CN104925680B - A kind of method of stabilizer tower crane body - Google Patents

A kind of method of stabilizer tower crane body Download PDF

Info

Publication number
CN104925680B
CN104925680B CN201510297865.3A CN201510297865A CN104925680B CN 104925680 B CN104925680 B CN 104925680B CN 201510297865 A CN201510297865 A CN 201510297865A CN 104925680 B CN104925680 B CN 104925680B
Authority
CN
China
Prior art keywords
steel
pipe pile
tower crane
pile column
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510297865.3A
Other languages
Chinese (zh)
Other versions
CN104925680A (en
Inventor
陈建荣
彭鹏
彭强
覃宗华
毛昌庆
郑先河
姚清涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
Original Assignee
CCCC Second Harbor Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co filed Critical CCCC Second Harbor Engineering Co
Priority to CN201510297865.3A priority Critical patent/CN104925680B/en
Publication of CN104925680A publication Critical patent/CN104925680A/en
Application granted granted Critical
Publication of CN104925680B publication Critical patent/CN104925680B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/16Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/62Constructional features or details
    • B66C23/72Counterweights or supports for balancing lifting couples
    • B66C23/78Supports, e.g. outriggers, for mobile cranes

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of method that the invention discloses stabilizer tower crane body, including installing tower crane, setting up wall-attached frame, attached wall operation for the first time and second time attached wall operation, this method is outside tower crane attached wall conventional method, for some special engineering, in the case of tower crane attached wall cannot be installed, devise a kind of wall-attached frame installing tower crane attached wall, implement to provide a kind of new thinking for installing of tower crane.

Description

A kind of method of stabilizer tower crane body
Technical field
The invention belongs to field of bridge construction, more particularly, it relates to a kind of method of stabilizer tower crane body.
Background technology
When tower crane require more than unattached height construction time, tower body must install one or multi-channel attached wall structure with Stablize tower body.Conventional method is to install attached wall structure to existing attachment, such as bridge tower or building On, to meet the use requirement of the perpendicularity of tower crane.But, for some special engineering, tower crane works Being necessarily required to attached wall structure, in the case of building, bridge tower etc. but can not be utilized to set up, this is accomplished by rationally Individually set up attached wall attachment to ensure the safe construction of tower crane.
As above-mentioned, for special engineering, solve tower crane and the problem of attached wall structure cannot be installed, for Feasibility and the economy of engineering construction it is critical that, there is higher society and economic benefit.
Summary of the invention
It is an object of the invention to solve at least the above and/or defect, and provide after at least and will say Bright advantage.
A further object of the invention is problem present on a kind of method solving new stabilizer tower crane body, This method can be widely used according to its wall-attached frame applied, and can reach to improve its installation And stability.
It is a still further object of the present invention to provide a kind of wall-attached frame structure, by arranging two near tower body side Root steel-pipe pile column, arranges the form of three steel-pipe pile columns away from tower body side, it is possible to reduce the material of column Material consumption, cost-effective.
In order to realize according to object of the present invention and further advantage, it is provided that a kind of stabilizer tower crane body Method, comprise the following steps:
S1: install tower crane
Tower crane is arranged on tower crane and is increased above the height at the first attached wall absolute altitude, described tower It is hung on horizontal cross-section square;
S2: set up wall-attached frame
S21: set up the first steel-pipe pile column and second that level interval is the first distance in described tower crane front Steel-pipe pile column, to higher than the height at described first attached wall absolute altitude, takes described tower crane in any horizontal cross-section On a summit be the first summit, the most described first steel-pipe pile column and described second steel-pipe pile column are equal The even both sides being distributed in described first summit, and described first summit be positioned at described first steel-pipe pile column and On the perpendicular bisector of the described second horizontal line of steel-pipe pile column;
S22: be located away from described tower crane at described first steel-pipe pile column and described second steel-pipe pile column To set up the level interval of word order be the 3rd steel-pipe pile column of described first distance, the 4th steel in side Pile tube column and the 5th steel-pipe pile column, described 4th steel-pipe pile column is built to higher than described first attached wall Height at absolute altitude, wherein, on horizontal cross-section, described first steel-pipe pile column, described second steel-pipe pile stand Post and described 4th steel-pipe pile column constitute equilateral triangle;
S23: by multiple connecting rods by adjacent described first steel-pipe pile column, described second steel-pipe pile Column, the 3rd steel-pipe pile column, the 4th steel-pipe pile column and the 5th steel-pipe pile column are fixing to be connected, and is formed Wall-attached frame;
S3: attached wall operation for the first time
Described first steel-pipe pile column is set up a pair first wall attaching rods, respectively by attached wall connector water Put down and be connected on the tower crane tower body of described first summit and the second vertex correspondence adjacent with described first summit, Described second steel-pipe pile column is set up a pair second wall attaching rods, respectively by attached wall connector level even Receive on the tower crane tower body of described first summit and the 3rd vertex correspondence adjacent with described first summit, its In, described first wall attaching rod and described second wall attaching rod are positioned at the level at place at described first attached wall absolute altitude On cross section;
S4: attached wall operation for the second time
Tower crane is increased above the height at the second attached wall absolute altitude, vertically sets up described first steel-pipe pile Column, described second steel-pipe pile column and described 3rd steel-pipe pile column are at higher than the second attached wall absolute altitude Highly, by multiple connecting rods, adjacent described first steel-pipe pile column, described second steel-pipe pile are stood Post, the 3rd steel-pipe pile column, the 4th steel-pipe pile column and the 5th steel-pipe pile column are fixing to be connected, described A pair the 3rd wall attaching rods are set up, respectively by attached wall connector level connection joint to institute on first steel-pipe pile column State on the tower crane tower body of the first summit and the second vertex correspondence adjacent with described first summit, described A pair the 4th wall attaching rods are set up, respectively by attached wall connector level connection joint to described on two steel-pipe pile columns On the tower crane tower body of the first summit and the 3rd vertex correspondence adjacent with described first summit, described 3rd attached Wall bar and described 4th wall attaching rod are positioned on the horizontal cross-section at described second attached wall absolute altitude;
S5: raise described tower crane to critical altitude.
Preferably, in described step S22: the 3rd steel-pipe pile column and the height phase of the 5th steel-pipe pile column Deng, and be the 1/2 of described first steel-pipe pile stem height now, use two short columns add three long vertical The arrangement of post, can meet Bearing Capacity of Steel Pipe Piles requirement, also can reduce the material usage of support, joint About cost.
Preferably, described connecting rod includes lateral rod member and diagonal brace rod member, wherein, described diagonal brace rod member During installation, the angle of inclination with horizontal cross-section is 45 °.
Preferably, described attached wall connector includes two semicircles being removably attached on described wall-attached frame Shape steel plate, welds hinged ear on a described semi-circular sheet steel of tower crane, described hinge ear and described the One steel-pipe pile column or any one of described second steel-pipe pile column are articulated and connected, be the most not only easy to mounting or dismounting but also Can guarantee that bonding strength.
Preferably, described first steel-pipe pile column is 3.6m with the horizontal range of described tower crane axis, neither Interfere with tower crane, also can reduce the length of wall attaching rod as far as possible..
Preferably, described first distance is 6m.
Preferably, the highest attachment point of described tower crane and the perpendicularity of the axis of described tower crane are less than 0.002.
The present invention at least includes following beneficial effect:
Novel form: outside tower crane attached wall conventional method, for some special engineering, it is impossible to install tower In the case of hanging attached wall, devising a kind of wall-attached frame installing tower crane attached wall, the installation for tower crane is implemented to carry Supply a kind of new thinking.
Safe and reliable: tower crane and steel-pipe pile support are all conventional equipment and structure, and work progress is without special work Skill, stable conditions, it is simple to controlling, construction technology risk is little.
Easy to make;Tower crane and wall attaching rod are finished product structure, between both by steel plate and bolt Connect, connect reliable and be convenient to mount and dismount.
Good economy performance: for some special engineering, it is necessary to install the tower crane exceeding free height construction, but In the case of attached wall structure cannot be installed, individually set up the input cost of wall-attached frame than putting into miscellaneous equipment Cost is greatly reduced, and feasibility and economy for engineering construction have tremendous influence.
Utilization prospect is good: along with the development of bridge construction, the most special formed building or bridge Beam has built up, and the most also will have more similar tower crane applicable cases and occur.The inventive method is also In the construction of Successful utilization Nanjing bridge, use prospect preferable.
Part is embodied by the further advantage of the present invention, target and feature by description below, and part also will By the research of the present invention and practice are understood by the person skilled in the art.
Accompanying drawing explanation
Fig. 1 is the schematic diagram of step S1 of the present invention;
Fig. 2 be the present invention step S2 in wall-attached frame and the top view of tower crane;
Fig. 3 is the side view of wall-attached frame in the present invention;
Fig. 4 is the schematic diagram of step S2 in the present invention;
Fig. 5 is the schematic diagram of step S4 in the present invention;
Fig. 6 is the structural representation of attached wall connector in the present invention.
Detailed description of the invention
The present invention is described in further detail below in conjunction with the accompanying drawings, to make those skilled in the art's reference Description word can be implemented according to this.
Should be appreciated that used herein such as " have ", " comprising " and " including " term not Allot other element one or more or the existence of a combination thereof or interpolation.
A kind of method of stabilizer tower crane body, comprises the following steps:
S1: install tower crane 1
As it is shown in figure 1, on the basis of tower crane 1 is arranged on tower crane 2 and be increased above the first attached wall absolute altitude The height at place, described tower crane is square on horizontal cross-section;
S2: set up wall-attached frame 3
S21: as in Figure 2-4, sets up the first steel that level interval is the first distance in described tower crane front Pile tube column 301 and the second steel-pipe pile column 302, to higher than the height at described first attached wall absolute altitude, take A described tower crane summit on any horizontal cross-section is the first summit 101, the most described first steel-pipe pile Column 1 and described second steel-pipe pile column 2 are evenly distributed on the both sides on described first summit 101, and institute State the first summit 101 and be positioned at described first steel-pipe pile column 301 and described second steel-pipe pile column 302 water On the perpendicular bisector of flat line;
S22: being located away from of described first steel-pipe pile column 301 and described second steel-pipe pile column 302 The 3rd steel-pipe pile column that the level interval of word order is described first distance is set up in the side of described tower crane 303, the 4th steel-pipe pile column 304 and the 5th steel-pipe pile column 305, described 4th steel-pipe pile column 304 Build to higher than the height at described first attached wall absolute altitude, wherein, described first steel-pipe pile on horizontal cross-section Column 301, described second steel-pipe pile column 302 and described 4th steel-pipe pile column 304 constitute equilateral three Dihedral;
S23: by multiple connecting rods 31 by adjacent described first steel-pipe pile column 301, described Two steel-pipe pile column the 302, the 3rd steel-pipe pile column the 303, the 4th steel-pipe pile column 304 and the 5th steel-pipe piles Column 305 is fixing to be connected, and forms wall-attached frame 3;
S3: attached wall operation for the first time
Described first steel-pipe pile column 301 is set up a pair first wall attaching rods 401, passes through attached wall respectively Connector 5 level connection joint is to described first summit 101 and second summit pair adjacent with described first summit On the tower crane tower body answered, a pair second wall attaching rods 402 set up by described second steel-pipe pile 302 column, Respectively by attached wall connector 5 level connection joint to described first summit 101 and adjacent with described first summit The 3rd summit 103 correspondence tower crane 1 tower body on, wherein, described first wall attaching rod 401 and described Two wall attaching rods 402 are positioned at described first attached wall absolute altitude on the horizontal cross-section at place;
S4: attached wall operation for the second time
As it is shown in figure 5, tower crane 1 to be increased above the height at the second attached wall absolute altitude, vertically set up Described first steel-pipe pile column 301, described second steel-pipe pile column and described 3rd steel-pipe pile column are paramount Height at the second attached wall absolute altitude, is stood adjacent described first steel-pipe pile by multiple connecting rods 31 Post 301, described second steel-pipe pile column the 302, the 3rd steel-pipe pile column the 303, the 4th steel-pipe pile column 304 Fixing with the 5th steel-pipe pile column 305 connect, described first steel-pipe pile column 301 is set up a pair the Three wall attaching rods 403, respectively by attached wall connector level connection joint to described first summit 101 with described On the tower crane tower body of the second summit 102 correspondence that the first summit is adjacent, at described second steel-pipe pile column 302 On set up a pair the 4th wall attaching rods, respectively by attached wall connector 5 level connection joint to described first summit 101 And on tower crane tower body corresponding to the 3rd summit 103 adjacent with described first summit, described 3rd wall attaching rod It is positioned on the horizontal cross-section at described second attached wall absolute altitude with described 4th wall attaching rod;
S5: raise described tower crane to critical altitude.
Wherein, in described step S22: the 3rd steel-pipe pile column 303 and the 5th steel-pipe pile column 305 The most equal, and be 1/2 highly of described first steel-pipe pile column 301 now.
Wherein, described connecting rod 31 includes lateral rod member 311 and diagonal brace rod member 312, wherein, described When diagonal brace rod member 312 is installed, the angle of inclination with horizontal cross-section is 45 °.
Wherein, as shown in Figure 6, described attached wall connector 5 includes that two are removably attached to described attached Semi-circular sheet steel in wall stand: semi-circular sheet steel 51 and semi-circular sheet steel 52, near an institute of tower crane State and on semi-circular sheet steel 52, weld hinged ear 53, described hinge ear and described first steel-pipe pile column 301 or Any one of described second steel-pipe pile column 302 is articulated and connected.
Wherein, described first steel-pipe pile column 301 is 3.6m with the horizontal range of described tower crane axis.
Wherein, described first distance is 6m.
Wherein, the highest attachment point of described tower crane and the perpendicularity of the axis of described tower crane are less than 0.002.
A kind of steel-pipe pile support of individually setting up is for connecting the tower crane attached wall method with stable tower body, and it is logical Cross and set up stable steel-pipe pile support, connect tower crane attached wall, so that the perpendicularity in tower crane work progress Meet code requirement, it is ensured that safety of tower crane is constructed.
Tower crane exceedes the height that works alone, surrounding has attachment but cannot connect attached wall or connect without attachment In the case of attached wall, the support set up can meet tower crane and use requirement.
The intensity of attached wall support and deformation all can guarantee that the operating specification requirement of tower crane in work progress.
The bearing capacity of steel-pipe pile column also can meet geology condition design requirement.
The present invention provide a kind of individually set up support for connect tower crane attached wall with the method for stable tower body and Structure.
Individually set up steel-pipe pile column in the present invention, be used for connecting tower crane attached wall with stable tower body, make tower body Perpendicularity meet specification and construction requirement, it is ensured that tower crane work safety.First according to tower crane in engineering Middle position, required working depth, attached wall arrange form and position, geological conditions etc., by setting Score separates out the version of steel-pipe pile support, design height.Steel-pipe pile attached wall support is pacified at tower crane attached wall Progressively set up before dress, reached, when wall attaching rod position is installed, wall attaching rod to be installed, it is ensured that tower crane working The perpendicularity making each sections tower body requires: unloaded, wind speed is not more than under 3m/s state, and tower crane tower body is The perpendicularity < 2/1000 of high attachment point following tower body axis.
The steel-pipe pile attached wall supporting structure that the present invention implements, it includes attached wall support and tower crane and tower body Location arrangements.Connect steel-pipe pile column and tower crane center distance 3.6m of attached wall, neither with tower crane Interfere, also can reduce the length of wall attaching rod as far as possible.
The steel-pipe pile attached wall supporting structure that the present invention implements, it includes the arrangement form of steel-pipe pile column.Steel Pile tube column is arranging two near tower body side, arranges three away from tower body side, and 5 steel-pipe piles stand altogether The attached wall support that post composition is stable.Bearing Capacity of Steel Pipe Piles requirement can be met, also can reduce the material of support Consumption, cost-effective.Meanwhile, the version of steel-pipe pile support and the rational height of tower crane attached wall determine The intensity of attached wall support and deformation, and the perpendicularity of tower crane is mainly determined by the deformation of support.
The steel-pipe pile attached wall supporting structure that the present invention implements, it includes the connection of wall attaching rod and steel-pipe pile column Part.Wall attaching rod and steel-pipe pile column use two semicircle steel plates to be clamped in steel-pipe pile by after bolt group pretension On column, wherein a semicircle Plate Welding hinge ear near tower body can be articulated and connected with wall attaching rod, it is simple to Mounting or dismounting also can guarantee that bonding strength.
A kind of steel-pipe pile attached wall support individually set up, it includes steel-pipe pile column, lateral rod member, diagonal brace Rod member, attached wall and tower crane attached wall connector.It is characterized in that tower crane tower body may connect to prop up by wall attaching rod On frame steel pipe post, the intensity of supporting structure and rigidity meet the use requirement of tower crane.
After the tower crane highly that works alone is arranged on tower crane, tower crane wall-attached frame facade is by two row's steel Pile tube squeezes into stratum, welds lateral the most successively, diagonal brace forms stable supporting structure.Along with tower The height that connects hung installs attached wall connecting rod with attached wall connector successively to be connected wall-attached frame.Wherein, steel-pipe pile Arrange shorter, act primarily as the effect sharing steel-pipe pile pull out force.
Steel-pipe pile column 301,302,304 is triangularly arranged stake position, beneficially Stability Analysis of Structures in plane And undertake tower crane full circle swinging work and bearing capacity of pile foundation during static inoperative, steel-pipe pile column 301, Using lateral rod member, diagonal brace rod member to connect between 302, now, tower body is connected with attached wall by wall-attached frame Bar constitutes rock-steady structure.
Attached wall connecting rod and attached wall connector by two pieces of semi-circular sheet steel by after bolt group pretension and steel pipe Stake column clamping connects.Welding two pieces of hinge otic placodes on the steel plate of tower crane side, hinge ear is connected with attached wall Bar connects through bearing pin and connects.
Industrial applicibility
Novel form: outside tower crane attached wall conventional method, for some special engineering, it is impossible to install tower In the case of hanging attached wall, devising a kind of wall-attached frame installing tower crane attached wall, the installation for tower crane is implemented to carry Supply a kind of new thinking.
Safe and reliable: tower crane and steel-pipe pile support are all conventional equipment and structure, and work progress is without special work Skill, stable conditions, it is simple to controlling, construction technology risk is little.
Easy to make;Tower crane and wall attaching rod are finished product structure, between both by steel plate and bolt Connect, connect reliable and be convenient to mount and dismount.
Good economy performance: for some special engineering, it is necessary to install the tower crane exceeding free height construction, but In the case of attached wall structure cannot be installed, individually set up the input cost of wall-attached frame than putting into miscellaneous equipment Cost is greatly reduced, and feasibility and economy for engineering construction have tremendous influence.
Utilization prospect is good: along with the development of bridge construction, the most special formed building or bridge Beam has built up, and the most also will have more similar tower crane applicable cases and occur.The inventive method is also In the construction of Successful utilization Nanjing bridge, use prospect preferable.The further advantage of the present invention, target and Part is embodied by feature by description below, and part is also by by the research of the present invention and practice being Those skilled in the art is understood.
Although embodiment of the present invention are disclosed as above, but it is not restricted to description and embodiment party Listed utilization in formula.It can be applied to various applicable the field of the invention completely.For being familiar with ability For the personnel in territory, it is easily achieved other amendment.Therefore without departing substantially from claim and etc. homotype Enclosing under limited general concept, the present invention is not limited to specific details and shown here as the figure with description Example.

Claims (7)

1. the method for a stabilizer tower crane body, it is characterised in that comprise the following steps:
S1: install tower crane
Tower crane is arranged on tower crane and is increased above the height at the first attached wall absolute altitude, described tower It is hung on horizontal cross-section square;
S2: set up wall-attached frame
S21: set up the first steel-pipe pile column and second that level interval is the first distance in described tower crane front Steel-pipe pile column, to higher than the height at described first attached wall absolute altitude, takes described tower crane in any horizontal cross-section On a summit be the first summit, the most described first steel-pipe pile column and described second steel-pipe pile column are equal The even both sides being distributed in described first summit, and described first summit be positioned at described first steel-pipe pile column and On the perpendicular bisector of the described second horizontal line of steel-pipe pile column;
S22: be located away from described tower crane at described first steel-pipe pile column and described second steel-pipe pile column To set up the level interval of word order be the 3rd steel-pipe pile column of described first distance, the 4th steel in side Pile tube column and the 5th steel-pipe pile column, described 4th steel-pipe pile column is built to higher than described first attached wall Height at absolute altitude, wherein, on horizontal cross-section, described first steel-pipe pile column, described second steel-pipe pile stand Post and described 4th steel-pipe pile column constitute equilateral triangle;
S23: by multiple connecting rods by adjacent described first steel-pipe pile column, described second steel-pipe pile Column, the 3rd steel-pipe pile column, the 4th steel-pipe pile column and the 5th steel-pipe pile column are fixing to be connected, and is formed Wall-attached frame;
S3: attached wall operation for the first time
Described first steel-pipe pile column is set up a pair first wall attaching rods, respectively by attached wall connector water Put down and be connected on the tower crane tower body of described first summit and the second vertex correspondence adjacent with described first summit, Described second steel-pipe pile column is set up a pair second wall attaching rods, respectively by attached wall connector level even Receive on the tower crane tower body of described first summit and the 3rd vertex correspondence adjacent with described first summit, its In, described first wall attaching rod and described second wall attaching rod are positioned at the level at place at described first attached wall absolute altitude On cross section;
S4: attached wall operation for the second time
Tower crane is increased above the height at the second attached wall absolute altitude, vertically sets up described first steel-pipe pile Column, described second steel-pipe pile column and described 3rd steel-pipe pile column are at higher than the second attached wall absolute altitude Highly, by multiple connecting rods, adjacent described first steel-pipe pile column, described second steel-pipe pile are stood Post, the 3rd steel-pipe pile column, the 4th steel-pipe pile column and the 5th steel-pipe pile column are fixing to be connected, described A pair the 3rd wall attaching rods are set up, respectively by attached wall connector level connection joint to institute on first steel-pipe pile column State on the tower crane tower body of the first summit and the second vertex correspondence adjacent with described first summit, described A pair the 4th wall attaching rods are set up, respectively by attached wall connector level connection joint to described on two steel-pipe pile columns On the tower crane tower body of the first summit and the 3rd vertex correspondence adjacent with described first summit, described 3rd attached Wall bar and described 4th wall attaching rod are positioned on the horizontal cross-section at described second attached wall absolute altitude;
S5: raise described tower crane to critical altitude.
2. the method for stabilizer tower crane body as claimed in claim 1, it is characterised in that described step In S22: the height of the 3rd steel-pipe pile column and the 5th steel-pipe pile column is equal, and it is described now The 1/2 of one steel-pipe pile stem height.
3. the method for stabilizer tower crane body as claimed in claim 2, it is characterised in that described connecting rod Part includes lateral rod member and diagonal brace rod member, wherein, with the inclination of horizontal cross-section when described diagonal brace rod member is installed Angle is 45 °.
4. the method for stabilizer tower crane body as claimed in claim 1, it is characterised in that described attached wall is even Fitting includes two semi-circular sheet steel being removably attached on described wall-attached frame, near one of tower crane Hinged ear, described hinge ear and described first steel-pipe pile column or described second is welded on described semi-circular sheet steel Any one of steel-pipe pile column is articulated and connected.
5. the method for stabilizer tower crane body as claimed in claim 1, it is characterised in that described first steel Pile tube column is 3.6m with the horizontal range of described tower crane axis.
6. the method for stabilizer tower crane body as claimed in claim 1, it is characterised in that described first away from From for 6m.
7. the method for stabilizer tower crane body as claimed in claim 1, it is characterised in that described tower crane The highest attachment point is less than 0.002 with the perpendicularity of the axis of described tower crane.
CN201510297865.3A 2015-06-03 2015-06-03 A kind of method of stabilizer tower crane body Active CN104925680B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510297865.3A CN104925680B (en) 2015-06-03 2015-06-03 A kind of method of stabilizer tower crane body

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510297865.3A CN104925680B (en) 2015-06-03 2015-06-03 A kind of method of stabilizer tower crane body

Publications (2)

Publication Number Publication Date
CN104925680A CN104925680A (en) 2015-09-23
CN104925680B true CN104925680B (en) 2016-12-07

Family

ID=54113159

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510297865.3A Active CN104925680B (en) 2015-06-03 2015-06-03 A kind of method of stabilizer tower crane body

Country Status (1)

Country Link
CN (1) CN104925680B (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106185549A (en) * 2016-09-22 2016-12-07 中建八局第四建设有限公司 A kind of wall-attaching equipment of construction elevator
CN108341335B (en) * 2017-01-21 2019-08-23 张家界航空工业职业技术学院 A kind of gantry tower crane
CN107628551B (en) * 2017-11-07 2019-03-05 广东大汉建设机械有限公司 A kind of intelligent link system applied to building tower crane
CN111287542A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Construction method of concrete tower tube
CN111285275A (en) * 2018-12-06 2020-06-16 深圳京创重工特种工程有限公司 Tower crane device for building concrete tower drum

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201217618Y (en) * 2008-05-23 2009-04-08 中核华兴达丰机械工程有限公司 Universal adjustable stay rod attachment apparatus of tower crane
JP5683005B2 (en) * 2011-03-24 2015-03-11 三和テッキ株式会社 Jack device for supporting leg of jib crane
CN103253603A (en) * 2013-05-19 2013-08-21 上海庞源机械租赁股份有限公司 Combined type wall-attached pull rod for tower crane
CN103935911B (en) * 2014-03-31 2016-03-09 中国建筑第八工程局有限公司 Tower crane attached wall supporting construction and construction method thereof
CN203794514U (en) * 2014-04-14 2014-08-27 广东庞源工程机械有限公司 Wall-attached combination pull rod of tower crane
CN103935899B (en) * 2014-04-14 2016-02-17 中交第二航务工程局有限公司 Adhesion type crane in bridge type and construction method

Also Published As

Publication number Publication date
CN104925680A (en) 2015-09-23

Similar Documents

Publication Publication Date Title
CN104925680B (en) A kind of method of stabilizer tower crane body
CN203034773U (en) Assembly type operating platform with variable diameter
CN202899361U (en) Drilling avoiding device with hook type connection piece for stone or porcelain plate curtain wall plate blocks and cross rod
CN102926554B (en) Steel hanging seat formwork support and construction method thereof
CN103276907B (en) Hoisting method for large-span hinged type herringbone steel arch
CN201793330U (en) Gantry hanger frame device
CN204662458U (en) Detachable pretightning force combined support frame system brace summer transition Connection Block
CN108914993B (en) A kind of works is by uneven settlement of foundation and the pilot system of horizontal loads
CN208668903U (en) A kind of fabricated scaffold
CN104310234B (en) Outer outstanding climbing tower crane support system
CN207526141U (en) Small-section tower-shaped steel structure assembled operating platform
CN110295607A (en) A kind of Larsen steel sheep pile support structure and method for supporting
CN113756504B (en) Construction method of right-angle aluminum alloy latticed shell with external corners
CN201825673U (en) Double-tower type low-tower frame self-balance lifting device
CN205575534U (en) Lattice formula groined type support body lifting means
CN108517970A (en) A kind of large-span truss hanging method
CN203795824U (en) Suspension type fastener scaffold erecting device
CN209620622U (en) A kind of promotion platform
CN211647379U (en) Interim device of dysmorphism component installation
CN209179519U (en) Hang the truss splicing steel construction moulding bed of auxiliary installation in a kind of gymnasium top
CN202769631U (en) Pipeline supporting and hanging structure
CN202790959U (en) Steel pipe truss structure based on aloft lateral support
CN203452291U (en) Sun-shading pull bar supporting system for construction
CN202913356U (en) Load-bearing frame for bridge construction
CN201915616U (en) Improved bidirectional stressed foundation joint attached to lifting scaffold

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhang Yongtao

Inventor after: Chen Jianrong

Inventor after: Peng Peng

Inventor after: Peng Qiang

Inventor after: Qin Zonghua

Inventor after: Mao Changqing

Inventor after: Zheng Xianhe

Inventor after: Yao Qingtao

Inventor before: Chen Jianrong

Inventor before: Peng Peng

Inventor before: Peng Qiang

Inventor before: Qin Zonghua

Inventor before: Mao Changqing

Inventor before: Zheng Xianhe

Inventor before: Yao Qingtao

CB03 Change of inventor or designer information