CN104632219A - 厚煤层大采高沿空留巷方法 - Google Patents
厚煤层大采高沿空留巷方法 Download PDFInfo
- Publication number
- CN104632219A CN104632219A CN201510018346.9A CN201510018346A CN104632219A CN 104632219 A CN104632219 A CN 104632219A CN 201510018346 A CN201510018346 A CN 201510018346A CN 104632219 A CN104632219 A CN 104632219A
- Authority
- CN
- China
- Prior art keywords
- face
- coal
- entry retaining
- gob
- side entry
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21C—MINING OR QUARRYING
- E21C41/00—Methods of underground or surface mining; Layouts therefor
- E21C41/16—Methods of underground mining; Layouts therefor
- E21C41/18—Methods of underground mining; Layouts therefor for brown or hard coal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F1/00—Ventilation of mines or tunnels; Distribution of ventilating currents
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F15/00—Methods or devices for placing filling-up materials in underground workings
- E21F15/02—Supporting means, e.g. shuttering, for filling-up materials
- E21F15/04—Stowing mats; Goaf wire netting; Partition walls
Abstract
一种厚煤层大采高沿空留巷方法,适用于井巷支护工程。开采上区段采煤工作面时,沿着采空区的边缘砌筑内置有通气管路的巷旁支撑墙体和压力缓冲墙体,两道墙体之间保持一定的水平距离L,形成沿空留巷;开采下区段采煤工作面时在下区段采煤工作面的轨道巷中实施沿空留巷,同时将位于工作面后方的上区段沿空留巷的巷旁支撑墙体表面的柔性膜袋去除,下区段采煤工作面回采结束后,向上区段采煤工作面的巷旁支撑墙体和压力缓冲墙体内的通气管路中注入二氧化碳,促使墙体发生碳化反应并破碎分解,实现完全无煤柱开采。本方法有利于沿空留巷的全程维护,实现了厚煤层大采高工作面的沿空留巷,显著提高了煤炭采出率,同时消除了墙体上下的应力集中。
Description
技术领域
本发明涉及沿空留巷技术领域,尤其是一种适应于井巷支护工程领域的厚煤层大采高沿空留巷方法。
背景技术
相对于传统的留煤柱护巷方式,沿空留巷具有明显的技术优势,如提高采出率、减少巷道掘进率、促进瓦斯治理、消除应力集中、改善采煤工作面的作业环境等等。在非再生能源迅速减少的背景下,提高能源资源采出率的重要性越来越凸显。而沿空留巷技术的显著优势之一即是通过减少遗留煤柱,大幅提高采区煤炭的采出率,减少资源浪费。目前该技术已在薄煤层和中厚煤层中得到广泛应用。
然而在厚煤层开采中,沿空留巷技术尚未得到突破。其原因在于厚煤层大采高工作面开采后,留下较大的空间,因而顶板垮落的范围广、运动的幅度大、扰动的程度强,留设在采空区边缘的沿空巷道难以在采动过程中保持稳定,很快就会出现片帮、冒顶甚至是断面闭合的剧烈矿压显现。沿空留巷的核心技术是巷旁充填,在大采高条件下,巷旁墙体会发生纵向压缩、横向滑移甚至是歪斜等多种运动形态,若要既满足充填墙体对顶板的支护作用,又保证充填墙体自身的稳定,就需要构筑尺寸较大的墙体。这又存在如下四个问题:(1)大尺度充填墙内外温差较大,将产生较高的温度应力,使其在硬化过程中就产生破坏,支撑效能低下;(2)充填工序繁琐,占时较长,影响工作面的正常采煤作业;(3)用料过多,拌料过程中产生大量粉尘,使作业环境恶化;(4)设备、材料、人力投入较多,成本过高。有少数矿区曾尝试对常规沿空留巷技术进行相应的强化后应用到厚煤层大采高工作面中,多因效果不佳而停止应用。
我国煤炭多属煤层群赋存条件,一个煤层的开采必将会对其它煤层造成影响,尤其是采后遗留煤柱上下的集中应力,更是采掘空间安全的隐患,当采用沿空留巷技术时,遗留的巷旁墙体也会造成一定范围的应力集中,对邻近其它煤层的安全开采带来极大干扰。
总之,厚煤层大采高工作面矿压显现剧烈,沿空留巷维护难度较大,目前尚没有形成能够适应于这种条件的沿空留巷方法,更无法消除巷旁墙体的应力集中问题。
发明内容
技术问题:本发明的目的是克服已有技术中的不足,提供一种厚煤层大采高沿空留巷方法。
技术方案:本发明的厚煤层大采高沿空留巷方法,包括如下步骤:
a.开采上区段采煤工作面之前,开掘上区段采煤工作面的运输巷、轨道巷和切眼,以及下区段采煤工作面的下区段采煤工作面轨道巷和下区段采煤工作面切眼,构成上区段采煤工作面通风系统;
b.在上区段采煤工作面回采过程中,在靠近下区段采煤工作面的一侧,紧跟上区段采煤工作面沿采空区的边缘安置柔性模袋,向柔性膜袋内注入高水材料,砌筑一道内置通气管路的充填墙体作为巷旁支撑墙体,形成沿空留巷,同时以同样的方式在巷旁支撑墙体的采空区一侧砌筑第二道充填墙体作为压力缓冲墙体,巷旁支撑墙体与压力缓冲墙体之间的间隔距离为L,间隔距离L为老顶周期来压步距的0.5~0.8倍;
c.随着上区段采煤工作面向前推进,并在其后方形成足够的充填空间时,重复步骤b,直至上区段采煤工作面回采结束;
d.按照步骤a的方式,在开采下区段采煤工作面前,开掘新的下一区段采煤工作面的轨道巷和切眼,开采下区段采煤工作面时沿空留巷成为该工作面的运输巷,构成下区段采煤工作面的通风系统,开采期间在下区段采煤工作面的下区段采煤工作面轨道巷中实施沿空留巷;
e.按照步骤b的方式,在下区段采煤工作面回采过程中,沿采空区的边缘安置柔性模袋,并向柔性膜袋内注入高水材料,砌筑新的充填墙体,形成新的沿空留巷,同时将工作面后方的上区段巷旁支撑墙体以及压力缓冲墙体表面的柔性膜袋去除;
f.下区段采煤工作面回采结束后,向上区段巷旁支撑墙体以及压力缓冲墙体的通气管路内泵送二氧化碳气体,使其碳化分解,实现充填墙体的自消除;
g.周而复始,接续完成新的下一区段采煤工作面回采。
所述的上区段采煤工作面和下区段采煤工作面沿空留巷一侧的采高与沿空留巷高度相等,沿空留巷一侧采高的控制范围S为充填体宽度的1.2~2.0倍。
所述的巷旁支撑墙体的高度与巷道高度相同,宽度为采高的0.5~1.5倍;所述的压力缓冲墙体的高度与采高相同,宽度为采高的0.2~1.0倍。
所述的通风管包括通气管,通气管的前端为螺纹管,后端为可与前端配合的螺纹套管,通气管上间隔套装有多个交叉布置的通气支管,通气管和通气支管的表面分别开有多个通气孔。
有益效果:由于采用了上述技术方案,本发明与现有技术相比具有如下优点:
(1)通过两道充填墙体的支撑作用,实现厚煤层大采高工作面的沿空留巷,丰富和发展了沿空留巷技术。压力缓冲墙体在采空区内支撑住采空区侧向的关键顶板块体,有效降低了巷道顶板的压力,为巷旁支撑墙体提供了良好的应力环境,使巷旁支撑墙体保持良好的支撑性能,有效维护沿空留巷的整体稳定性性。
(2)上区段充填墙体保留至下区段工作面回采结束,有利于沿空留巷的全程维护。充填墙体自本工作面回采保留至下一工作面回采结束,在两道充填墙体的共同作用下,充分缓解顶板的压力,使沿空留巷在多次采动影响中保持相对稳定。
(3)实现厚煤层大采高采煤工作面沿空留巷,大大提高了煤炭采出率。厚煤层采煤工作面之间常常留设数十米宽的煤柱,造成极其严重的资源损失,本发明为厚煤层大采高工作面提供了无煤柱沿空留巷方法,消除了工作面之间的遗留煤柱,显著提高了煤炭的采出率。
(4)通过充填墙体的碳化分解,消除了墙体上下的应力集中。工作面回采结束后,向通风管路内注入二氧化碳,促使充填墙体自内部迅速碳化分解、充填墙体消除,避免了因充填墙体遗留而产生的应力集中,在煤层群赋存条件下实现对上下邻近煤层的充分卸压,有利于采掘空间维护、瓦斯抽采以及动力灾害防治。
附图说明
图1是本发明的厚煤层大采高沿空留巷的平面示意图;
图2是图1的A-A剖面图;
图3是本发明的通气管结构示意图。
图中:1-上区段采煤工作面;2-下区段采煤工作面;3-运输巷;4-轨道巷;5-下区段采煤工作面轨道巷;6-切眼;7-下区段采煤工作面切眼;8-采空区;9-柔性模袋;10-通风管;10-1-通气管;10-2-螺纹管;10-3螺纹套管;10-4-通气管分支;10-5-通气孔;11-巷旁支撑墙体;12-沿空留巷;13-压力缓冲墙体;L-水平距离;S-沿空留巷一侧采高的控制范围。
具体实施方式
下面结合附图对本发明的一个实施例作进一步的描述:
如图1所示,本发明的厚煤层大采高沿空留巷方法,在开采上区段采煤工作面1时,先开掘下区段采煤工作面2的下区段采煤工作面轨道巷5和下区段采煤工作面切眼7,连同上区段采煤工作面1的运输巷3、轨道巷4和切眼6,构成上区段采煤工作面1的通风系统;开采上区段采煤工作面1时,沿着采空区8的边缘砌筑内置有通气管路10的巷旁支撑墙体11和压力缓冲墙体13,两道墙体之间保持一定的水平距离L,形成沿空留巷12;开采下区段采煤工作面2时,沿空留巷12成为该工作面的运输巷,开采期间在下区段采煤工作面的轨道巷5中实施沿空留巷,同时将位于工作面后方的上区段沿空留巷12的巷旁支撑墙体11以及压力缓冲墙体13表面的柔性膜袋去除,下区段采煤工作面回采结束时,向上区段采煤工作面1的巷旁支撑墙体11和压力缓冲墙体13内的通气管路10内注入二氧化碳,促使墙体发生碳化反应并破碎分解,实现完全无煤柱开采,依此类推,具体步骤如下:
a.开采上区段采煤工作面1之前,开掘上区段采煤工作面1的运输巷3、轨道巷4和切眼6,以及下区段采煤工作面2的下区段采煤工作面轨道巷5和下区段采煤工作面切眼7,构成上区段采煤工作面通风系统;
b.在上区段采煤工作面1回采过程中,在靠近下区段采煤工作面2的一侧,紧跟上区段采煤工作面1沿采空区8边缘安置柔性模袋9,向柔性膜袋9内注入高水材料,砌筑一道内置通气管路10的充填墙体作为巷旁支撑墙体11,形成沿空留巷12,同时以同样的方式在巷旁支撑墙体11的采空区一侧砌筑第二道充填墙体作为压力缓冲墙体13,巷旁支撑墙体11与压力缓冲墙体13之间的间隔距离为L,间隔距离L为老顶周期来压步距的0.5~0.8倍,如图2所示;
c.随着上区段采煤工作面1向前推进,并在其后方形成足够的充填空间时,重复步骤b,直至上区段采煤工作面1回采结束;
d.按照步骤a的方式,在开采下区段采煤工作面2前,开掘新的下一区段采煤工作面的轨道巷和切眼,开采下区段采煤工作面2时的沿空留巷12成为该工作面的运输巷,构成下区段采煤工作面2的通风系统,开采期间在下区段采煤工作面2的下区段采煤工作面轨道巷5中实施沿空留巷;
e.按照步骤b的方式,在下区段采煤工作面2回采过程中,沿采空区的边缘安置柔性模袋,并向柔性膜袋内注入高水材料,砌筑新的充填墙体,形成新的沿空留巷,同时将工作面后方的上区段巷旁支撑墙体11以及压力缓冲墙体13表面的柔性膜袋9去除;
f.下区段采煤工作面2回采结束后,向上区段巷旁支撑墙体11以及压力缓冲墙体13的通气管路10内泵送二氧化碳气体,使其碳化分解,实现充填墙体的自消除;
g.周而复始,接续完成新的下一区段采煤工作面回采。
所述的上区段采煤工作面1和下区段采煤工作面2沿空留巷一侧的采高与沿空留巷高度相等,沿空留巷一侧采高的控制范围S为充填体宽度的1.2~2.0倍。
所述的巷旁支撑墙体的高度与巷道高度相同,宽度为采高的0.5~1.5倍;所述的压力缓冲墙体13的高度与采高相同,宽度为采高的0.2~1.0倍。
所述的通风管10包括通气管10-1,通气管10-1的前端为螺纹管10-2,后端为可与前端配合的螺纹套管10-3,通气管10-1上间隔套装有多个交叉布置的通气支管10-4,通气管10-1和通气支管10-4的表面分别开有多个通气孔10-5。
Claims (4)
1.一种厚煤层大采高沿空留巷方法,其特征是包括如下步骤:
a.开采上区段采煤工作面(1)之前,开掘上区段采煤工作面(1)的运输巷(3)、轨道巷(4)和切眼(6),以及下区段采煤工作面(2)的下区段采煤工作面轨道巷(5)和下区段采煤工作面切眼(7),构成上区段采煤工作面通风系统;
b.在上区段采煤工作面(1)回采过程中,在靠近下区段采煤工作面(2)的一侧,紧跟上区段采煤工作面(1)沿采空区(8)的边缘安置柔性模袋(9),向柔性膜袋(9)内注入高水材料,砌筑一道内置通气管路(10)的充填墙体作为巷旁支撑墙体(11),形成沿空留巷(12),同时以同样的方式在巷旁支撑墙体(11)的采空区一侧砌筑第二道充填墙体作为压力缓冲墙体(13),巷旁支撑墙体(11)与压力缓冲墙体(13)之间的间隔距离为L,间隔距离L为老顶周期来压步距的0.5~0.8倍;
c.随着上区段采煤工作面(1)向前推进,并在其后方形成足够的充填空间时,重复步骤b,直至上区段采煤工作面(1)回采结束;
d.按照步骤a的方式,在开采下区段采煤工作面(2)前,开掘新的下一区段采煤工作面的轨道巷和切眼,开采下区段采煤工作面(2)时沿空留巷(12)成为该工作面的运输巷,构成下区段采煤工作面(2)的通风系统,开采期间在下区段采煤工作面(2)的下区段采煤工作面轨道巷(5)中实施沿空留巷;
e.按照步骤b的方式,在下区段采煤工作面(2)回采过程中,沿采空区的边缘安置柔性模袋,并向柔性膜袋内注入高水材料,砌筑新的充填墙体,形成新的沿空留巷,同时将工作面后方的上区段巷旁支撑墙体(11)以及压力缓冲墙体(13)表面的柔性膜袋(9)去除;
f.下区段采煤工作面(2)回采结束后,向上区段巷旁支撑墙体(11)以及压力缓冲墙体(13)的通气管路(10)内泵送二氧化碳气体,使其碳化分解,实现充填墙体的自消除;
g.周而复始,接续完成新的下一区段采煤工作面回采。
2.根据权利要求1所述的厚煤层大采高沿空留巷方法,其特征是:所述的上区段采煤工作面(1)和下区段采煤工作面(2)沿空留巷一侧的采高与沿空留巷高度相等,沿空留巷一侧采高的控制范围S为充填体宽度的1.2~2.0倍。
3.根据权利要求1所述的厚煤层大采高沿空留巷方法,其特征是:所述的巷旁支撑墙体的高度与巷道高度相同,宽度为采高的0.5~1.5倍;所述的压力缓冲墙体(13)的高度与采高相同,宽度为采高的0.2~1.0倍。
4.根据权利要求1所述的厚煤层大采高沿空留巷方法,其特征是:所述的通风管(10)包括通气管(10-1),通气管(10-1)的前端为螺纹管(10-2),后端为可与前端配合的螺纹套管(10-3),通气管(10-1)上间隔套装有多个交叉布置的通气支管(10-4),通气管(10-1)和通气支管(10-4)的表面分别开有多个通气孔(10-5)。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510018346.9A CN104632219B (zh) | 2015-01-14 | 2015-01-14 | 厚煤层大采高沿空留巷方法 |
PCT/CN2015/098029 WO2016112772A1 (zh) | 2015-01-14 | 2015-12-21 | 厚煤层大采高沿空留巷方法 |
AU2015377025A AU2015377025B2 (en) | 2015-01-14 | 2015-12-21 | Thick coal seam large seam height gob-side retained passageway method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510018346.9A CN104632219B (zh) | 2015-01-14 | 2015-01-14 | 厚煤层大采高沿空留巷方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104632219A true CN104632219A (zh) | 2015-05-20 |
CN104632219B CN104632219B (zh) | 2017-03-29 |
Family
ID=53211398
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510018346.9A Active CN104632219B (zh) | 2015-01-14 | 2015-01-14 | 厚煤层大采高沿空留巷方法 |
Country Status (3)
Country | Link |
---|---|
CN (1) | CN104632219B (zh) |
AU (1) | AU2015377025B2 (zh) |
WO (1) | WO2016112772A1 (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016112772A1 (zh) * | 2015-01-14 | 2016-07-21 | 中国矿业大学 | 厚煤层大采高沿空留巷方法 |
WO2016112749A1 (zh) * | 2015-01-14 | 2016-07-21 | 中国矿业大学 | 充填墙体自消除的无煤柱沿空留巷方法 |
CN107701188A (zh) * | 2017-10-25 | 2018-02-16 | 太原理工大学 | 一种用于沿空掘巷窄煤柱采空侧静态胀裂切顶卸压法 |
CN109057794A (zh) * | 2018-08-13 | 2018-12-21 | 中煤能源研究院有限责任公司 | 一种大煤柱掘进无煤柱开采的采煤方法 |
CN109209428A (zh) * | 2018-08-13 | 2019-01-15 | 中煤能源研究院有限责任公司 | 一种可实现巷间煤柱回采的工作面巷道布置结构 |
CN110242322A (zh) * | 2019-07-02 | 2019-09-17 | 中国矿业大学(北京) | 一种特厚煤层沿空留巷的巷道布置方法 |
CN110905507A (zh) * | 2019-12-06 | 2020-03-24 | 河南力行科创矿山技术开发有限公司 | 高瓦斯大采高高效开采工作面超前切顶卸压沿空留巷工艺 |
Families Citing this family (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106528965B (zh) * | 2016-10-21 | 2019-06-14 | 重庆大学 | 工作面端头应力集中系数的获取方法 |
CN107083959A (zh) * | 2017-06-02 | 2017-08-22 | 天地科技股份有限公司 | 一种沿空留巷方法 |
CN111027219B (zh) * | 2019-12-12 | 2023-07-25 | 神华准格尔能源有限责任公司 | 相邻同向协同开采露天煤矿公共运输帮的高度确定方法 |
CN113530543B (zh) * | 2021-06-04 | 2022-07-26 | 华能煤炭技术研究有限公司 | 一种留巷顺槽切顶高度设计方法及留巷顺槽维护方法 |
CN115263308B (zh) * | 2022-08-30 | 2023-08-08 | 乌海市天誉煤炭有限责任公司 | 一种爆破切顶沿空留巷方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4400035A (en) * | 1980-04-15 | 1983-08-23 | Tatabanyai Szenbanyak | Process for the extraction of thick coal seams |
CN101915101A (zh) * | 2010-08-20 | 2010-12-15 | 天地科技股份有限公司 | 一种急倾斜厚煤层采煤方法 |
CN101936164A (zh) * | 2010-08-17 | 2011-01-05 | 天地科技股份有限公司 | 极软厚煤层超前支护抱采放顶煤采煤法与液压支架结构 |
CN102383857A (zh) * | 2011-07-05 | 2012-03-21 | 徐州贝壳迈宁矿业科技有限公司 | 一种固体充填采煤垒砌矸石墙沿空留巷工艺 |
CN203067026U (zh) * | 2013-01-16 | 2013-07-17 | 中国矿业大学 | 一种中空内置加强筋的沿空留巷充填墙体结构 |
CN103742148A (zh) * | 2014-01-14 | 2014-04-23 | 山东科技大学 | 一种急倾斜煤层柔掩支护下行矸石充填的采煤法 |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
PL159027B1 (pl) * | 1988-11-07 | 1992-11-30 | Jan B Gwiazda | Sposób i scianowy kompleks podsadzkowy do podsadzania wyrobiska górniczego PL |
CN101725368B (zh) * | 2009-11-28 | 2011-08-17 | 山东科技大学 | 厚煤层大采高工作面沿空留巷方法 |
CN102425454B (zh) * | 2011-09-22 | 2013-10-30 | 中国矿业大学 | 一种砌筑填充组合式沿空留巷墙体的构筑方法 |
CN103089298B (zh) * | 2013-01-23 | 2014-11-19 | 中国矿业大学 | 一种构筑侧向多列沿空留巷充填墙体的结构及方法 |
CN103883336B (zh) * | 2014-04-11 | 2016-03-16 | 山东科技大学 | 一种先主动后让压支护的可调节沿空留巷墙体及其施工方法 |
CN104074534B (zh) * | 2014-06-27 | 2016-08-24 | 辽宁工程技术大学 | 一种综采/综放工作面的沿空留巷方法 |
CN104632219B (zh) * | 2015-01-14 | 2017-03-29 | 中国矿业大学 | 厚煤层大采高沿空留巷方法 |
-
2015
- 2015-01-14 CN CN201510018346.9A patent/CN104632219B/zh active Active
- 2015-12-21 WO PCT/CN2015/098029 patent/WO2016112772A1/zh active Application Filing
- 2015-12-21 AU AU2015377025A patent/AU2015377025B2/en not_active Ceased
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4400035A (en) * | 1980-04-15 | 1983-08-23 | Tatabanyai Szenbanyak | Process for the extraction of thick coal seams |
CN101936164A (zh) * | 2010-08-17 | 2011-01-05 | 天地科技股份有限公司 | 极软厚煤层超前支护抱采放顶煤采煤法与液压支架结构 |
CN101915101A (zh) * | 2010-08-20 | 2010-12-15 | 天地科技股份有限公司 | 一种急倾斜厚煤层采煤方法 |
CN102383857A (zh) * | 2011-07-05 | 2012-03-21 | 徐州贝壳迈宁矿业科技有限公司 | 一种固体充填采煤垒砌矸石墙沿空留巷工艺 |
CN203067026U (zh) * | 2013-01-16 | 2013-07-17 | 中国矿业大学 | 一种中空内置加强筋的沿空留巷充填墙体结构 |
CN103742148A (zh) * | 2014-01-14 | 2014-04-23 | 山东科技大学 | 一种急倾斜煤层柔掩支护下行矸石充填的采煤法 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2016112772A1 (zh) * | 2015-01-14 | 2016-07-21 | 中国矿业大学 | 厚煤层大采高沿空留巷方法 |
WO2016112749A1 (zh) * | 2015-01-14 | 2016-07-21 | 中国矿业大学 | 充填墙体自消除的无煤柱沿空留巷方法 |
CN107701188A (zh) * | 2017-10-25 | 2018-02-16 | 太原理工大学 | 一种用于沿空掘巷窄煤柱采空侧静态胀裂切顶卸压法 |
CN107701188B (zh) * | 2017-10-25 | 2019-02-26 | 太原理工大学 | 一种用于沿空掘巷窄煤柱采空侧静态胀裂切顶卸压法 |
CN109057794A (zh) * | 2018-08-13 | 2018-12-21 | 中煤能源研究院有限责任公司 | 一种大煤柱掘进无煤柱开采的采煤方法 |
CN109209428A (zh) * | 2018-08-13 | 2019-01-15 | 中煤能源研究院有限责任公司 | 一种可实现巷间煤柱回采的工作面巷道布置结构 |
CN110242322A (zh) * | 2019-07-02 | 2019-09-17 | 中国矿业大学(北京) | 一种特厚煤层沿空留巷的巷道布置方法 |
CN110905507A (zh) * | 2019-12-06 | 2020-03-24 | 河南力行科创矿山技术开发有限公司 | 高瓦斯大采高高效开采工作面超前切顶卸压沿空留巷工艺 |
Also Published As
Publication number | Publication date |
---|---|
AU2015377025B2 (en) | 2018-03-22 |
CN104632219B (zh) | 2017-03-29 |
WO2016112772A1 (zh) | 2016-07-21 |
AU2015377025A1 (en) | 2017-06-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104632219A (zh) | 厚煤层大采高沿空留巷方法 | |
CN104564072B (zh) | 近距离煤层群完全无煤柱连续卸压开采方法 | |
AU2013354613B2 (en) | Method of local filling to control surface subsidence in worked-out area | |
AU2015345830B2 (en) | Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence | |
US20190301283A1 (en) | Method for recovering room-mining coal pillars by solid filling in synergy with artificial pillars | |
CN109763822A (zh) | 大倾角厚煤层多区段无煤柱错层护巷及段间煤柱充填方法 | |
CN104100271B (zh) | 预掘导硐充填人造帮二次复用巷旁支护成巷方法 | |
CN103953345B (zh) | 一种沿空小断面留巷开采方法 | |
CN102587960A (zh) | 一种高瓦斯煤层回采工作面巷道的布置方法 | |
CN109139012A (zh) | 一种矿用链臂锯连续切顶造缝方法 | |
CN103939135A (zh) | 一种综采工作面撤架通道快速施工方法 | |
CN104727847B (zh) | 充填墙体自消除的无煤柱沿空留巷方法 | |
CN102102518B (zh) | 一种水库坝体下厚煤层放顶煤协调开采方法 | |
CN104088638A (zh) | 大倾角煤层长壁大采高工作面煤壁片帮及冒顶控制技术 | |
CN105909284B (zh) | 一种大采高煤壁片帮防治控制方法 | |
CN104863588A (zh) | 超前预设墩柱沿空留巷方法 | |
CN104533419A (zh) | 一种部分回收大煤柱残煤的方法 | |
CN104594943A (zh) | 一种用于瓦斯治理的地面复合l型钻井和瓦斯治理方法 | |
CN103953346A (zh) | 一种无煤柱开采方法 | |
CN105781552A (zh) | 一种高瓦斯突出煤层立体冲孔石门揭煤新方法 | |
CN105240012A (zh) | 一种实现煤柱同采的f型区段采煤方法 | |
CN103375169A (zh) | 使金刚石绳锯用于大截面地下岩石工程的方法 | |
CN207847649U (zh) | 一种超高巷道沿空留巷用支护装置 | |
CN103883336B (zh) | 一种先主动后让压支护的可调节沿空留巷墙体及其施工方法 | |
CN110145363B (zh) | 一种实现综采面垮落到充填开采过渡的顶板控制方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information |
Address after: 221116 Research Institute of China University of Mining and Technology,, Jiangsu Applicant after: China University of Mining & Technology Address before: 221116 Research Institute, China University of Mining and Technology, Xuzhou University, Jiangsu, China, Applicant before: China University of Mining & Technology |
|
COR | Change of bibliographic data | ||
GR01 | Patent grant | ||
GR01 | Patent grant |