CN104942251B - Cast-on time determining method of steel mill continuous casting machines - Google Patents
Cast-on time determining method of steel mill continuous casting machines Download PDFInfo
- Publication number
- CN104942251B CN104942251B CN201510374921.9A CN201510374921A CN104942251B CN 104942251 B CN104942251 B CN 104942251B CN 201510374921 A CN201510374921 A CN 201510374921A CN 104942251 B CN104942251 B CN 104942251B
- Authority
- CN
- China
- Prior art keywords
- time
- casting
- amount
- casting machine
- water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- General Factory Administration (AREA)
Abstract
The invention provides a cast-on time determining method of steel mill continuous casting machines. The method comprises the steps that a cast-on decision controller is connected with a manufacturing execution system (MES) database of a steel mill and an MES client side system; a target function of a cast-on decision is established, the to-be-cast-on frequency and left task restraint condition, the constraint condition about whether continuous casting is needed during the to-be-cast-on frequency, the constraint condition between the to-be-cast-on frequency time and the planned period starting and ending time, the amount of redundant metal besides the needed metal amount planned to need to be finished in the task period on a production line, and other constraint conditions are established, and the established known physical quantity and parameter values are obtained; the cast-on time shown in the specification of a jth cast-on time of an ith casting machine in a kth planned period is obtained through an optimal solver. Whether the to-be-cast-on frequency of the continuous casting machines is continuous or not can be judged, the cast-on time can be scientifically calculated, a foundation is laid for formulating a reasonable steel mill production dispatching operation plan, the production running among shifts can be stabilized, and the amount of accumulated metal is reduced.
Description
Technical field
The present invention relates to technical field of metallurgical control, be specifically related to the casting time side of determination of a kind of steel plant continuous casting machine
Method.
Background technology
Conticaster casting time decision-making (Casting start time decision of continuous caster,
CSDCC) the very corn of a subject task determines that whether conticaster respectively time even can water and time concrete opening is watered with front watering wait opening to water time
Between.Conticaster waits to open that to water rationally determining of time casting time be the precondition of establishment steel smelting-continuous casting production schedules.Mesh
Before, in actual production, steel-making continuous casting production schedules is typically to have worked out after manually being determined casting time by dispatcher
Becoming, the science of casting time and reasonability become the key factor that can restriction steel mill production schedules be implemented smoothly.Cause
This research CSDCC problem has important realistic meaning.
The metals resources amount balance of the molten iron/molten steel on steel mill production line is that the important bar watering decision-making effectiveness is opened in impact
Part.In recent years, the planned dispatching problem that domestic and international experts and scholars produce for steel smelting-continuous casting is widely paid close attention to, and research obtains substantially
Progress.In the research relevant to conticaster casting time, Hubert M etc. devises one and utilizes the circulation of known iron water amount repeatedly
In generation, calculates the dispatching algorithm of casting time;The round grade of Tan have studied including watering and time opening and to water etc. from minimum power consumption angle
Schedule job Time Calculation method;Wang Chuan etc. propose and solve other under assuming certain conticaster casting time known case even
The method of the casting time of casting machine.But, at present research, can the big multipair conticaster that affects connect the factor watered according to plan and enter
Go simplification process, research emphasis has been concentrated on the preparation method side of production schedules being analyzed time factor processing
Face, is not directed to molten iron on the production line affecting casting time/molten steel metals resources be balanced each factor and opens the relation watering decision-making
Research, thus constrain the real world applications effect of steel-making continuous casting Production Scheduling Study on Problems achievement.
Summary of the invention
In order to overcome defect present in above-mentioned prior art, it is an object of the invention to provide a kind of steel plant continuous casting machine
Casting time determines that method, the method are capable of conticaster and water the scientific algorithm of time casting time.
In order to realize the above-mentioned purpose of the present invention, according to an aspect of the present invention, the invention provides a kind of steel mill
The casting time of conticaster determines method, and it comprises the steps:
S1, controller is connected with manufacturing execution system (MES) data base and the MES FTP client FTP of steel mill respectively;
S2, sets up to open and waters objective function of decision-making, and described object function is:
Wherein, k is plan phase sequence number, k ∈ 1,2 ..., and Ω }, Ω is plan phase sum;I is casting machine serial number, i ∈ 1,
2 ..., H}, H are casting machine sum;J for watering sequence number, It is that the i-th casting machine waters time sum;ρ is molten steel
Density;η is metal loss factor;q0Steel amount is averagely watered for each heat;Whole process average stream time kth plan phase;For
Start time kth plan phase;For finish time kth plan phase;Cast for kth plan phase the i-th casting machine jth casting plan
Stove number;Time minimum interval is watered for kth plan phase the i-th casting machine jth;Water secondary leaving over for kth plan phase the i-th casting machine jth to appoint
Business finish time;Time legacy tasks average pull rate is watered for kth plan phase the i-th casting machine jth;Cast for the kth plan phase i-th
Machine jth waters time casting cycle;Wait to open for kth plan phase the i-th casting machine jth and water time average pull rate;For the kth plan phase i-th
Casting machine jth waters time legacy tasks basal area;Wait to open for kth plan phase the i-th casting machine jth and water subtask basal area;It is
K plan phase the i-th casting machine jth is watered time legacy tasks and is watered steel amount;C1 is benefit coefficient;C2 is cost coefficient;For the kth plan phase
Enter iron, for known quantity;For stock's amount of metal that kth plan is initial, for known quantity;For overstocking of the kth plan end of term
Amount of metal, for Unknown Process variable;For the line safety inventory amount of metal of kth plan phase, for Unknown Process variable;For kth
Plan phase metal loss amount, for Unknown Process variable;Steel amount is watered, for Unknown Process variable for the kth plan phase;For kth meter
Draw phase the i-th casting machine jth to wait to open to water time to open and water the moment, for unknown number to be asked;
Formula (1) represents that object function is deducted the cost structure of overstocked amount of metal by serialization degree income;Formula (2) represents even
Continuousization degree (Θk) water time casting time sum divided by H platform even equal to the legacy tasks casting time of each conticaster with waiting to open
Time plan phase that casting machine is total;(3) overstocked amount of metal is representedIron is entered respectively by this plan phaseOpening inventory
Amount of metalSafety on line stock's amount of metalMetal loss amountWater steel amountRelation constitute;Formula
(4) the expression plan phase adds up to water steel amount and time waters steel amount sum equal to the legacy tasks amount of each conticaster with waiting to open to water;Formula (5) table
Show that the H platform conticaster unit interval within the plan phase averagely waters steel amountEqual to accumulative steel amount of watering divided by plan phase length;Formula
(6) represent when planning phase metal loss factor and being known, accumulative metal loss amount and the accumulative mutual relation watering steel amount;Formula (7)
Represent when averagely watering the steel amount average line stock amount of metal of calculating with the unit intervalTime, it should utilize metal loss factor η
It is converted to the iron water amount of respective numbers;Formula (8) represents that safety on line stock's amount of metal needs at average line stock metal
A random fluctuation demand amount of metal is added on the basis of amount
S3, set up wait to open water time and legacy tasks constraints, wait to open whether connect between watering time water constraints, respectively treat
Open time time of watering and plan beginning and ending time phase constraints and the constraints of overstocked amount of metal,
S4, controller obtains each known quantity parameter in step S2 by MES data storehouse and full factory each MES FTP client FTP
Value;
S5, according to the exploitation intermediate variable of known quantity parameter in step S4, described intermediate variable includes respectively waiting to open watering
Secondary casting cycle, each casting machine legacy tasks casting time, each casting machine single bit time water steel amount, collects metal loss factor, whole
Overstock in amount of metal formula coefficient before real number decision variable after reason, arrange after coefficient before Real-valued decision variable;
S6, determines each coefficient of object function according to the intermediate variable that step S5 obtains, and waters secondary for the i-th conticaster jth,
Order:
F (i, j)=f (i, j)+arrange after before Real-valued decision variable coefficient × conticaster i jth water time casting time x (i,
J), (i, j), ((i, j), wherein, (i is j) that Real-valued defined in matlab becomes to sdpvar to described x for i, j)=sdpvar to make p=f
The function of amount;
S7, determines the restriction relation in step S3 according to the intermediate variable that step S5 obtains;
S8, utilizes Optimization Solution device solvesdp (F ,-p), obtain kth plan phase the i-th casting machine jth wait open water time open water time
CarveAnd whether connect, between watering time, the parameter wateredWherein, solvesdp () is matlab majorized function, and F is that total constraint is closed
System, object function identifier total when being maximizing for-p;
S9, controller is according to obtainingData carry out the shop job scheduling of steel smelting-continuous casting production, and to life
Produce operation system to implement effectively to control.
The angle of molten iron/molten steel metals resources balance that the present invention is to be processed from steel mill's production line, establishes with continuous casting
Produce total benefit to be the conticaster of object function to the maximum and open and water the mixed integer programming algorithm of decision-making and solve.It is capable of continuous casting
Machine waters the scientific algorithm of time casting time, lays the foundation for working out rational production schedule of steelmaking plant production plan, also contributes to
Stablize the production run between each order of classes or grades at school, reduce the overstocked amount of metal on production line, opening in order to water and carry for steel plant continuous casting machine
Supply technological means.
In the preferred embodiment of the present invention, in described step S3, constraints is:
1) respectively wait to open the company between watering time and water relation constraint:
Wherein,For binary variable, 1 represents that kth plan phase the i-th casting machine jth is watered secondary company with legacy tasks and watered, and 0 represents
Break and water,For unknown number to be asked;
F1: when judge wait open water time whether connect between legacy tasks water time, in formula (9)
Formula (9-10) represent when wait open water time even water with legacy tasks time, casting time point takes legacy tasks finish time,
Non-company takes legacy tasks finish time and terminates certain moment to the plan phase plus watering the minor tick time when watering;Formula (11) represents kth meter
Draw i-th conticaster jth of phase and water the difference that time legacy tasks amount plans equal to this casting machine previous plan phase to water steel amount with casting amount
Value;
F2: when decision-making remaining respectively wait open water time between whether connect water time, in formula (9)
Formula (9), (12) represent when except remaining adjacent with legacy tasks respectively wait open water that time interconnection is watered mutually time, this casting time
Point waters time finish time before taking, and non-company waters time finish time and terminates the some time to the plan phase plus watering the minor tick time before taking when watering
Carve;
F3: respectively wait to open time time of watering and plan beginning and ending time phase relation constraint condition:
F4: overstocked amount of metal constraints:
In the preferred embodiment of the present invention, the intermediate variable obtained in described step S5 is:
Respectively wait to open and water the stove number * average Metal Weight of each stove in time casting cycle=respectively wait to open waters time/(wait to open and water time pulling rate *
Wait to open and water time basal area * molten steel density);
Each casting machine legacy tasks casting time=each casting machine legacy tasks molten steel amount/(each casting machine legacy tasks pulling rate * respectively casts
Machine legacy tasks basal area * molten steel density);
Each casting machine single bit time waters steel amount=water time pulling rate * and waters time basal area * molten steel density;
The metal loss factor collected=(1+ metal loss factor/(1-metal loss factor)+whole process logistics time/
((plan finish time phase-start time plan phase) * (1-metal loss factor));
After arrangement, in overstocked amount of metal formula, before real number decision variable, coefficient=-each casting machine single bit time waters steel amount * and collects
Metal loss factor;
Constant term in amount of metal constraint formulations=estimate into ferrum total amount+opening inventory iron-stochastic demand is overstock after arrangement
The metal loss factor * of stock's amount of metal-collect (respectively wait to open and water time casting by each casting machine legacy tasks molten steel amount sum+each casting machine
Cycle * each casting machine single bit time waters steel amount+plan phase finish time * each casting machine single bit time and waters steel amount sum);
During metal loss factor * each casting machine unit that after arrangement, before Real-valued decision variable, coefficient=cost coefficient * collects
Between water steel amount+income coefficient/((plan finish time phase-start time plan phase) * conticaster number).
In the another kind of preferred implementation of the present invention, described intermediate variable set-up procedure S3 obtained according to step S5
In the method for restriction relation be:
1) watering time for the i-th conticaster the 1st, make F1 (1,1)=0, i=1,2 ..., H, described H is positive integer;
F1 (i, j)=F1 (i, j)+set (casting machine i legacy tasks casting time+casting machine i water time between minimum time interval * casting
First binary variable y of machine i (i, 1)≤first casting time x of casting machine i (i, 1)≤casting machine i legacy tasks casting time
+ (plan finish time phase-casting machine i legacy tasks first binary variable y of casting time * casting machine i (i, 1)), wherein, y (i,
1) corresponding in constraints(i, j) corresponding in constraints for yX (i, 1) is corresponding in constraints
(i, j) corresponding in constraints for xSet () be MATLAB YALMIP optimization tool in constraints function is set;
2) the i-th conticaster jth is watered time, make F2 (1,2)=0, i=1,2 ..., H,
F2 (i, j)=F2 (i, j)+set ((casting machine i jth-1 casting time x (i, j-1)+casting machine i water time casting cycle)+
Casting machine i water time between minimum time interval * casting machine i jth binary variable y (i, j)≤casting machine i jth casting time x (and i, j) <
=(casting machine i jth-1 casting time x (i, j-1)+casting machine i waters time casting cycle)+(plan finish time phase-(casting machine i jth-1
Casting time x (i, j-1)+casting machine i waters time casting cycle)+casting machine i jth binary variable y (i, j)));
3) the i-th conticaster jth is watered time, make F3 (1,1)=0, i=1,2 ..., H, X (i, j)≤plan start time phase);
4) the i-th conticaster jth is watered time, make F4 (1,1)=0, i=1,2 ..., H,
((i, j)+set (overstocks in amount of metal formula coefficient * conticaster i before real number decision variable to F4 after arrangement for i, j)=F4
Jth waters time casting time x (i overstocks constant term in amount of metal constraint formulations after j)≤arrangement);
5) F1=F1 (i, j), F2=F2 (i, j), F3=F3 (i, j), F4=F4 (i, j);
Total restriction relation: F=F1+F2+F3+F4.
By arrange constraints F1 (i, j), F2 (i, j), F3 (i, j), it is possible to achieve under different task state accurately
Determining the casting time of each steel plant continuous casting machine, by arranging constraints F4, (i j) may insure that between the adjacent plan phase not
The fluctuation of stock's amount of metal occur, the continuous casting production for equalization stable creates favorable conditions.
The additional aspect of the present invention and advantage will part be given in the following description, and part will become from the following description
Obtain substantially, or recognized by the practice of the present invention.
Accompanying drawing explanation
Above-mentioned and/or the additional aspect of the present invention and advantage are from combining the accompanying drawings below description to embodiment and will become
Substantially with easy to understand, wherein:
Fig. 1 is steel smelting-continuous casting production process schematic diagram in prior art;
Fig. 2 is molten iron/molten steel equilibrium of stock relationship change schematic diagram;
Fig. 3 is the casting time Gantt chart of actual design decision-making;
Fig. 4 be the design for Fig. 3 utilize that the method for the present invention is optimized by the casting time Gantt chart of class's decision-making;
Fig. 5 is the casting time Gantt chart of the per diem decision-making that the design for Fig. 3 utilizes the method for the present invention to be optimized.
Detailed description of the invention
Embodiments of the invention are described below in detail, and the example of described embodiment is shown in the drawings, the most from start to finish
Same or similar label represents same or similar element or has the element of same or like function.Below with reference to attached
The embodiment that figure describes is exemplary, is only used for explaining the present invention, and is not considered as limiting the invention.
Fig. 1 is 3 production links that existing steel smelting-continuous casting process mainly comprises: steel-making, refine and continuous casting.Make steel and connect
The casting each self-contained parallel unit of link, and refine link generally comprises multiple parallel unit, to realize different refinery practice
Requirement.General steel smelting-continuous casting production process is as shown in Figure 1: the high temperature liquid iron shipped from blast furnace is through hot metal pre process procedures
After be blended in converter smelting becomes the ladle that molten steel, molten steel are poured under converter on chassis, by overhead traveling crane and the hauling operation of chassis,
Steel ladle is transported to refine link, and the refined molten steel on different refining equipments successively according to manufacturing technique requirent, refine completes
After, then by overhead traveling crane and chassis, steel ladle be transported to continuous casting and implement casting, forming strand.
In steel mill's production scheduling, heat refers to the molten steel that certain converter produces in a smelting cycle, due to one
The molten steel of heat is loaded in a ladle, so the object being scheduled before steel-making to continuous casting is heat, heat is steel mill
Production unit minimum in production scheduling.Water the secondary heat set referring to direct casting on same conticaster, be that steel mill produces
Production unit maximum in scheduling.Steel smelting-continuous casting scheduling scheme formulates flow process: first turned according to technical standard by user's contract
Turn to production contract;Then according to the establishment charging plan such as steel capacity and technological requirement and casting plan, and heat is combined
Roll the establishment hot rolling modular plan such as rolling power and technological requirement, form steel-making and produce, with hot rolling, the production lot meter coordinated mutually
Draw.In Production Lot Planning, it has been determined that water secondary casting casting machine and water time processing sequence of interior heat and production work
Skill.The research contents of the present invention is namely based on Production Lot Planning and steel mill MES data storehouse, opening of research steel plant continuous casting machine
Water the time.
In practical situation, steel mill typically has some conticasters, carry out conticaster in time opening opening of watering time and water decision-making,
The present invention turns to target with the comprehensive benefit maximum of decision-making, i.e. from the cost minimization of the overstocked amount of metal controlled production line with make
The serialization degree Income Maximum of conticaster considers.
The metals resources equilibrium condition of the molten iron/molten steel on production line can affect the casting time of conticaster and run shape
State.In order to quantify and the metals resources relevant influence factor of balance, carry out Unify legislation with overstocked amount of metal and constituent relation formula thereof:
[overstocking amount of metal]=[initial line stock amount of metal]+[adding up into iron]-[adding up to water steel amount]-[accumulative metal loss
Amount]-[end of term safety on line stock amount of metal].If it is excessive to overstock amount of metal, then waters decision objective disagree, if being less than with opening
Zero, entail dangers to end of term safety on line stock amount of metal and the direct casting of next plan phase conticaster, ensureing enough peaces again
In the case of full stock's amount of metal, the lower limit of overstocked amount of metal is controlled standard and is set to zero by the present invention.Add up in the plan phase to water steel
Amount waters steel amount sum for each conticaster, and separate unit conticaster waters steel amount and watered steel amount and this meter by previous plan phase legacy tasks respectively
Draw expectation to open to water and time water steel amount and constitute.
It is relevant that accumulative metal loss amount adds up to water steel amount with the plan phase.Calculate for simplifying, present invention assumes that plan phase metal
Loss factor is equal to metal loss factor known to the previous plan phase, then this plan phase adds up metal loss amount and is represented by: tired
Meter metal loss amount=loss factor × add up to water steel amount/(1-loss factor).
Safety on line stock's amount of metal is made up of average line stock amount of metal and random fluctuation demand two parts amount of metal,
Wherein, average line stock amount of metal formula " average inventory=mean unit time output × average flow time " calculates;
Random fluctuation demand amount of metal embodies and need to consider because the change at random factors such as casting cycle, pulling rate, flow sheet equipment fault cause
The demand to metals resources more than the part of average computation value, calculate for simplifying, be empirically taken as constant.Fig. 2 is
Molten iron/molten steel equilibrium of stock relationship change schematic diagram.
For the conticaster serialization extent description in decision objective be: serialization degree=each casting machine activity duration it
With/(during opening casting machine quantity × plan).
Accordingly, content of policy decision and the optimization aim of CSDCC problem are specified.In the present embodiment, ask for beneficially problem
Solve, make following basic assumption:
(1) within the plan phase, each conticaster waits to open that to water sub-quantity known, waters phenomenon with occurring without unplanned stopping in watering time;
(2) the plan phase enters ferrum total amount and can predict, and each conticaster waters order limit without preferentially connecting.
The casting time that the invention provides a kind of steel plant continuous casting machine determines method, and it comprises the steps:
S1, opens and waters decision controller and be connected with the MES data storehouse of steel mill and full factory each MES FTP client FTP respectively;
S2, sets up to open and waters objective function of decision-making, and object function is:
Wherein, k is plan phase sequence number, k ∈ 1,2 ..., and Ω }, Ω is plan phase sum;I is casting machine serial number, i ∈ 1,
2 ..., H}, H are casting machine sum;J for watering sequence number, It is that the i-th casting machine waters time sum;ρ is
Molten steel density;η is metal loss factor;q0Steel amount is averagely watered for each heat;Whole process average stream time kth plan phase;For start time kth plan phase;For finish time kth plan phase;For kth plan phase the i-th casting machine jth casting plan
Casting furnace number;Time minimum interval is watered for kth plan phase the i-th casting machine jth;Time something lost is watered for kth plan phase the i-th casting machine jth
Remain in office business finish time;Time legacy tasks average pull rate is watered for kth plan phase the i-th casting machine jth;For the kth plan phase
I casting machine jth waters time casting cycle;Wait to open for kth plan phase the i-th casting machine jth and water time average pull rate;For the kth plan phase
I-th casting machine jth waters time legacy tasks basal area;Wait to open for kth plan phase the i-th casting machine jth and water subtask basal area;
Water time legacy tasks for kth plan phase the i-th casting machine jth and water steel amount;C1 is benefit coefficient;C2 is cost coefficient;For kth meter
Draw the phase enter iron, for known quantity;For stock's amount of metal that kth plan is initial, for known quantity;For the kth plan end of term
Overstock amount of metal, for Unknown Process variable;For the line safety inventory amount of metal of kth plan phase, for Unknown Process variable;
For kth plan phase metal loss amount, for Unknown Process variable;Steel amount is watered, for Unknown Process variable for the kth plan phase;For
Kth plan phase the i-th casting machine jth is waited to open to water time to open and is watered the moment, for unknown number to be asked.
Formula (1) represents that object function is deducted the cost structure of overstocked amount of metal by serialization degree income, wherein: benefit system
Number C1The continuous casting zone ton steel energy medium brought, middle Bao Naicai, auxiliary material etc. can be improved from serialization degree and consume minimizing,
And labor productivity raising brings the factors such as cost of labor saving to be calculated reference value;Cost coefficient C2Can unite from steel mill
Count in the average ton steel production cost in storehouse because molten iron/molten steel overstocks the power consumption cost of the LF operation intensification that wait is caused
Increase relation etc. calculates.
Formula (2) represents serialization degree ΘkTime casting is watered with waiting to open equal to the legacy tasks casting time of each conticaster
Time sum is divided by H platform conticaster total time plan phase.
Formula (3) represents overstocked amount of metalIron is entered respectively by this plan phaseOpening inventory amount of metalOnline
Safety inventory amount of metalMetal loss amountWater steel amountRelation constitute, wherein For known parameters.
Formula (4) the expression plan phase add up to water steel amount equal to each conticaster legacy tasks amount with wait to open water time water steel amount it
With.
Formula (5) represents that the H platform conticaster unit interval within the plan phase averagely waters steel amountEqual to accumulative water steel amount divided by
Plan phase length.
Formula (6) represents that, when planning phase metal loss factor and being known, accumulative metal loss amount waters the mutual of steel amount with accumulative
Relation.
Formula (7) represents when averagely watering the steel amount average line stock amount of metal of calculating with the unit intervalTime, it should utilize gold
Belong to loss factor η and be converted to the iron water amount of respective numbers.
Formula (8) represents that safety on line stock's amount of metal needs to add one on the basis of average line stock amount of metal at random
Variation demand amount of metal
S3, set up wait to open water time and legacy tasks constraints, wait to open whether connect between watering time water constraints, respectively treat
Open time time of watering and plan beginning and ending time phase constraints and the constraints of overstocked amount of metal, in the present embodiment, about
Bundle condition is:
1) respectively wait to open the company between watering time and water relation constraint:
Wherein,For binary variable, 1 represents that kth plan phase the i-th casting machine jth is watered secondary company with legacy tasks and watered, and 0 represents
Break and water,For unknown number to be asked;
F1: when judge wait open water time whether connect between legacy tasks water time, in formula (9)
Formula (9-10) represent when wait open water time even water with legacy tasks time, casting time point takes legacy tasks finish time,
Non-company takes legacy tasks finish time and terminates certain moment to the plan phase plus watering the minor tick time when watering;Formula (11) represents kth meter
Draw i-th conticaster jth of phase and water the difference that time legacy tasks amount plans equal to this casting machine previous plan phase to water steel amount with casting amount
Value;
F2: when decision-making remaining respectively wait open water time between whether connect water time, in formula (9)
Formula (9), (12) represent when except remaining adjacent with legacy tasks respectively wait open water that time interconnection is watered mutually time, this casting time
Point waters time finish time before taking, and non-company waters time finish time and terminates the some time to the plan phase plus watering the minor tick time before taking when watering
Carve;
F3: respectively wait to open time time of watering and plan beginning and ending time phase relation constraint condition:
F4: overstocked amount of metal constraints:
S4, opens and waters MES data storehouse that decision controller passes through and MES FTP client FTP obtains each known quantity ginseng in step S2
The value of number;
S5, according to the exploitation intermediate variable of known quantity parameter in step S4, described intermediate variable includes respectively waiting to open watering
Secondary casting cycle, each casting machine legacy tasks casting time, each casting machine single bit time water steel amount, collects metal loss factor, whole
Overstock in amount of metal formula coefficient before real number decision variable after reason, arrange after coefficient before Real-valued decision variable.
In the present embodiment, it is thus achieved that intermediate variable be:
Respectively wait to open and water the stove number * average Metal Weight of each stove in time casting cycle=respectively wait to open waters time/(wait to open and water time pulling rate *
Wait to open and water time basal area * molten steel density);
Each casting machine legacy tasks casting time=each casting machine legacy tasks molten steel amount/(each casting machine legacy tasks pulling rate * respectively casts
Machine legacy tasks basal area * molten steel density);
Each casting machine single bit time waters steel amount=water time pulling rate * and waters time basal area * molten steel density;
The metal loss factor collected=(1+ metal loss factor/(1-metal loss factor)+whole process logistics time/
((plan finish time phase-start time plan phase) * (1-metal loss factor));
After arrangement, in overstocked amount of metal formula, before real number decision variable, coefficient=-each casting machine single bit time waters steel amount * and collects
Metal loss factor;
Constant term in amount of metal constraint formulations=estimate into ferrum total amount+opening inventory iron-stochastic demand is overstock after arrangement
The metal loss factor * of stock's amount of metal-collect (respectively wait to open and water time casting by each casting machine legacy tasks molten steel amount sum+each casting machine
Cycle * each casting machine single bit time waters steel amount+plan phase finish time * each casting machine single bit time and waters steel amount sum);
During metal loss factor * each casting machine unit that after arrangement, before Real-valued decision variable, coefficient=cost coefficient * collects
Between water steel amount+income coefficient/((plan finish time phase-start time plan phase) * conticaster number).
S6, determines each coefficient of object function according to the intermediate variable that step S5 obtains, and waters secondary for the i-th conticaster jth,
Order:
F (i, j)=f (i, j)+arrange after before Real-valued decision variable coefficient × conticaster i jth water time casting time x (i,
J), (i, j), ((i, j), wherein, (i is j) that Real-valued defined in matlab becomes to sdpvar to described x for i, j)=sdpvar to make p=f
The function of amount;
S7, determines the restriction relation in step S3 according to the intermediate variable that step S5 obtains.Particularly as follows:
1) watering time for the i-th conticaster the 1st, make F1 (1,1)=0, i=1,2 ..., H, described H is positive integer;
F1 (i, j)=F1 (i, j)+set (casting machine i legacy tasks casting time+casting machine i water time between minimum time interval * casting
First binary variable y of machine i (i, 1)≤first casting time x of casting machine i (i, 1)≤casting machine i legacy tasks casting time
+ (plan finish time phase-casting machine i legacy tasks first binary variable y of casting time * casting machine i (i, 1)), wherein, y (i,
1) corresponding in constraints(i, j) corresponding in constraints for yX (i, 1) is corresponding in constraints(i, j) corresponding in constraints for xSet () be MATLAB YALMIP optimization tool in constraints letter is set
Number;
2) the i-th conticaster jth is watered time, make F2 (1,2)=0, i=1,2 ..., H,
F2 (i, j)=F2 (i, j)+set ((casting machine i jth-1 casting time x (i, j-1)+casting machine i water time casting cycle)+
Casting machine i water time between minimum time interval * casting machine i jth binary variable y (i, j)≤casting machine i jth casting time x (and i, j) <
=(casting machine i jth-1 casting time x (i, j-1)+casting machine i waters time casting cycle)+(plan finish time phase-(casting machine i jth-1
Casting time x (i, j-1)+casting machine i waters time casting cycle)+casting machine i jth binary variable y (i, j)));
3) the i-th conticaster jth is watered time, make F3 (1,1)=0, i=1,2 ..., H,
F3 (i, j)=F3 (i, j)+set (plan finish time phase≤conticaster i jth water time casting time x (i, j)≤
Start time plan phase);
4) the i-th conticaster jth is watered time, make F4 (1,1)=0, i=1,2 ..., H,
((i, j)+set (overstocks in amount of metal formula coefficient * conticaster i before real number decision variable to F4 after arrangement for i, j)=F4
Jth waters time casting time x (i overstocks constant term in amount of metal constraint formulations after j)≤arrangement);
5) F1=F1 (i, j), F2=F2 (i, j), F3=F3 (i, j), F4=F4 (i, j);Total restriction relation: F=F1+
F2+F3+F4。
S8, utilizes Optimization Solution device solvesdp (F ,-p), obtain kth plan phase the i-th casting machine jth wait open water time open water time
CarveAnd whether connect, between watering time, the parameter wateredWherein, solvesdp () is matlab majorized function, and F is total restriction relation
Identifier, object function identifier total when being maximizing for-p;
S9, controller is according to obtainingData carry out the shop job scheduling of steel smelting-continuous casting production, and to life
Produce operation system to implement effectively to control.
Owing to CSDCC problem comprises real number decision variable simultaneouslyWith 0-1 decision variableBelong to mixed integer programming to ask
Topic, and solvesdp is exactly the function solving above decision problem.Solvesdp function can be by input model target letter
Number, constraints, variable quantity and classification, the identification of the feature such as independence of variable, solve MIXED INTEGER in auto-call library
Special solved function BNB20 of planning is consistent with the method for solving needed for CSDCC problem.
It is as follows that its branch and bound method used (function BNB20) solves CSDCC problem principle:
The first step. arranging initial continuous casting and producing total benefit is f=-∞, by the 0-1 decision variable of former CSDCC problemPine
The continuous variable that relaxation is 0-1 scope, solves the optimal solution of the CSDCC* problem after relaxing, if each solvedComponent is all 0
Or 1 value, then in this solutionBe exactly CSDCC problem optimum respectively wait to open water time casting time and water time between connect the state of watering.
Target function value is both to have obtained continuous casting to produce total benefit.
If second step. in solution at least oneValue b of variable (i, j)kFor non-zero or 1, then to b (i, j)kRound nearby
[b(i,j)]k, and to CSDCC problem addition of constraints respectivelyNew to form two
CSDCC* ', CSDCC* " problem, the most respectively by continuous variable to CSDCC* ', CSDCC* " seek optimal solution.
3rd step. by current solution CSDCC* ', CSDCC* " continuous casting that obtains produce total benefit with both continuous casting produces total
Benefit comparison, finds out the maximum and produces, as continuous casting, the upper bound f*. that total benefit is new
If the 4th step. CSDCC* ', CSDCC* " continuous casting produce in total benefit and have less than f*, then cut this branch;If
More than or equal to f* butDo not meet 0 or 1 value, then repeat the continuation of second step method rightVariable branch. until all ofIt is all
0 or 1 value, nowBe exactly CSDCC problem respectively wait to open water time casting time and water time between connect the state of watering, f* is
Excellent continuous casting produces total benefit.As can be seen here, those skilled in the art utilize the method for the present invention just can accurately obtain kth plan
Phase the i-th casting machine jth is waited to open to water time to open and is watered the moment
The angle of molten iron/molten steel metals resources balance that the present invention is to be processed from steel mill's production line, establishes with continuous casting
Produce total benefit to be the conticaster of object function to the maximum and open and water the mixed integer programming algorithm of decision-making and solve.It is capable of continuous casting
Machine waters the scientific algorithm of time casting time, contributes to working out rational production schedule of steelmaking plant production plan, stablize each order of classes or grades at school it
Between working condition, reduce the overstocked amount of metal on production line, opening in order to water and provide technological means for steel plant continuous casting machine.
In a preferred embodiment of the present invention, open with certain steel plant continuous casting machine domestic and water decision-making real data as reality
Example, carries out the application validity check of algorithm. and compare analysis with producing actual decision-making (by manually determining in production) result.
Example enterprises has 5 conticasters, and in production, CSDCC is by manually determining.Take the creation data of 3 continuous teams and groups such as
Under: ρ=7.1t/
m3、 C1=43.5 yuan/1%, C2
=1.8 yuan/t, each class conticaster parameter is as shown in table 1, wherein, and NoFor casting machine number, gr1For teams and groups number.When the opening of actual decision-making is watered
Between Gantt chart as shown in Figure 3, using this as the basis of inventive algorithm results contrast.
Experiment point two groups: one group is with teams and groups' activity duration for the plan phase, and each conticaster of each teams and groups waters steel and always water number of times, enter
Iron is identical with producing reality, is called for short by class's decision-making;Another group is with the whole day activity duration for the plan phase, and each conticaster of whole day is opened
Water always water number of times, enter iron with produce reality identical, be called for short per diem decision-making.
Table 1. each teams and groups conticaster parameter
Utilizing computational methods of the present invention to calculate, obtain such as the data of Fig. 4, Fig. 5 and Biao 2, Fig. 4 is opening by class's decision-making
Water time Gantt chart.Fig. 5 is the casting time Gantt chart of per diem decision-making. table 2 is with casting time as foundation, by above-mentioned relevant general
Read calculate actual and open the index contrast tables such as desired value and metal balance that the method watering decision-making and utilize the present invention calculates, table
Middle band " * " numerical value has been deducted and has been unsatisfactory for (14) formula and overstocks the value of calculation of amount of metal nonnegativity restrictions part.
Table 2 decision objective and the contrast of metals resources balance index
For being analyzed as follows of Fig. 3-Fig. 5 and Biao 2: walkthrough
1) result of decision calculated in the present inventive method is substantially better than actual decision-making in terms of producing stability contorting. and actual
Decision-making occurs in that in 201min waters steel while 5 conticasters, the situation of only 1 conticaster casting in 66min;And the present invention
The result of calculation of method has remained that within the casting plan phase 2 and above conticaster even water, and produces relative equilibrium stable. from
In table 2 actual decision-making with also have embodiment by the standard deviation data of class's decision-making. its reason is: relative to the method for the present invention, for
Reach the casting sequence of each casting plan, carry out quantifying meter to metals resources balance on production line owing to lacking during actual decision-making
The means calculated, teams and groups 1,2 all occur in that because of unlatching conticaster in advance and cause-138t ,-1946t respectively and overstock amount of metal, leading
The safety on line stock's amount of metal having caused respective numbers is not enough, and causes teams and groups 3 to postpone to open conticaster, makes again the plan phase terminate
Time overstocked amount of metal increase. and during the casting time of the conticaster utilizing the method for the present invention to calculate, because having considered ferrum
The influence factor of steel equilibrium of stock has also quantified the constituent relation between each factor, effectively prevent because of the unreasonable of casting time
The production instability problem produced.
2) method of the present invention is better than actual decision-making in terms of total benefit. and essentially identical in whole day average serialization degree
In the case of, the cost that the overstocked amount of metal difference that main reason is that under different decision mode of total benefit difference is caused occurs
Change is caused, and wherein, actual decision-making have impact on total benefit because its overstocked amount of metal significantly deviate from its control standard.
3) when be intended to phase time range from a class be loosened to one day (three classes) and only whole day scope limit each company
Casting machine wait open water time sum time, the present invention can find in bigger time range and meet each conticaster of new constraints, respectively waters
Secondary optimization casting time, and it is simultaneously achieved decision objective and the further optimization of the metals resources each index of balance, embody
Stronger Parameters variation adapts to ability. and in actual applications, the increase plan phase has reduction to predict the risk into iron accuracy, also
The effectiveness of the result of decision may be affected, therefore, it should in the decision basis with the daily planning phase, with teams and groups' activity duration be
The plan phase carries out opening calculation and check and the adjustment watering decision-making.
Conticaster of the present invention is opened and watered the purpose of decision-making is on the basis of guaranteeing to produce stable row, is overstock by minimizing and is giving birth to
Produce overstocked amount of metal on line to reduce cost, to improve the serialization degree of conticaster to increase benefit, finally realize continuous casting and give birth to
Produce the maximization of total benefit.Accumulative steel amount and opening inventory amount of metal, safety on line stock's metal is watered considering the plan phase
Measure, add up, on the basis of iron, the overstocked factor such as amount of metal mutual relation and process time constraint, to establish with CSDCC total
Benefit is the Integer programming of target to the maximum.In producing according to reality, each order of classes or grades at school company alternately waters state and plans even to water
The feature that stove number is relevant, devise using safety on line stock's amount of metal of previous plan phase with overstocked amount of metal sum as rear one
The processing method of the opening inventory amount of metal of plan phase, and apply YALMIP optimization toolbox based on MATLAB to solve.
Application example shows, the present invention can solve the casting time decision problem of steel mill multiple stage conticaster. under the same conditions with
Actual decision-making compares, and can improve the total benefit of decision-making, reduce overstock on production line metals resources amount, stablize adjacent teams and groups
Between working condition, opening in order to water and provide technological means for steel plant continuous casting machine.
In the description of this specification, reference term " embodiment ", " some embodiments ", " example ", " specifically show
Example " or the description of " some examples " etc. means to combine this embodiment or example describes specific features, structure, material or spy
Point is contained at least one embodiment or the example of the present invention.In this manual, to the schematic representation of above-mentioned term not
Necessarily refer to identical embodiment or example.And, the specific features of description, structure, material or feature can be any
One or more embodiments or example in combine in an appropriate manner.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that: not
These embodiments can be carried out multiple change in the case of departing from the principle of the present invention and objective, revise, replace and modification, this
The scope of invention is limited by claim and equivalent thereof.
Claims (4)
1. the casting time of a steel plant continuous casting machine determines method, it is characterised in that comprise the steps:
S1, opens and waters decision controller and be connected with MES data storehouse and the MES FTP client FTP of steel mill respectively;
S2, sets up to open and waters objective function of decision-making, and described object function is:
Wherein, k is plan phase sequence number, k ∈ 1,2 ..., and Ω }, Ω is plan phase sum;I is casting machine sequence number, i ∈ 1,2 ...,
H}, H are casting machine sum;J for watering sequence number, It is that the i-th casting machine waters time sum;ρ is molten steel density;η
For metal loss factor;q0Steel amount is averagely watered for each heat;Whole process average stream time kth plan phase;For kth plan
Start time phase;For finish time kth plan phase;For kth plan phase the i-th casting machine jth casting plan casting furnace number;
Time minimum interval is watered for kth plan phase the i-th casting machine jth;At the end of watering time legacy tasks for kth plan phase the i-th casting machine jth
Carve;Time legacy tasks average pull rate is watered for kth plan phase the i-th casting machine jth;Water secondary for kth plan phase the i-th casting machine jth
Casting cycle;Wait to open for kth plan phase the i-th casting machine jth and water time average pull rate;Water for kth plan phase the i-th casting machine jth
Secondary legacy tasks basal area;Wait to open for kth plan phase the i-th casting machine jth and water subtask basal area;For the kth plan phase i-th
Casting machine jth is watered time legacy tasks and is watered steel amount;C1 is benefit coefficient;C2 is cost coefficient;Iron is entered for the kth plan phase, for
Known quantity;For stock's amount of metal that kth plan is initial, for known quantity;For the overstocked amount of metal in the kth plan end of term, for not
Know process variable;For the line safety inventory amount of metal of kth plan phase, for Unknown Process variable;Damage for kth plan phase metal
Consumption, for Unknown Process variable;Steel amount is watered, for Unknown Process variable for the kth plan phase;For kth plan phase the i-th casting machine
J waits to open to water time to open and waters the moment, for unknown number to be asked;
Formula (1) represents that object function is deducted the cost structure of overstocked amount of metal by serialization degree income;
Formula (2) represents serialization degree (Θk) water time casting time equal to the legacy tasks casting time of each conticaster with waiting to open
Sum is divided by H platform conticaster total time plan phase;
Formula (3) represents overstocked amount of metalIron is entered respectively by this plan phaseOpening inventory amount of metalOnline
Safety inventory amount of metalMetal loss amountWater steel amountRelation constitute;
Formula (4) the expression plan phase adds up to water steel amount and time waters steel amount sum equal to the legacy tasks amount of each conticaster with waiting to open to water;
Formula (5) represents that the H platform conticaster unit interval within the plan phase averagely waters steel amountSteel amount is watered divided by meter equal to accumulative
Draw phase length;
Formula (6) represents when planning phase metal loss factor and being known, accumulative metal loss amount and the accumulative mutual relation watering steel amount;
Formula (7) represents when averagely watering the steel amount average line stock amount of metal of calculating with the unit intervalTime, it should utilize metal
Loss factor η is converted to the iron water amount of respective numbers;
Formula (8) represents that safety on line stock's amount of metal needs to add a random fluctuation on the basis of average line stock amount of metal
Demand amount of metal
S3, set up wait to open water time and legacy tasks constraints, wait to open whether connect between watering time water constraints, respectively wait to open to water
Secondary time and plan beginning and ending time phase constraints and the constraints of overstocked amount of metal;
S4, controller obtains taking of each known quantity parameter in step S2 by the MES data storehouse of steel mill and MES FTP client FTP
Value;
S5, according to physical quantity known in step S4 and the exploitation intermediate variable of parameter, described intermediate variable includes respectively waiting out
Water time casting cycle, each casting machine legacy tasks casting time, each casting machine single bit time water steel amount, the metal loss factor that collects,
Overstock in amount of metal formula coefficient before real number decision variable after arrangement, arrange after coefficient before Real-valued decision variable;
S6, determines each coefficient of object function according to the intermediate variable that step S5 obtains, and waters secondary for the i-th conticaster jth, order:
F (i, j)=f (i, j)+arrange after before Real-valued decision variable coefficient × conticaster i jth water time casting time x (i, j),
(i, j), ((i, j), wherein, (i j) is Real-valued variable defined in matlab to sdpvar to described x for i, j)=sdpvar to make p=f
Function;
S7, determines the restriction relation in step S3 according to the intermediate variable that step S5 obtains;
S8, utilizes Optimization Solution device solvesdp (F ,-p), obtains kth plan phase the i-th casting machine jth and waits to open to water time to open and water the moment
And whether connect between watering time and to waterWherein, solvesdp () is matlab majorized function, and F is total restriction relation identifier ,-p
For object function identifier total during maximizing;
S9, controller is according to obtainingData carry out the shop job scheduling of steel smelting-continuous casting production, and to production run
System is implemented effectively to control.
2. the casting time of steel plant continuous casting machine as claimed in claim 1 determines method, it is characterised in that: in described step S3
Constraints is:
1) respectively wait to open the company between watering time and water relation constraint:
Wherein,For binary variable, 1 represents that kth plan phase the i-th casting machine jth is watered secondary company with legacy tasks and watered, and 0 represents disconnected waters,For unknown number to be asked;
F1: when judge wait open water time whether connect between legacy tasks water time, in formula (9)
Formula (9-10) represent when wait open water time even water with legacy tasks time, casting time point takes legacy tasks finish time, non-company
Taking legacy tasks finish time when watering terminates certain moment to the plan phase plus watering the minor tick time;
Formula (11) represents that i-th conticaster jth of kth plan phase is watered time legacy tasks amount and watered equal to the plan of this casting machine previous plan phase
Steel amount and the difference of casting amount;
F2: when decision-making remaining respectively wait open water time between whether connect water time, in formula (9)
Formula (9), (12) represent when except remaining adjacent with legacy tasks respectively wait open water that time interconnection is watered mutually time, this casting time point takes
Before water time finish time, non-company waters time finish time and terminates certain moment to the plan phase plus watering the minor tick time before taking when watering;
F3: respectively wait to open time time of watering and plan beginning and ending time phase relation constraint condition:
F4: overstocked amount of metal constraints:
3. the casting time of steel plant continuous casting machine as claimed in claim 1 determines method, it is characterised in that: in described step S5
The intermediate variable obtained is:
Respectively wait to open and water the stove number * average Metal Weight of each stove in time casting cycle=respectively wait to open waters time/(wait to open and water time pulling rate * and wait out
Water time basal area * molten steel density);
Each casting machine legacy tasks casting time=each casting machine legacy tasks molten steel amount/(each casting machine legacy tasks each casting machine of pulling rate * is lost
Remain in office business basal area * molten steel density);
Each casting machine single bit time waters steel amount=water time pulling rate * and waters time basal area * molten steel density;
The metal loss factor collected=(1+ metal loss factor/(1-metal loss factor)+whole process logistics time/((meter
Draw finish time phase-start time plan phase) * (1-metal loss factor));
After arrangement, in overstocked amount of metal formula, before real number decision variable, coefficient=-each casting machine single bit time waters the gold that steel amount * collects
Belong to loss factor;
Constant term in amount of metal constraint formulations=estimate into ferrum total amount+opening inventory iron-stochastic demand stock is overstock after arrangement
The metal loss factor * of amount of metal-collect (respectively wait to open and water time casting cycle * by each casting machine legacy tasks molten steel amount sum+each casting machine
Each casting machine single bit time waters steel amount+plan phase finish time * each casting machine single bit time and waters steel amount sum);
Metal loss factor * each casting machine single bit time that after arrangement, before Real-valued decision variable, coefficient=cost coefficient * collects waters
Steel amount+income coefficient/((plan finish time phase-start time plan phase) * conticaster number).
4. the casting time of steel plant continuous casting machine as claimed in claim 1 determines method, it is characterised in that: described according to step
The method of the restriction relation in intermediate variable set-up procedure S3 that S5 obtains is:
1) watering time for the i-th conticaster the 1st, make F1 (1,1)=0, i=1,2 ..., H, described H is positive integer;
F1 (i, j)=F1 (i, j)+set (casting machine i legacy tasks casting time+casting machine i water time between minimum time interval * casting machine i
First binary variable y (i, 1)≤first casting time x of casting machine i (i, 1)≤casting machine i legacy tasks casting time+
(plan finish time phase-casting machine i legacy tasks first binary variable y of casting time * casting machine i (i, 1)), wherein, y (i,
1) corresponding in constraints(i, j) corresponding in constraints for yX (i, 1) is corresponding in constraints
(i, j) corresponding in constraints for xSet () be MATLAB YALMIP optimization tool in constraints function is set;
2) the i-th conticaster jth is watered time, makes F2 (1,2)=0, i=1,2 ..., H, j=2,3 ...,
F2 (i, j)=F2 (i, j)+set ((casting machine i jth-1 casting time x (i, j-1)+casting machine i waters time casting cycle)+casting machine i
Minimum time interval * casting machine i jth binary variable y (i, j)≤casting machine i jth casting time x (i, j)≤(casting between watering time
Machine i jth-1 casting time x (i, j-1)+casting machine i waters time casting cycle)+(finish time phase-(casting machine i jth-1 is opened when watering in plan
Between x (i, j-1)+casting machine i water time casting cycle)+casting machine i jth binary variable y (i, j)));
3) the i-th conticaster jth is watered time, makes F3 (1,1)=0, i=1,2 ..., H, j=1,2 ...,
((i, j) (plan finish time phase≤conticaster i jth waters time casting time x (i, j)≤plan to+set to F3 for i, j)=F3
Start time phase);
4) the i-th conticaster jth is watered time, makes F4 (1,1)=0, i=1,2 ..., H, j=1,2 ...,
((i, j)+set (overstocks in amount of metal formula coefficient * conticaster i jth before real number decision variable to F4 after arrangement for i, j)=F4
Water time casting time x (i overstocks constant term in amount of metal constraint formulations after j)≤arrangement);
5) make F1=F1 (i, j), F2=F2 (i, j), F3=F3 (i, j), F4=F4 (i, j);
Total restriction relation: F=(F1+F2+F3+F4).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510374921.9A CN104942251B (en) | 2015-07-01 | 2015-07-01 | Cast-on time determining method of steel mill continuous casting machines |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510374921.9A CN104942251B (en) | 2015-07-01 | 2015-07-01 | Cast-on time determining method of steel mill continuous casting machines |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104942251A CN104942251A (en) | 2015-09-30 |
CN104942251B true CN104942251B (en) | 2017-01-11 |
Family
ID=54157608
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510374921.9A Active CN104942251B (en) | 2015-07-01 | 2015-07-01 | Cast-on time determining method of steel mill continuous casting machines |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104942251B (en) |
Families Citing this family (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111769555B (en) * | 2020-07-08 | 2021-04-30 | 山东大学 | Short-flow iron and steel enterprise load optimization regulation and control method and system considering process limitation |
CN114298567B (en) * | 2021-12-30 | 2024-06-21 | 重庆大学 | Method and system for scheduling casting schedule and dynamic decision-making of casting time of continuous casting machine |
CN114393188B (en) * | 2022-01-04 | 2023-11-17 | 重庆钢铁股份有限公司 | Method for automatically judging ladle casting time in continuous casting process by system |
CN116618597B (en) * | 2023-05-23 | 2024-05-14 | 华院计算技术(上海)股份有限公司 | Continuous casting cutting optimization method and system based on mixed integer programming |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05245607A (en) * | 1992-03-09 | 1993-09-24 | Sumitomo Metal Ind Ltd | Method for detecting drift flow in inner part of mold for continuous casting |
AT411822B (en) * | 2002-09-12 | 2004-06-25 | Voest Alpine Ind Anlagen | METHOD AND DEVICE FOR STARTING A CASTING PROCESS |
CN101770615A (en) * | 2010-01-25 | 2010-07-07 | 重庆大学 | Steelmaking-continuous casting production operation plan and real-time dispatching optimization method and system based on mixed intelligent optimization algorithm |
CN101944202A (en) * | 2010-09-03 | 2011-01-12 | 昆明理工大学 | Just-in-time-based parallel forward calculation programing method for steel-making production planned time |
CN102266927B (en) * | 2011-08-01 | 2013-02-13 | 东北大学 | Control method for molten-steel casting sequence of continuous casting machine |
CN103631243B (en) * | 2013-12-13 | 2015-12-30 | 重庆大学 | A kind of steel smelting-continuous casting rescheduling method based on genetic algorithm and system |
-
2015
- 2015-07-01 CN CN201510374921.9A patent/CN104942251B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN104942251A (en) | 2015-09-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106779220B (en) | Steelmaking-continuous casting-hot rolling integrated scheduling method and system | |
CN109359884B (en) | Aviation complex equipment structural member workshop operation planning and rescheduling method | |
CN103839114B (en) | Steelshop sequential plan auto-designing system | |
CN104942251B (en) | Cast-on time determining method of steel mill continuous casting machines | |
CN102346882B (en) | Bilayer planning method for intelligent scheduling for steelmaking-continuous welding production | |
WO2017088674A1 (en) | Steelmaking batch grouping and production scheduling method for whole process production | |
CN1885328B (en) | Steelmaking-continuous casting tundish batch plan method and system | |
CN105550751A (en) | Steelmaking-continuous casting scheduling method utilizing priority policy hybrid genetic algorithm | |
CN102266927B (en) | Control method for molten-steel casting sequence of continuous casting machine | |
Zhang et al. | Robust scheduling of hot rolling production by local search enhanced ant colony optimization algorithm | |
CN103631243B (en) | A kind of steel smelting-continuous casting rescheduling method based on genetic algorithm and system | |
CN106611221B (en) | It is a kind of for solving the steel smelting-continuous casting rescheduling method of conticaster failure | |
CN108303958B (en) | A kind of multi-objective flexible dispatching method of steel-making continuous casting process | |
CN105631759A (en) | Steel making factory multi-target scheduling plan compiling method considering molten iron supply condition | |
CN108665092B (en) | Full-process production scheduling and optimizing method based on mixed firefly algorithm | |
CN106055836B (en) | Continuous casting unit pours the Multipurpose Optimal Method of heat selection, sequence and casting time decision | |
CN108876050B (en) | Method for setting and automatically converting contract main process of iron and steel enterprise | |
CN101520656A (en) | On-line multi-mode time optimization scheduling method for steelmaking and continuous casting production | |
CN112668901B (en) | Steel mill production scheduling method and system considering energy consumption | |
CN101344781A (en) | Plate coil automatic scheduling method and system for cold rolling hot galvanizing units | |
CN100449431C (en) | Method and device for controlling an installation for producing steel | |
CN104122861B (en) | The conflict resolution method lax based on the waiting time and Optimization Scheduling | |
CN107403264A (en) | A kind of transporting equipment ladle path preparation method for considering the constraint of production equipment operation plan | |
Lü et al. | Multiproduct and multistage integrated production planning model and algorithm based on an available production capacity network | |
Zhang et al. | Solving the order planning problem at the steelmaking shops by considering logistics balance on the plant-wide process |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |