CN104895053A - 一种节段式空腔灌注桩的施工方法 - Google Patents
一种节段式空腔灌注桩的施工方法 Download PDFInfo
- Publication number
- CN104895053A CN104895053A CN201510331517.3A CN201510331517A CN104895053A CN 104895053 A CN104895053 A CN 104895053A CN 201510331517 A CN201510331517 A CN 201510331517A CN 104895053 A CN104895053 A CN 104895053A
- Authority
- CN
- China
- Prior art keywords
- reinforcing cage
- pile
- sectional type
- fluid injection
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
本发明公开了一种节段式空腔灌注桩的施工方法:设置分段式具有注液腔体的钢筋笼体,将数个所述钢筋笼体同轴线的依次下放安装至施工现场的桩孔内,每一段钢筋笼体的上端下放至所述桩孔的孔口位置时,向该段钢筋笼体的注液腔体内注入液体并与相邻的上段钢筋笼体连接,如此重复,直至全部钢筋笼体下放至所述桩孔,形成接成一体的钢筋笼桩,然后向桩孔内的所述钢筋笼桩浇筑混凝土,形成灌注桩。本发明减小桩身自重,在达到相同竖向承载能力的情况下,可减小桩体长度或直径,降低工程造价和灌注桩成孔费用,减少弃土和泥浆排放。
Description
技术领域:
本发明涉及一种节段式空腔灌注桩的施工方法。
背景技术:
混凝土灌注桩具有单桩承载力大、桩长和桩径设计灵活、施工受环境限制少等优点广泛应用于各类土木工程,如楼房、桥梁、码头等。但在应用过程中,灌注桩存在以下不足,如:
(1)桩体自重过大,损失一部分竖向承载能力;
(2)在保证灌注桩安全系数的前提下,桩体的实际使用压应力远小于其设计时抗压强度设计值,以至于在浇筑过程中混凝土用量过多,造成材料浪费;
(3)施工中产生弃土和泥浆。
发明内容:
本发明提供一种能够满足桩基础各项承载能力和耐久性的同时,减小桩身自重和灌注桩混凝土用量的节段式空腔灌注桩的施工方法。
为了实现上述发明目的,本发明提供一种节段式空腔灌注桩的施工方法,设置分段式具有注液腔体的钢筋笼体,将数个所述钢筋笼体同轴线的依次下放安装至施工现场的桩孔内,每一段钢筋笼体的上端下放至所述桩孔的孔口位置时,向该段钢筋笼体的注液腔体内注入液体并与相邻的上段钢筋笼体连接,如此重复,直至全部钢筋笼体下放至所述桩孔,形成接成一体的钢筋笼桩,然后向桩孔内的所述钢筋笼桩浇筑混凝土,形成灌注桩。
进一步地,所述钢筋笼体包括钢筋笼、注液腔体、固定环和固定绳,注液腔体通过固定环和固定绳固定在钢筋笼内。
进一步地,所述钢筋笼包括主筋和箍筋,若干所述主筋围成一圆柱状的笼体,所述箍筋环绕设置在该笼体上。
进一步地,所述注液腔体与钢筋笼同轴设置。
进一步地,所述注液腔体为上下两端为球面的圆柱体,且上端球面上设有注入口。
进一步地,所述注液腔体外圆周面上设有凹槽。
进一步地,所述注入口上连接有阀。
进一步地,所述阀包括连接管和弹性管,所述弹性管的上管口与连接管的下管口密封连接,所述连接管密封设置在注入口上。
进一步地,所述注液腔体内注入的液体为水。
本发明利用注液腔体代替部分混凝土,在满足桩基础各项承载能力和耐久性的同时,又节约灌注桩混凝土用量。由此产生的有益效果是:减小桩身自重,该减小量可用于承担上部荷载,在达到相同竖向承载能力的情况下,可减小桩体长度或直径,降低工程造价和灌注桩成孔费用,减少弃土和泥浆排放,节能环保。
附图说明:
图 1 为本发明剖视结构示意图。
图 2 为本发明局部剖视结构示意图。
图 3 为图 2中桩体剖视结构示意图。
其中
1、注液腔体;2、阀;3、固定环;4、固定绳;5、灌注桩;6、钢筋笼;11、凹槽;61、主筋;62、箍筋。
具体实施方式:
下面结合附图对本发明作进一步的说明。
请参照图1至图3,本发明一种节段式空腔灌注桩的施工方法,该施工方法是设置分段式具有注液腔体1的钢筋笼体,将数个钢筋笼体同轴线的依次下放安装至施工现场的桩孔内,当第一段钢筋笼体的上端口下放至施工现场桩孔的孔口位置时,向第一段钢筋笼体的注液腔体1内注入液体,并将第二段钢筋笼体的下端口与第一段钢筋笼体的上端口固定连接,接着下放第二段钢筋笼体至第二段钢筋笼体的上端口至桩孔的孔口位置时,向第二段钢筋笼体的注液腔体1内注入液体,如此重复第二段钢筋笼体的施工过程安装余下的钢筋笼体,直至余下的钢筋笼体填充完整桩孔并形成钢筋笼桩,然后向桩孔内的钢筋笼桩浇筑混凝土,直至混凝土完全覆盖钢筋笼桩,形成灌注桩5。
本发明中钢筋笼体包括钢筋笼6、注液腔体1、固定环3和固定绳4,固定环3和固定绳4分别固定连接在注液腔体1的上下两端,注液腔体1通过固定环3和固定绳4固定在钢筋笼6内,且注液腔体1与钢筋笼6同轴设置。
本发明中的钢筋笼6包括主筋61和箍筋62,若干根主筋61围成一圆柱状的笼体,箍筋62环绕设置在该笼体上,注液腔体1通过固定环3和固定绳4固定连接在钢筋笼6的主筋61上。
注液腔体1为上下两端为球面的圆柱体,且上侧球面上设有注入口,注入口上连接有阀2,通过外接水管向注液腔体1内注水。在注液腔体1内水注满后,抽离外接水管,关闭将阀2,使得注液腔体1内的液体不外漏。
本发明为增加注液腔体与注液腔体周围混凝土的摩擦力,在注液腔体1的外圆周面上分层设有若干凹槽11。
本发明中的注液腔体1灌满水的作用一方面增加抗压性能,另一方面减小浮力,防止带动钢筋笼6在桩孔内上浮,以及防止拉断系环3和系绳4,因此,注液腔体1安装位置和数量应事先核算,已保证钢筋笼6的重量加其与混凝土的摩擦力之和大于注液腔体1在流态混凝土中的浮力,并有一定的安全富余。
注液腔体1两端为球面,以提高注液腔体1的抗压性能。注液腔体1的侧面凹槽11以增加注液腔体1与周围混凝土的摩擦力,抑制注液腔体1上浮,并减小系环3和系绳4的拉力。注液腔体1的尺度根据灌注桩5、混泥土导管尺度、灌注桩5力学要求、以及制作、运输、安装等工艺确定。注液腔体1为一容器体,该容器体可用高分子聚合材料,如PVC、尼龙等制成,也可在制作时内部灌注发泡体代替现场灌水,从而提高安装效率,但要保证系环3和系绳4的强度,并核算防止上浮的安全性。
钢筋笼6及注液腔体1安装完成后,采用双导管或三导管方式进行混凝土灌注,要求导管避开系绳4沿钢筋笼6和注液腔体1之间空隙下放,并沿圆周均匀布置,灌注过程中应同步升降。混凝土灌注工艺要求与常规灌注桩相同。
以上所述仅是本发明的优选实施方式,应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下还可以作出若干改进,这些改进也应视为本发明的保护范围。
Claims (8)
1. 一种节段式空腔灌注桩的施工方法,其特征在于:设置分段式具有注液腔体(1)的钢筋笼体,将数个所述钢筋笼体同轴线的依次下放安装至施工现场的桩孔内,每一段钢筋笼体的上端下放至所述桩孔的孔口位置时,向该段钢筋笼体的注液腔体(1)内注入液体并与相邻的上段钢筋笼体连接,如此重复,直至全部钢筋笼体下放至所述桩孔,形成接成一体的钢筋笼桩,然后向桩孔内的所述钢筋笼桩浇筑混凝土,形成灌注桩。
2.如权利要求1所述的节段式空腔灌注桩的施工方法,其特征在于:所述钢筋笼体包括钢筋笼(6)、注液腔体(1)、固定环(3)和固定绳(4),注液腔体(1)通过固定环(3)和固定绳(4)固定在钢筋笼(6)内。
3.如权利要求2所述的节段式空腔灌注桩的施工方法,其特征在于:所述钢筋笼(6)包括主筋(61)和箍筋(62),若干所述主筋(61)围成一圆柱状的笼体,所述箍筋(62)环绕设置在该笼体上。
4.如权利要求2所述的节段式空腔灌注桩的施工方法,其特征在于:所述注液腔体(1)与钢筋笼(6)同轴设置。
5.如权利要求1所述的节段式空腔灌注桩的施工方法,其特征在于:所述注液腔体(1)为上下两端为球面的圆柱体,且上端球面上设有注入口。
6.如权利要求1所述的节段式空腔灌注桩的施工方法,其特征在于:所述注液腔体(1)外圆周面上设有凹槽(11)。
7.如权利要求5所述的节段式空腔灌注桩的施工方法,其特征在于:所述注入口上连接有阀(2)。
8.如权利要求1所述的节段式空腔灌注桩的施工方法,其特征在于:所述注液腔体(1)内注入的液体为水。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510331517.3A CN104895053B (zh) | 2015-06-16 | 2015-06-16 | 一种节段式空腔灌注桩的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510331517.3A CN104895053B (zh) | 2015-06-16 | 2015-06-16 | 一种节段式空腔灌注桩的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104895053A true CN104895053A (zh) | 2015-09-09 |
CN104895053B CN104895053B (zh) | 2017-03-22 |
Family
ID=54027982
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510331517.3A Expired - Fee Related CN104895053B (zh) | 2015-06-16 | 2015-06-16 | 一种节段式空腔灌注桩的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104895053B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106894411A (zh) * | 2017-02-25 | 2017-06-27 | 荆门创佳机械科技有限公司 | 一种液压预应力钢管桩 |
CN107059843A (zh) * | 2017-02-24 | 2017-08-18 | 荆门创佳机械科技有限公司 | 一种充气预应力钢管桩及施工方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05132929A (ja) * | 1991-11-14 | 1993-05-28 | Jiototsupu:Kk | 中空場所打ち杭の造成方法 |
CN1083151A (zh) * | 1991-03-09 | 1994-03-02 | 株式会社北雄产业 | 现场浇注空心混凝土桩的制作方法和制作装置 |
CN1186141A (zh) * | 1997-12-25 | 1998-07-01 | 叶长生 | 一种灌注桩及其施工方法 |
CN103422495A (zh) * | 2013-07-25 | 2013-12-04 | 科达集团股份有限公司 | 一种空心钻孔灌注桩及其施工方法 |
CN204715347U (zh) * | 2015-06-16 | 2015-10-21 | 苏交科集团股份有限公司 | 一种节段式空腔灌注桩 |
-
2015
- 2015-06-16 CN CN201510331517.3A patent/CN104895053B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1083151A (zh) * | 1991-03-09 | 1994-03-02 | 株式会社北雄产业 | 现场浇注空心混凝土桩的制作方法和制作装置 |
JPH05132929A (ja) * | 1991-11-14 | 1993-05-28 | Jiototsupu:Kk | 中空場所打ち杭の造成方法 |
CN1186141A (zh) * | 1997-12-25 | 1998-07-01 | 叶长生 | 一种灌注桩及其施工方法 |
CN103422495A (zh) * | 2013-07-25 | 2013-12-04 | 科达集团股份有限公司 | 一种空心钻孔灌注桩及其施工方法 |
CN204715347U (zh) * | 2015-06-16 | 2015-10-21 | 苏交科集团股份有限公司 | 一种节段式空腔灌注桩 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059843A (zh) * | 2017-02-24 | 2017-08-18 | 荆门创佳机械科技有限公司 | 一种充气预应力钢管桩及施工方法 |
CN106894411A (zh) * | 2017-02-25 | 2017-06-27 | 荆门创佳机械科技有限公司 | 一种液压预应力钢管桩 |
Also Published As
Publication number | Publication date |
---|---|
CN104895053B (zh) | 2017-03-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101270582B (zh) | 地下洞室内设置支撑柱的方法 | |
CN104179174B (zh) | 一种多孔注浆管异形桩及其成桩方法 | |
CN102086645B (zh) | 嵌岩桩及其施工方法 | |
CN111622207B (zh) | 一种诱导式注浆方法 | |
CN107761722B (zh) | 一种提高钢管桩桩侧承载力的装置及方法 | |
CN109138011B (zh) | 既有建筑物地基加固与纠偏方法 | |
CN105804076A (zh) | 预应力锚索以及基坑支护预应力锚索施工方法 | |
CN110966026A (zh) | 一种高水充填支柱巷旁支护方法 | |
CN204023559U (zh) | 一种多孔注浆管异形桩 | |
CN110130324B (zh) | 一种钢管微型桩及其施工方法 | |
CN204715347U (zh) | 一种节段式空腔灌注桩 | |
CN104895053A (zh) | 一种节段式空腔灌注桩的施工方法 | |
CN105369799A (zh) | 预制桩地下连续墙混凝土预制桩及施工方法 | |
CN108842792B (zh) | 一种分层内抬升卸荷式地拉锚杆及施工方法 | |
CN101793027B (zh) | 一种桩心注浆静压锚杆桩 | |
CN105605335A (zh) | 一种用于顶进施工的大口径预应力钢筒混凝土管 | |
CN210315518U (zh) | 一种钢管微型桩 | |
CN105134125B (zh) | 瓦斯立井壁后环空底端封堵施工工艺 | |
CN104452746A (zh) | 一种钻孔灌注桩的施工方法 | |
CN111519604A (zh) | 一种深孔袖阀管注浆装置及其应用方法 | |
CN106245641A (zh) | Phc管桩后压浆施工工艺及phc管桩复合桩 | |
CN107218010B (zh) | 破损钻孔套管堵水桥塞及双桥塞式堵水方法 | |
CN206110124U (zh) | 一种灌注桩桩端后压浆装置 | |
CN102733414B (zh) | 方锥型锚墩联合水平撑杆的水池抗浮方法 | |
CN107882020A (zh) | 一种小直径树根桩施工方法及清洗注浆装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Xu Zhishuan Inventor after: Fu Gui Inventor before: Xu Zhishuan Inventor before: Li Xu |
|
COR | Change of bibliographic data | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170322 Termination date: 20170616 |
|
CF01 | Termination of patent right due to non-payment of annual fee |