CN102409811B CN 201110230544 CN201110230544A CN102409811B CN 102409811 B CN102409811 B CN 102409811B CN 201110230544 CN201110230544 CN 201110230544 CN 201110230544 A CN201110230544 A CN 201110230544A CN 102409811 B CN102409811 B CN 102409811B
Authority
CN
China
Prior art keywords
metal
base plate
metal base
buckling parts
fixed
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110230544
Other languages
Chinese (zh)
Other versions
CN102409811A (en
Inventor
邵启雁
付梓
崔卓立
蔡庆军
王荣涛
郭青松
吴黄忠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN 201110230544 priority Critical patent/CN102409811B/en
Publication of CN102409811A publication Critical patent/CN102409811A/en
Application granted granted Critical
Publication of CN102409811B publication Critical patent/CN102409811B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention discloses an air-tight heat insulation metal roof and a construction method thereof. The air-tight heat insulation metal roof comprises a roof truss, a plurality of purline supports, a plurality of purlines, a plurality of metal bottom plates, a plurality of metal top plates and glass wool, wherein the purline supports are welded on the truss at fixed intervals; the plurality of purlines are fixed on the purline supports through bolts; the adjacent metal bottom plates are mutually buckled and fixed on the purlines through a plurality of fixed bases; the adjacent metal top platesare mutually buckled and fixed on the metal bottom plates through a heat insulation metal fixed seat; and the glass wool is spread between the metal bottom plates and the metal top plates. By adopting the air-tight heat insulation metal roof and the construction method thereof, air-tight heat insulation construction of plant roofs of high-technology industries such as electronics, biological pharmacy and the like is realized; and the air-tight heat insulation metal roof and the construction method have the advantages of high construction efficiency, low construction cost and a small number ofconstruction processes.

Description

Airtight insulated metal roofing and job practices thereof
Technical field
The present invention relates to a kind of roofing and job practices thereof, refer to a kind of airtight insulated metal roofing and job practices thereof especially.
Background technology
Along with developing rapidly of high-tech industry such as China's electronics, bio-pharmaceuticals become a kind of trend, there is the factory building of airtight heat insulation requirement to increase gradually, but present conventional roofing and job practices thereof are not suitable for the airtight heat insulation constructions of high-tech industry such as electronics, bio-pharmaceuticals, and can not satisfy airtight heat insulation requirement well, it is slow to have speed of application simultaneously, the construction cost height, problem such as working procedure is loaded down with trivial details.
Summary of the invention
The objective of the invention is to overcome the defective of prior art, and a kind of airtight insulated metal roofing and job practices thereof are provided, it has airtight thermal stability height, can satisfy airtight heat insulation requirement, and the efficiency of construction height, and construction cost is low, the advantage that working procedure is few.
The technical scheme that realizes above-mentioned purpose is:
A kind of airtight insulated metal roofing of the present invention, roofing is fixed on the purlin, comprising:
A plurality of purlin holders are welded on the described truss described purlin holder constant spacing;
A plurality of purlins, described purlin by bolt in described purlin holder;
A plurality of metal base plates, mutual snapping between the described adjacent metal base plate, and be fixed on the described purlin by the plurality of fixed base;
A plurality of metal top plate, mutual snapping and be fixed on the described metal base plate by a heat insulating metal holder between the described adjacent metal top board;
Glass wool, described glass wool are layed between described metal base plate and the described metal top plate.
Above-mentioned adjacent metal base plate comprises one first metal base plate and one second metal base plate; The end of described first metal base plate forms first buckling parts of one first metal base plate; The end of second metal base plate forms second buckling parts of one second metal base plate; Described first metal base plate and described second metal base plate are anchored on described firm banking by one first clip component: first end chucking of the described first clip component is fixed between the two adjacent described firm bankings, second end of the described first clip component is fastened on first buckling parts of described first metal base plate, and is fastened under second buckling parts of described second metal base plate.
Paste the Ethylene Propylene Terpolymer adhesive tape between second end of first buckling parts of above-mentioned first metal base plate, the first clip component and second buckling parts of second metal base plate, the button seam place of second buckling parts of described second metal base plate and first buckling parts of first metal base plate is marked with fluid sealant.
Above-mentioned adjacent metal top board comprises one first metal top plate and one second metal top plate, and the end of described first metal top plate forms first buckling parts of one first metal top plate; The end of described second metal top plate forms second buckling parts of one second metal top plate; Described first metal top plate and described second metal top plate are anchored on described heat insulating metal holder by one second clip component; First end chucking of the described second clip component is fixed in the top of described heat insulating metal holder, and the bottom chucking of heat insulating metal holder is fixed on second buckling parts of described second metal base plate; Second end is fastened on first buckling parts of described first metal top plate, and is fastened under second buckling parts of described second metal top plate.
Above-mentioned heat insulating metal holder is made up of three parts, and top is that stainless steel, centre are divided into galvanized steel plain sheet for white flame-retarded resin, bottom.
A kind of job practices based on airtight insulated metal roofing of the present invention may further comprise the steps:
S1: set up roofing truss, with a plurality of purlin holder constant spacings be welded on the described truss, again with a plurality of purlins by bolt in described purlin holder;
S2: with plurality of fixed base constant spacing be welded on the described purlin;
S3: on described firm banking, lay metal base plate, mutual snapping and being fixed on the described firm banking between the described adjacent metal base plate;
S4: on described metal base plate, lay glass wool;
S5: on described glass wool, lay metal top plate, mutual snapping and be fixed on the described metal base plate by a heat insulating metal holder between the described adjacent metal top board;
S6: carry out airtight receipts limit at gable, ridge, cornice place, will receive side plate and truss is fixed, and finish the laying of edge's metal base plate and metal top plate.
As follows to carrying out mutual snapping between the above-mentioned adjacent metal base plate and being fixed on the described firm banking:
Form one first buckling parts in the end of one first metal base plate;
End at second metal base plate of adjacent described first metal base plate forms one second buckling parts;
First end of one first clip component chucking is fixed between the two adjacent firm bankings, second end of the described first clip component is fastened on first buckling parts of described first metal base plate;
Second buckling parts of described second metal base plate is fastened on second end of the described first clip component.
As follows to carrying out mutual snapping between the described adjacent metal top board and being fixed on the described metal base plate:
Form one first buckling parts in the end of one first metal top plate;
End in second metal top plate of adjacent described first metal top plate forms one second buckling parts;
First end of one second clip component chucking is fixed in the top of described heat insulating metal holder, second end of the described second clip component is fastened on first buckling parts of described first metal top plate;
The bottom chucking of described heat insulating metal holder is fixed on second buckling parts of described second metal base plate,
Second buckling parts of described second metal top plate is fastened on second end of the described second clip component.
Be fastened at second end with the above-mentioned first clip component before first buckling parts of described first metal base plate, first buckling parts at described first metal base plate pastes the Ethylene Propylene Terpolymer adhesive tape earlier; Be fastened at second buckling parts with described second metal base plate before second end of the described first clip component, second end at the described first clip component pastes the Ethylene Propylene Terpolymer adhesive tape earlier.
After second buckling parts with above-mentioned second metal base plate is fastened on second end of the described first clip component, also comprise step: inject fluid sealant at second buckling parts of described second metal base plate and the outside button of first buckling parts seam place of described first metal base plate.
The present invention has been owing to adopted above technical scheme, makes it have following beneficial effect to be:
The airtight thermal stability height of roofing, anticorrosion, antirust and fireproof performance is good, simple in structure being convenient to installed, and realized the airtight heat insulation construction of high-tech industry factory building roofs such as electronics, bio-pharmaceuticals, guaranteed the speed of application of double-deck airtight insulated metal roofing, reduced the operation of construction, it is good to have air-tightness, heat-proof quality height, efficiency of construction height, construction cost is low, the advantage that working procedure is few.
Description of drawings
Fig. 1 is the roof structure schematic diagram of the airtight insulated metal roofing of the present invention and job practices thereof;
Fig. 2 decomposes view for the metal base plate buckling parts of the airtight insulated metal roofing of the present invention and job practices thereof;
Fig. 3 is the metal base plate buckling parts buckling state structural representation of the airtight insulated metal roofing of the present invention and job practices thereof;
Fig. 4 is the metal top plate buckling parts buckling state structural representation of the airtight insulated metal roofing of the present invention and job practices thereof;
Fig. 5 fastens the installation steps schematic diagram for the metal base plate of the airtight insulated metal roofing of the present invention and job practices thereof.
The specific embodiment
The invention will be further described below in conjunction with the drawings and specific embodiments.
See also Fig. 1, a kind of airtight insulated metal roofing of the present invention comprises a roofing truss 3, also comprises:
A plurality of metal base plates 7, mutual snapping between the adjacent metal base plate 7, and be fixed on the purlin 2 by plurality of fixed base 5; Purlin 2 is anchored on purlin holder 1 by bolt 4, is welded on the truss 3 purlin holder 1 constant spacing; Glass wool 8 is layed on the metal base plate 7, and this glass wool 8 is the PE(polyethylene) the film glass cotton, thickness in monolayer is 80mm, weight is 16kg/m; A plurality of metal top plate 9 are layed on the glass wool 8, mutual snapping and be fixed on the metal base plate 7 by a heat insulating metal holder 6 between the adjacent metal top board 9, and metal top plate 9 adopts the 0.8mmPVDF steel plates.Heat insulating metal holder 6 is made up of three parts, top is that stainless steel, centre are divided into galvanized steel plain sheet for white flame-retarded resin, bottom, its middle and upper part stainless steel contacts with the upper strata flashing board, prevent from getting rusty and influence the cleanliness factor of air, middle part flame-retarded resin material is cut off the heat that top plate brings, play heat-blocking action, bottom not galvanized steel plain sheet is play anticorrosion and the effect of top plate strength of stability.
See also Fig. 2,3, adjacent metal base plate 7 comprises one first metal base plate 71 and one second metal base plate 72; The end parts of first metal base plate 71 forms first buckling parts 11 of one first metal base plate 71; The end parts of second metal base plate 72 forms first buckling parts 11 of second buckling parts, 15, the first metal base plates 71 of one second metal base plate 72 and second buckling parts 15 of second metal base plate 72 is anchored on firm banking 5 by one first clip component 12; First end, 121 chuckings of the first clip component 12 are fixed between the two adjacent firm bankings 5, second end 122 of the first clip component 12 is fastened on first buckling parts 11 of first metal base plate 71, and is fastened on second buckling parts 15 times of second metal base plate 72.
Paste Ethylene Propylene Terpolymer (EPDM) adhesive tape 13 between second buckling parts 15 of first buckling parts 11 of first metal base plate 71, second end of the first clip component 12 and second metal base plate 72, the button seam place of second buckling parts 15 of second metal base plate 72 and first buckling parts 11 of first metal base plate 71 is marked with fluid sealant 14, fluid sealant 14 is sealing silicone grease glue, guarantees the airtight effect of roofing by adhesive tape 13 and fluid sealant 14.Metal base plate 7 is the 0.8mmGL corrugated steel, and adopts the airtight sheet material of metal.
See also Fig. 4, adjacent metal top board 9 comprises one first metal top plate 91 and one second metal top plate 92, and itself and above-mentioned metal base plate manner are similar, the end of first metal top plate 91 form first buckling parts 11 of one first metal top plate 91 '; The end of second metal top plate 92 form second buckling parts 15 of one second metal top plate 92 '; First buckling parts 11 of first metal top plate 91 ' and second buckling parts 15 of second metal top plate 92 ' be anchored on heat insulating metal holder 6 by one second clip component 16; The bottom chucking of heat insulating metal holder 6 is fixed on second buckling parts 15 of second metal base plate 72; Top 6, the second ends that first end of the second clip component 16 chucking is fixed in the heat insulating metal holder be fastened on first buckling parts 11 of first metal top plate 91 ' on, and be fastened on second buckling parts 15 of second metal top plate 92 ' down.
The job practices of this airtight insulated metal roofing may further comprise the steps:
S1: set up roofing truss 3, with a plurality of purlin holder 1 constant spacings be welded on the truss 3, more a plurality of purlins 2 are fixed in the purlin holder 1 by bolt 4;
Double-deck airtight heat insulating metal heat-insulated roof purlin holder 1 welding procedure, planeness is had relatively high expectations, after truss 3 constructions are finished, need to proofread and correct construction to steel column and roofing, and check and proofread and correct the result, treat all to check meet the requirements after, and all truss 3 anticorrosion, antirust and fire prevention are handled, all purlin holder 1 arrangement pitchs process calculate, and through the design audit, can carry out purlin holder 1 and arrange welding procedure.After purlin holder 1 was welded with truss 3, antiseptic and rustproof processing was carried out in trimming, finish paint brush ring oxygen coating.After purlin holder 1 installation, carry out same direction, same absolute altitude height measure, if same direction height surpasses 20mm, should give the adjustment of metal shimming, pad must pass through anticorrosion, antirust processing, treating that all highly put to adjust finishes, and carries out purlin 2 and installs, and 1 employing of purlin 2 and purlin holder bolt 4 carries out fastening.
S2: with plurality of fixed base 5 constant spacings be welded on the purlin 2;
Before firm banking 5 is installed, should carry out firm banking 5 and measure unwrapping wire, firm banking 5 adopts the fine melt welding with purlin 2 welding, and trimming in time, does anticorrosion, antirust processing.
S3: on firm banking 5, lay metal base plate 7, snapping and being fixed on the firm banking 5 mutually between the adjacent metal base plate 7;
See also Fig. 5, as follows to carrying out mutual snapping between the adjacent metal base plate 7 and being fixed on the firm banking 5:
Form one first buckling parts 11 in the end of one first metal base plate 71;
End at second metal base plate 72 of adjacent this first metal base plate 71 forms one second buckling parts 15;
First buckling parts 11 at first metal base plate 71 pastes Ethylene Propylene Terpolymer adhesive tape 13;
First end 121 chucking of one first clip component 12 is fixed between the two adjacent firm bankings 5, second end 122 of the first clip component 12 is fastened on first buckling parts 11 of first metal base plate 71;
Second end at the first clip component 12 pastes Ethylene Propylene Terpolymer adhesive tape 13;
Second buckling parts 15 of second metal base plate 72 is fastened on second end of the first clip component 12;
Inject fluid sealant 14 at second buckling parts 15 of second metal base plate 72 and first buckling parts, the 11 outside button seam places of first metal base plate 71.
Metal base plate 7 fastens plural number by manual fastening means and electronic fastening means, when connecting by manual fastening means, fastens once every a constant spacing.Can once reach temporary fixed by manual fastening means every three meters fastenings earlier, fasten once by electronic fastening means whole piece again, totally twice, in whole process, to keep the clean and tidy of roofing.
The laying of metal base plate 7 and die casting are carried out simultaneously.
Before laying metal base plate 7, earlier set up the moulding pallet according to scheme, the forming supporter table top is stacked the uncoiling machine, cutting off machine, facility such as forming machine and coil of strip material, about 16 tons of gross weight, the forming supporter stage body is the steel pipe scaffold support system, when steel pipe scaffold is set up, need can to set up through strict calculating support system, scaffolding height is consistent with the pitched roof minimum point, set up need after finishing qualified by inspection after, can come into operation, carry out template again and lay the uncoiling machine, the forming press hoisted in position carries out security maintenance simultaneously all around, thereby realize base plate 7 die casting a slices laying a slice, make the laying of base plate 7 and die casting carry out simultaneously.When carrying out the construction of coil of strip die cast, 40 meters of moulding base plate 7 length (maximum length can to 300 meters), crest height 166mm, at any time check in the press casting procedure whether moulding base plate 7 adheres to specification, as crest height, crest face horizontal dimension, should stop die casting immediately when pinpointing the problems.
S4: on metal base plate 7, lay glass wool 8; Bilayer laid by glass wool 8 and seam crossing staggers, and for the prevention change in weather is laid for the subregion generally speaking, the glass wool 8 in a zone is laid and finished by passed examination, and subsequent handling is carried out in this zone at once.
S5: on glass wool 8, lay metal top plate 9, snapping and be fixed on the metal base plate 7 by a heat insulating metal holder 6 and (see also Fig. 3) mutually between the adjacent metal top board 9;
Should evenly arrange by design size when heat insulating metal holder 6 is installed, can not arbitrarily install, need after the installation to check and accept.
As follows to carrying out mutual snapping between the adjacent metal top board 9 and being fixed on the metal base plate 7:
Form in the end of one first metal top plate 91 one first buckling parts 11 ';
Form in the end of second metal top plate 92 of adjacent this first metal top plate 91 one second buckling parts 15 ';
First end of one second clip component 16 chucking is fixed in the top of heat insulating metal holder 6, with second end of the second clip component 16 be fastened on first buckling parts 11 of first metal top plate 91 ' on;
With heat insulating metal holder 6 bottom chucking be fixed on second buckling parts 15 of second metal base plate 72,
With second buckling parts 15 of second metal top plate 92 ' be fastened on second end of the second clip component 16.
S6: carry out airtight receipts limit at gable, ridge, cornice place, gable is received side plate 17 and end receipts side plate 10 and truss 3 to be fixed, and finish the laying of edge's metal base plate 7 and metal top plate 9, realize that eaves limit and partition wall slit place closes up, reach 100 grades in order to ensure tightness, side plate 17 received by gable and end receipts side plate 10 is the thick galvanized steel plain sheet of 2mm.
In addition, calcium silicate board internal partition wall end face absolute altitude is concordant with metal Roof purlin 2 upper surfaces, combine with roofing metal base plate 7, play airtight effect, ridge, gable are not done when waterproof is received the limit and must be taked as corresponding measures such as interim receipts limit or plastic paper covering are installed this one to be carried out interim waterproof, prevent glass wool 8 water inlets.
Below the present invention of embodiment has been described in detail by reference to the accompanying drawings, and those skilled in the art can make the many variations example to the present invention according to the above description.Thereby some details among the embodiment should not constitute limitation of the invention, and the scope that the present invention will define with appended claims is as protection scope of the present invention.

Claims (8)

1. an airtight insulated metal roofing comprises a roofing truss, it is characterized in that, also comprises:
A plurality of purlin holders are welded on the described truss described purlin holder constant spacing;
A plurality of purlins, described purlin by bolt in described purlin holder;
A plurality of metal base plates, mutual snapping between the described adjacent metal base plate, and be fixed on the described purlin by the plurality of fixed base; Described adjacent metal base plate comprises one first metal base plate and one second metal base plate; The end of described first metal base plate forms first buckling parts of one first metal base plate; The end of second metal base plate forms second buckling parts of one second metal base plate; Described first metal base plate and described second metal base plate are anchored on described firm banking by one first clip component:
First end chucking of the described first clip component is fixed between the two adjacent described firm bankings, second end of the described first clip component is fastened on first buckling parts of described first metal base plate, and is fastened under second buckling parts of described second metal base plate;
A plurality of metal top plate, mutual snapping and be fixed on the described metal base plate by a heat insulating metal holder between the described adjacent metal top board;
Glass wool, described glass wool are layed between described metal base plate and the described metal top plate.
2. according to the described airtight insulated metal roofing of claim 1, it is characterized in that, paste the Ethylene Propylene Terpolymer adhesive tape between second end of first buckling parts of described first metal base plate, the described first clip component and second buckling parts of described second metal base plate, the button seam place of second buckling parts of described second metal base plate and first buckling parts of described first metal base plate is marked with fluid sealant.
3. airtight insulated metal roofing according to claim 1 is characterized in that, described adjacent metal top board comprises one first metal top plate and one second metal top plate, and the end of described first metal top plate forms first buckling parts of one first metal top plate; The end of described second metal top plate forms second buckling parts of one second metal top plate; Described first metal top plate and described second metal top plate are anchored on described heat insulating metal holder by one second clip component;
The bottom chucking of described heat insulating metal holder is fixed on second buckling parts of described second metal base plate;
First end chucking of the described second clip component is fixed in the top of described heat insulating metal holder, and second end is fastened on first buckling parts of described first metal top plate, and is fastened under second buckling parts of described second metal top plate.
4. airtight insulated metal roofing according to claim 1 is characterized in that, described heat insulating metal holder is made up of three parts, and top is that stainless steel, centre are divided into galvanized steel plain sheet for white flame-retarded resin, bottom.
5. the job practices based on airtight insulated metal roofing is characterized in that, may further comprise the steps:
S1: set up roofing truss, with a plurality of purlin holder constant spacings be welded on the described truss, again with a plurality of purlins by bolt in described purlin holder;
S2: with plurality of fixed base constant spacing be welded on the described purlin;
S3: on described firm banking, lay metal base plate, mutual snapping and being fixed on the described firm banking between the described adjacent metal base plate; Carry out mutual snapping between the described adjacent metal base plate and be fixed on the described firm banking:
Form one first buckling parts in the end of one first metal base plate;
End at second metal base plate of adjacent described first metal base plate forms one second buckling parts;
First end of one first clip component chucking is fixed between the two adjacent firm bankings, second end of the described first clip component is fastened on first buckling parts of described first metal base plate;
Second buckling parts of described second metal base plate is fastened on second end of the described first clip component;
S4: on described metal base plate, lay glass wool;
S5: on described glass wool, lay metal top plate, mutual snapping and be fixed on the described metal base plate by a heat insulating metal holder between the described adjacent metal top board;
S6: carry out airtight receipts limit at gable, ridge, cornice place, will receive side plate and truss is fixed, and finish the laying of edge's metal base plate and metal top plate.
6. according to claim 5ly it is characterized in that based on airtight insulated metal roofing job practices, as follows to carrying out mutual snapping between the described adjacent metal top board and being fixed on the described metal base plate:
Form one first buckling parts in the end of one first metal top plate;
End in second metal top plate of adjacent described first metal top plate forms one second buckling parts;
First end of one second clip component chucking is fixed in the top of described heat insulating metal holder, second end of the described second clip component is fastened on first buckling parts of described first metal top plate;
The bottom chucking of described heat insulating metal holder is fixed on second buckling parts of described second metal base plate,
Second buckling parts of described second metal top plate is fastened on second end of the described second clip component.
7. according to claim 5 based on airtight insulated metal roofing job practices, it is characterized in that, be fastened at second end with the described first clip component before first buckling parts of described first metal base plate, first buckling parts at described first metal base plate pastes the Ethylene Propylene Terpolymer adhesive tape earlier;
Be fastened at second buckling parts with described second metal base plate before second end of the described first clip component, second end at the described first clip component pastes the Ethylene Propylene Terpolymer adhesive tape earlier.
8. according to claim 5 based on airtight insulated metal roofing job practices, it is characterized in that, after second buckling parts with described second metal base plate is fastened on second end of the described first clip component, also comprise step: inject fluid sealant at second buckling parts of described second metal base plate and the outside button of first buckling parts seam place of described first metal base plate.
CN 201110230544 2011-08-12 2011-08-12 Air-tight heat insulation metal roof and construction method thereof Active CN102409811B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110230544 CN102409811B (en) 2011-08-12 2011-08-12 Air-tight heat insulation metal roof and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110230544 CN102409811B (en) 2011-08-12 2011-08-12 Air-tight heat insulation metal roof and construction method thereof

Publications (2)

Publication Number Publication Date
CN102409811A CN102409811A (en) 2012-04-11
CN102409811B true CN102409811B (en) 2013-09-25

Family

ID=45912117

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110230544 Active CN102409811B (en) 2011-08-12 2011-08-12 Air-tight heat insulation metal roof and construction method thereof

Country Status (1)

Country Link
CN (1) CN102409811B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103174262B (en) * 2013-03-20 2015-06-10 江苏扬州建工建设集团有限公司 Construction method for super-long steel plate roof
CN104234331B (en) * 2013-06-20 2016-08-10 五冶集团上海有限公司 The cornice of airtight metal roofing and gable airtight receipts limit installation method
CN104652714B (en) * 2015-01-30 2017-01-18 广西壮族自治区冶金建设公司 Construction method for pore-forming installation of self-made mold for steel structure roofing lining panels
CN106760262B (en) * 2016-12-13 2019-09-10 上海宝冶集团有限公司 Metal Roof breaks the hot method of breaking of hot fitting pedestal and metal roof tile junction

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001279876A (en) * 2000-03-31 2001-10-10 Yodogawa Steel Works Ltd Method and structure for repairing roof and clamp for repairing roof used in the same
CN201635223U (en) * 2010-03-19 2010-11-17 中国江苏国际经济技术合作公司 Metal roof system mounting joint device with layering and grading error adjustment
CN201671250U (en) * 2010-01-09 2010-12-15 深圳南玻幕墙及光伏工程有限公司 Novel photovoltaic roof system

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10169129A (en) * 1996-12-13 1998-06-23 Sekisui House Ltd Roof provided with solar battery

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001279876A (en) * 2000-03-31 2001-10-10 Yodogawa Steel Works Ltd Method and structure for repairing roof and clamp for repairing roof used in the same
CN201671250U (en) * 2010-01-09 2010-12-15 深圳南玻幕墙及光伏工程有限公司 Novel photovoltaic roof system
CN201635223U (en) * 2010-03-19 2010-11-17 中国江苏国际经济技术合作公司 Metal roof system mounting joint device with layering and grading error adjustment

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
万伟民.《波峰166mm 双层气密隔热金属屋面施工技术》.《城市建设理论研究》.2011,(第9期),正文第2章第1节,第3章1-12节,图2-3. *
万利民 *
崔卓立 *
蔡庆军 *
邵启雁 *

Also Published As

Publication number Publication date
CN102409811A (en) 2012-04-11

Similar Documents

Publication Publication Date Title
CN102409811B (en) Air-tight heat insulation metal roof and construction method thereof
US9322176B2 (en) Sustainable energy efficient roof system
US10626616B2 (en) Reverse ballasted roof system
CN211114476U (en) Point type roof steel gutter system
CN111980309A (en) Sloping roof system adopting modular tile hanging downstream frame and construction method
CN102155072B (en) Roof gutter system capable of generating slope
CN103088970A (en) Round head mesh-type bolt-free roofing system and construction method thereof
CN106939671B (en) Metal sandwich roof plate construction method
CN102182280B (en) Gable side sliding roof panel rigid waterproof system
CN111042420A (en) Roof construction process for light steel villa
CN109610743B (en) Waterproof and heat-insulating method for traditional building roof
CN208718252U (en) Heat dissipation rain-proof goes along with sb. to guard him wall structure
EP3020883A1 (en) System for mounting of wall and/or roof cladding materials and method for mounting of wall and/or roof cladding on a building structure
CN106939699B (en) Construction method for galvanized steel sheet waterproof layer on inner side of open type ceramic plate curtain wall
CN115822181A (en) Method for mounting roof color steel plate
CN104863311A (en) Waterproofing treatment construction method for metal roof trepanning
CN212866673U (en) Oblique roofing connection structure that cornices in composite insulation board house
AU2021261963B2 (en) A Roof
CN112942835B (en) Construction method of wind-uncovering-resistant outer wall system
CN219080603U (en) Connection structure of steel roofing and concrete roofing
JP2011144574A (en) Structure of photovoltaic panel-installed roof, and method for constructing the same
CN109025031B (en) Movable container office building corridor lighting ceiling and construction method thereof
CN204590449U (en) Metal Roof perforate waterproof construction
CN117211476A (en) Construction process of metal roof skylight
CN1218528A (en) Method of isolating metal deck roof structure

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant