CN104615520A - Test method for evaluating startup and shutdown life of server - Google Patents
Test method for evaluating startup and shutdown life of server Download PDFInfo
- Publication number
- CN104615520A CN104615520A CN201510104857.2A CN201510104857A CN104615520A CN 104615520 A CN104615520 A CN 104615520A CN 201510104857 A CN201510104857 A CN 201510104857A CN 104615520 A CN104615520 A CN 104615520A
- Authority
- CN
- China
- Prior art keywords
- server
- test
- switching
- time delay
- start time
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention provides a test method for evaluating the startup and shutdown life of a server and relates to an evaluation and test technology for startup and shutdown reliability. The method utilizes a switching circuit system to enable the server to automatically carry out startup and shutdown testing, therefore, evaluation on the startup and shutdown life and reliability of the server is realized. The method realizes the evaluation on the startup and shutdown life and reliability of the server, reduces a lot of time and labor, and improves the stability and reliability of the whole server.
Description
Technical field
The present invention relates to the assessment measuring technology of switching on and shutting down reliability, particularly relate to the method for testing in a kind of evaluating server switching on and shutting down life-span.
Background technology
As the leader of China services device industry, the technical merit of LANGCHAO in server research and development is also being advanced by leaps and bounds, now through having stood in the most significant end of China services device research and development.Meanwhile, along with the fast development of China's IT industry, large data age arrives, and the client of enterprise-level is also increasing severely day by day to the quantity required of server, and client starts to need to buy large batch of server to dispose the core application of oneself.Thus, client, except to except the stability of server, it is also proposed higher requirement to the reliability of server.
In the performance history of server, the reliability of switching on and shutting down is extremely important, and it directly affects the product quality of server.This test was all that this mode can not meet current testing requirement completely by carrying out switching on and shutting down checking manually, complex operation, inefficiency in the past, so the method in this evaluating server switching on and shutting down life-span is urgently improved.
Summary of the invention
In order to overcome the above problems, propose the method for testing in a kind of evaluating server switching on and shutting down life-span herein, in order to the manual testing of emulating server switching on and shutting down, this design make use of a subtest program, improves testing efficiency, saves the test duration, reduce human input, improving product competitive power.
The method of testing in a kind of evaluating server switching on and shutting down life-span, a SWITCHING CIRCUITRY is utilized to make server automatically carry out the test of cycling switch machine, during test, this test macro is only needed to be connected by the power supply of operation steps with server to be measured, after starting test, test macro can start the test of unattended circulating pressure automatically.
Powered on again by power-off after emulating server normal shutdown, and by delay procedure, boot action is again carried out to server; If server energy normal boot-strap, after start, this test macro will repeat power operation automatically, carries out unattended switching on and shutting down loop test.
Operation steps is,
1), a server system to be measured is prepared---can shutdown command be automatically performed after entering operating system;
2), testing tool is connected with server to be measured;
3), testing tool powers on, and carries out start time delay, switching on and shutting down number of times, time of fire alarming setting by liquid crystal panel simultaneously;
4), start test, start time delay and time of fire alarming reset simultaneously;
5), single-chip microcomputer brings into operation, and start time delay starts counting;
6), start time delay counting reach preset value after single-chip microcomputer send starting-up signal to server, simultaneously alarm timer starts timing;
7), after server start, instrument consumption detection starts detecting instrument output power consumption;
8) if instrument exports power consumption be less than or equal to 20W, represent that server is in off-mode, now disconnect server power supply, number counter numerical value+1, and jump to start time delay and time of fire alarming homing action; If instrument exports power consumption be greater than 20W, represent that server is also in open state, alarm timer continues timing, reports to the police, now need manually to fix a breakdown, restart test after failture evacuation after alarm timer arrives preset value;
9), after number counter arrives preset value, test is stopped.
Adopt this method of testing, greatly save artificial operation, only need to arrange first successfully, just not at needs human intervention.This method of testing, is powered on by power-off after emulating server normal shutdown again, and carries out boot action again by delay procedure to server.If server energy normal boot-strap, after start, this test macro will repeat power operation automatically, carries out unattended switching on and shutting down loop test.Thus assessment is in the switching on and shutting down life-span of the server ground.
Accompanying drawing explanation
Fig. 1 is signal wiring schematic diagram.
Fig. 2 is operational flow diagram.
Embodiment
More detailed elaboration is carried out to content of the present invention below:
One, operation steps and explanation
1, a server system to be measured is prepared---can shutdown command be automatically performed after entering operating system.
2, testing tool is connected with server to be measured.
3, testing tool powers on, and carries out start time delay, switching on and shutting down number of times, time of fire alarming setting by liquid crystal panel simultaneously.
4, start test, start time delay and time of fire alarming reset simultaneously.
5, single-chip microcomputer brings into operation, and start time delay starts counting.
6, after time delay counting of starting shooting reaches preset value, single-chip microcomputer sends starting-up signal to server, and alarm timer starts timing simultaneously.
7, after server start, instrument consumption detection starts detecting instrument output power consumption.
If 8 instruments export power consumption be less than or equal to 20W, represent that server is in off-mode, now disconnect server power supply, number counter numerical value+1, and jump to start time delay and time of fire alarming homing action; If instrument exports power consumption be greater than 20W, represent that server is also in open state, alarm timer continues timing, reports to the police, now need manually to fix a breakdown, restart test after failture evacuation after alarm timer arrives preset value.
9, after number counter arrives preset value, test is stopped.
The present invention thoroughly improves the assessment method of testing of server development to switching on and shutting down reliability, full automatic process is become from manual test in the past, use procedure is safe and reliable, simple to operate, can use widely in the switching on and shutting down reliability demonstration of server.Book server stability test method is applicable to all single supplies or dual power supply server, to operating system no requirement (NR), the method shows well in test process, stable performance, test request can be reached well, for the server product quality of company and competitive power provide powerful guarantee.
Claims (3)
1. the method for testing in an evaluating server switching on and shutting down life-span, it is characterized in that, a SWITCHING CIRCUITRY is utilized to make server automatically carry out the test of cycling switch machine, during test, this test macro is only needed to be connected by the power supply of operation steps with server to be measured, after starting test, test macro can start the test of unattended circulating pressure automatically.
2. method according to claim 1, is characterized in that, is powered on again, and carry out boot action again by delay procedure to server by power-off after emulating server normal shutdown; If server energy normal boot-strap, after start, this test macro will repeat power operation automatically, carries out unattended switching on and shutting down loop test.
3. method according to claim 1, is characterized in that,
Operation steps is,
1), a server system to be measured is prepared---can shutdown command be automatically performed after entering operating system;
2), testing tool is connected with server to be measured;
3), testing tool powers on, and carries out start time delay, switching on and shutting down number of times, time of fire alarming setting by liquid crystal panel simultaneously;
4), start test, start time delay and time of fire alarming reset simultaneously;
5), single-chip microcomputer brings into operation, and start time delay starts counting;
6), start time delay counting reach preset value after single-chip microcomputer send starting-up signal to server, simultaneously alarm timer starts timing;
7), after server start, instrument consumption detection starts detecting instrument output power consumption;
8) if instrument exports power consumption be less than or equal to 20W, represent that server is in off-mode, now disconnect server power supply, number counter numerical value+1, and jump to start time delay and time of fire alarming homing action; If instrument exports power consumption be greater than 20W, represent that server is also in open state, alarm timer continues timing, reports to the police, now need manually to fix a breakdown, restart test after failture evacuation after alarm timer arrives preset value;
9), after number counter arrives preset value, test is stopped.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510104857.2A CN104615520A (en) | 2015-03-10 | 2015-03-10 | Test method for evaluating startup and shutdown life of server |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510104857.2A CN104615520A (en) | 2015-03-10 | 2015-03-10 | Test method for evaluating startup and shutdown life of server |
Publications (1)
Publication Number | Publication Date |
---|---|
CN104615520A true CN104615520A (en) | 2015-05-13 |
Family
ID=53149977
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510104857.2A Pending CN104615520A (en) | 2015-03-10 | 2015-03-10 | Test method for evaluating startup and shutdown life of server |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104615520A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105573779A (en) * | 2015-12-08 | 2016-05-11 | 浪潮电子信息产业股份有限公司 | Method for automatically and repeatedly refreshing BIOS (Basic Input Output System)+ME (management engine) |
WO2018107378A1 (en) * | 2016-12-14 | 2018-06-21 | 深圳中兴力维技术有限公司 | Testing method and testing apparatus |
CN108225748A (en) * | 2017-11-17 | 2018-06-29 | 力帆实业(集团)股份有限公司 | A kind of key durance test device |
CN110245042A (en) * | 2019-06-21 | 2019-09-17 | 广东虹勤通讯技术有限公司 | A kind of laptop shipment mode capabilities automatic test approach and system |
CN113589092A (en) * | 2021-09-28 | 2021-11-02 | 苏州浪潮智能科技有限公司 | Fatigue machine, equipment power-on and power-off test system and power-on and power-off test method |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005180952A (en) * | 2003-12-16 | 2005-07-07 | Matsushita Electric Ind Co Ltd | Test circuit, semiconductor integrated circuit, and its manufacturing method |
CN201378313Y (en) * | 2009-04-16 | 2010-01-06 | 浪潮电子信息产业股份有限公司 | Device for on/off fatigue tests used for microcomputer and server |
JP2012160149A (en) * | 2011-02-03 | 2012-08-23 | Toshiba Corp | Duplex circuit, semiconductor device and test method |
CN102752156A (en) * | 2011-04-19 | 2012-10-24 | 鸿富锦精密工业(深圳)有限公司 | Test device for server |
CN102937927A (en) * | 2011-08-15 | 2013-02-20 | 鸿富锦精密工业(深圳)有限公司 | Method and system for testing stability of server |
-
2015
- 2015-03-10 CN CN201510104857.2A patent/CN104615520A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005180952A (en) * | 2003-12-16 | 2005-07-07 | Matsushita Electric Ind Co Ltd | Test circuit, semiconductor integrated circuit, and its manufacturing method |
CN201378313Y (en) * | 2009-04-16 | 2010-01-06 | 浪潮电子信息产业股份有限公司 | Device for on/off fatigue tests used for microcomputer and server |
JP2012160149A (en) * | 2011-02-03 | 2012-08-23 | Toshiba Corp | Duplex circuit, semiconductor device and test method |
CN102752156A (en) * | 2011-04-19 | 2012-10-24 | 鸿富锦精密工业(深圳)有限公司 | Test device for server |
CN102937927A (en) * | 2011-08-15 | 2013-02-20 | 鸿富锦精密工业(深圳)有限公司 | Method and system for testing stability of server |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105573779A (en) * | 2015-12-08 | 2016-05-11 | 浪潮电子信息产业股份有限公司 | Method for automatically and repeatedly refreshing BIOS (Basic Input Output System)+ME (management engine) |
WO2018107378A1 (en) * | 2016-12-14 | 2018-06-21 | 深圳中兴力维技术有限公司 | Testing method and testing apparatus |
CN108225748A (en) * | 2017-11-17 | 2018-06-29 | 力帆实业(集团)股份有限公司 | A kind of key durance test device |
CN110245042A (en) * | 2019-06-21 | 2019-09-17 | 广东虹勤通讯技术有限公司 | A kind of laptop shipment mode capabilities automatic test approach and system |
CN113589092A (en) * | 2021-09-28 | 2021-11-02 | 苏州浪潮智能科技有限公司 | Fatigue machine, equipment power-on and power-off test system and power-on and power-off test method |
CN113589092B (en) * | 2021-09-28 | 2022-01-04 | 苏州浪潮智能科技有限公司 | Fatigue machine, equipment power-on and power-off test system and power-on and power-off test method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104615520A (en) | Test method for evaluating startup and shutdown life of server | |
CN103970630A (en) | Method for testing overall stability of server | |
CN102255774A (en) | Test system and test method for switch-on and switch-off of communication device as well as fault location method | |
CN106909479B (en) | Startup and shutdown test fixture | |
CN105067928A (en) | Automobile electronic product dark current automatic test method and device | |
TW201205322A (en) | Computer component power-consumption database | |
CN201378313Y (en) | Device for on/off fatigue tests used for microcomputer and server | |
CN102087625A (en) | Boot test system and test method | |
RU2015102081A (en) | METHOD, DEVICE AND SYSTEM FOR CALCULATING ELECTRICITY COSTS | |
CN103267919A (en) | Automatic startup and shutdown device | |
CN106019167A (en) | Intelligent electric energy meter clock battery performance testing method based on working condition simulation | |
CN103576092A (en) | Remote controller and device and method for detecting electricity capacity of battery of remote controller | |
CN106201797A (en) | The method that fatigue tester collocation 4U tool realizes multinode AC test | |
JP2013225309A (en) | System conducting restart test and power-on/power-off test of computer | |
CN201242718Y (en) | Automatic startup apparatus | |
CN102419395A (en) | Method and device for testing energy efficiency of induction cooker | |
CN107295125A (en) | A kind of handheld terminal on-off circuit and control method | |
CN203310938U (en) | Startup/shutdown test system of electronic device | |
CN102681872A (en) | Automatic cold boot method of notebook computer | |
CN202475392U (en) | Selector switch capable of controlling on-off of power supply | |
CN106354592A (en) | Computer automatic startup and shutdown testing device | |
CN102981077B (en) | High-low pressure impact tester and testing method thereof | |
CN102435940A (en) | Device for testing on-off of luminous body | |
CN104300506B (en) | A kind of band prevents the battery protecting circuit of leakage function | |
CN204329464U (en) | Refrigerator intelligent electric-saving device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20150513 |
|
WD01 | Invention patent application deemed withdrawn after publication |