CN104747798B CN201510057996.4A CN201510057996A CN104747798B CN 104747798 B CN104747798 B CN 104747798B CN 201510057996 A CN201510057996 A CN 201510057996A CN 104747798 B CN104747798 B CN 104747798B
Authority
CN
China
Prior art keywords
joint
installation
setting
waterstop joint
waterstop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510057996.4A
Other languages
Chinese (zh)
Other versions
CN104747798A (en
Inventor
赵向东
吴建军
秦宗凯
涂晓
龚小东
杨培娜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Northwest Construction Investment Group Co Ltd
Original Assignee
Zhongtian Northwest Construction Investment Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Northwest Construction Investment Group Co Ltd filed Critical Zhongtian Northwest Construction Investment Group Co Ltd
Priority to CN201510057996.4A priority Critical patent/CN104747798B/en
Publication of CN104747798A publication Critical patent/CN104747798A/en
Application granted granted Critical
Publication of CN104747798B publication Critical patent/CN104747798B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/0243Laying or reclaiming pipes on land, e.g. above the ground above ground
    • F16L1/0246Laying or reclaiming pipes on land, e.g. above the ground above ground at a certain height off the ground
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03CDOMESTIC PLUMBING INSTALLATIONS FOR FRESH WATER OR WASTE WATER; SINKS
    • E03C1/00Domestic plumbing installations for fresh water or waste water; Sinks
    • E03C1/12Plumbing installations for waste water; Basins or fountains connected thereto; Sinks
    • E03C1/122Pipe-line systems for waste water in building
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)
  • Sink And Installation For Waste Water (AREA)

Abstract

The present invention provides a kind of drainpipe construction method of installation, and this approach includes the following steps, using setting-out blanket label template, is positioned to waterstop joint, casting concrete.Waterstop joint and installation drainpipe are installed.The wooden inventive method can be to installing quick and precisely with the kitchen and toilet drainpipe above and below the same vertical plane in building, it avoids the soil stack caused by pre-buried waterstop joint deviations and is connected deviation, line and mark circle label are identified to the socket joint depth of drainpipe, Pipe installing is tight, leak does not occur, when installation, effectively carry out the visualized management of socket joint depth, percolating water caused by pipe joint socket joint depth deficiency caused by socket joint depth deficiency can not be checked when avoiding construction, installation effectiveness is high, when saving of labor saves.

Description

The construction method of installation of kitchen and bath's drainpipe
Technical field
The present invention relates to the constructions of the realm of building construction more particularly to drainage pipeline.
Background technology
In the prior art, it when positioning being installed to kitchen and bath's drainage pipeline, needs to carry out pipeline location measurement to every floor plate, with The position for determining drainage pipeline, is installed, and this method work consuming takes, and efficiency is low, and the linking rate between pipeline floor is low, easily Pipe joint is caused to loosen infiltration.
When being installed to kitchen and bath's drainpipe, on-site cutting, assembling, and the U- between carrying out more water are mostly used to kitchen and bath's pipeline PVC drainings are ascended a height pipe installation, and using the technique installed after first box out, after filling-up hole, pipe root easy to leak causes kitchen and bath's pipe leakage, Harmful effect is caused to resident family.
Invention content
The purpose of the present invention is exactly to provide a kind of peace of kitchen and bath's drainpipe to overcome the above-mentioned problems of the prior art Fill construction method, when this method saving of labor saves, when structure construction it is disposable it is pre-buried Pipe installing is tight in place, leak does not occur.
To achieve the purpose of the present invention, the construction method of installation of kitchen and bath's drainpipe of the invention, includes the following steps:Using Setting-out blanket carries out the positioning of waterstop joint, determines that the waterstop joint in the position of template, forms multiple waterstop joint sites;Described it will stop Water section is mounted in template, and casting concrete carries out pre-buried processing around waterstop joint;Batch production processing is carried out to drainpipe It is deep-controlled with visualization socket joint, binder be used in combination that tool is fixedly mounted on to the port of the waterstop joint.
Preferably, the construction method of installation of kitchen and bath's drainage pipeline further includes:Drainpipe is carried out to cutting and group in advance After dress, then carry out that described to carry out visualization socket joint to drainpipe deep-controlled.
Wherein, described to drainpipe visualize that socket joint is deep-controlled to include:Mark socket joint deep on the drainpipe Scale timberline;Again using the midpoint of marking line as the center of circle, make circles mark, marking line is made to be located at the centre position of circles mark.
Preferably, the diameter of the circles mark is less than marking line.
Wherein, the setting-out blanket is made of Corvic, which is provided with a plurality of parallel transverse crease lines and is put down with a plurality of The grid-like plane of coordinate setting that capable longitudinal broken line is formed.
Preferably, setting-out blanket edge is equipped with locating plate or locating clip for being installed in template.
Preferably, the sleeve is spigot-and-socket waterstop joint.
Beneficial effects of the present invention embody in the following areas:
1, the construction method of installation of kitchen and bath's drainpipe of the invention, above and below the same vertical plane using the buildings setting-out Tan Duitongdong The installation of kitchen and toilet soil stack fast and accurately positioned with waterstop joint is pre-buried, avoid because pre-buried waterstop joint positioning is inclined Caused by difference soil stack be connected deviation, without ruler every layer kitchen and toilet roof plate template be laid with after the completion of carry out it is pre-buried fixed Position measures, and greatly reduces the time of the pre-buried positioning of waterstop joint;
2, setting-out blanket used in the construction method of installation of kitchen and bath's drainpipe of the invention is made of Corvic, has There is certain flexibility, convenient for curling harvesting, occupied space is few, reusable, of low cost.
3, the construction method of installation of kitchen and bath's drainpipe of the invention is right using structure construction when being installed to drainpipe Waterstop joint casting concrete, disposably pre-buried Pipe installing is tight in place, and leak does not occur.
4, the construction method of installation of kitchen and bath's drainpipe of the invention, line and mark are identified to the socket joint depth of drainpipe Circle label when installation, effectively carries out the visualized management of socket joint depth, can not check that socket joint depth deficiency is led when avoiding construction Percolating water caused by the pipe joint socket joint depth deficiency of cause.
Description of the drawings
Fig. 1 is the construction process figure of the present invention
Fig. 2 is the structural schematic diagram of the setting-out blanket of the present invention;
Reference sign:1, flexible plane, 2, location hole, 3, positioning side, 31, locating clip.
Specific implementation mode
It is a feature of the present invention that being installed using the kitchen and toilet soil stack above and below the same vertical plane in the buildings setting-out Tan Duitongdong It is fast and accurately positioned with waterstop joint is pre-buried, avoids the soil stack caused by pre-buried waterstop joint deviations and hold in the mouth Deviation is connect, and when saving of labor's section, improves the installation effectiveness of drainpipe.
It is a further feature of the invention that when the present invention installs drainpipe, waterstop joint is poured using when structure construction Concrete is built, disposably pre-buried Pipe installing is tight in place, and leak does not occur;Batch production is carried out to drainage pipeline in advance to cut It cuts, assembling processing, and line and mark circle label is identified to the socket joint depth of drainpipe, when installation, it is deep effectively to carry out socket joint The visualized management of degree can not check that pipe joint socket joint depth deficiency caused by socket joint depth deficiency causes when avoiding construction Percolating water.
Embodiment 1
Setting-out blanket as shown in Figure 2, including the flexible plane 1 made of Corvic material, and, it is arranged described Flexible plane, multiple location holes compatible with multiple waterstop joints 2;Wherein, setting-out blanket edge is additionally provided with for being determined Positioning side 3 of the position in template, positioning side 3 are equipped with locating clip 31.
Embodiment 2
The installation of drainpipe
1, setting-out blanket marks template
The length and width of bathroom floor are measured using ruler (other instruments for measuring length are equally applicable to the present invention) Degree, waterstop joint diameter and waterstop joint are in template layout design position size;According to the dimension data of measurement, setting-out is correspondingly cut out Blanket makes setting-out blanket have size identical as template, and the position of waterstop joint is marked on setting-out blanket;Sealing section according to label It sets, processing of leaving a blank will be carried out on setting-out blanket, the waterstop joint position marked on setting-out blanket is made to leave a blank.
It can be to the waterstop joint with the kitchen and toilet soil stack installation above and below the same vertical plane in building using setting-out blanket It is pre-buried fast and accurately to be positioned, it avoids the soil stack caused by pre-buried waterstop joint deviations and is connected deviation, Pre-buried positioning measurement is carried out after the completion of every layer of kitchen and toilet roof plate template is laid with without ruler, it is pre-buried to greatly reduce waterstop joint The time of positioning.
2, the positioning of waterstop joint
The setting-out blanket cut is placed in template, tool is made to be flushed with the avris of floor, using color spray paint in setting-out blanket Position of leaving a blank is sprayed and is filled, and template surface is made to form multiple coloured locating pieces of tool.
3, the installation of waterstop joint
Sealing is saved into the color locating piece position that steel nail is fixedly mounted in template, the side at edge and the locating piece Edge flushes, then is located at the socket of template to waterstop joint and carries out processing of leaving a blank, and clears up the miscellaneous of waterstop joint socket and its inner wall Object pours into a mould concrete around waterstop joint, and waterstop joint is made to be embedded in concrete in advance.
4, the installation of drainpipe
It is according to the design requirement of toilet pipeline, drainage pipeline is pre- advanced according to size using socket drain pipe road The necessary cutting of row and installation, and socket joint depth marking line is marked on bell-and-spigot pipe, then using the midpoint of marking line as the center of circle, make to justify Circle label, makes marking line be located at the centre position of circles mark, and leakage half-turn accomplishes visualized management after making pipe joint socket joint, Cutting and assembled tubing are assembled at the scene again;It is uniformly applied to waterstop joint bellmouth inner wall with binder and waits pacifying Drainage pipeline, is installed to rapidly the socket of waterstop joint by the drainage pipeline outer wall surface of dress, and when structure construction is disposably pre-buried Measurement error is avoided in place, it is faster.
Although above-mentioned elaborate the present invention, but not limited to this, those skilled in the art can basis The principle of the present invention is modified, and therefore, the various modifications that all principles according to the invention carry out all should be understood as falling into this The protection domain of invention.

Claims (4)

1. a kind of construction method of installation of kitchen and bath's drainpipe, which is characterized in that include the following steps:
A, setting-out blanket marks template
Using the length of ruler measurement bathroom floor with width, waterstop joint diameter and waterstop joint in template layout design position ruler It is very little;According to the dimension data of measurement, setting-out blanket is correspondingly cut out, makes setting-out blanket that there is size identical as template, and in setting-out blanket The position of upper label waterstop joint;According to the waterstop joint position of label, processing of leaving a blank will be carried out on setting-out blanket, make to be marked on setting-out blanket It leaves a blank the waterstop joint position of note;
Use the pre-buried progress of waterstop joint of the kitchen and toilet soil stack installation above and below the same vertical plane in the buildings setting-out Tan Duitongdong Fast and accurately position;
B, the positioning of waterstop joint
The setting-out blanket cut is placed in template, it is made to be flushed with the avris of floor, uses color spray paint leaving a blank in setting-out blanket Position is sprayed and is filled, and template surface is made to form multiple color locating pieces;
C, the installation of waterstop joint
Sealing is saved into the color locating piece position that steel nail is fixedly mounted in template, the edge at edge and the locating piece is neat It is flat, then be located at the socket of template to waterstop joint and carry out processing of leaving a blank, and the sundries of waterstop joint socket and its inner wall is cleared up, Casting concrete around waterstop joint, makes waterstop joint be embedded in concrete in advance;
D, the installation of drainpipe
Using socket drain pipe road, according to the design requirement of toilet pipeline, drainage pipeline is carried out in advance according to size must The cutting and installation wanted, and socket joint depth marking line is marked on bell-and-spigot pipe, then using the midpoint of marking line as the center of circle, make circle mark Note, makes marking line be located at the centre position of circles mark, and leakage half-turn accomplishes visualized management after making pipe joint socket joint, then will Cutting and assembled tubing are assembled at the scene;Waterstop joint bellmouth inner wall and to be installed is uniformly applied to binder Drainage pipeline is installed to rapidly the socket of waterstop joint by drainage pipeline outer wall surface.
2. construction method of installation as described in claim 1, which is characterized in that the diameter of the circles mark is less than marking line.
3. construction method of installation as described in claim 1, which is characterized in that the setting-out blanket is made of Corvic, It which is provided with the grid-like plane of coordinate setting that a plurality of parallel transverse crease lines are formed with a plurality of parallel longitudinal broken line.
4. construction method of installation as described in claim 1, which is characterized in that setting-out blanket edge is equipped with for being installed Locating plate in template or locating clip.
CN201510057996.4A 2015-02-04 2015-02-04 The construction method of installation of kitchen and bath's drainpipe Expired - Fee Related CN104747798B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510057996.4A CN104747798B (en) 2015-02-04 2015-02-04 The construction method of installation of kitchen and bath's drainpipe

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510057996.4A CN104747798B (en) 2015-02-04 2015-02-04 The construction method of installation of kitchen and bath's drainpipe

Publications (2)

Publication Number Publication Date
CN104747798A CN104747798A (en) 2015-07-01
CN104747798B true CN104747798B (en) 2018-08-21

Family

ID=53587901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510057996.4A Expired - Fee Related CN104747798B (en) 2015-02-04 2015-02-04 The construction method of installation of kitchen and bath's drainpipe

Country Status (1)

Country Link
CN (1) CN104747798B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106481076A (en) * 2016-11-16 2017-03-08 南通安装集团股份有限公司 A kind of pre-buried technique of draining pipe collar
CN111075991B (en) * 2019-11-25 2021-10-01 宁夏昌禾装饰工程有限公司 Water pipeline laying method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2908679A1 (en) * 1979-03-06 1980-09-18 Bosch Gmbh Robert Drain water reuse system for toilet flushing - has fresh water stop valve controlled by level indicator (NL 9.9.80)
CN101691772A (en) * 2009-10-28 2010-04-07 朱成三 Fabricated novel installation process for drain pipe
CN102587654A (en) * 2012-02-23 2012-07-18 中国建筑第二工程局有限公司 Construction method for PVC (poly vinyl chloride) drainage direct-buried pipe fitting
CN202755650U (en) * 2012-07-31 2013-02-27 福建亚通新材料科技股份有限公司 Novel embedded pipe fitting for drainage and pollution discharge of building floors
CN103089014A (en) * 2013-02-05 2013-05-08 浙江新东阳建设集团有限公司 Construction method of through floor pipe

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4811929B2 (en) * 2006-03-30 2011-11-09 株式会社クボタ Drainage collecting pipe
JP2008144508A (en) * 2006-12-12 2008-06-26 Bridgestone Corp Siphon draining system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2908679A1 (en) * 1979-03-06 1980-09-18 Bosch Gmbh Robert Drain water reuse system for toilet flushing - has fresh water stop valve controlled by level indicator (NL 9.9.80)
CN101691772A (en) * 2009-10-28 2010-04-07 朱成三 Fabricated novel installation process for drain pipe
CN102587654A (en) * 2012-02-23 2012-07-18 中国建筑第二工程局有限公司 Construction method for PVC (poly vinyl chloride) drainage direct-buried pipe fitting
CN202755650U (en) * 2012-07-31 2013-02-27 福建亚通新材料科技股份有限公司 Novel embedded pipe fitting for drainage and pollution discharge of building floors
CN103089014A (en) * 2013-02-05 2013-05-08 浙江新东阳建设集团有限公司 Construction method of through floor pipe

Also Published As

Publication number Publication date
CN104747798A (en) 2015-07-01

Similar Documents

Publication Publication Date Title
CN103669562A (en) Cantilever bay window board concrete overall pouring structure and construction method thereof
CN103089014A (en) Construction method of through floor pipe
CN103025971B (en) Improvement waste discharge accessory
CN107630565B (en) Method and equipment for closing opening of external wall
CN104747798B (en) The construction method of installation of kitchen and bath's drainpipe
CN106049862A (en) Inflatable adjustable type construction mold for reserved hole in concrete structure plate, and construction method
CN105019651B (en) Hollow brick fills wall into the efficient installation engineering method of winding box
CN109899600A (en) A kind of building pipe mounting process
CN207469307U (en) A kind of gang form structure of the inspection shaft cast-in-place construction of town road pipeline
CN102605938B (en) Building wall-whitewashing, plastering and leveling or ground leveling guiding rule and assorted punched ribs
CN109750723A (en) A kind of construction method of installation of kitchen and bath's drainpipe
CN109838619A (en) A method of installation building pipe
CN203654993U (en) Concrete structure cantilever bay window board
CN109519609A (en) A kind of building pipe mounting process
CN109899599A (en) A kind of building pipe mounting process
CN107401208A (en) A kind of construction method of installation of kitchen and bath's drainpipe
CN107489815A (en) A kind of pipeline mounting construction method
CN212897583U (en) One-time pre-embedding device for steel sleeve
CN215671081U (en) Positioning tool template for embedding water stop joint
CN109056702A (en) The construction method of coercion underground continuous wall
CN214772202U (en) Blade for cutting anti-crack groove of blank
CN104131697B (en) Tool type formwork system for kitchen and bath concrete waterproof guide wall and construction method of tool type formwork system
CN210034649U (en) Socket-type waterproof PVC embedded functional part
CN210003941U (en) Detachable anti-seepage sleeve assembly
CN203462591U (en) Embedded type points warehouse seam

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180821

CF01 Termination of patent right due to non-payment of annual fee