The construction method that a kind of steel structural roof interior lining panel is installed from molding jig pore-forming
Technical field
The present invention relates to the construction method that a kind of steel structural roof interior lining panel is installed from molding jig pore-forming, for building neck
Domain.
Background technology
At present in architectural engineering industrial premises, public building long-span roofing, for reducing roofing deadweight, mitigate load,
Usually adopt interior lining panel roofing, interior lining panel roofing is a kind of novel construction process being formed in recent years, due to its easy construction, work
The superioritys such as skill uniqueness, the good, attractive appearance of water resistance, are used widely in recent years, and achieve preferable economic benefit
And social benefit.But the steel structure roofing liner interior lining panel of traditional method construction is uneven, in base surface, presence nail road is not straight,
Leave the phenomenons such as nail is excessive after finished product, have a strong impact on the sensorial effects of roofing.
Content of the invention
For solving problem above, the present invention provides the construction party that a kind of steel structural roof interior lining panel is installed from molding jig pore-forming
Method.
The technical scheme is that the construction method that a kind of steel structural roof interior lining panel is installed from molding jig pore-forming, bag
Include surveying setting-out, mounting purlines, make mould and interior lining panel punching, interior lining panel be hung to operating platform, roofing interior lining panel install with
And cleanup step, concrete operations condition is as follows:
Described surveying setting-out is to carry out roofing interior lining panel row in advance according to design drawing and engineering entity size before construction
Plate layout drawing, further according to row plate layout drawing carry out live unwrapping wire, by often across or node eject roof purline installation control line;
Described mounting purlines are by traditional steel house panel installation techniques construction;During construction, main purlin and bearing section
Point plate, secondary purlin are with bolts with main purlin, and between secondary purlin and secondary purlin, spreading is with bolts by purlin supporting plate,
The connecting bolt of primary and secondary purlin must be tightened shimming one by one;Main purlin must strictly check slope top and toe absolute altitude when installing, draws
Line corrects, fixes;Meet when joint installs straight it is necessary to scene be carried out using specific purpose tool again take hole, secondary purlin typesetting
When to ensure gutter position accurately, first by fixed flat at gutter during installation;
The described mould and interior lining panel punching of making is that first the width according to interior lining panel and purlin center distance make a square
Shape base, width ratio interior lining panel width 2mm, length direction 1m shorter than pre- making interior lining panel length, it is easy to the interior lining panel making hole
Carry away base, be fixed into a firm base using steel nail, then carry out labelling according to purlin centre-to-centre spacing on base length direction,
This be labeled as after on surface layer interior lining panel, snap the line is ready, base is put on one piece of smooth ground well, in 5 20 pieces
Liner plate is put in mould, according to being marked at the good line of ink marker of bullet on surface layer interior lining panel, then drilling on base;
It is after the completion of pore-forming on the mould of ground that described interior lining panel is hung to operating platform, puts neat, profit by length classification
With the hole position accomplished fluently as suspension centre, sling into punch die with the rope made of hemp on the operational platform;Once 45 pieces can be lifted by crane, peace simultaneously
Install and lift by crane again after finishing, it is to avoid on operating platform load is excessive and the security performance that has influence on operating platform.For preventing from lifting
Journey interior lining panel deforms, and should make backing using shaped steel, it is to avoid interior lining panel deforms in hoisting process, should combine simultaneously during lifting
Consider that material placement location holding capacity situation determines and once lift quantity, reduce manually secondary transhipment as far as possible.Vertical transport sheet material
When it should be noted that guaranteeing that all of interior lining panel is face-up, and all of overlap edge (female rib) should be towards installing the direction starting.
It is to be not less than a pitch of waves according to the transverse lap of interior lining panel that described roofing interior lining panel is installed, and longitudinal lap joint is not less than
120mm, is fixed on roofing time purlin using the crest that tap bolt penetrates interior lining panel vertical wave stricture of vagina, tap bolt must be with secondary purlin
Bar supporting surface is vertical, fixing firm;
Described cleaning is after the interior lining panel in installation operating platform region, and workmen is with water by interior lining panel bottom surface
Scrub at pollution, for there is scratching place, application is mended with the paint-adding pen of mother matrix solid colour, it is to avoid formation aberration and shadow
Sound is attractive in appearance.
Know-why:
In traditional method, workman faces upward head on the operational platform and exerts oneself nailing, the shortcoming causing hole position wayward and training off,
So that the interior lining panel nail road that construction completes is horizontal uneven vertical, have a strong impact on attractive in appearance.Key technology of the present invention is on ground
Pore-forming on mould, improves drilling precision and drilling efficiency, overcomes workman and faces upward head on the operational platform and exert oneself nailing, causes hole
The shortcoming that position is wayward and trains off, ensures that the construction quality of roofing coloured silk steel lining plate.
The present invention has the prominent advantages that:
1. economical: using mould construction, there is light and fast, about 20 pieces of interior lining panels of a rapid shaping, save manpower, apply
Work speed is fast, and the reduction of erection time, energy-saving, the cost of input is considerably less, obtains effect fairly good;
2. attractive in appearance: the steel structure roofing interior lining panel nail road being completed using present invention construction is smooth vertical and horizontal, attractive in appearance;
3. simple to operate: simple to operate it is easy to grasp it is not necessary to main equipment.
Brief description
Fig. 1 is the technological process of the construction method that steel structural roof interior lining panel of the present invention is installed from molding jig pore-forming
Figure.
Specific embodiment
Below by way of drawings and Examples, technical scheme is further illustrated.
Embodiment 1
One instantiation of the construction method that steel structural roof interior lining panel of the present invention is installed from molding jig pore-forming,
Comprise the steps:
On probation, construction in five meters of car technological transformation project assembly shop civil engineerings of certain company with the construction of public work roof boarding
Front roofing interior lining panel row's plate layout drawing has been carried out according to engineering entity size, and carry out live unwrapping wire by figure;Traditionally apply
Work mounting purlines;Width according to interior lining panel and purlin center distance one rectangular base of making, width ratio interior lining panel width 2mm,
Length direction makes the slightly short 1m of interior lining panel length than pre-, then using steel nail be fixed on smooth good ground one firm
Base, then carry out labelling according to purlin centre-to-centre spacing on base length direction, 15 pieces of interior lining panels are put in mould, the bottom of according to simultaneously
It is marked at the good line of ink marker of bullet on surface layer interior lining panel on seat, then punch;After the completion of pore-forming, put neat by length classification, using
The hole position accomplished fluently, as suspension centre, according to a conventional method in interior lining panel handling to operating platform, once lifts by crane 5 pieces simultaneously;Using wearing
Thoroughly formula fixed installation interior lining panel, first by interior lining panel according to the direction orthogonal with gutter, is emitted on mounted purlin, by setting
Meter requirement extend in gutter, first produced hole position is directed at purlin position when fixing, straight after squeezed into tapping screw right
Answer hole position;After the interior lining panel in operating platform region installs, with water by scrub at the pollution of interior lining panel bottom surface, for going out
Now scratch place, the paint-adding pen for mother matrix solid colour mends.After the completion of construction, quality is very good, obtains the favorable comment of Construction Party.
Embodiment 2
Another of the construction method that steel structural roof interior lining panel of the present invention is installed from molding jig pore-forming is specifically real
Example, comprises the steps:
Move on probation during a phase technological transformation project press workshop civil engineering is constructed with public work roof boarding in certain company's passenger car,
Before construction, roofing interior lining panel row's plate layout drawing is carried out according to design drawing, and carried out live unwrapping wire by figure;Traditionally apply
Work mounting purlines;Width according to interior lining panel and purlin center distance one rectangular base of making, width ratio interior lining panel width 2mm,
Length 1m shorter than interior lining panel length, is then fixed into firm base using steel nail on smooth good ground, rectangular in base
Carry out labelling according to purlin centre-to-centre spacing upwards, 20 pieces of interior lining panels are put in mould simultaneously, according to being marked on surface layer interior lining panel
The good line of ink marker of bullet, then punches;After the completion of pore-forming, put neat by length classification, by the use of the hole position accomplished fluently as suspension centre, by normal
Rule method, in interior lining panel handling to operating platform, once lifts by crane 4 pieces simultaneously;Interior lining panel is fixedly mounted using penetration, first will
Interior lining panel, according to the direction orthogonal with gutter, is emitted on mounted purlin, is first directed at produced hole position when fixing
Purlin position, straight after squeeze into corresponding hole position with tapping screw;After the interior lining panel in operating platform region installs, will with water
Scrub at the pollution of interior lining panel bottom surface, for occurring scratching place, the paint-adding pen for mother matrix solid colour mends.Construction completes
Quality is very good afterwards, after this completion of works is checked and accepted, obtains Guangxi high grade project prize.
Embodiment 3
One instantiation of the construction method that steel structural roof interior lining panel of the present invention is installed from molding jig pore-forming,
Comprise the steps:
On probation in certain passenger car resettlement one phase technological transformation project body workshop engineering roof boarding construction, according to engineering before construction
Entity size has carried out roofing interior lining panel row's plate layout drawing, and carries out live unwrapping wire by figure;Traditionally construction and installation purlin;
Width according to interior lining panel and purlin center distance make a rectangular base, width ratio interior lining panel width 2mm, and length compares interior lining panel
The short 1m of length, is then fixed into firm base using steel nail on smooth good ground, then according to purlin on base length direction
Bar centre-to-centre spacing carries out labelling, 20 pieces of interior lining panels is put in mould simultaneously, and according to being marked on base, bullet on surface layer interior lining panel is good
The line of ink marker, then punches;After the completion of pore-forming, put neat by length classification, by the use of the hole position accomplished fluently as suspension centre, routinely side
Method, in interior lining panel handling to operating platform, once lifts by crane 5 pieces simultaneously;Interior lining panel is fixedly mounted using penetration, first by liner
Plate, according to the direction orthogonal with gutter, is emitted on mounted purlin, first produced hole position is directed at purlin when fixing
Position, straight after squeeze into corresponding hole position with tapping screw;After the interior lining panel in operating platform region installs, with water by liner
Scrub at the pollution of plate bottom surface, for occurring scratching place, the paint-adding pen for mother matrix solid colour mends.Matter after the completion of construction
Amount is very good, after this completion of works is checked and accepted, obtains national high grade project prize.