-18 2012-12-18 Walking device of cantilever suspended basket

Publications (1)

Publication Number Publication Date
CN203065974U true CN203065974U (en) 2013-07-17

Family

ID=48764785

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201220701501 Expired - Fee Related CN203065974U (en) 2012-12-18 2012-12-18 Walking device of cantilever suspended basket

Country Status (1)

Country Link
CN (1) CN203065974U (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947594A (en) * 2015-07-03 2015-09-30 金少平 Rhombic construction frame
CN104947596A (en) * 2015-07-03 2015-09-30 金少平 Rhombic building frame
CN104963297A (en) * 2015-07-03 2015-10-07 金少平 Novel rhombic building rack
CN105040593A (en) * 2015-07-03 2015-11-11 金少平 Rhombus-shaped building frame for bridge
CN106284101A (en) * 2015-07-03 2017-01-04 金少平 A kind of Novel rhombus false work
CN108103955A (en) * 2017-12-11 2018-06-01 中铁十六局集团第三工程有限公司 A kind of bridge cantilever construction load-carrying members Hanging Basket jacking trailer system

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104947594A (en) * 2015-07-03 2015-09-30 金少平 Rhombic construction frame
CN104947596A (en) * 2015-07-03 2015-09-30 金少平 Rhombic building frame
CN104963297A (en) * 2015-07-03 2015-10-07 金少平 Novel rhombic building rack
CN105040593A (en) * 2015-07-03 2015-11-11 金少平 Rhombus-shaped building frame for bridge
CN106284101A (en) * 2015-07-03 2017-01-04 金少平 A kind of Novel rhombus false work
CN108103955A (en) * 2017-12-11 2018-06-01 中铁十六局集团第三工程有限公司 A kind of bridge cantilever construction load-carrying members Hanging Basket jacking trailer system
CN108103955B (en) * 2017-12-11 2024-02-13 中铁十六局集团第三工程有限公司 Hanging basket jacking traction system for bridge cantilever construction bearing structure

Similar Documents

Publication Publication Date Title
CN203065974U (en) Walking device of cantilever suspended basket
CN204174541U (en) Continuous girder bridge suspended casting suspended basket push unit
CN202544854U (en) Lining trolley for subway station
CN201695346U (en) Combination device adopting hydraulic jack mobile walking suspended cradle
CN103758042A (en) Cable compacting machine
CN202116985U (en) Automatic traveling system of hanging basket
CN206667458U (en) The constructing device of vestibule system steel structure girder
CN105863686B (en) Inverted arch formwork hoisting walking carriage
CN203320928U (en) Overhead hanging basket
CN204024079U (en) Prefabricated assembled Metro Station Structure quick tensioning equipment
CN107747399B (en) Hanging basket walking system and working method thereof
CN203430008U (en) Integrally movable type construction platform for cast-in-situ of elevator shaft
CN203715155U (en) Heavy cover plate lifting device
CN105858488A (en) Indoor and outdoor moving hoisting frame for buildings
CN205636520U (en) Jack top pushes away and hangs basket device that moves ahead
CN205711761U (en) A kind of Novel hanging basket of convenience and safety
CN203403683U (en) Double-layer rib penetrating device
CN201913702U (en) Hydraulic demoulding and erecting device for external mold of prefabricated box girder
CN102865086A (en) Full hydraulic needle beam steel mold trolley
CN103752662B (en) Fluid pressure type veneer reeling machine
CN202688889U (en) Walking mechanism for moving hanging basket by using front clamped type jack
CN201981485U (en) Leg replacing mechanism for pier side bracket of bridge pier
CN202194590U (en) Headframe type mechanical and electrical integration workover rig
CN203160140U (en) Hydraulic jack traction gear of traveling-track-free suspension basket on suspension-pouring beam
CN204727495U (en) A kind of large-tonnage cable carries hoisting crane

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130717