CN104832181B - 燕尾式段隧道施工工艺 - Google Patents

燕尾式段隧道施工工艺 Download PDF

Info

Publication number
CN104832181B
CN104832181B CN201510244645.4A CN201510244645A CN104832181B CN 104832181 B CN104832181 B CN 104832181B CN 201510244645 A CN201510244645 A CN 201510244645A CN 104832181 B CN104832181 B CN 104832181B
Authority
CN
China
Prior art keywords
excavation
mid
base tunnel
board
preliminary bracing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510244645.4A
Other languages
English (en)
Other versions
CN104832181A (zh
Inventor
周卫霞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical First Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201510244645.4A priority Critical patent/CN104832181B/zh
Publication of CN104832181A publication Critical patent/CN104832181A/zh
Application granted granted Critical
Publication of CN104832181B publication Critical patent/CN104832181B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

燕尾式段隧道施工工艺涉及铁路隧道施工工艺。主要是为解决目前燕尾式段隧道施工速度慢等问题而发明的。按以下步骤进行:开挖中导洞上导坑,施作中导洞上导坑初期支护;开挖中导洞下导坑,施作中导洞下导坑初期支护Ⅱ;施作中隔墙Ⅲ;同时安装中隔墙左侧的临时横撑;开挖右侧上导坑,施作右侧上导坑初期支护Ⅳ;开挖右侧中导坑,施作右侧中导坑初期支护Ⅴ;开挖右侧下导坑,施作右侧下导坑初期支护Ⅵ;施作右侧洞的二次衬砌Ⅶ;开挖左侧上导坑,施作左侧上导坑初期支护Ⅷ;开挖左侧中导坑,施作左侧中导坑初期支护Ⅸ;开挖左侧下导坑8,施作左侧下导坑初期支护Ⅹ;施作左侧洞的二次衬砌Ⅺ。优点是施工进度快。

Description

燕尾式段隧道施工工艺
技术领域:
本发明涉及铁路隧道施工工艺,特别是涉及一种双线隧道大跨段经双连拱段过渡成两座分离式隧道的燕尾段隧道施工工艺。
背景技术:
目前,由于线路走向和地质原因,在隧道工程设计中,经常会遇到由双线隧道大跨段经双连拱段过渡成两座分离式隧道的燕尾式铁路隧道,由于燕尾段施工集中了连拱段开挖、中隔墙防水施工、小间距段施工及控制爆破技术等,施工技术难度较高。由于断面结构特殊,目前施工中多采用弱爆破,短进尺,早封闭,勤量测等技术手段来控制,施工速度慢,不能满足隧道总体进度计划的要求,并且安全难以保证。
发明内容:
本发明所要解决的技术问题是提供一种燕尾式段隧道施工工艺,其解决了双线隧道大跨段经双连拱段过渡成两座分离式隧道的燕尾式铁路隧道施工难度大的工艺问题,从而大大提高了此种情形下隧道施工进度,解决了安全难以保证的难题。
本发明的目的是这样实现的:
一种燕尾式段隧道施工工艺,按以下步骤进行:
a、开挖中导洞上导坑;施作中导洞上导坑初期支护Ⅰ;
b、开挖中导洞下导坑;施作中导洞下导坑初期支护Ⅱ;
c、施作中隔墙Ⅲ;同时安装中隔墙左侧的临时横撑;
d、待中隔墙混凝土达到设计强度后开挖右侧上导坑;施作右侧上导坑初期支护Ⅳ;
e、开挖右侧中导坑;施作右侧中导坑初期支护Ⅴ;
f、开挖右侧下导坑;施作右侧下导坑初期支护Ⅵ;
g、施作右侧洞的二次衬砌Ⅶ;
h、开挖左侧上导坑;施作左侧上导坑初期支护Ⅷ;
i、开挖左侧中导坑;施作左侧中导坑初期支护Ⅸ;
j、开挖左侧下导坑;施作左侧下导坑初期支护Ⅹ;
k、施作左侧洞的二次衬砌Ⅺ。
燕尾式段中导洞按二台阶法开挖,先挖中导洞上导坑,后挖中导洞下导坑,中导洞上导坑初期支护及中导洞下导坑初期支护均采用喷射厚10cm的C25素混凝土;中导洞中线顶部加设一排径向φ22mm的砂浆锚杆,砂浆锚杆纵向单排布置,相邻砂浆锚杆的间距为50cm,砂浆锚杆垂直于岩面安装,埋入岩石中的长度>3.0m,外露长度>1.0m,外露部分埋入中隔墙混凝土中;
中隔墙Ⅲ的混凝土浇筑是在经对隧道进行监控量测,确认围岩的变形完成其总变形量的90%以后才能进行;中隔墙用C30混凝土浇筑,在中隔墙墙顶和墙脚预埋φ22mm短钢筋,每米设置3排,每排设置4根;同时在中隔墙墙顶预埋防水板,与拱部防水板焊接成整体;墙内每隔8m预埋φ50mm加劲型软式透水盲管,盲管要在墙顶露出30cm,以便与左右线拱部盲管三通连接;在中隔墙底部要设置洞内的φ100mm加筋型软式透水盲管;
待中隔墙混凝土强度达到设计强度的70%以后才能进行右侧导坑的开挖;右侧导坑采用上、中、下三台阶法开挖,风枪打眼,控制爆破,周边眼采用光面爆破技术,装载机配合自卸车进行出碴,为减少对中隔墙的震动和飞石的直接撞击以及控制飞石的方向,爆破设计时要控制最小抵抗线的方向,在中隔墙的左侧架设临时钢管横撑,临时钢管的一端顶在中隔墙上,另一端顶在中导洞上、下导坑初期支护上,中隔墙右侧墙面挂设草帘或竹条板或钢板的防护层,避免中隔墙受到伤害和发生移位;
左侧导坑采用上、中、下三台阶法开挖,左侧导坑开挖时,应该在中隔墙的右侧架设临时钢管横撑,左侧墙面挂设防护层,避免中隔墙受到伤害和发生移位。
左、右侧上导坑初期支护采用厚200mm的C25喷射混凝土,挂φ6.5mm,250mm×250mm钢筋网,拱部设置Φ25CD反循环注浆锚杆,长度3.0m,间距1.2m×1.0m(环×纵),梅花形布置,钢拱架采用I12工字钢,用连接钢板焊接成型,钢拱架间距1.2m,钢拱架之间设置Φ22mm连接筋,环向上连接筋的间距为1.0m,在钢拱架的内外缘交错布置,架设钢拱架时先初喷厚30mm的混凝土,再架立工字钢钢拱架,然后再喷射混凝土至设计厚度;钢拱架内侧保护层厚度>30mm,钢架要求与初喷混凝土密切接触,空隙要用砂浆垫平,钢架必须放置在牢固的基础上。
本发明的优点是:施工进度快,降低了工程成本,开挖作业面小,减少了对环境的影响和破坏,保证了施工安全。
附图说明:
图1是燕尾式段隧道施工程序图;
图2是燕尾式段隧道施工工艺流程图。
具体实施方式:
一种燕尾式段隧道施工工艺,按以下步骤进行:
a、开挖中导洞上导坑1;施作中导洞上导坑初期支护Ⅰ;
b、开挖中导洞下导坑2;施作中导洞下导坑初期支护Ⅱ;
c、施作中隔墙Ⅲ;同时安装中隔墙左侧的临时横撑;
d、待中隔墙混凝土达到设计强度后开挖右侧上导坑3;施作右侧上导坑初期支护Ⅳ;
e、开挖右侧中导坑4;施作右侧中导坑初期支护Ⅴ;
f、开挖右侧下导坑5;施作右侧下导坑初期支护Ⅵ;
g、施作右侧洞的二次衬砌Ⅶ;
h、开挖左侧上导坑6;施作左侧上导坑初期支护Ⅷ;
i、开挖左侧中导坑7;施作左侧中导坑初期支护Ⅸ;
j、开挖左侧下导坑8;施作左侧下导坑初期支护Ⅹ;
k、施作左侧洞的二次衬砌Ⅺ。
燕尾式段中导洞按二台阶法开挖,先挖中导洞上导坑1,后挖中导洞下导坑2,中导洞上导坑初期支护及中导洞下导坑初期支护均采用喷射厚10cm的C25素混凝土;中导洞中线顶部加设一排径向φ22mm的砂浆锚杆,砂浆锚杆纵向单排布置,相邻砂浆锚杆的间距为50cm,砂浆锚杆垂直于岩面安装,埋入岩石中的长度>3.0m,外露长度>1.0m,外露部分埋入中隔墙混凝土中;
中隔墙Ⅲ的混凝土浇筑是在经对隧道进行监控量测,确认围岩的变形完成其总变形量的90%以后才能进行;中隔墙用C30混凝土浇筑,在中隔墙墙顶和墙脚预埋φ22mm短钢筋,每米设置3排,每排设置4根;同时在中隔墙墙顶预埋防水板,与拱部防水板焊接成整体;墙内每隔8m预埋φ50mm加劲型软式透水盲管,盲管要在墙顶露出30cm,以便与左右线拱部盲管三通连接;在中隔墙底部要设置洞内的φ100mm加筋型软式透水盲管;
待中隔墙混凝土强度达到设计强度的70%以后才能进行右侧导坑的开挖;右侧导坑采用上3、中4、下5三台阶法开挖,风枪打眼,控制爆破,周边眼采用光面爆破技术,装载机配合自卸车进行出碴,为减少对中隔墙的震动和飞石的直接撞击以及控制飞石的方向,爆破设计时要控制最小抵抗线的方向,在中隔墙的左侧架设临时钢管横撑,临时钢管的一端顶在中隔墙上,另一端顶在中导洞上、下导坑初期支护上,中隔墙右侧墙面挂设草帘或竹条板或钢板的防护层,避免中隔墙受到伤害和发生移位;
左侧导坑采用上6、中7、下8三台阶法开挖,左侧导坑开挖时,应该在中隔墙的右侧架设临时钢管横撑,左侧墙面挂设防护层,避免中隔墙受到伤害和发生移位;
左、右侧上导坑初期支护采用厚200mm的C25喷射混凝土,挂φ6.5mm,250mm×250mm钢筋网,拱部设置Φ25CD反循环注浆锚杆,长度3.0m,间距1.2m×1.0m(环×纵),梅花形布置,钢拱架采用I12工字钢,用连接钢板焊接成型,钢拱架间距1.2m,钢拱架之间设置Φ22mm连接筋,环向上连接筋的间距为1.0m,在钢拱架的内外缘交错布置,架设钢拱架时先初喷厚30mm的混凝土,再架立工字钢钢拱架,然后再喷射混凝土至设计厚度;钢拱架内侧保护层厚度>30mm,钢架要求与初喷混凝土密切接触,空隙要用砂浆垫平,钢架必须放置在牢固的基础上。

Claims (1)

1.燕尾式段隧道施工工艺,其特征是:按以下步骤进行:
a、开挖中导洞上导坑(1);施作中导洞上导坑初期支护Ⅰ;
b、开挖中导洞下导坑(2);施作中导洞下导坑初期支护Ⅱ;
c、施作中隔墙Ⅲ;同时安装中隔墙左侧的临时横撑;
d、待中隔墙混凝土达到设计强度后开挖右侧上导坑(3);施作右侧上导坑初期支护Ⅳ;
e、开挖右侧中导坑(4);施作右侧中导坑初期支护Ⅴ;
f、开挖右侧下导坑(5);施作右侧下导坑初期支护Ⅵ;
g、施作右侧洞的二次衬砌Ⅶ;
h、开挖左侧上导坑(6);施作左侧上导坑初期支护Ⅷ;
i、开挖左侧中导坑(7);施作左侧中导坑初期支护Ⅸ;
j、开挖左侧下导坑(8);施作左侧下导坑初期支护Ⅹ;
k、施作左侧洞的二次衬砌Ⅺ;
燕尾式段中导洞按二台阶法开挖,先挖中导洞上导坑,后挖中导洞下导坑,中导洞上导坑初期支护及中导洞下导坑初期支护均采用喷射厚10cm的C25素混凝土;中导洞中线顶部加设一排径向φ22mm的砂浆锚杆,砂浆锚杆纵向单排布置,相邻砂浆锚杆的间距为50cm,砂浆锚杆垂直于岩面安装,埋入岩石中的长度>3.0m,外露长度>1.0m,外露部分埋入中隔墙混凝土中;
中隔墙Ⅲ的混凝土浇筑是在经对隧道进行监控量测,确认围岩的变形完成其总变形量的90%以后才能进行;中隔墙用C30混凝土浇筑,在中隔墙墙顶和墙脚预埋φ22mm短钢筋,每米设置3排,每排设置4根;同时在中隔墙墙顶预埋防水板,与拱部防水板焊接成整体;墙内每隔8m预埋φ50mm加劲型软式透水盲管,盲管要在墙顶露出30cm,以便与左右线拱部盲管三通连接;在中隔墙底部要设置洞内的φ100mm加筋型软式透水盲管;
待中隔墙混凝土强度达到设计强度的70%以后才能进行右侧导坑的开挖;右侧导坑采用上、中、下三台阶法开挖,风枪打眼,控制爆破,周边眼采用光面爆破技术,装载机配合自卸车进行出碴,为减少对中隔墙的震动和飞石的直接撞击以及控制飞石的方向,爆破设计时要控制最小抵抗线的方向,在中隔墙的左侧架设临时钢管横撑,临时钢管的一端顶在中隔墙上,另一端顶在中导洞上、下导坑初期支护上,中隔墙右侧墙面挂设草帘或竹条板或钢板的防护层,避免中隔墙受到伤害和发生移位;
左侧导坑采用上、中、下三台阶法开挖,左侧导坑开挖时,应该在中隔墙的右侧架设临时钢管横撑,左侧墙面挂设防护层,避免中隔墙受到伤害和发生移位;
左、右侧上导坑初期支护采用厚200mm的C25喷射混凝土,挂φ6.5mm,250mm×250mm钢筋网,拱部设置Φ25CD反循环注浆锚杆,长度3.0m,间距环向1.2m×纵向1.0m,梅花形布置,钢拱架采用I12工字钢,用连接钢板焊接成型,钢拱架间距1.2m,钢拱架之间设置Φ22mm连接筋,环向上连接筋的间距为1.0m,在钢拱架的内外缘交错布置,架设钢拱架时先初喷厚30mm的混凝土,再架立工字钢钢拱架,然后再喷射混凝土至设计厚度;钢拱架内侧保护层厚度>30mm,钢架要求与初喷混凝土密切接触,空隙要用砂浆垫平,钢架必须放置在牢固的基础上。
CN201510244645.4A 2015-05-14 2015-05-14 燕尾式段隧道施工工艺 Active CN104832181B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510244645.4A CN104832181B (zh) 2015-05-14 2015-05-14 燕尾式段隧道施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510244645.4A CN104832181B (zh) 2015-05-14 2015-05-14 燕尾式段隧道施工工艺

Publications (2)

Publication Number Publication Date
CN104832181A CN104832181A (zh) 2015-08-12
CN104832181B true CN104832181B (zh) 2016-11-30

Family

ID=53810323

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510244645.4A Active CN104832181B (zh) 2015-05-14 2015-05-14 燕尾式段隧道施工工艺

Country Status (1)

Country Link
CN (1) CN104832181B (zh)

Families Citing this family (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105275472A (zh) * 2015-11-13 2016-01-27 河北科技师范学院 无中墙连拱隧道的施工方法
CN106014449B (zh) * 2016-07-05 2018-02-02 重庆建工市政交通工程有限责任公司 双线小净距大断面节理岩体地铁隧道的施工方法
CN106988767A (zh) * 2017-04-06 2017-07-28 铁道第三勘察设计院集团有限公司 深埋中心水沟的软弱围岩隧道支护结构
CN106979013A (zh) * 2017-04-07 2017-07-25 中交第二航务工程局有限公司 一种偏压浅埋软弱围岩的超大断面隧道的开挖施工方法
CN106884665B (zh) * 2017-04-19 2018-11-06 中铁一局集团有限公司 一种基于拱套拱的双连拱进洞施工方法
CN107905798A (zh) * 2017-11-01 2018-04-13 中国建筑第八工程局有限公司 采用中导洞法进行平顶直墙暗挖施工的方法
CN108678771B (zh) * 2018-07-15 2023-06-23 中铁二十局集团有限公司 穿越断层破碎带隧道初期支护及中隔壁加强支护装置
CN109441480B (zh) * 2018-11-02 2020-06-09 云南建投第三建设有限公司 一种连拱隧道后行洞掌子面临时支护施工工法
CN110307003B (zh) * 2019-08-12 2024-04-12 中铁二院工程集团有限责任公司 适用于预防隧道底部变形的泄压导洞及其施工方法
CN112253139B (zh) * 2020-11-03 2023-04-28 中铁隆工程集团有限公司 通道范围正洞开挖流程的施工方法
CN112412474A (zh) * 2020-11-25 2021-02-26 中交二航局第二工程有限公司 连拱隧道施工方法
CN113153308B (zh) * 2021-03-09 2023-12-08 中铁八局集团有限公司 双联拱隧道塌方段施工方法
CN113187514B (zh) * 2021-05-25 2024-02-23 中铁九局集团第七工程有限公司 一种市域铁路矿山法隧道燕尾段施工方法

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100701633B1 (ko) * 2005-06-01 2007-03-30 윤석렬 투아치 터널의 중앙부를 지지하는 하중분배판 및 이를 이용한 투아치 터널의 시공방법
CN101892845B (zh) * 2010-01-26 2012-12-12 中铁第四勘察设计院集团有限公司 一种五孔四线铁路水底隧道及其修建方法
CN102094654A (zh) * 2011-03-28 2011-06-15 中铁二院工程集团有限责任公司 高速铁路三线隧道构造
CN102155232B (zh) * 2011-04-02 2013-06-12 中铁二院工程集团有限责任公司 地形偏压条件下大跨不对称双连拱铁路隧道施工方法
CN203130092U (zh) * 2013-01-16 2013-08-14 中铁二院工程集团有限责任公司 高速铁路浅埋偏压地段大跨不对称双连拱三线隧道
CN103256052B (zh) * 2013-05-17 2015-04-15 北京国道通公路设计研究院股份有限公司 一种整体直中墙式双连拱隧道的施工方法
CN103244130B (zh) * 2013-05-31 2015-04-29 中南大学 人字形隧道断面快速挖扩施工方法

Also Published As

Publication number Publication date
CN104832181A (zh) 2015-08-12

Similar Documents

Publication Publication Date Title
CN104832181B (zh) 燕尾式段隧道施工工艺
JP7125550B2 (ja) 逆アーチを備えた2段階高速閉鎖トンネルの支持構造及びその施工方法
CN105257301B (zh) 一种浅埋暗挖隧道软弱围岩塌方加固处理方法
CN110374633B (zh) 隧道穿越松散体的洞口段施工方法
CN104963689A (zh) 隧道三台阶七步开挖方法
CN109736827B (zh) 城市地铁硬岩地层联络通道高压气体膨胀致裂开挖的方法
CN103821167A (zh) 一种地铁车站主体的施工方法
CN109339029B (zh) 一种既有隧道上方基坑开挖抗隆起变形的施工方法
CN102226403A (zh) 地铁大跨度车站主体拱盖法施工方法及车站主体结构
CN102587922A (zh) 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法
CN101806217A (zh) 三线并行小净距浅埋、偏压隧道群进洞施工方法
CN109026026A (zh) 下穿既有管廊的大断面多线多连拱暗挖隧道群的施工方法
CN110159298B (zh) 一种地铁暗挖车站初支扣拱施工方法
CN207063982U (zh) 一种导洞内机械辅助止水暗挖车站结构
CN205013013U (zh) 适用于上软下硬地层的暗挖车站支护结构
CN102748040A (zh) 地铁大跨度车站主体结构及其柱拱法施工方法
CN109184747A (zh) 一种深部软岩巷道的支护方法
CN105201516A (zh) 一种地铁车站主体结构及其四联拱pba暗挖施工方法
CN201801872U (zh) 联合支护开挖溶蚀地质深基坑
CN105370289A (zh) 一种复杂环境既有管线超长浅埋暗挖施工方法
CN103953355A (zh) 一种泥水盾构隧道内接收施工方法
KR101479267B1 (ko) 터널 벽체를 선시공한 후 터널 내부를 굴착하는 비개착 터널 시공방법
CN205036380U (zh) 一种四联拱pba暗挖地铁车站主体结构
CN104863613B (zh) 岩质地层暗挖地下结构高边墙锚拉初支结构及施工方法
CN104120739A (zh) 一种多导洞开挖一次成拱的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant