AU2015345830B2 - Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence - Google Patents

Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence Download PDF

Info

Publication number
AU2015345830B2
AU2015345830B2 AU2015345830A AU2015345830A AU2015345830B2 AU 2015345830 B2 AU2015345830 B2 AU 2015345830B2 AU 2015345830 A AU2015345830 A AU 2015345830A AU 2015345830 A AU2015345830 A AU 2015345830A AU 2015345830 B2 AU2015345830 B2 AU 2015345830B2
Authority
AU
Australia
Prior art keywords
mining
stope
roadway
winged
coal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
AU2015345830A
Other versions
AU2015345830A1 (en
Inventor
Liqiang MA
Qiankun MIAO
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Publication of AU2015345830A1 publication Critical patent/AU2015345830A1/en
Application granted granted Critical
Publication of AU2015345830B2 publication Critical patent/AU2015345830B2/en
Ceased legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C41/00Methods of underground or surface mining; Layouts therefor
    • E21C41/16Methods of underground mining; Layouts therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings

Abstract

A coal mining method with digging, mining and filling parallel operations under the control of cover rock cracks and surface subsidence. Stope transportation roadways, stope branch roadways and double-wing mining chambers (3) are disposed in a stope, wherein the stope transportation roadways and the stope branch roadways are transportation roadways, and coal mining is carried out in the double-wing mining chambers (3). All the double-wing mining chambers (3) are sequentially exploited and are sequentially timely filled, two sides of each double-wing mining chamber (3) are supported by unexploited coal or the filled double-wing mining chamber (3) to control a top board, and the length of each of the double-wing mining chambers (3) and the number of one-stage filled double-wing mining chambers are controlled to realize the zero (less) support of the double-wing mining chambers (3), so as to finally realize non-pillar mining. The method reduces the support engineering amount of the double-wing mining chambers, reduces the number of filled airtight walls, realizes digging, mining and filling parallel operations, can effectively control the mining cover rock cracks and surface subsidence and realizes water resource protection mining (water conservation mining) and safe and efficient stoping of coal under buildings, railways and water.

Description

1 2015345830 05 Oct 2016
COAL MINING METHOD WITH DIGGING, MINING AND FILLING PARALLEL OPERATIONS UNDER CONTROL OF COVER ROCK CRACKS AND SURFACE SUBSIDENCE
Field of the Invention
The present invention relates to a coal mining method, belongs to the field of coal mining technology, and particularly relates to a parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence.
Background of the Invention
Water-preserved mining refers to mining by a reasonable coal mining method and process, so as to ensure the mining disturbance will not cause damage to the waterbearing structure in the water bearing strata; or ensure the water level in the water bearing strata can recover within a certain time period though the water-bearing strucutre is damaged to some degree and some water loss occurs; or ensure the normal water supply will not be affected and at least the water supply can meet the demand of the ground ecosystem for water resource even though the underground water level can't recover to the original level.
Existing water-preserved mining techniques have a poor mining ratio, or can't attain a good water preservation effect, or don't have high recovery efficiency owing to the filling method. It is desirable to develop a coal mining method, which can realize quick, safe, and efficient coal mining while preserving water resources.
In addition, there is a large quantity of coal in “three unders”(under constructions, railroads, and water bodies) in China. According to the result of preliminary statistics performed in state-owned major coal mines, the total quantity of such coal is as high as 13.79 billion tons. As the technical level of coal mining is improved, to release the coal under constructions, railroads, and water bodies, techniques for mining the coal under constructions, railroads, and water bodies have been developed greatly. Presently, commonly used methods for controlling surface subsidence mainly include: coordinated mining, partial mining, grouting into separated strata in overburden, and mining with filling, etc. Coordinated mining utilizes the counter balancing among surface deformations resulted from simultaneous mining at multiple working faces to attain the purpose of reducing surface deformation, but it involves simultaneous mining at multiple working faces and is constrained by the layout of protected objects on the ground surface; therefore, it has severe impacts on the exploitation design and has limited applicability. Partial mining controls overlaying strata movement and surface subsidence by mining coal partially and reserving permanent coal pillars in certain width, and mainly includes Wongawilli mining, board and pillar mining, strip mining, limited thickness mining, knife mining, and roadway mining, etc. Though these methods can control surface subsidence to some degree, their mining ratios are not high, usually about 50%. Grouting into separated strata in overburden utilizes bore grouting to fill the space of separated strata between upper hard strata and lower soft strata, to attain the purpose of controlling the overlying bed subsidence above the hard strata and the surface subsidence; with that method, the surface subsidence reduction ratio is usually not higher than 40%. Compared with other methods for controlling surface subsidence, mining with filling is the most effective method for controlling surface subsidence at present, and the gob can be filled partially or fully. Depending on the layout of working face, the filling method can be gob filling along long-wall working 2 2015345830 05 Oct 2016 face, strip filling, or roadway filling, etc.. The problems existing in these methods mainly include: difficulties in coordination between coal mining and filling, complex filling system, large filling space, and long filling time, etc..
Contents of the Invention
Technical problem: To overcome the drawbacks in the prior art, the present invention provides a parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence, which is simple, can attain a high coal mining ratio, achieves a good surface subsidence control effect, and safely and efficiently controls overlaying strata fracture and surface subsidence.
Technical solution: The parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence provided in the present invention comprises the following steps: a. arranging a stope haulage roadway I along the edge part or middle part of a stope, and digging a stope branch roadway I perpendicularly or obliquely to the stope haulage roadway I; b. performing multiple two-winged adit mining in the coal mass in the stope branch roadway I from inner side to outer side, wherein, each two-winged adit mining and the corresponding section of the stope branch roadway I is referred to as a stage; c. performing an alternate two-winged adit mining in the next stage at an interval equal to the width of a two-winged mining adit along the stope branch roadway I, whenever the two-winged adit mining in each stage is completed; d. building sealing walls in the stope branch roadway I and filling the two-winged adits and the corresponding sections of the stope branch roadway I, after the multiple stages two-winged adit mining is completed; e. repeating steps b and c to continue the two-winged adit mining in the stope branch roadway I, while executing the steps d; f. repeating the steps b, c, d, and e, till all two-winged adits in the stope branch roadway I have been mined and filled; g. digging a next stope branch roadway I parallel to the stope branch roadway I at one side of the stope branch roadway I, while mining and filling the two-winged adits in the stope branch roadway I; h. repeating the steps b, c, d, e, and f, till the next stope branch roadway I and all twowinged adits therein have been mined and filled; i. repeating the steps b, c, d, e, f, and g, till all stope branch roadways I and all twowinged adits therein at one side of the stope haulage roadway I have been mined and filled; j. digging a stope haulage roadway II on the other side of the stope and digging a stope branch roadway II at one side of the stope haulage roadway II, while mining and filling the stope branch roadway I and the two-winged adits at one side of the stope haulage roadway I, wherein, the stope branch roadway II is located between two adjacent stope branch roadway I;
k. performing two-winged adits mining and filling in the stope branch roadway II 3 2015345830 05 Oct 2016 with the method described in the step b, c, d, e, f, and g, till the coal resource in the entire stope has been mined and filled.
The included angle a between the direction perpendicular to stope branch roadway and the adit is determined according to the requirement of the working angle of the coal mining equipment; the width of each two-winged adit is equal to the working width of the coal mining equipment; the distance Lbetween adjacent stope branch roadways at the same side of the stope haulage roadway is determined with a formula L~L\+2\j2cosa, where, Li is the width of a stope branch roadway, and L2 is the length of an adit.
Beneficial effects: In the present invention, stope branch roadways and two-winged adits are arranged, the two-winged adit and the corresponding section of the stope branch roadway are referred to as a stage, sealing walls are built in the stope branch roadway after multiple stages of mining is completed, and the two-winged adits are filled uniformly, to minimize the quantity of the sealing walls. The stope branch roadways are used as main haulage passages, and the coal mining work is carried out in the two-winged adits; the two-winged adits are filled timely, and two-winged adits that have not been mined or have been filled are utilized as roof supports, and the length of two-winged adits is controlled to eliminate the requirement for supporting; after the filling mass meets the strength requirement, the two-winged adits that have not been mined in the reserved coal pillars are mined with the same method, so that the coal is replaced by the filling mass. The coal mining method provided in the present invention overcomes the drawbacks in the existing coal mining method for mining the coal under constructions, railroads, and water bodies, such as low recovery ratio, difficulties in coordination between mining and filling, and complex production system, etc., realizes safe and efficient recovery of the coal under constructions, railroads, and water bodies while preserving the water resources, and can effectively control overlaying strata fractures and surface subsidence. The method enables synchronous and coordinated coal mining and filling, attains a high recovery ratio, achieves a good surface subsidence control effect, and realizes safe and efficient water-preserved coal mining through parallel digging, mining and filling operation while effectively controlling overlaying strata fractures and surface subsidence. The method is simple, can realize a high coal recovery ratio and a good surface subsidence control effect, and has wide practicability.
Description of the Drawings
Fig. 1 is a schematic diagram of first stage mining along the first stope branch roadway I at one side of the stope haulage roadway I (1) in the present invention;
Fig. 2 is a schematic diagram of second stage mining along the first stope branch roadway I at one side of the stope haulage roadway I (1) in the present invention;
Fig. 3 is a schematic diagram of third stage mining along the first stope branch roadway I at one side of the stope haulage roadway I (1) in the present invention;
Fig. 4 is a schematic diagram of filling for the first time in the first stope branch roadway I at one side of the stope haulage roadway I (1) in the present invention;
Fig. 5 is a schematic diagram of filling for the second time in the first stope branch roadway I at one side of the stope haulage roadway I (1) in the present invention;
Fig. 6 is a schematic diagram after the first stope branch roadway I at one side of the 4 2015345830 05 Oct 2016 stope haulage roadway I (1) is filled in the present invention;
Fig. 7 is a schematic diagram after the second stope branch roadway I at one side of the stope haulage roadway I (1) is filled in the present invention;
Fig. 8 is a schematic diagram after the first stope branch roadway Π at one side of the stope haulage roadway II (7) is dug in the present invention;
Fig. 9 is a schematic diagram after all stope branch roadways I at one side of the stope haulage roadway I (1) are filled in the present invention;
Fig. 10 is a schematic diagram after the second stage mining along the first stope branch roadway II at one side of the stope haulage roadway II (7) is completed in the present invention;
Fig. 11 is a schematic diagram after the third stage mining along the first stope branch roadway II at one side of the stope haulage roadway II (7) is completed in the present invention;
Fig. 12 is a schematic diagram after the filling for the first time in the first stope branch roadway II at one side of the stope haulage roadway II (7) is completed in the present invention;
Fig. 13 is a schematic diagram after the filling for the second time in the first stope branch roadway II at one side of the stope haulage roadway Π (7) is completed in the present invention;
Fig. 14 is a schematic diagram after the first stope branch roadway Π at one side of the stope haulage roadway Π (7) is filled in the present invention;
Fig. 15 is a schematic diagram after the working face is mined and filled in the present invention;
Fig. 16 is a schematic diagram of the method provided in the present invention.
In the figures: 1, 6 - stope haulage roadway; 2,1- stope branch roadway; 3 - twowinged adit; 4 - sealing wall; 5 - filling mass; 8 - triangular coal.
Detailed Description of the Embodiments
Hereunder the present invention will be further detailed in an embodiment, with reference to the accompanying drawings. The parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence provided in the present invention includes the following steps: a. as shown in Fig. 1, a stope haulage roadway 11 is arranged along the edge part of a stope, and a stope branch roadway I 2 is dug perpendicularly or obliquely to the stope haulage roadway I 1; or, a stope haulage roadway 11 can be arranged in the middle of the stope directly, and a stope branch roadway 12 is arrange at each side of the stope haulage roadway 11. b. then, performing multiple two-winged adits mining in the coal mass along the stope branch roadway 12 from inner side to outer side; the included angle a between the direction perpendicular to stope branch roadway 12 and the two-winged adit 3 shall meet the requirement of turning of the coal mining equipment during operation; the smaller the angle, the less the triangular coal 8 in the schematic diagram will be, and the higher the recovery ratio will be. Each two-winged adit 3 and the 5 2015345830 05 Oct 2016
corresponding section of the stope branch roadway 12 is referred to as a stage, and the width of each two-winged adit is equal to the working width of the coal mining equipment; a next stage two-winged adit 3 at an interval equal to the width of a two-winged adit 3 is mined along the stope branch roadway 12, whenever the twowinged adit 3 mining in each stage is completed, as shown in Figs. 2~3. The width and depth of the adit 3 are determined according to the geological conditions of the coal seam. The width and depth of the two-winged adit 3 can be increased if the roof is stable. If the geologic conditions of the stope branch roadway I 2 are poor, the roadway roof in the triangular area of the two-winged adit 3 (i.e., the intersection point between the two-winged adit 3 and the stope branch roadway I 2) can be supported with crawler movable supports or the like. c. sealing walls 4 are built up in the stope branch roadway I 2 and the two-winged adits 3 that have been mined and the corresponding sections of the stope branch roadway I 2 are filled, after multiple stages two-winged adits 3 mining are completed; the specific number of stages can be determined according to the geologic conditions of coal seam; if the geologic conditions of coal seam are good, more stages can be used; otherwise less stages can be used; especially, the number of stages should be determined according to the roof conditions, to ensure that roadway wall rocks will not have severe deformation, i.e., there is no severe roof collapse, and the deformation of the sides is within a reasonable range. In the schematic diagrams, 3 stages are shown. Sealing walls 5 are built up in the stope branch roadway 2, and the two-winged mining adit 3 that have been mined in steps b and c and the corresponding sections of the stope branch roadway 2 are filled, as shown in Fig. 4. d. the steps b and c are repeated to continue two-winged mining adits 3 mining in the stope branch roadway 12, while the steps d is executed. e. a next stope branch roadway 12 parallel to the stope branch roadway 12 is dug at one side of the stope branch roadway I 2, while the two-winged mining adits 3 in the stope branch roadway 12 are mined and filled, as shown in Fig. 5. f. the steps b, c, d, and e are repeated, till all two-winged mining adits 3 in the stope branch roadway I 2 have been mined and filled, as shown in Fig. 6. g. the steps b, c, d, e, and f are repeated, till the next stope branch roadway I 2 and all two-winged mining adits 3 therein have been mined and filled, as shown in Fig. 7. h. a stope haulage roadway Π 2 is dug on the other side of the stope, and a stope branch roadway II7 is dug at one side of the stope haulage roadway II 6, while the stope branch roadway I 2 and the two-winged adits 3 at one side of the stope haulage roadway I 1 are mined and filled, wherein, the stope branch roadway II 7 is located between two adjacent stope branch roadway 12, as shown in Fig. 8. i. the steps b, c, d, e, f, and g are repeated, till all stope branch roadways I 2 and all two-winged adits 3 therein at one side of the stope haulage roadway I 1 have been mined and filled, as shown in Fig. 9; the distance L between adjacent stope branch roadways at the same side of the stope haulage roadway is determined with a formula L~Li+2\jiCOfia, as shown in Fig. 16, where, Li is the width of a stope branch roadway, hi is the length of an adit, and a is the included angle between the direction perpendicular to stope branch roadway 2 and adit. j. the two-winged adits 3 in the stope branch roadway II7 are mined and filled with 2015345830 05 Oct 2016 6 the method described in the steps b, c, d, e, f, and g, till all coal resource in the first stope branch roadway II 7 at one side of the stope haulage roadway II 6 has been mined out and filled, as shown in Figs. 10-14. k. the above steps are repeated, till the remaining two-winged adits 3 at one side of the stope haulage roadway II 6 are mined, as shown in Fig. 15.

Claims (4)

  1. Claims
    1. A parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence, comprising the following steps: a. arranging a stope haulage roadway 1(1) along the edge part or middle part of a stope, and digging a stope branch roadway I (2) perpendicularly or obliquely to the stope haulage roadway 1(1); b. performing multiple two-winged adits mining in the coal mass in the stope branch roadway I (2) from inner side to outer side, wherein, each two-winged adit (3) and the corresponding section of the stope branch roadway I (2) is referred to as a stage; c. performing next stage two-winged adit (3) mining at an interval equal to the width of a two-winged adit (3) along the stope branch roadway I (2), whenever each stage two-winged mining adit (3) mining is completed; d. building up sealing walls (4) in the stope branch roadway I (2) and filling the two-winged adits (3) that have been mined and the corresponding sections of the stope branch roadway I (2), after multiple stages two-winged adits (3) mining is completed; e. repeating steps b and c to continue two-winged adits (3) mining in the stope branch roadway I (2), while executing the steps d; f. repeating the steps b, c, d, and e, till all two-winged adits (3) in the stope branch roadway I (2) have been mined and filled; g. digging a next stope branch roadway I (2) parallel to the stope branch roadway I (2) at one side of the stope branch roadway I (2), while mining and filling the two-winged adits (3) in the stope branch roadway I (2); h. repeating the steps b, c, d, e, and f, till the next stope branch roadway I (2) and all two-winged mining adits (3) in it have been mined and filled; i. repeating the steps b, c, d, e, f, and g, till all stope branch roadways I (2) and all two-winged adits (3) therein at one side of the stope haulage roadway 1(1) have been mined and filled; j. digging a stope haulage roadway II (6) on the other side of the stope and digging a stope branch roadway II (7) at one side of the stope haulage roadway II (6), while mining and filling the stope branch roadway I (2) and the twowinged adits (3) at one side of the stope haulage roadway I (1), wherein, the stope branch roadway II (7) is located between two adjacent stope branch roadway I (2); k. performing two-winged adits (3) mining and filling in the stope branch roadway II (7) with the method described in the steps b, c, d, e, f, and g, till coal resource in the entire stope has been mined out and filled.
  2. 2. The parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence according to claim 1, wherein: the included angle a between the direction perpendicular to stope branch roadway and the adit is determined according to the requirement of the working angle of the coal mining equipment.
  3. 3. The parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence according to claim 1, wherein: a width of each two-winged adit is equal to the working width of a coal mining equipment.
  4. 4. The parallel digging, mining and filling operation coal mining method for controlling overlaying strata fracture and surface subsidence according to claim 1, wherein: distance L between adjacent stope branch roadways at the same side of the stope haulage roadway is determined with a formula L~L\+2\jicosa, where, Li is the width of a stope branch roadway, and L2 is the length of an adit.
AU2015345830A 2014-11-13 2015-05-12 Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence Ceased AU2015345830B2 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
CN201410643437.7A CN104481536B (en) 2014-11-13 2014-11-13 Cover rock crack and surface subsidence controlled digging, mining and filling parallel operation coal mining method
CN201410643437.7 2014-11-13
PCT/CN2015/078725 WO2016074456A1 (en) 2014-11-13 2015-05-12 Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence

Publications (2)

Publication Number Publication Date
AU2015345830A1 AU2015345830A1 (en) 2016-08-11
AU2015345830B2 true AU2015345830B2 (en) 2016-10-27

Family

ID=52756128

Family Applications (1)

Application Number Title Priority Date Filing Date
AU2015345830A Ceased AU2015345830B2 (en) 2014-11-13 2015-05-12 Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence

Country Status (4)

Country Link
US (1) US20180195386A1 (en)
CN (1) CN104481536B (en)
AU (1) AU2015345830B2 (en)
WO (1) WO2016074456A1 (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104481536B (en) * 2014-11-13 2017-02-08 中国矿业大学 Cover rock crack and surface subsidence controlled digging, mining and filling parallel operation coal mining method
CN106150535A (en) * 2016-07-02 2016-11-23 河南理工大学 A kind of strip-type wangeviry mining method technology offset method for protecting support
CN106522948A (en) * 2016-11-25 2017-03-22 山东科技大学 Short-wall waste rock gluing continuous mining and continuous filling mining method
CN108412494B (en) * 2018-03-05 2019-03-29 乌海市天裕工贸有限公司 A kind of long-armed longitudinally oriented strip belt paste body filling process for stoping
CN109798116B (en) * 2019-04-04 2022-04-01 中国矿业大学(北京) Method for realizing complete coal pillar-free mining area or belt area of double-wing arrangement working face
CN111750822B (en) * 2019-10-31 2022-04-26 河南理工大学 Coal mining induced overlying strata and surface subsidence collaborative dynamic prediction method
CN113605970B (en) * 2021-08-30 2022-06-07 中国矿业大学 Overlying strata isolation grouting filling method for coal gangue underground emission reduction
CN113982580A (en) * 2021-10-18 2022-01-28 兖州煤业股份有限公司 Jigsaw filling coal mining method
CN114320298B (en) * 2022-01-05 2024-03-01 国家能源集团国源电力有限公司 Coal mining method
CN114562330B (en) * 2022-04-02 2022-11-08 中国矿业大学 Method for controlling diffusion range of filling slurry for overburden rock isolation grouting
CN114991858B (en) * 2022-05-20 2023-03-03 中国矿业大学 Maximum lag filling distance determination method based on filling stope stability

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392643A (en) * 2011-11-17 2012-03-28 中国矿业大学 Under-building filling, mining and coal pillar recovering method

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2123109C1 (en) * 1996-04-29 1998-12-10 Акционерное общество "Угольная компания "Прокопьевскуголь" Method for mining of coal series in marginal zones of opencast
RU2364722C1 (en) * 2008-04-16 2009-08-20 Государственное образовательное учреждение высшего профессионального образования "Сибирский государственный индустриальный университет" Developing method of heavy abrupt layer with cast solid stowing
CN102587914A (en) * 2012-03-19 2012-07-18 河南理工大学 Strip-type Wongawilli mining method of coal buried under building
CN103174424B (en) * 2012-11-27 2015-07-15 河南理工大学 Breast and pillar method under long-wall arrangement
CN103696771B (en) * 2013-12-18 2015-06-10 中国矿业大学 Skip-mining type wangeviry stope branch roadway filling and coal mining method
CN103821515B (en) * 2014-02-20 2016-05-04 山西晋煤集团技术研究院有限责任公司 A kind of double face filling coal mining technique
CN103883350B (en) * 2014-04-04 2016-04-27 山东科技大学 The filling coal mining method of adopting is jumped at a kind of interval
CN104481536B (en) * 2014-11-13 2017-02-08 中国矿业大学 Cover rock crack and surface subsidence controlled digging, mining and filling parallel operation coal mining method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102392643A (en) * 2011-11-17 2012-03-28 中国矿业大学 Under-building filling, mining and coal pillar recovering method

Also Published As

Publication number Publication date
AU2015345830A1 (en) 2016-08-11
CN104481536B (en) 2017-02-08
WO2016074456A1 (en) 2016-05-19
US20180195386A1 (en) 2018-07-12
CN104481536A (en) 2015-04-01

Similar Documents

Publication Publication Date Title
AU2015345830B2 (en) Coal mining method with digging, mining and filling parallel operations under control of cover rock cracks and surface subsidence
AU2019435042B2 (en) Two-step grouting modified coal mining method under water-preservation for roof aquifer
US10012080B2 (en) Skip-mining type wangeviry stope branch roadway filling and coal mining method
CN103557002B (en) A kind of mechanized concentrates drop shaft filling-up method
Yuan Theory and practice of integrated coal production and gas extraction
AU2013354613B2 (en) Method of local filling to control surface subsidence in worked-out area
CN103615250B (en) The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes
CN104832178A (en) A layering and partially filling coal mining method of thick seams
CN113175325B (en) Coal and intergrown sandstone type uranium ore coordinated mining method based on key layer protection
CN104100271B (en) Pre-pick is led cave filling artificial side secondary multiplexing roadside support and is become lane method
CN103821558A (en) Coal mine gob filling mining system and gob-side entry retaining filling process
AU2021106168A4 (en) High-gas Coal Seam Group Pressure Relief Mining Method Based on Gob-side Entry Retaining in the First Mining Whole Rock Pressure Relief Working Face
CN105089668A (en) Longwall working face coal-pillar-free mining method
CN104847355A (en) Continuous mining method for hollow ground of medium-thickness steeply inclined ore body
CN104632219A (en) Large mining height gob-side entry retaining method for thick coal seams
CN103775095A (en) Ridge soft-foundation tunnel advance double guide tunnel and construction method thereof
CN111828007A (en) Stoping method for residual studs in underground mine goaf
CN108266189A (en) A kind of lane top Tunnelling Along Goaf goaf isolation method
Li et al. Trial of small gateroad pillar in top coal caving longwall mining of large mining height
CN104533419A (en) Method for partial recovery of residual coal from wide coal pillar
CN104727847A (en) Non chain pillar gob-side entry retaining method with filling wall self-erasure
CN203716985U (en) Advanced dual guide hole of mountain ridge soft foundation tunnel
CN105927225A (en) Full-seam extraction method for stoping bottom layering of shallow extremely thick loose coal seam
Sidorenko et al. Substantiation of parameters of the technology of mining thick flat beds by underground method with splitting the bed into two
CN203570313U (en) Double-alley chain type stoping and filling arrangement structure

Legal Events

Date Code Title Description
FGA Letters patent sealed or granted (standard patent)
MK14 Patent ceased section 143(a) (annual fees not paid) or expired