CN104727847B - 充填墙体自消除的无煤柱沿空留巷方法 - Google Patents

充填墙体自消除的无煤柱沿空留巷方法 Download PDF

Info

Publication number
CN104727847B
CN104727847B CN201510018347.3A CN201510018347A CN104727847B CN 104727847 B CN104727847 B CN 104727847B CN 201510018347 A CN201510018347 A CN 201510018347A CN 104727847 B CN104727847 B CN 104727847B
Authority
CN
China
Prior art keywords
filled
coal
gob
curtate
entry retaining
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510018347.3A
Other languages
English (en)
Other versions
CN104727847A (zh
Inventor
张农
韩昌良
谢正正
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201510018347.3A priority Critical patent/CN104727847B/zh
Publication of CN104727847A publication Critical patent/CN104727847A/zh
Application granted granted Critical
Publication of CN104727847B publication Critical patent/CN104727847B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Abstract

一种充填墙体自消除的无煤柱沿空留巷方法,适用于井巷支护工程。在开采上区段采煤工作面时,沿着采空区的边缘向柔性模袋内泵送高水材料,构筑形成巷旁充填墙体,并在充填墙体内预置通气管,开采下区段采煤工作面时,将该采煤工作面后方的柔性模袋割破,开采完毕后,向通气管内注入二氧化碳,促使充填墙体发生碳化反应并破碎分解,实现巷旁墙体自消除。该方法在沿空留巷服务期间,能够充分发挥高水材料巷旁墙体的高支撑性能,在沿空留巷报废后,可实现充填墙体自消除,避免了因充填墙体遗留而产生的应力集中,达到对上下邻近煤层充分卸压的效果,对于采掘空间维护、瓦斯抽采以及动力灾害防治具有积极的作用。

Description

充填墙体自消除的无煤柱沿空留巷方法
技术领域
[0001]本发明涉及沿空留巷技术,尤其是一种适应于井巷支护工程领域的充填墙体自消除的无煤柱沿空留巷方法。
背景技术
[0002]在近距离煤层群赋存条件下,开采其中一个煤层势必对其它煤层造成影响,而先采煤层的遗留煤柱在上下岩层中形成的集中应力则是其中最为关键的不利影响之一。采动应力集中制约了矿井的生产布局、采掘空间维护以及卸压瓦斯治理,往往带来顶板垮冒、冲击地压、瓦斯突出等严重后果。无煤柱沿空留巷可以在很大程度上降低这种影响的程度,消除因煤柱集中应力产生的动力灾害。
[0003]现有的沿空留巷技术能够取消工作面之间的煤柱,但却留下了一个与工作面推进距离等长的充填墙体,充填墙体的宽度约为采高的0.5〜1.5倍。也就是说,当前的沿空留巷技术是将数十米的煤柱置换为数米宽的充填墙体。由于充填墙体的强度比煤体更高,因而充填墙体上的集中应力比相同尺寸的煤体更强烈,尽管充填墙体的宽度较小,但受岩层垮落角的影响,仍然在上下岩层中产生较大范围的应力集中区,不利于邻近煤层的安全开采。为了避免应力集中区的影响,邻近层开采时,不得不留设大煤柱,造成较严重的资源浪费。
[0004]深部煤炭开采的技术难度因地应力的增高而加大,煤层群条件下往往选择一个简单煤层首先开采,并通过无煤柱沿空留巷技术实现对邻近煤层的卸压,以降低邻近复杂煤层的开采难度。随着我国煤炭开采深度的持续增加,无煤柱沿空留巷技术越发体现其显著的技术优势。但是目前尚缺少一种既无煤柱又无岩柱的沿空留巷方法,现有的沿空留巷方法在很大程度上限制了近距离煤层群保护层开采的卸压范围,阻碍了连续卸压开采技术的发展。
发明内容
[0005]技术问题:本发明的目的是克服已有技术中的不足,提供一种充填墙体自消除、既无煤柱又无岩柱的沿空留巷方法。
[0006]技术方案:本发明的充填墙体自消除的无煤柱沿空留巷方法,包括如下步骤:
[0007] a.开采上区段采煤工作面的过程中,在位于上区段采煤工作面的后方,沿着采空区的边缘安置柔性模袋,将高水材料栗入柔性模袋内,砌筑成一垛充填墙体,使上区段采煤工作面(I)后方的巷道形成沿空留巷,砌筑过程中,在充填墙体内预置包有防渗薄膜的通风管;
[0008] b.随着上区段采煤工作面向前推进并在其后方形成足够的充填空间时,重复步骤a,砌筑下一垛充填墙体,直至上区段采煤工作面回采结束,砌筑下一垛充填墙体时,使柔性模袋之间紧密连接;
[0009] c.将沿空留巷作为下区段采煤工作面的一条回采巷道,开采下区段采煤工作面时,将下区段采煤工作面后方的沿采空区边缘安置的柔性模袋割破,使柔性模袋失去对充填墙体的封闭和约束作用;
[0010] d.随着下区段采煤工作面向前推进,重复步骤C,直至下区段采煤工作面回采结束;
[0011 ] e.通过通风管向充填墙体内注入二氧化碳,促使充填墙体发生碳化反应并破碎分解,实现充填墙体的自消除。
[0012]所述的充填墙体宽度为工作面平均采高的0.5-1.5倍,高度与采高相等,每垛墙体的长度为1.8〜3.0m。
[0013]所述的通风管包括通气管,通气管的前端为螺纹管,后端为可与前端配合的螺纹套管,通气管上间隔套装有多个交叉布置的通气支管,通气管和通气支管的表面分别开有多个通气孔。
[0014]所述向充填墙体内注入的二氧化碳为干燥的或者带有水汽的二氧化碳气体。
[0015]有益效果:由于采用了上述技术方案,本发明与现有技术相比具有如下优点:
[0016] (I)沿空留巷服务期间,柔性模袋的密封条件可使充填墙体避免受到风化作用,能够充分发挥高水材料巷旁墙体的高支撑性能。
[0017] (2)沿空留巷报废后,立刻将柔性模袋打开,在井下空气的风化作用下,充填墙体强度逐渐弱化,并由表及里发生崩解,使其支撑作用减弱,有利于顶板垮落。
[0018] (3 )工作面回采结束后,通过通风管路注入二氧化碳,促使充填墙体自内部迅速碳化分解,实现充填墙体自消除,避免了因充填墙体遗留而产生的应力集中,达到对上下邻近煤层充分卸压的效果,对于采掘空间维护、瓦斯抽采以及动力灾害防治具有积极的作用。
[0019] (4)回采结束后,区段之间既无煤柱又无岩柱,因而上下邻近煤层开采时不需留设煤柱,能够显著提高煤炭的采出率。
附图说明
[0020]图1是本发明的沿空留巷示意图。
[0021]图2是本发明的通气管结构示意图。
[0022 ]图中:1-上区段采煤工作面;2-采空区;3-柔性模袋;4-充填墙体;5-沿空留巷;6-通风管;6-1-通气管;6-2-螺纹管;6-3-通气孔;6-4-通气支管;6_5_螺纹套管,7-下区段采煤工作面。
具体实施方式
[0023]下面结合附图对本发明的一个实施例作进一步的描述:
[0024]如图1所示,本发明的巷旁墙体自消除的无煤柱沿空留巷方法,在开采上区段采煤工作面I时,沿着采空区2的边缘、向柔性模袋3内栗送高水材料,构筑成巷旁充填墙体4,并在充填墙体4内预置通风管6,开采下区段采煤工作面7时,将该采煤工作面7后方的柔性模袋3割破,开采完毕后,向通气管6内注入二氧化碳,促使充填墙体发生碳化反应并破碎分解,实现巷旁墙体自消除。具体实施步骤如下:
[0025] a.开采上区段采煤工作面I的过程中,在位于上区段采煤工作面I的后方,沿着采空区2的边缘安置柔性模袋3,将高水材料栗入柔性模袋3内,砌筑成一垛充填墙体4,使上区段采煤工作面I后方的巷道形成沿空留巷5,砌筑过程中,在充填墙体4内预置包有防渗薄膜的通风管6;所述的通风管6包括通气管6-1,通气管6-1的前端为螺纹管6-2,后端为可与前端配合的螺纹套管6-5,通气管6-1上间隔套装有多个交叉布置的通气支管6-4,通气管6-1和通气支管6-4的表面分别开有多个通气孔6-3。
[0026] b.随着上区段采煤工作面I向前推进并在其后方形成足够的充填空间时,重复步骤a,砌筑下一垛充填墙体4,直至上区段采煤工作面I回采结束,砌筑下一垛充填墙体4时,使柔性模袋3之间紧密连接,将多垛充填墙体4内的通风管6螺纹连接在一起,形成通气管路,所述的充填墙体4宽度为工作面平均采高的0.5〜1.5倍,高度与采高相等,每垛墙体4的长度为1.8〜3.0m。
[0027] c.将沿空留巷5作为下区段采煤工作面7的一条回采巷道,开采下区段采煤工作面7时,将下区段采煤工作面7后方的沿采空区2边缘安置的柔性模袋3割破,使柔性模袋3失去对充填墙体4的封闭和约束作用;
[0028] d.随着下区段采煤工作面7向前推进,重复步骤c多次,直至下区段采煤工作面7回采结束;
[0029] e.通过通风管6向充填墙体4内注入二氧化碳,促使充填墙体4发生碳化反应并破碎分解,实现充填墙体4的自消除。所述向充填墙体4内注入的二氧化碳为干燥的或者带有水汽的二氧化碳气体。

Claims (4)

1.一种充填墙体自消除的无煤柱沿空留巷方法,其特征是包括如下步骤: a.开采上区段采煤工作面(I)的过程中,在位于上区段采煤工作面(I)的后方,沿着采空区(2)的边缘安置柔性模袋(3),将高水材料栗入柔性模袋(3)内,砌筑成一垛充填墙体(4),使上区段采煤工作面(I)后方的巷道形成沿空留巷(5),砌筑过程中,在充填墙体(4)内预置包有防渗薄膜的通风管(6); b.随着上区段采煤工作面(I)向前推进并在其后方形成足够的充填空间时,重复步骤a,砌筑下一垛充填墙体(4),直至上区段采煤工作面(I)回采结束,砌筑下一垛充填墙体(4)时,使柔性模袋(3)之间紧密连接; c.将沿空留巷(5)作为下区段采煤工作面(7)的一条回采巷道,开采下区段采煤工作面(7)时,将下区段采煤工作面(7)后方的沿采空区(2)边缘安置的柔性模袋(3)割破,使柔性模袋(3)失去对充填墙体(4)的封闭和约束作用; d.随着下区段采煤工作面(7)向前推进,重复步骤C,直至下区段采煤工作面(7)回采结束; e.通过通风管(6)向充填墙体(4)内注入二氧化碳,促使充填墙体(4)发生碳化反应并破碎分解,实现充填墙体(4)的自消除。
2.根据权利要求1所述的充填墙体自消除的无煤柱沿空留巷方法,其特征是:所述的充填墙体(4)宽度为工作面平均采高的0.5-1.5倍,高度与采高相等,每垛墙体的长度为1.8〜3.0m0
3.根据权利要求1所述的充填墙体自消除的无煤柱沿空留巷方法,其特征是:所述的通风管(6)包括通气管(6-1),通气管(6-1)的前端为螺纹管(6-2),后端为可与前端配合的螺纹套管(6-5),通气管(6-1)上间隔套装有多个交叉布置的通气支管(6-4),通气管(6-1)和通气支管(6-4)的表面分别开有多个通气孔(6-3)。
4.根据权利要求1所述的充填墙体自消除的无煤柱沿空留巷方法,其特征是:所述向充填墙体(4)内注入的二氧化碳为干燥的或者带有水汽的二氧化碳气体。
CN201510018347.3A 2015-01-14 2015-01-14 充填墙体自消除的无煤柱沿空留巷方法 Active CN104727847B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510018347.3A CN104727847B (zh) 2015-01-14 2015-01-14 充填墙体自消除的无煤柱沿空留巷方法

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201510018347.3A CN104727847B (zh) 2015-01-14 2015-01-14 充填墙体自消除的无煤柱沿空留巷方法
AU2015377002A AU2015377002B2 (en) 2015-01-14 2015-11-30 Non-coal-pillar gob-side entry retaining method having filling-wall self-elimination
PCT/CN2015/095905 WO2016112749A1 (zh) 2015-01-14 2015-11-30 充填墙体自消除的无煤柱沿空留巷方法

Publications (2)

Publication Number Publication Date
CN104727847A CN104727847A (zh) 2015-06-24
CN104727847B true CN104727847B (zh) 2016-11-02

Family

ID=53452187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510018347.3A Active CN104727847B (zh) 2015-01-14 2015-01-14 充填墙体自消除的无煤柱沿空留巷方法

Country Status (3)

Country Link
CN (1) CN104727847B (zh)
AU (1) AU2015377002B2 (zh)
WO (1) WO2016112749A1 (zh)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105114080A (zh) * 2015-08-11 2015-12-02 冀中能源峰峰集团有限公司 一种保护层及无人化薄煤层开采方法
CN105350966B (zh) * 2015-10-29 2017-08-22 中国矿业大学(北京) 留煤柱开采下保护层实现上被保护层连续卸压的方法
CN107503790B (zh) * 2017-08-06 2018-03-30 陕西富源煤业有限责任公司 快速回采综采面瓦斯综合抽放布置治理方法
CN109236354B (zh) * 2018-10-23 2019-10-29 煤科集团沈阳研究院有限公司 一种基于沿空留巷瓦斯治理的面式抽采方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0383362A2 (de) * 1987-06-03 1990-08-22 Dpu Deutsche Projekt Union Gmbh Vorrichtung zum Verfüllen von bergmännisch hergestellten Hohlräumen, insbesondere im Steinkohlenbergbau
CN102852550A (zh) * 2012-04-01 2013-01-02 中国矿业大学 一种无煤柱半原位沿空留巷方法
CN103266893A (zh) * 2013-05-08 2013-08-28 中国矿业大学(北京) 无煤柱采煤方法在下保护层开采中的应用
CN103628911A (zh) * 2013-12-06 2014-03-12 中国矿业大学 一种综采/放工作面分段式沿空留巷方法
CN103953346A (zh) * 2014-05-13 2014-07-30 中国矿业大学 一种无煤柱开采方法
WO2014187163A1 (zh) * 2013-05-20 2014-11-27 中国矿业大学 一种特厚煤层倾斜分层固体充填采煤方法

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4174135A (en) * 1978-04-10 1979-11-13 Bechtel International Corporation Underground formed wall single-entry mining method
WO2002033221A2 (en) * 2000-08-15 2002-04-25 Sean Philip Brennan Explosion proof walls
CN101701526B (zh) * 2009-11-05 2011-07-06 冀中能源邯郸矿业集团有限公司 一种采空区袋式充填方法
CN102155225B (zh) * 2011-03-11 2012-11-14 中国矿业大学 煤矿气体充填开采方法
CN102606207A (zh) * 2012-04-06 2012-07-25 陕西开拓建筑科技有限公司 一种矿山采空区充填兼留巷的装置系统及充填方法
CN103147793B (zh) * 2013-02-22 2016-01-20 山东科技大学 薄煤层巷旁充填无煤柱护巷方法
CN103452586A (zh) * 2013-08-28 2013-12-18 武汉理工大学 一种采空区膨胀材料预应力充填的方法其预应力充填材料
CN104632219B (zh) * 2015-01-14 2017-03-29 中国矿业大学 厚煤层大采高沿空留巷方法
CN104564072B (zh) * 2015-01-14 2017-01-18 中国矿业大学 近距离煤层群完全无煤柱连续卸压开采方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0383362A2 (de) * 1987-06-03 1990-08-22 Dpu Deutsche Projekt Union Gmbh Vorrichtung zum Verfüllen von bergmännisch hergestellten Hohlräumen, insbesondere im Steinkohlenbergbau
CN102852550A (zh) * 2012-04-01 2013-01-02 中国矿业大学 一种无煤柱半原位沿空留巷方法
CN103266893A (zh) * 2013-05-08 2013-08-28 中国矿业大学(北京) 无煤柱采煤方法在下保护层开采中的应用
WO2014187163A1 (zh) * 2013-05-20 2014-11-27 中国矿业大学 一种特厚煤层倾斜分层固体充填采煤方法
CN103628911A (zh) * 2013-12-06 2014-03-12 中国矿业大学 一种综采/放工作面分段式沿空留巷方法
CN103953346A (zh) * 2014-05-13 2014-07-30 中国矿业大学 一种无煤柱开采方法

Also Published As

Publication number Publication date
AU2015377002A1 (en) 2016-09-01
WO2016112749A1 (zh) 2016-07-21
AU2015377002B2 (en) 2016-09-29
CN104727847A (zh) 2015-06-24

Similar Documents

Publication Publication Date Title
CN104727847B (zh) 充填墙体自消除的无煤柱沿空留巷方法
CN101832149B (zh) 一种井下注热抽采煤层瓦斯的方法
CN102635392B (zh) 超前留巷施工抽采工程的无煤柱煤与瓦斯共采方法
CN107120137B (zh) 一种煤巷掘进沿煤层底板深孔预裂爆破抽采方法
CN104632219B (zh) 厚煤层大采高沿空留巷方法
WO2016112771A1 (zh) 近距离煤层群完全无煤柱连续卸压开采方法
CN103670496A (zh) 单一低透气性突出煤层沿空留巷与预抽区段煤层瓦斯方法
CN104712358A (zh) 基于首采全岩卸压工作面沿空留巷的高瓦斯煤层群卸压共采方法
CN106368701A (zh) 利用水力压裂卸压控制回采巷道留巷的方法及装置
CN101725352A (zh) 一种固体充填综采回收房式煤柱方法
CN102644476B (zh) 保护层机巷高位钻场穿层钻孔抽采被保护层瓦斯的方法
CN105134286B (zh) L型井采空区瓦斯抽采方法
CN101126316A (zh) 一种长壁综采回收房式开采煤柱的方法
CN102828768A (zh) 高瓦斯煤矿瓦斯抽采方法和抽采系统
CN104594943A (zh) 一种用于瓦斯治理的地面复合l型钻井和瓦斯治理方法
CN103821515A (zh) 一种对拉工作面充填采煤工艺
WO2020192055A1 (zh) 一种顶板含水层两步骤注浆改性保水采煤方法
CN103899350A (zh) 综放工作面架载顶煤瓦斯抽采系统
CN105863639A (zh) 松散煤层的采煤方法
US20180195386A1 (en) Parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence
CN102102518A (zh) 一种水库坝体下厚煤层放顶煤协调开采方法
CN106089275A (zh) 一种井工煤矿综采工作面用防冒顶结构及实施方法
CN108843354A (zh) 一种倾斜特厚煤层巷顶沿空掘巷非对称锚秆支护方法
CN202768055U (zh) 高瓦斯煤矿瓦斯抽采系统
CN109854294B (zh) 一种烟气驱替增强采空区瓦斯抽采及采空区防治火灾方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
COR Change of bibliographic data
CB02 Change of applicant information

Address after: 221116 Research Institute of China University of Mining and Technology,, Jiangsu

Applicant after: China University of Mining & Technology

Address before: 221116 Research Institute, China University of Mining and Technology, Xuzhou University, Jiangsu, China,

Applicant before: China University of Mining & Technology

CB03 Change of inventor or designer information

Inventor after: Zhang Nong

Inventor after: Han Changliang

Inventor after: Xie Zhengzheng

Inventor before: Zhang Nong

Inventor before: Han Changliang

C14 Grant of patent or utility model
GR01 Patent grant