CN104859788A - Octagon floating drilling production storage and offloading (FDPSO) rapid construction method - Google Patents

Octagon floating drilling production storage and offloading (FDPSO) rapid construction method Download PDF

Info

Publication number
CN104859788A
CN104859788A CN201510232282.2A CN201510232282A CN104859788A CN 104859788 A CN104859788 A CN 104859788A CN 201510232282 A CN201510232282 A CN 201510232282A CN 104859788 A CN104859788 A CN 104859788A
Authority
CN
China
Prior art keywords
fdpso
octagon
dock
buoyancy aid
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510232282.2A
Other languages
Chinese (zh)
Other versions
CN104859788B (en
Inventor
马延德
谢彬
董庆辉
王世圣
谢文会
喻西崇
赵静
刘健
孙瑞雪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China National Offshore Oil Corp CNOOC
CNOOC Research Institute Co Ltd
Dalian Shipbuilding Industry Co Ltd
Original Assignee
China National Offshore Oil Corp CNOOC
CNOOC Research Institute Co Ltd
Dalian Shipbuilding Industry Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China National Offshore Oil Corp CNOOC, CNOOC Research Institute Co Ltd, Dalian Shipbuilding Industry Co Ltd filed Critical China National Offshore Oil Corp CNOOC
Priority to CN201510232282.2A priority Critical patent/CN104859788B/en
Publication of CN104859788A publication Critical patent/CN104859788A/en
Application granted granted Critical
Publication of CN104859788B publication Critical patent/CN104859788B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Buildings Adapted To Withstand Abnormal External Influences (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention relates to an octagon FDPSO rapid construction method comprising steps of: (1) building a lower buoyancy aid and an internal function cabin of the octagon FDPSO on a berth or on a plane ground; (2) at the same time, dividing an upper buoyancy aid of the FDPSO into a plurality of functional blocks and conducting individual construction of the plurality of functional blocks on land in the peripheral of a dock; (3) launching the lower buoyancy aid after the construction thereof and dragging the whole body of the buoyancy aid within the dock, closing a dock gate, withdrawing water from the dock so as to anchor the lower buoyancy aid within the dock; (4) lifting the plurality of functional areas the construction of which has been completed to the upper part of the lower buoyancy aid through a suspension apparatus for modular assembly and folding; (5) installing and debugging relevant work equipments of each functional area; (6) opening the dock gate and filling in water so as to make the octagon FDPSO float in the ocean under seawater buoyancy effect. The synchronous construction of the upper and lower parts of the octagon FDPSO of the present invention shortens the time for building required on berth, dock or plane ground, thus achieving the purpose of rapid construction.

Description

A kind of fast construction method of octagon FDPSO
Technical field
The present invention relates to a kind of fast construction method of octagon FDPSO, belong to field of ocean engineering.
Background technology
In order to meet economy and the practicality requirement of ocean marginal oil field, be developed and a kind ofly integrate drilling well, oil recovery, production, oil storage and outer defeated octagon FDPSO (floating drilling, production, storage and offloading unit, floating type well drilling, production storage handler) Multifunctional marine design library part editor and reuse.As Figure 1 and Figure 4, the bottom buoyancy aid 1 of octagon FDPSO, in order to meet the requirement of stability, is designed to size and from larger eight prism structures of weight average, the inside of eight prisms is provided with multiple functional cabin 11 by dividing plate by this device.Meanwhile, in order to meet the demand such as drilling and storage of oil, the deck of the top buoyancy aid 2 of the octagon FDPSO be wholely set with bottom buoyancy aid 1 being divided into the mac function of multiple intensive layout, each mac function being configured with corresponding working equipment 22.
Because this octagon FDPSO volume is comparatively large, therefore the construction of this device can only adopt at present and build in dock after floating launching, build on building berth after dynamic launching or build rear dragging move to half and dive and refute the three kinds of mode of construction that launch a ship on level land.But all there is certain defect in these three kinds of mode of construction, when adopt build in dock time, due to octagon FDPSO cross section and height dimension is excessive, functional module arrange intensive, therefore make the production cycle in dock extend; When employing is built on building berth, because the principal dimensions of octagon FDPSO and body are from great, the bearing capacity of conventional launching platform and size can not meet its lower water demand, therefore need to carry out large-scale redevelopment to building berth, but which not only adds shipbuilding cost, but also there is certain potential safety hazard, make production cycle become longer; When employing is built on level land, although dock and building berth resource can not be taken, but because octagon FDPSO principal dimensions and body are from great, level land is built and is required higher to harbour foundation bearing, corresponding barge etc. of half-and-half diving is built resource allocation request and also can correspondingly be improved, and then adds the cost of shipbuilding.
Summary of the invention
For the problems referred to above, the object of this invention is to provide and a kind ofly can reduce dock, building berth resource occupation time and significantly reduce the fast construction method of the octagon FDPSO of laid down cost pacifically.
For achieving the above object, the present invention takes following technical scheme: a kind of fast construction method of octagon FDPSO, and it comprises following content:
1) on building berth or level land, carry out the bottom buoyancy aid of octagon FDPSO and the construction in its inside function cabin;
2) carry out step 1) while, the top buoyancy aid of octagon FDPSO is divided into multiple mac function to build respectively by the surrounding lands of dock;
3) after the bottom buoyancy aid of octagon FDPSO has been built, by its lower water and entirety drags in dock, close dock gate and also dock is drawn water, make the bottom buoyancy aid pedestal of octagon FDPSO in dock;
4) by constructed multiple mac function by hanging apparatus respectively handling carry out modularization assembling to the top of the bottom buoyancy aid of octagon FDPSO and close up, make it form the top buoyancy aid of a complete octagon FDPSO;
5) in the installation and adjustment work of the enterprising line correlation working equipment of each mac function;
6) open dock gate and make water-filling in dock, octagon FDPSO entirety under buoyant of sea water effect floats on marine, and then the lower water conservancy project completing octagon FDPSO is done.
Build size and weight demands that the described building berth of the bottom buoyancy aid of described octagon FDPSO or level land need meet the bottom buoyancy aid of described octagon FDPSO.
The described hanging apparatus used needs size and the weight demands of content with funtion block.
Described hanging apparatus adopts large-sized gantry to hang or marine crane barge hanging apparatus.
The present invention is owing to taking above technical scheme, it has the following advantages: 1, the present invention builds owing to octagon FDPSO to be divided into upper and lower two parts simultaneously, therefore shorten and take the time that resource built pacifically by building berth, dock, increasing not significantly under laid down cost prerequisite, reaching fast construction object.2, the present invention builds due to top buoyancy aid is divided into multiple mac function, and by hanging apparatus, each mac function is carried out modularization assembling at buoyancy aid top, bottom and closed up, operation side has been carried out plane expansion by actv., thus shortens production cycle, reduces laid down cost.
Accompanying drawing explanation
Fig. 1 is the integral structure schematic diagram of existing octagon FDPSO;
Fig. 2 is the construction diagram of circuit of octagon FDPSO of the present invention;
Fig. 3 is the top buoyancy aid A-A cross section structure schematic diagram of octagon FDPSO of the present invention;
Fig. 4 is the bottom buoyancy aid B-B cross section structure schematic diagram of octagon FDPSO of the present invention.
Detailed description of the invention
Below in conjunction with drawings and Examples, the present invention is described in detail.
As shown in Figure 2 and Figure 3, the inventive method comprises the following steps:
1) on building berth or level land 3, the bottom buoyancy aid 1 of octagon FDPSO and the construction in its inside function cabin 11 is carried out.
2) carry out step 1) while, the top buoyancy aid 2 of octagon FDPSO is divided into multiple mac function 21 to build respectively by the surrounding lands of dock 4.
3) after the bottom buoyancy aid 1 of octagon FDPSO has been built, by its lower water and entirety drags in dock 6, close dock gate 5 and also dock 6 is drawn water, make bottom buoyancy aid 1 pedestal of octagon FDPSO in dock 6.
4) by constructed multiple mac function 21 by hanging apparatus respectively handling carry out modularization assembling to the top of bottom buoyancy aid 1 and close up, make it form the top buoyancy aid 2 (as shown in Figure 3) of a complete octagon FDPSO.
5) in the installation and adjustment work of the enterprising line correlation working equipment of each mac function 21.
6) open dock gate 5 and make water-filling in dock 6, octagon FDPSO entirety under buoyant of sea water effect floats on marine, and then the lower water conservancy project completing octagon FDPSO is done.
In above-described embodiment, the building berth of construction bottom buoyancy aid 1 or level land 3 need meet size and the weight demands of bottom buoyancy aid 1.
In above-described embodiment, the hanging apparatus of use needs size and the weight demands of content with funtion block 21.
In above-described embodiment, hanging apparatus can adopt large-sized gantry to hang or marine crane barge hanging apparatus.
The various embodiments described above are only for illustration of the present invention, and wherein the structure, connection mode etc. of each parts all can change to some extent, and every equivalents of carrying out on the basis of technical solution of the present invention and improvement, all should not get rid of outside protection scope of the present invention.

Claims (5)

1. a fast construction method of octagon FDPSO, it comprises following content:
1) on building berth or level land, carry out the bottom buoyancy aid of octagon FDPSO and the construction in its inside function cabin;
2) carry out step 1) while, the top buoyancy aid of octagon FDPSO is divided into multiple mac function to build respectively by the surrounding lands of dock;
3) after the bottom buoyancy aid of octagon FDPSO has been built, by its lower water and entirety drags in dock, close dock gate and also dock is drawn water, make the bottom buoyancy aid pedestal of octagon FDPSO in dock;
4) by constructed multiple mac function by hanging apparatus respectively handling carry out modularization assembling to the top of the bottom buoyancy aid of octagon FDPSO and close up, make it form the top buoyancy aid of a complete octagon FDPSO;
5) in the installation and adjustment work of the enterprising line correlation working equipment of each mac function;
6) open dock gate and make water-filling in dock, octagon FDPSO entirety under buoyant of sea water effect floats on marine, and then the lower water conservancy project completing octagon FDPSO is done.
2. the fast construction method of a kind of octagon FDPSO as claimed in claim 1, is characterized in that: build size and weight demands that the described building berth of the bottom buoyancy aid of described octagon FDPSO or level land need meet the bottom buoyancy aid of described octagon FDPSO.
3. the fast construction method of a kind of octagon FDPSO as claimed in claim 1, is characterized in that: the described hanging apparatus of use needs size and the weight demands of content with funtion block.
4. the fast construction method of a kind of octagon FDPSO as claimed in claim 2, is characterized in that: the described hanging apparatus of use needs size and the weight demands of content with funtion block.
5. the fast construction method of a kind of octagon FDPSO as claimed in claim 1 or 2 or 3 or 4, is characterized in that: described hanging apparatus adopts large-sized gantry to hang or marine crane barge hanging apparatus.
CN201510232282.2A 2015-05-08 2015-05-08 A kind of quick method of construction of octagonal FDPSO Active CN104859788B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510232282.2A CN104859788B (en) 2015-05-08 2015-05-08 A kind of quick method of construction of octagonal FDPSO

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510232282.2A CN104859788B (en) 2015-05-08 2015-05-08 A kind of quick method of construction of octagonal FDPSO

Publications (2)

Publication Number Publication Date
CN104859788A true CN104859788A (en) 2015-08-26
CN104859788B CN104859788B (en) 2018-05-04

Family

ID=53906069

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510232282.2A Active CN104859788B (en) 2015-05-08 2015-05-08 A kind of quick method of construction of octagonal FDPSO

Country Status (1)

Country Link
CN (1) CN104859788B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107187545A (en) * 2017-05-22 2017-09-22 南通中远船务工程有限公司 The installation method of gas compression Module functionality unit
CN107264721A (en) * 2017-05-22 2017-10-20 南通中远船务工程有限公司 The installation method of gas compression module

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102145734A (en) * 2010-02-10 2011-08-10 烟台来福士海洋工程有限公司 Method for integrally folding semi-submersible drilling platform
KR20120032609A (en) * 2010-09-29 2012-04-06 대우조선해양 주식회사 Method for installing the topside of floating marine plant
CN102849180A (en) * 2012-09-18 2013-01-02 渤海装备辽河重工有限公司 Launching process of jack-up offshore drilling platform by airbag
CN202743445U (en) * 2012-06-07 2013-02-20 中国海洋石油总公司 Floating type production platform with both drilling and oil storage functions
CN103171743A (en) * 2012-10-15 2013-06-26 大连理工大学 Butting octagonal frustum pyramid type floating production and oil storage system
CN103213654A (en) * 2010-03-10 2013-07-24 烟台来福士海洋工程有限公司 Construction method for ocean platform
CN103921905A (en) * 2014-04-17 2014-07-16 大连理工大学 Semi-submersible module for combining into large-scale floating body on the water and assembling method thereof

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102145734A (en) * 2010-02-10 2011-08-10 烟台来福士海洋工程有限公司 Method for integrally folding semi-submersible drilling platform
CN103213654A (en) * 2010-03-10 2013-07-24 烟台来福士海洋工程有限公司 Construction method for ocean platform
KR20120032609A (en) * 2010-09-29 2012-04-06 대우조선해양 주식회사 Method for installing the topside of floating marine plant
CN202743445U (en) * 2012-06-07 2013-02-20 中国海洋石油总公司 Floating type production platform with both drilling and oil storage functions
CN102849180A (en) * 2012-09-18 2013-01-02 渤海装备辽河重工有限公司 Launching process of jack-up offshore drilling platform by airbag
CN103171743A (en) * 2012-10-15 2013-06-26 大连理工大学 Butting octagonal frustum pyramid type floating production and oil storage system
CN103921905A (en) * 2014-04-17 2014-07-16 大连理工大学 Semi-submersible module for combining into large-scale floating body on the water and assembling method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107187545A (en) * 2017-05-22 2017-09-22 南通中远船务工程有限公司 The installation method of gas compression Module functionality unit
CN107264721A (en) * 2017-05-22 2017-10-20 南通中远船务工程有限公司 The installation method of gas compression module
CN107187545B (en) * 2017-05-22 2019-11-05 南通中远海运船务工程有限公司 The installation method of gas compression Module functionality unit

Also Published As

Publication number Publication date
CN104859788B (en) 2018-05-04

Similar Documents

Publication Publication Date Title
CN108820148B (en) Semi-submersible platform and lower floating body thereof
CN205707197U (en) Waters information monitoring platform
CN105151236A (en) Platform device for submerging, surfacing, moving and carrying floating piers and towers and working method thereof
CN102296565A (en) Deep-water ring-shaped floating type artificial harbor
CN104743058B (en) The method of tension leg platform (TLP) upper chunk floating support mounting
CN105480380B (en) Tension leg platform (TLP) upper module and the closure workmanship of lower float structure
CN205150165U (en) Ship's fix anchor system
CN109866887A (en) The oblique self-stabilization type semi-submerged platform of column outside a kind of band
CN105083471A (en) Ship positioning anchor system
CN106715255A (en) Buoyant turret mooring with porous turret cage
CN103241668A (en) Device and method for installing deep sea submarine storage tank
CN104802928A (en) Semi-submersible platform building combining method
CN104210627A (en) Device and method for launching after flat ground construction of self-elevating platform
KR20170039613A (en) Buoyant structure for petroleum drilling
US7270071B1 (en) Deep draft semisubmersible movable offshore structure
CN104859788A (en) Octagon floating drilling production storage and offloading (FDPSO) rapid construction method
CN103074878A (en) Construction method for artificial island platform
CN104452790A (en) Caisson with apron boards and adjusting method for caisson during air floatation towing
CN103374905A (en) Movable self-installation platform
CN203064175U (en) Artificial island platform
CN203472445U (en) Walking type semi-submersible amphibious engineering ship
KR102117387B1 (en) Arrangement scheme of living quarter in semi-submersible drilling rig
CN104802950A (en) Self-elevating type underwater floater tension leg platform and establishing method thereof
CN204623785U (en) A kind of jack up underwater buoyant body tension leg platform
CN107323618A (en) A kind of series connection many float-type mixing mooring and positioning systems of new tension leg platform (TLP) for ultra-deep-water operation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 100010 Beijing, Chaoyangmen, North Street, No. 25, No.

Applicant after: China Offshore Oil Group Co., Ltd.

Applicant after: CNOOC research institute limited liability company

Applicant after: Dalian Shipping Heavy Industry Group Co., Ltd.

Address before: 100010 Beijing, Chaoyangmen, North Street, No. 25, No.

Applicant before: China National Offshore Oil Corporation

Applicant before: CNOOC Research Institute

Applicant before: Dalian Shipping Heavy Industry Group Co., Ltd.

CB02 Change of applicant information
GR01 Patent grant
GR01 Patent grant