CN104847049B - Ceiling structure - Google Patents

Ceiling structure Download PDF

Info

Publication number
CN104847049B
CN104847049B CN201510283104.2A CN201510283104A CN104847049B CN 104847049 B CN104847049 B CN 104847049B CN 201510283104 A CN201510283104 A CN 201510283104A CN 104847049 B CN104847049 B CN 104847049B
Authority
CN
China
Prior art keywords
suspension member
extension portion
main suspension
extension
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510283104.2A
Other languages
Chinese (zh)
Other versions
CN104847049A (en
Inventor
谭泳霖
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGZHOU GUANGJIN DECORATION MATERIALS CO Ltd
Original Assignee
GUANGZHOU GUANGJIN DECORATION MATERIALS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGZHOU GUANGJIN DECORATION MATERIALS CO Ltd filed Critical GUANGZHOU GUANGJIN DECORATION MATERIALS CO Ltd
Priority to CN201510283104.2A priority Critical patent/CN104847049B/en
Publication of CN104847049A publication Critical patent/CN104847049A/en
Application granted granted Critical
Publication of CN104847049B publication Critical patent/CN104847049B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Building Environments (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of ceiling structure, including:Spandrel girder, spandrel girder are fixed on metope, provided with the first extension portion;Main suspension member, main suspension member are provided with load receiving part and the second extension portion, and load receiving part is provided with keel in itself for carrying keel or load receiving part;Wherein, the first extension portion mutually mounts with the second extension portion, and main suspension member carry is on spandrel girder.Keel are installed by the way of carry, direct carry keel after spandrel girder is installed, avoids hammering into suspension rod one by one the troublesome operation of expandable nail, it is easy for installation, it is easily disassembled after installation.

Description

Ceiling structure
Technical field
The invention belongs to the field of fitting up, and in particular to a kind of smallpox framework.
Background technology
Ceiling is installed on roof, the roof space can be beautified, using multilayer ceiling structure, level can be utilized Visual effect make floor space structure more attractive.But traditional installation furred ceiling method is the default position according to keel Put, position the position of expandable nail, expandable nail is squeezed on roof, suspension rod is hung on into roof, suspension rod bottom is provided with hook, links up with hook Keel are hung, typically fixing keel needs multiple hooks, roof needs to head into many expandable nails, multiple keel that tangle , it is necessary to the artificial length for adjusting suspension rod one by one, adjustment keel is horizontal, then installs ceiling on keel again for end or middle part, It is very inconvenient that workers with long time faces upward head operation.Also, this installation method complexity is cumbersome, and need to carry out complicated positioning, For Levelling operation, it is necessary to there is the professional installer of experience to install, labor intensity is big and takes considerable time, once installation, It will be difficult to adjust and dismantle, and be unfavorable for maintenance and the installation other equipment in later stage.
The content of the invention
Based on this, the present invention disclose a kind of ceiling structure, and keel are installed by the way of carry, installs after spandrel girder directly Carry keel are connect, avoid hammering into suspension rod one by one the troublesome operation of expandable nail, it is easy for installation, it is easily disassembled after installation.
A kind of ceiling structure, including:Spandrel girder, spandrel girder are fixed on metope, provided with the first extension portion;Main suspension member, main suspension member Provided with load receiving part and the second extension portion, load receiving part is provided with keel in itself for carrying keel or load receiving part;Wherein, the first extension portion and the Two extension portions mutually mount, and main suspension member carry is on spandrel girder.
In one of the embodiments, main suspension member comprises at least the first main suspension member and the second main suspension member, the first main suspension member The distance between second extension portion and load receiving part are more than the distance between the second extension portion and load receiving part of the second main suspension member.
In one of the embodiments, the first extension portion is setting up and down at least two layers, or/and, the second extension portion is upper and lower At least two layers set.
In one of the embodiments, main suspension member comprises at least the first main suspension member and the second main suspension member, the first main suspension member Cooperation between the second extension portion and the first extension portion of cooperation and the second main suspension member between second extension portion and the first extension portion is wrong up and down Open, the load receiving part of the first main suspension member and the load receiving part of the second main suspension member are staggered up and down, are formed sandwich construction.
In one of the embodiments, the first extension portion or/and the second extension portion are slideway, and the first extension portion and the second extension portion are slided Coordinate.
In one of the embodiments, the first extension portion includes the first hook portion and the second hook portion, and the second extension portion is provided with and is engaged The 3rd hook portion and the 4th hook portion, the first hook portion and the 3rd hook portion mutually hook cooperation, the second hook portion and the 4th mutual hook of hook portion Hang and coordinate.
In one of the embodiments, secondary suspension member is also included, main suspension member is provided with the 3rd extension portion, and secondary suspension member is provided with the 4th and hung Portion, the 3rd extension portion and the 4th extension portion mutually mount, secondary suspension member carry is on main suspension member.
In one of the embodiments, main suspension member be at least two, secondary suspension member simultaneously carry at least two main suspension members.
In one of the embodiments, the 3rd extension portion is setting up and down at least two layers, or/and, the 4th extension portion is upper and lower At least two layers set.
In one of the embodiments, secondary suspension member include at least two layers it is setting up and down carry additionally part, most last layer is carried additionally Part is provided with the 4th extension portion, and adjacent two layers carry additionally part and are provided with the hanging structure being mutually matched and mutually mount.
The advantages of below to such scheme or principle illustrate:
1st, ceiling structure includes:Spandrel girder, main suspension member;
Spandrel girder is fixed on metope, and to provide support to live suspension member, spandrel girder is provided with the first extension portion, and main suspension member is provided with the Two extension portions, the first extension portion mutually mount with the second extension portion, and main suspension member carry is on spandrel girder, it is only necessary to fix spandrel girder and wall Face, it is possible to main suspension member is installed by way of carry, it is not necessary to which nail main suspension member again in addition, and load receiving part is used to carry Keel or load receiving part are provided with keel in itself, and keel can be used for installing ceiling, and after the main suspension member of carry, the position of keel is true It is fixed, it is not necessary to leveling again, it is simple to operate, and the mode of carry can be with nondestructive demounting, as long as the first extension portion is hung with second Portion matches can carry and arranged in pairs or groups on spandrel girder, can changing different main suspension members, after ceiling structure installation after can To load and unload repeatedly, decorate beneficial to safeguarding with change.
2nd, main suspension member comprises at least the first main suspension member and the second main suspension member, the second extension portion of the first main suspension member and load receiving part it Between distance be more than the second extension portion and the distance between load receiving part of the second main suspension member, by the first main suspension member of different length and Collocation between second main suspension member, multilayer load receiving part up and down can be formed, step-like sandwich construction is formed after ceiling is installed, It is easy to operate.
3rd, the first extension portion is setting up and down at least two layers, or/and, the second extension portion is setting up and down at least two layers, the When one extension portion is multilayer, the second extension portion can adjust single main suspension member relative to spandrel girder with carry in the first extension of any layer portion Height and position;Similarly or the second extension of multilayer portion) or the first extension portion and the second extension portion be simultaneously multilayer.
4th, main suspension member comprises at least the first main suspension member and the second main suspension member, the second extension portion and the first extension portion of the first main suspension member Between the main suspension member of cooperation and second the second extension portion and the first extension portion between cooperation up and down stagger, make the first main suspension member The load receiving part of load receiving part and the second main suspension member staggers up and down, forms sandwich construction;
For example, the second extension portion of the first main suspension member is two layers, the second extension portion of the second main suspension member is two layers, and the first extension portion is Two layers:
Can be that the second extension of first layer portion's carry of the first main suspension member is in the first extension of first layer portion, the of the second main suspension member Two layer of second extension portion carry is in the first extension of first layer portion;
Can also be, the second extension of first layer portion's carry of the first main suspension member in the first extension of first layer portion, the second main suspension member The second extension of first layer portion's carry is in the first extension of second layer portion;
Can also be, the second extension of first layer portion's carry of the first main suspension member in the first extension of first layer portion, the second main suspension member The second extension of second layer portion's carry is in the first extension of second layer portion;
Can also be, the second extension of second layer portion's carry of the first main suspension member in the first extension of first layer portion, the second main suspension member The second extension of second layer portion's carry is in the first extension of first layer portion;
Can also be, the second extension of second layer portion's carry of the first main suspension member in the first extension of first layer portion, the second main suspension member The second extension of second layer portion's carry is in the first extension of second layer portion;
Can also be, the second extension of second layer portion's carry of the first main suspension member in the first extension of first layer portion, the second main suspension member The second extension of first layer portion's carry is in the first extension of second layer portion.
5th, the first extension portion or/and the second extension portion are slideway, and the first extension portion and the second extension portion are slidably matched, slided by slideway Main suspension member, according to the installation needs of ceiling, position of the main suspension member relative to spandrel girder horizontal direction, operation letter can be adjusted It is single.
6th, the first extension portion includes the first hook portion and the second hook portion, and the second extension portion is provided with the 3rd hook portion being engaged and the 4th hook Portion, the first hook portion and the 3rd hook portion mutually hook cooperation, and the second hook portion and the 4th hook portion mutually hook cooperation, the first hook portion and The direction of two hook portions can be with identical or opposite;
By the way of hook, prevent from sliding, make the connection of main suspension member and spandrel girder more firm, and including upper and lower two Hook portion, the stress point of contact have two, and usual load receiving part is located at the lower section of the 4th hook portion, makes in installation ceiling main suspension member hand Afterwards, the connection of main suspension member and spandrel girder still consolidates.
7th, secondary suspension member is also included, main suspension member is provided with the 3rd extension portion, and secondary suspension member is provided with the 4th extension portion, the 3rd extension portion and the 4th Extension portion mutually mounts, secondary suspension member carry on main suspension member, spandrel girder is usually the crossbeam of strip, horizontal or near horizontally disposed, It is smaller that span is obtained on plumb height, for secondary suspension member carry on main suspension member, the 3rd extension portion passes through master below the second extension portion The length of suspension member itself can extend the height adjustment range of spandrel girder;And the mode of carry is simple to operate, as needed may be used With the secondary suspension member that chooses whether to arrange in pairs or groups.
8th, main suspension member is at least two, and secondary suspension member simultaneously at least two main suspension members, for the pair of strip hang by carry Part, as long as the second extension portion matches with the first extension portion, can also carry installation, such as the upholstery border positioned at the bottom, for hiding Spandrel girder and metope mounting structure are decorated, often using strip, direct carry is in completing installation on multiple main suspension members, without dividing Cut.
9th, the 3rd extension portion is setting up and down at least two layers, or/and, the 4th extension portion is setting up and down at least two layers, with Principle in foregoing 3rd is identical, can adjust height and position of the secondary suspension member relative to main suspension member.
10th, secondary suspension member include at least two layers it is setting up and down carry additionally part, the part of carrying additionally of most last layer is provided with the 4th extension portion, phase Carry additionally part and be provided with the hanging structure being mutually matched and mutually mount for adjacent two layers, the mode that multilayer is carried additionally, can carry additionally as needed Length selection carry additionally it is several layers of carry additionally part, a specification can be made by carrying additionally part, reduce cost.
Brief description of the drawings
Fig. 1 is the structure chart of ceiling structure of the embodiment of the present invention;
Fig. 2 is the zoomed-in view of A in Fig. 1;
Fig. 3 is the zoomed-in view of B in Fig. 1;
Fig. 4 is girder structures figure in the embodiment of the present invention;
Fig. 5 is the side view of spandrel girder in the embodiment of the present invention;
Fig. 6 is the structure chart of the first main suspension member in the embodiment of the present invention;
Fig. 7 is the structure chart of the second main suspension member in the embodiment of the present invention;
Fig. 8 is the side view of the second main suspension member in the embodiment of the present invention;
Fig. 9 is the structure chart of the first secondary suspension member structure in the embodiment of the present invention;
Figure 10 is the structure chart of the second secondary suspension member in the embodiment of the present invention;
Figure 11 is the side view of the second secondary suspension member in the embodiment of the present invention;
Figure 12 is the scheme of installation of ceiling structure of the embodiment of the present invention;
Figure 13 is the structure chart of middle cross beam of the embodiment of the present invention;
Figure 14 is the sectional view of middle cross beam of the embodiment of the present invention;
Figure 15 is the structure chart of upper pendant in the embodiment of the present invention;
Figure 16 is the structure chart of lower pendant in the embodiment of the present invention;
Figure 17 is upper pendant, the scheme of installation of lower pendant in the embodiment of the present invention;
Figure 18 is the structure chart of connector in the embodiment of the present invention;
Figure 19 is the installation diagram of connector and false keel in the embodiment of the present invention.
Description of reference numerals:
100th, connector, the 110, first plumbing arm, the 111, first shell fragment, 1111, first buckles, the 112, second shell fragment, 1121, Second buckles, and the 120, second plumbing arm, the 121, the 3rd shell fragment, the 1211, the 3rd buckles, and 130, connecting portion, 200, keel, 300, secondary dragon Bone, 400, ceiling, 500, crossbeam, 510, slideway, the 520, first bending structure, 600, suspender member, 610, upper pendant, 611, hang Extension portion, the 612, second bending structure, 613, plumbing arm, the 614, first positioning hole, 621, cell wall, the 622, second positioning hole, 623, hold Section, 700, spandrel girder, the 711, first hook portion, the 712, second hook portion, the 800, first main suspension member, the second of the 810, first main suspension member Extension portion, the 900, second main suspension member, the 910, first secondary suspension member, the 4th extension portion of the 911, first secondary suspension member, 912, load receiving part, 920, Second mate's suspension member, the 4th extension portion of the 921, second secondary suspension member, 930, the extension portion of first layer the 3rd.940th, the extension portion of the second layer the 3rd, 950, Second extension portion of the second main suspension member.
Embodiment
The present invention is described in further detail with reference to embodiment and accompanying drawing, but embodiments of the present invention are not limited to This.
As shown in drawings, spandrel girder 700 is fixed on metope, can use nail joint or be directly embedded into metope.
Spandrel girder 700 is provided with the first extension portion, and the first extension portion is setting up and down two layers.
Main suspension member is provided with load receiving part and the second extension portion.
Main suspension member includes the first main suspension member 800, the second main suspension member 900, and the first main carry of suspension member 810 is hung in first layer first Portion, the second extension portion carry of the second main suspension member are located at the second main suspension member 900 in the first extension of second layer portion, the first main suspension member 800 Top.
The first extension of first layer portion includes the first hook portion 711 and the second hook portion 712, and the first main suspension member 810 is provided with what is be engaged 3rd hook portion and the 4th hook portion, the first hook portion 711 and the 3rd hook portion mutually hook cooperation, the second hook portion 712 and the 4th hook portion phase Mutually hook and coordinate.First hook portion 711, the second hook portion 712, the 3rd hook portion, the 4th hook portion are slideway, the first hook portion 711 and the 3rd Hook portion is slidably matched, the second hook portion 712 and the 4th hook portion are slidably matched.
(not limited to this, can also the first main suspension member 800 for carrying keel 200 for the load receiving part 912 of first main suspension member 800 Itself it is provided with keel).
Second main suspension member 900 is provided with upper and lower two layers of the 3rd extension portions, and the first secondary suspension member 910 is provided with the 4th extension of the first secondary suspension member Portion 911, the 4th extension portion 911 of the first secondary suspension member and the extension portion 930 of first layer the 3rd mutually mounting, the first secondary carry of suspension member 910 in On second main suspension member 900.The second secondary carry of suspension member 920 is in the extension portion 940 of the second layer the 3rd of the second main suspension member 900, the first secondary extension Part 910 is positioned at the second secondary top of suspension member 920.
Second secondary suspension member 920 simultaneously carry on the multiple second main suspension members 900.
Can also be, secondary suspension member include at least two layers it is setting up and down carry additionally part, most last layer carrys additionally part provided with the 4th Extension portion, adjacent two layers carry additionally part and are provided with the hanging structure being mutually matched and mutually mount.The form of part is carried additionally by multilayer, can With the flexible quantity and length for selecting to carry additionally part, to adjust suspension height.
Can also be that the 3rd extension portion is setting up and down at least two layers, the 4th extension portion is setting up and down at least two layers.It is logical The carry that mutually staggers is crossed, forms hierarchical structure irregular in height.
Can also be that the distance between the second extension portion of the first main suspension member and load receiving part are more than the second extension of the second main suspension member The distance between portion and load receiving part.
Crossbeam 500 is fixed on roof, and crossbeam 500 is saved installing space, can consolidated using expandable nail as far as possible close to roof It is fixed, metope can also be directly embedded into.Crossbeam 500 is in inverted groove-like, and the edge of the groove both sides cell wall 621 is to bent intermediate Form hook-shaped slideway 510.Slideway 510 is horizontal or nearly horizontality.
The top of suspender member 600 is provided with hanging portion 611.
Hanging portion 611 slide located at the slideway 510 of crossbeam 500 on, the bottom of suspender member 600, which has, to be used to carry keel 200 loading end 623, keel 200 are set up on loading end 623.
Suspender member 600 includes upper pendant 610 and lower pendant setting up and down, and fastener.
The top of upper pendant 610 is provided with hanging portion 611, and hanging portion 611 is to be oppositely arranged simultaneously outside flattened both wings, crossbeam 500 edge of cell wall 621 is folded upward at being formed the first bending structure 520, and it is curved that the edge of hanging portion 611 is bent to form downwards second Folded structure 612, the first bending structure 520 and the second bending structure 612 mutually hook.
The bottom of upper pendant 610 has two plumbing arms being oppositely arranged 613, plumbing arm 613 to be provided with the first positioning hole 614, lower extension Part is the upward groove shape of notch, and its cell wall 621 is provided with the second positioning hole 622, bottom land forms loading end 623, and keel 200 are clipped in Between both sides cell wall 621, two cell walls 621 of lower pendant are clipped between two plumbing arms 613 of upper pendant 610.
First positioning hole 614 is elongated hole setting up and down, and fastener passes through the first positioning hole 614 and the second positioning hole 622 connect upper pendant 610 with lower pendant.
A piece crossbeam 500 arranges at least two suspender members 600.
Crossbeam 500 is at least two, a piece keel 200 of carrying, at least two hanging jointly of at least two suspender members 600 Part 600 is divided on different crossbeams 500.
During installation:
Crossbeam 500 is fixed on roof, upper pendant 610 and crossbeam 500 are slidably installed, slides upper pendant 610 to adjust Upper pendant 610 is relative to the position of crossbeam 500, and keel 200 are installed on the loading end 623 of lower pendant, by the of upper pendant 610 Second positioning hole 622 of a positioning hole 614 and lower pendant is aligned, adjusts upper pendant 610 and lower pendant up and down by elongated hole Relative position, carrys out the height of adjustment keel 200, fastener through the first positioning hole 614 and the second positioning hole 622 by lower pendant with Upper pendant 610 is connected, keel 200 is hung on roof.
Also include false keel 300, connector 100, connector 100 is used to connect keel 200 and false keel 300.
Connector 100 includes connecting portion 130 and the first plumbing arm 110 and the second plumbing arm 120 that are oppositely arranged, the first plumbing arm 110 top and the top of the second plumbing arm 120 are connected by connecting portion 130, the bottom of the first plumbing arm 110 and the second plumbing arm 120 Bottom between at intervals of construction opening, connector 100 is ridden on keel 200, and keel 200 are located at the first plumbing arm 110 and Between two plumbing arms 120, by the way of carry, without using screw nail joint.Connector 100 is slidably matched with keel 200.
First plumbing arm 110 is relatively set with the first shell fragment 111 and the second shell fragment 112, and the bottom of the first shell fragment 111 is bent to First buckles 1111, and the bottom of the second shell fragment 112 is bent to second and buckles 1121.
Second plumbing arm 120 is relatively set with the 3rd shell fragment 121 and the 4th shell fragment, and the bottom of the 3rd shell fragment 121 is bent to Three buckle 1211, and the bottom of the 4th shell fragment is bent to the 4th and buckled.
First, which buckles 1111 and the 3rd, buckles 1211 and lines up first row, and second, which buckles 1121 and the 4th, hangs and line up second row, First row and second row arranged in parallel, first, which buckles 1111, second, buckles the 1121, the 3rd and buckles the 1211, the 4th and buckle in four sides Shape is symmetrically distributed.So, the first plumbing arm 110 of connector 100, the second plumbing arm 120 respectively have two secondary dragons of forced section support Bone 300, four forced sections in the distribution of long side shape are formed altogether, make stress equalization between false keel 300, connector 100;First hangs Button 1111 and second buckle 1121 buckle it is in opposite direction, first buckle 1111 with the 3rd buckle 1211 to buckle direction identical, 3rd buckle 1211 and the 4th buckle buckle it is in opposite direction.
False keel 300 is provided with groove, and the edge of the two side walls of groove is bent to the 3rd extension portion, and first buckles 1111 and Three, which buckle 1211, mutually buckles with the edge of a wherein side wall for groove, is slidably matched;Second, which buckles 1121 and the 4th, hangs Button is mutually buckled with the edge of another side wall of groove, is slidably matched, and the carry of false keel 300 is in the lower section of keel 200.
First, which buckles 1111 and the 3rd, buckles 1211 backwards, and the two stretches out, and the cell wall of the groove of false keel 300 is inside Bending, first, which buckles 1111 and the 3rd, buckles width of the maximum span more than the opening of both sides cell wall of 1211 stretching, extensions;During installation, Push false keel 300 from the bottom up, first, which buckles 1111, second, buckles the 1121, the 3rd and buckle the 1211, the 4th and buckle and have fully embedded into In groove, first, which buckles 1111 and the 3rd, buckles 1211 and buckles the side cell wall of groove, second buckles 1121 and the 4th and buckle Detain the opposite side cell wall of groove, you can complete installation.(in the present embodiment first buckle 1111 and second buckle 1121 mutually the back of the body , can also opposite face to, but not limited to this embodiment)
It is installed on by the construction opening on connector 100 by what connector 100 rode on keel 200, makes keel 200 Between the first plumbing arm 110 and the second plumbing arm 120 of connector 100, the adjusting connector 100 of sliding connector 100 is relative to dragon The position of bone 200, by the 3rd extension portion carry of false keel 300 in the first of connector 100 buckle 1111, second buckle 1121, 3rd, which buckles the 1211, the 4th, buckles, first buckle 1111, second buckle the 1121, the 3rd buckle the 1211, the 4th buckle it is common will The carry of false keel 300 in the lower section of keel 200, adjustment keel relative to connector 100 position.Even if install false keel 300 Afterwards, the relative position of be slidably matched adjustment keel 200, connector 100, false keel 300 can also be passed through.
The manufacture method of connector 100:
The raw material of connector 100 is single piece type, and the middle part of single piece type raw material is connecting portion 130, by 130 liang of lateral bendings of connecting portion To roll over for the first plumbing arm 110 and the second plumbing arm 120, it is construction opening that gap is left between the first plumbing arm 110 and the second plumbing arm 120, The edge of the both sides of first plumbing arm 110 is laterally bent to the first shell fragment 111 and the second shell fragment 112, by the bottom of the first shell fragment 111 Longitudinal direction is bent to first and buckles 1111, and the bottom of the second shell fragment 112 is longitudinally bent into second buckles 1121.
Whole connector 100 is that the bending of single piece type raw material forms, and processing is simple, cost is low, and single piece type thin slice matter itself Amount is light.
Ceiling 400 is installed on the bottom of false keel 300.
Each technical characteristic of embodiment described above can be combined arbitrarily, to make description succinct, not to above-mentioned reality Apply all possible combination of each technical characteristic in example to be all described, as long as however, the combination of these technical characteristics is not deposited In contradiction, the scope that this specification is recorded all is considered to be.
Embodiment described above only expresses the several embodiments of the present invention, and its description is more specific and detailed, but simultaneously Can not therefore it be construed as limiting the scope of the patent.It should be pointed out that come for one of ordinary skill in the art Say, without departing from the inventive concept of the premise, various modifications and improvements can be made, these belong to the protection of the present invention Scope.Therefore, the protection domain of patent of the present invention should be determined by the appended claims.

Claims (9)

  1. A kind of 1. ceiling structure, it is characterised in that including:
    Spandrel girder, spandrel girder are fixed on metope, provided with the first extension portion;
    Main suspension member, main suspension member are provided with load receiving part and the second extension portion, and load receiving part is provided with keel in itself for carrying keel or load receiving part, The keel are used to install ceiling;
    Wherein, the first extension portion mutually mounts with the second extension portion, and main suspension member carry is on spandrel girder;The main suspension member comprises at least the One main suspension member and the second main suspension member, the distance between the second extension portion of the first main suspension member and load receiving part are more than the described second master The distance between second extension portion of suspension member and load receiving part.
  2. 2. ceiling structure according to claim 1, it is characterised in that the first extension portion is setting up and down at least two Layer, or/and, the second extension portion is setting up and down at least two layers.
  3. 3. ceiling structure according to claim 2, it is characterised in that the second extension portion of the first main suspension member and described the The cooperation between cooperation and the second extension portion of the second main suspension member and the first extension portion between one extension portion is staggered up and down, The load receiving part of the described first main suspension member and the load receiving part of the second main suspension member is set to stagger up and down, form sandwich construction.
  4. 4. ceiling structure according to claim 1, it is characterised in that the first extension portion or/and the second extension portion are Slideway, the first extension portion and the second extension portion are slidably matched.
  5. 5. ceiling structure according to claim 4, it is characterised in that the first extension portion includes the first hook portion and second hook Portion, the second extension portion are provided with the 3rd hook portion and the 4th hook portion being engaged, and first hook portion and the 3rd hook portion are mutual Hook and coordinate, second hook portion and the 4th hook portion mutually hook cooperation.
  6. 6. ceiling structure according to any one of claims 1 to 5, it is characterised in that also include secondary suspension member, the main suspension member Provided with the 3rd extension portion, the secondary suspension member is provided with the 4th extension portion, and the 3rd extension portion and the 4th extension portion mutually mount, the pair Suspension member carry is on the main suspension member.
  7. 7. ceiling structure according to claim 6, it is characterised in that the main suspension member is at least two, the secondary suspension member Carry is at least two main suspension members simultaneously.
  8. 8. ceiling structure according to claim 6, it is characterised in that the 3rd extension portion is setting up and down at least two Layer, or/and, the 4th extension portion is setting up and down at least two layers.
  9. 9. ceiling structure according to claim 6, it is characterised in that the secondary suspension member is setting up and down including at least two layers Part is carried additionally, carrying additionally part described in most last layer is provided with the 4th extension portion, and part is carried additionally described in adjacent two layers and is provided with what is be mutually matched Hanging structure simultaneously mutually mounts.
CN201510283104.2A 2015-05-28 2015-05-28 Ceiling structure Expired - Fee Related CN104847049B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510283104.2A CN104847049B (en) 2015-05-28 2015-05-28 Ceiling structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510283104.2A CN104847049B (en) 2015-05-28 2015-05-28 Ceiling structure

Publications (2)

Publication Number Publication Date
CN104847049A CN104847049A (en) 2015-08-19
CN104847049B true CN104847049B (en) 2018-04-06

Family

ID=53846996

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510283104.2A Expired - Fee Related CN104847049B (en) 2015-05-28 2015-05-28 Ceiling structure

Country Status (1)

Country Link
CN (1) CN104847049B (en)

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
TW399116B (en) * 1998-09-11 2000-07-21 Hunter Douglas International Curved building panel
CN201593258U (en) * 2010-02-05 2010-09-29 北京易天梭装饰材料有限公司 Device for fixing soft membrane ceiling
CN103452223B (en) * 2013-07-19 2015-10-21 百益百利(福州)幕墙工程有限公司 The stone panel mounting process of furred ceiling suspension member and use furred ceiling suspension member
CN203769172U (en) * 2013-11-28 2014-08-13 北新建材(上海)有限公司 Hanger
CN203742052U (en) * 2013-12-24 2014-07-30 广州市广京装饰材料有限公司 Ceiling and keel assembling structure
CN204023865U (en) * 2014-06-17 2014-12-17 北新集团建材股份有限公司 A kind of longitudinal furred ceiling fastener
CN204163299U (en) * 2014-09-01 2015-02-18 福建省郦屋生态建筑装饰有限公司 For the indoor integrated finishing assembly of integration
CN204781552U (en) * 2015-05-28 2015-11-18 广州市广京装饰材料有限公司 It flower structure

Also Published As

Publication number Publication date
CN104847049A (en) 2015-08-19

Similar Documents

Publication Publication Date Title
CN104847048B (en) Ceiling keel structure and installation method
EP2116662B1 (en) Suspended ceiling cloud with flexible panel
CN104878868B (en) Ceiling keel structure and installation method
MXPA01005400A (en) Suspended curved ceiling system.
CN209653290U (en) A kind of face stone dry-hanging mounting structure of facade
MX2015005473A (en) Flexible drywall grid member for framing drywall structures.
CN204940660U (en) Full suspended ceiling combines self-contained provision for disengagement
US20210222441A1 (en) Interchangeable Board And Batten
CN204781552U (en) It flower structure
CN104847049B (en) Ceiling structure
CN108779641A (en) Flat dry wall ceiling suspension
CN202055390U (en) Aluminum suspended ceiling
CN110259024A (en) A kind of metope exempts from levelling wall panel assembly and installation method
CN104878869A (en) Ceiling keel structure and mounting method
CN201486012U (en) Suspended ceiling margin-ending structure
CN204781541U (en) Smallpox keel structure
CN106013660B (en) A kind of abatvoix and its installation method
CN104847050B (en) Ceiling structure
RU165838U1 (en) BAGUETTE FOR FASTENING A TENSIONED BELT
CN104533005A (en) Ceiling connecting piece and ceiling with ceiling connecting pieces
CN103741927A (en) Floor mounting structure
CN205296536U (en) Joint formula keel connecting piece
CN107724635A (en) The installation method of decorative board for wall connecting assembly and decorative board for wall
CN203783071U (en) Angular line structure
CN205296538U (en) A compound connecting piece for integrated furred ceiling of double entry

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180406