CN104612330B - Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming - Google Patents

Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming Download PDF

Info

Publication number
CN104612330B
CN104612330B CN201510005365.8A CN201510005365A CN104612330B CN 104612330 B CN104612330 B CN 104612330B CN 201510005365 A CN201510005365 A CN 201510005365A CN 104612330 B CN104612330 B CN 104612330B
Authority
CN
China
Prior art keywords
concrete
block
load
steel pipe
tubular member
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510005365.8A
Other languages
Chinese (zh)
Other versions
CN104612330A (en
Inventor
陈利民
李洪泉
张小迪
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing University of Technology
Original Assignee
Beijing University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing University of Technology filed Critical Beijing University of Technology
Priority to CN201510005365.8A priority Critical patent/CN104612330B/en
Publication of CN104612330A publication Critical patent/CN104612330A/en
Application granted granted Critical
Publication of CN104612330B publication Critical patent/CN104612330B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
  • Manufacturing Of Tubular Articles Or Embedded Moulded Articles (AREA)

Abstract

Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming, when making concrete filled steel tubular member, appropriate concrete grout is first poured, block is then depressed into design attitude under the control loading of pressure seat in the plane, then block and steel-pipe welding are got up while sealing steam vent.The prestressing force size of concrete filled steel tube is determined by the ratio of volume of concrete and steel pipe volume.In pressure seat in the plane control loading procedure, if block does not have in place also, but the load that forcing press applies has been above prestressing force, illustrates that concrete grout is excessive, it is desirable to reduce grouting.If block is in place, but forcing press load is less than prestressing force, illustrates that concrete grout is few, it is necessary to increase grouting.Second load forming method is the precompression of default concrete filled steel tubular member;Loading Method is controlled with position to be loaded until preliminary dimension to concrete filled steel tubular member;Grouting quantity is adjusted in the loading procedure of second load forming method, when block is pressed onto predeterminated position, the load of forcing press is just preset pressure.

Description

Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure into Type method
Technical field
The present invention relates to a kind of embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming, Belong to prestressed concrete technology field.
Background technology
It is single at present mostly by pressure grouting concrete filled steel tube preparation method, but due to the mobility of concrete itself Pure use concrete vibrating mode, one side corner narrow gap is still difficult to fill real, when on the other hand sealing between concrete grout and hush panel Gap is easier, has caused its actual bearing capacity ratio design load to decrease.
The present invention solves the problem using embedded cap method, and penetration concrete slurry first is slightly more some more than amount of calculation, then with position Control method control pressure machine is loaded onto the design height of concrete filled steel tubular member, while exhaust of the gas in steel pipe in block Mouth discharge, in place rear welded still pipe and block seals exhaust outlet simultaneously.Side so can be as far as possible filled under pressure Angular gap forms pre-stressed steel pipe concrete component, improves the bearing capacity of component.
The content of the invention
Add object of the present invention is to provide a kind of embedded hat type pre-stressed steel pipe concrete component and its control of secondary position Compression moulding method is carried, the present invention controls lower loading welding block and steel pipe forming with embedded block and pressure seat in the plane, than commonly shaking Smash method making concrete filled steel tube it is finer and close, be easier to fill corner gap, so as to improve bearing capacity.
To achieve the above object, the technical solution adopted by the present invention is a kind of embedded hat type pre-stressed steel pipe concrete component And its secondary position control on-load pressure method of forming, hat type pre-stressed steel pipe concrete component is embedded including steel pipe, with steam vent Embedded block, when making concrete filled steel tubular member, first pours appropriate concrete grout, then block under the control loading of pressure seat in the plane Design attitude is depressed into, then block and steel-pipe welding are got up while sealing steam vent.The prestressing force size of concrete filled steel tube by The ratio of volume of concrete and steel pipe volume is determined.In pressure seat in the plane control loading procedure, if block does not have in place also, but pressure The load that machine applies has been above prestressing force, illustrates that concrete grout is excessive, it is desirable to reduce grouting.If block is in place, but It is forcing press load less than prestressing force, illustrates that concrete grout is few, it is necessary to increase grouting.
Second load forming method is the precompression of concrete filled steel tubular member default first;Secondly Loading Method is controlled to steel with position Pipe concrete component is loaded until preliminary dimension;Grouting quantity is adjusted in the loading procedure of last second load forming method, makes lid When cap is pressed onto predeterminated position, the load of forcing press is just preset pressure.
Compared with prior art, the present invention has the advantages that.
1st, the prestressed concrete filled steel tubular member of accurate satisfaction setting can be manufactured.
2nd, than conventional method making of vibrating concrete filled steel tubular member even compact, gas hole defect are few.
3rd, than the concrete filled steel tubular member high capacity of conventional method making of vibrating.
Brief description of the drawings
Fig. 1 is the steel core concrete column under forcing press after the completion of being in the milk.
Fig. 2 is the steel core concrete column that prosecutor formula in place is issued to design height.
Specific embodiment
The present invention is described in further detail below in conjunction with drawings and Examples.
As shown in Figure 1-2, preset the precompression of steel core concrete column according to demand first, be then more than to being poured into steel pipe The concrete grout of steel pipe volume, then covers block, now the total height of steel core concrete column L bigger than design height.
The component in making is loaded with displacement-controlled method control pressure machine, as block is moved down, component total height is gradually Close to design height, the load that forcing press applies also constantly increases.If block does not have in place also, but the load that forcing press applies Preset pressure is had been above, illustrates that concrete grout is excessive, it is desirable to reduce grouting, repeats bits control loading again removes slurry until block position Move during for L, forcing press load is preset pressure.Welding block and steel pipe are while sealing exhaust outlet.
If block has been pressed onto position, but forcing press load still less than preset pressure, illustrate that concrete grout is few, it is necessary to increase Plus grouting.When block displacement is L, forcing press load is preset pressure for re grouting, loading.Welding block and steel pipe are simultaneously Sealing exhaust outlet.
In position control loading procedure, the gas in steel pipe is discharged by the exhaust outlet in block.

Claims (1)

1. the on-load pressure method of forming is controlled in a kind of secondary position of embedded hat type pre-stressed steel pipe concrete component, it is characterised in that:It is interior Embedding hat type pre-stressed steel pipe concrete component includes steel pipe, the embedded block with steam vent, when making concrete filled steel tubular member, Appropriate concrete grout is first poured, block is then depressed into design attitude under the control loading of pressure seat in the plane, then block and steel pipe Weld sealing steam vent simultaneously;The prestressing force size of concrete filled steel tube is determined by the ratio of volume of concrete and steel pipe volume It is fixed;In pressure seat in the plane control loading procedure, if block does not have in place also, but the load that forcing press applies has been above prestressing force, Illustrate that concrete grout is excessive, it is desirable to reduce grouting;If block is in place, but forcing press load is less than prestressing force, explanation Concrete grout is few, it is necessary to increase grouting;Second load forming method is the precompression of concrete filled steel tubular member default first;Secondly Loading Method is controlled with position to be loaded until preliminary dimension to concrete filled steel tubular member;In the loading procedure of last second load forming method Adjustment grouting quantity, when block is pressed onto predeterminated position, the load of forcing press is just preset pressure;In position control loading procedure, steel Gas in pipe is discharged by the exhaust outlet in block.
CN201510005365.8A 2015-01-06 2015-01-06 Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming Expired - Fee Related CN104612330B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510005365.8A CN104612330B (en) 2015-01-06 2015-01-06 Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510005365.8A CN104612330B (en) 2015-01-06 2015-01-06 Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming

Publications (2)

Publication Number Publication Date
CN104612330A CN104612330A (en) 2015-05-13
CN104612330B true CN104612330B (en) 2017-06-20

Family

ID=53146957

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510005365.8A Expired - Fee Related CN104612330B (en) 2015-01-06 2015-01-06 Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming

Country Status (1)

Country Link
CN (1) CN104612330B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110306726B (en) * 2018-03-27 2022-03-18 王哲 Composite structure and manufacturing method thereof

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1030411C (en) * 1991-05-24 1995-11-29 钟莉 Energy storing steel tube concrete making method and the members thereof
JPH05171737A (en) * 1991-12-25 1993-07-09 Asahi Chem Ind Co Ltd Filling type steel tube concrete pillar
JPH10110531A (en) * 1996-10-04 1998-04-28 Nkk Corp Concrete filling method in steel pipe concrete pole
JP2003184100A (en) * 2001-12-19 2003-07-03 Yoshinori Matsuki Preventive pile for preventing landslide, and increasing method of preventing and supporting force of support pile for structure foundation
CN202324346U (en) * 2011-11-21 2012-07-11 陕西建工集团第二建筑工程有限公司 Concrete pumping and lifting construction device in concrete column pipe of steel pipe
CN103240802B (en) * 2013-05-16 2015-07-08 淮海工学院 Production method of prestress concrete filled steel tube
CN203320810U (en) * 2013-07-09 2013-12-04 宏润建设集团股份有限公司 Steel tube concrete structure
CN203412195U (en) * 2013-07-18 2014-01-29 杭州博数土木工程技术有限公司 Concrete filled steel tube complete combination column

Also Published As

Publication number Publication date
CN104612330A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN104074143B (en) Prestressing force intelligent circulation mud jacking system and its control method
CN108301568A (en) A kind of assembling structure of assembly concrete component
CN207260443U (en) A kind of grout sleeve prefabricated for building structure
CN104612330B (en) Embedded hat type pre-stressed steel pipe concrete component and its secondary position control on-load pressure method of forming
CN102817328B (en) Method for heightening support
CN202809633U (en) Connecting structure of pre-stressed high-strength concrete (PHC) pipe pile and bearing platform
CN208396278U (en) A kind of overhanging U bolt built-in fitting
CN209115120U (en) A kind of lining of hidden digging structure two concrete vault anticreep sky device
CN110644471B (en) Connection structure of staple bolt formula precast tubular pile and prefabricated cushion cap
CN201056690Y (en) Squeezing and expanding cast-in-place pile
CN112609986A (en) Method for controlling pouring forming quality of concrete batter post
CN101158163B (en) Pneumatic caisson bottom closing construction process
CN114319329B (en) Anchor rod static pressure pipe pressing device and cast-in-place pile construction method
CN205077480U (en) Double cannula bored concrete pile structure
CN213682685U (en) Steel form shell concrete combination T type standard festival
CN114411700A (en) Steel pile body for steel pipe grouting pile construction while sinking pipe and grouting
CN204645071U (en) A kind of device utilizing soil bearing capacity between PHC pipe pile
CN214363666U (en) Pile head reinforcing device for single-pile vertical compression-resistant static load experiment
CN207526119U (en) A kind of reinforcement tools of regularization outer wall template
CN206396750U (en) Pile foundation squeezing unit
CN104863172A (en) Device and method for utilizing bearing force of between-pile soil of PHC pipe pile
CN112780026A (en) Device and method for improving grouting fullness of sleeve
CN206545235U (en) Reinforcing pile stake top stress bringing device
CN107794914B (en) Prestressed concrete pipe pile combining post-grouting and diameter-expanding technology and manufacturing method thereof
CN109176838A (en) Floor brick die and floor tile production method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170620

Termination date: 20200106

CF01 Termination of patent right due to non-payment of annual fee