CN104631231A - 地铁运营线路隧道内整体道床破除施工方法 - Google Patents
地铁运营线路隧道内整体道床破除施工方法 Download PDFInfo
- Publication number
- CN104631231A CN104631231A CN201510001488.4A CN201510001488A CN104631231A CN 104631231 A CN104631231 A CN 104631231A CN 201510001488 A CN201510001488 A CN 201510001488A CN 104631231 A CN104631231 A CN 104631231A
- Authority
- CN
- China
- Prior art keywords
- concrete
- cut
- tunnel
- construction method
- saw
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01B—PERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
- E01B37/00—Making, maintaining, renewing, or taking-up the ballastway or the track, not provided for in a single one of groups E01B27/00 - E01B35/00
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种地铁运营线路隧道内整体道床破除施工方法,包括以下施工步骤:1)第一阶段混凝土破除;2)第二阶段混凝土破除,安装临时钢枕过渡线路,恢复行车;3)第三阶段混凝土破除。利用低噪音绳锯、墙锯完成既有道床切割,利用研制的地铁隧道内悬臂吊吊运切割的既有板,从而完成既有整体道床破除,该方法施工噪音低、运营线不停运施工、安全可靠,满足城市文明施工、运营线运输、运营线安全和施工工效要求。
Description
技术领域
本发明涉及整体道床破除施工领域,具体是地铁运营线路隧道内整体道床破除的施工方法。
背景技术
在城市市区繁华区域,临近居民区、商业区,为减少列车在行驶过程中对其的干扰,需对既有隧道内整体道床破除,在国内、外尚属首次,没有设计、施工先例可借鉴。针对在不停运条件下施工,在切割机械设备选型、吊运设备研发及临时运行线路过渡措施等设备、方法都有针对性的选择,保证环保、安全的完成破除施工。
发明内容
本发明的目的是提供一种地铁运营线路隧道内整体道床破除施工方法,解决了高效、快速、安全、低噪音的把既有整体道床破除、临时线路过渡开通恢复运营状态,确保了运营不受影响。
本发明的技术方案如下:
铁运营线路隧道内整体道床破除施工方法,在地铁运营线路隧道内封锁要点施工,具体的施工步骤如下:
1)第一阶段混凝土破除:用高频、低噪音墙锯在枕木头外侧沿着道床纵向将两侧水沟混凝土切开,用手持锯分成小块,用电镐和液压镐凿除,装袋外运,切割深度利用特制的长4.3m铝合金直尺,根据隧道半径和隧道收敛值,现场采集切割面距离直尺垂直距离及距离隧道中心水平距离,确定切割深度;
2)解除既有无缝线路:用内燃锯轨机将既有无缝钢轨改成25m标轨有缝线路,并且钻眼用夹板连接,绳锯安装槽切割:在3.6m板中间用墙锯切缝和电镐凿除25cm宽绳锯安装槽,切割深度为第一阶段切除口混凝土面到隧道管壁距离;
3)第二阶段混凝土破除及临时过渡:使用两台高频、低噪音绳锯进行第二阶段混凝土切割,并用隧道内悬臂吊吊走切除的混凝土板;
4)第三阶段混凝土破除:使用高频、低噪音墙锯切割基底素混凝土,切割完成后,使用高频、低噪音液压镐和电镐破除基地素砼,破除完成后人工清理。
所述的铝合金直尺长4.3m,测量切割深度。
所述的墙锯、绳锯均属于高频、低噪音设备进行混凝土切割。
所述地铁隧道内采用特制悬臂吊车,宽度不超过2.6m,能通过150m小半径曲线,满足运行线路限界要求。
本发明的施工方法解决了高效、快速、安全、低噪音的把既有整体道床破除且在封锁点内将线路恢复运营状态,不影响运营,确保了施工过程、运营安全。
附图说明
图1为本发明的整体道床破除三阶段横断面。
图中标号为:1为第一阶段切除区,2为第一阶段切除区,3为第一阶段切除区。
具体实施方式
参见附图, 铁运营线路隧道内整体道床破除的施工方法,在地铁运营线路隧道内封锁要点施工,具体的施工步骤如下:
1)第一阶段混凝土破除:用高频、低噪音墙锯在枕木头外侧沿着道床纵向将两侧水沟混凝土切开,用手持锯分成小块,用电镐和液压镐凿除,装袋外运,切割深度利用特制的长4.3m铝合金直尺,根据隧道半径和隧道收敛值,现场采集切割面距离直尺垂直距离及距离隧道中心水平距离,确定切割深度;
2)解除既有无缝线路:用内燃锯轨机将既有无缝钢轨改成25m标轨有缝线路,并且钻眼用夹板连接,绳锯安装槽切割:在3.6m板中间用墙锯切缝和电镐凿除25cm宽绳锯安装槽,切割深度为第一阶段切除口混凝土面到隧道管壁距离;
3)第二阶段混凝土破除及临时过渡:使用两台高频、低噪音绳锯进行第二阶段混凝土切割,并用隧道内悬臂吊吊走切除的混凝土板;
4)第三阶段混凝土破除:使用高频、低噪音墙锯切割基底素混凝土,切割完成后,使用高频、低噪音液压镐和电镐破除基地素砼,破除完成后人工清理。
所述的铝合金直尺长4.3m,测量切割深度。墙锯、绳锯均属于高频、低噪音设备进行混凝土切割。地铁隧道内采用特制悬臂吊车,宽度不超过2.6m,能通过150m小半径曲线,满足运行线路限界要求。
Claims (4)
1.铁运营线路隧道内整体道床破除施工方法,其特征在于,在地铁运营线路隧道内封锁要点施工,具体的施工步骤如下:
1)第一阶段混凝土破除:用高频、低噪音墙锯在枕木头外侧沿着道床纵向将两侧水沟混凝土切开,用手持锯分成小块,用电镐和液压镐凿除,装袋外运,切割深度利用特制的长4.3m铝合金直尺,根据隧道半径和隧道收敛值,现场采集切割面距离直尺垂直距离及距离隧道中心水平距离,确定切割深度;
2)解除既有无缝线路:用内燃锯轨机将既有无缝钢轨改成25m标轨有缝线路,并且钻眼用夹板连接,绳锯安装槽切割:在3.6m板中间用墙锯切缝和电镐凿除25cm宽绳锯安装槽,切割深度为第一阶段切除口混凝土面到隧道管壁距离;
3)第二阶段混凝土破除及临时过渡:使用两台高频、低噪音绳锯进行第二阶段混凝土切割,并用隧道内悬臂吊吊走切除的混凝土板;
4)第三阶段混凝土破除:使用高频、低噪音墙锯切割基底素混凝土,切割完成后,使用高频、低噪音液压镐和电镐破除基地素砼,破除完成后人工清理。
2.根据权利要求1所述的施工方法,其特征在于:所述的铝合金直尺长4.3m,测量切割深度。
3.根据权利要求1所述的施工方法,其特征在于:所述的墙锯、绳锯均属于高频、低噪音设备进行混凝土切割。
4.根据权利要求1所述的施工方法,其特征在于:所述地铁隧道内采用特制悬臂吊车,宽度不超过2.6m,能通过150m小半径曲线,满足运行线路限界要求。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510001488.4A CN104631231B (zh) | 2015-01-04 | 2015-01-04 | 地铁运营线路隧道内整体道床破除施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510001488.4A CN104631231B (zh) | 2015-01-04 | 2015-01-04 | 地铁运营线路隧道内整体道床破除施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104631231A true CN104631231A (zh) | 2015-05-20 |
CN104631231B CN104631231B (zh) | 2017-05-10 |
Family
ID=53210432
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510001488.4A Active CN104631231B (zh) | 2015-01-04 | 2015-01-04 | 地铁运营线路隧道内整体道床破除施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104631231B (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105019942A (zh) * | 2015-07-20 | 2015-11-04 | 甘肃路桥建设集团有限公司 | 隧道二衬钢筋混凝土的拆除方法 |
CN107858881A (zh) * | 2017-11-17 | 2018-03-30 | 中铁上海工程局集团有限公司 | 一种地铁运营线百米长轨更换施工装置及方法 |
CN113529506A (zh) * | 2021-06-02 | 2021-10-22 | 北京铁科特种工程技术有限公司 | 一种用于城市轨道整体道床换铺的施工方法 |
CN113529505A (zh) * | 2021-06-02 | 2021-10-22 | 北京铁科特种工程技术有限公司 | 一种用于城轨无砟轨道板的成套切割设备 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10114087B4 (de) * | 2001-03-22 | 2004-09-02 | Leonhard Weiss Gmbh & Co. | Vorrichtung zum Verlegen von Y-förmigen Gleisschwellen auf einem Gleisbett |
CN101173492A (zh) * | 2007-11-26 | 2008-05-07 | 中铁四局集团有限公司 | 有砟轨道客运专线道岔原位铺设方法 |
CN101215812A (zh) * | 2007-12-27 | 2008-07-09 | 中铁二局股份有限公司 | 客运专线长枕埋入式大号无砟道岔施工方法 |
CN102102315A (zh) * | 2009-12-18 | 2011-06-22 | 许吉锭 | 枕体栓接弹性道口的施工方法 |
CN103243619A (zh) * | 2013-04-27 | 2013-08-14 | 洛阳双瑞橡塑科技有限公司 | 板式可更换组合道床系统及施工工艺 |
-
2015
- 2015-01-04 CN CN201510001488.4A patent/CN104631231B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE10114087B4 (de) * | 2001-03-22 | 2004-09-02 | Leonhard Weiss Gmbh & Co. | Vorrichtung zum Verlegen von Y-förmigen Gleisschwellen auf einem Gleisbett |
CN101173492A (zh) * | 2007-11-26 | 2008-05-07 | 中铁四局集团有限公司 | 有砟轨道客运专线道岔原位铺设方法 |
CN101215812A (zh) * | 2007-12-27 | 2008-07-09 | 中铁二局股份有限公司 | 客运专线长枕埋入式大号无砟道岔施工方法 |
CN102102315A (zh) * | 2009-12-18 | 2011-06-22 | 许吉锭 | 枕体栓接弹性道口的施工方法 |
CN103243619A (zh) * | 2013-04-27 | 2013-08-14 | 洛阳双瑞橡塑科技有限公司 | 板式可更换组合道床系统及施工工艺 |
Non-Patent Citations (2)
Title |
---|
朱家坤等: "改造地铁轨枕埋入式整体道床为浮置板道床实现减震降噪的施工技术", 《科技创业家》 * |
段启楠等: "地铁既有道床降振改造施工设备及工艺研究", 《安徽建筑》 * |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105019942A (zh) * | 2015-07-20 | 2015-11-04 | 甘肃路桥建设集团有限公司 | 隧道二衬钢筋混凝土的拆除方法 |
CN107858881A (zh) * | 2017-11-17 | 2018-03-30 | 中铁上海工程局集团有限公司 | 一种地铁运营线百米长轨更换施工装置及方法 |
CN107858881B (zh) * | 2017-11-17 | 2024-03-22 | 中铁上海工程局集团有限公司 | 一种地铁运营线百米长轨更换施工装置及方法 |
CN113529506A (zh) * | 2021-06-02 | 2021-10-22 | 北京铁科特种工程技术有限公司 | 一种用于城市轨道整体道床换铺的施工方法 |
CN113529505A (zh) * | 2021-06-02 | 2021-10-22 | 北京铁科特种工程技术有限公司 | 一种用于城轨无砟轨道板的成套切割设备 |
Also Published As
Publication number | Publication date |
---|---|
CN104631231B (zh) | 2017-05-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631219A (zh) | 地铁运营线路隧道内整体道床改浮置板道床施工方法 | |
CN104631231A (zh) | 地铁运营线路隧道内整体道床破除施工方法 | |
CN205934734U (zh) | 一种预制t梁横移辅助架设装置 | |
CN202555892U (zh) | 一种钢管定尺切割装置 | |
CN103362078A (zh) | 新旧框架桥置换过程中旧框架桥拆除方法 | |
CN104389272B (zh) | 多功能移动式操作平台 | |
CN205223864U (zh) | 一种移动模架用钢筋绑扎胎具 | |
CN105350408A (zh) | 地铁既有整体道床切割劈裂破除改造施工方法 | |
CN204457786U (zh) | 一种b管片拆除后的扩挖大直径盾构隧道建造地铁车站 | |
CN105274911A (zh) | 地铁既有整体道床切割凿除顶推破除改造施工方法 | |
CN205552887U (zh) | 一种可精确切割的混凝土切割机 | |
CN202359511U (zh) | 一种地铁隧道水沟与道床一次性浇筑模板结构 | |
CN209227545U (zh) | 一种明挖隧道支撑系统 | |
CN204266135U (zh) | 多功能移动式操作平台 | |
CN203960901U (zh) | 一种通信人/手井的非迁移式支撑保护系统 | |
CN108240226B (zh) | 近距离交叠地铁隧道同步建设预留盾构空推条件施工方法 | |
CN203545492U (zh) | 锅炉炉顶附着式起重机行走轨道装置 | |
CN201209232Y (zh) | 长钢轨倒运专用卡 | |
CN205477663U (zh) | 一种仰拱同步衬砌钢模台车 | |
CN205367490U (zh) | 轨道交叉转换装置 | |
CN106927365A (zh) | 轨道交叉转换装置 | |
CN205474623U (zh) | 一种升降坡轨道连接装置 | |
CN204569212U (zh) | 一种手推式的工艺吊码理料工具 | |
CN206455828U (zh) | 一种渠道半断面切缝机 | |
CN204311770U (zh) | 一种建筑用防护栏 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |