CN104612004B - Existing line D beam overall longitudinally-moving construction method - Google Patents

Existing line D beam overall longitudinally-moving construction method Download PDF

Info

Publication number
CN104612004B
CN104612004B CN201510036765.5A CN201510036765A CN104612004B CN 104612004 B CN104612004 B CN 104612004B CN 201510036765 A CN201510036765 A CN 201510036765A CN 104612004 B CN104612004 B CN 104612004B
Authority
CN
China
Prior art keywords
steel
big coaster
coaster
big
steel sleeper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510036765.5A
Other languages
Chinese (zh)
Other versions
CN104612004A (en
Inventor
谷金明
乔文禄
李平
李向宇
马炮胜
于开卉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
China Railway Sixth Group Co Ltd
Original Assignee
TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP, China Railway Sixth Group Co Ltd filed Critical TAIYUAN RAILWAY CONSTRUCTION Co Ltd ZHONGTIE 6-BUREAU GROUP
Priority to CN201510036765.5A priority Critical patent/CN104612004B/en
Publication of CN104612004A publication Critical patent/CN104612004A/en
Application granted granted Critical
Publication of CN104612004B publication Critical patent/CN104612004B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01BPERMANENT WAY; PERMANENT-WAY TOOLS; MACHINES FOR MAKING RAILWAYS OF ALL KINDS
    • E01B29/00Laying, rebuilding, or taking-up tracks; Tools or machines therefor
    • E01B29/06Transporting, laying, removing or renewing sleepers
    • E01B29/09Transporting, laying, removing or renewing sleepers under, or from under, installed rails
    • E01B29/13Transporting, laying, removing or renewing sleepers under, or from under, installed rails for moving sleepers in a direction parallel to the rails, e.g. for spacing or aligning them

Abstract

The invention discloses an existing line D beam overall longitudinally-moving construction method. The lifting height of a D beam is calculated according to field D beam high-order arrangement, head blocks are placed on an existing line, a steel sleeper is placed on each head block, the steel sleepers are installed, upper brackets are connected, after the D beam is lifted in place, gaps between the steel sleepers above the head blocks and the head blocks are plugged through wooden footplates, wooden edges are tightly punched, the D beam is longitudinally moved to an existing line reinforced position, a jack falls back, the D beam falls to a required position, the head blocks and the steel sleepers above the line are removed, and the D beam is connected and fastened. By the adoption of the construction method, the D beam can be quickly and longitudinally moved, blocking key points and construction procedures are reduced, instability and the easy-to-topple risk in the D beam moving process are reduced, a contact net does not need to be powered off, the railway transport capacity is greatly released, station track limitation is avoided, the blocking key points are reduced, and construction time is saved.

Description

A kind of this line D beam entirety longitudinal shift construction method
Technical field
The invention belongs to construction of railways field, more particularly, to a kind of this line D beam entirety longitudinal shift construction method.
Background technology
Divide diplopore prefabricated D beam hole-specifically in strengthening construction in railway frame structure, just beam reinforces line to adopt D type according to design requirement Road, under conditions of not interrupting railways train operation, conventional construction method need to using the big coaster of slide rail in length and breadth movement defeated D beam arrive reinforcing position Put, working procedure is loaded down with trivial details, construction " skylight point " time is short, and the monolithic beam center of gravity of D type just beam is higher, bottom surface is narrow, is moving In be easy to topple, directly there is potential safety hazard and risk in tearing assembling construction open, there is no larger security reliability.
Content of the invention
It is an object of the invention to provide a kind of line D beam entirety longitudinal shift construction method is it is intended to solve traditional railway frame Structure divides diplopore prefabricated D beam hole-specifically strengthening construction tedious process, and the engineering time is long, the problem of poor stability.
It is interior that the present invention is achieved in that a kind of this line D beam entirety longitudinal shift construction method includes a little outer preparation and point Operation, concrete grammar includes:
Step one, the outer preparation of point:
The first step, " taking out one every six " rule of being engaged according to work require, and sleeper replacement at the reinforcing of this line is steel sleeper;
Second step, in the range of the D beam vertical shift of this line cleaning D beam walk row of channels;
3rd step, prepare big coaster outside circuit, a steel sleeper placed by every big coaster, and headblock assorted by big coaster Plate, timber wedge, crowbar;
4th step, hydraulic jack is transported in advance circuit D beam two ends, D beam two ends are installed steel and shored, and install oil pipe And oil pump, jack withstands steel and shores;
Operation in step 2, point:
The first step, upper installation connect steel sleeper above former D beam hardened link;
Second step, D beam two ends steel shore lower section install hydraulic jack, overall jack-up D beam, make D beam bottom be higher than the flange of rail Steel sleeper, space plug sheeting caps between big coaster and steel sleeper, wheel walked by the urgent big coaster of timber wedge;
3rd step, remove big coaster and walk timber wedge at wheel, promote big coaster simultaneously, position, wood are reinforced in D beam vertical shift to this line Wheel walked by the urgent big coaster of wedge;
4th step, falling D beam.
The first step, above the described former D beam hardened link of connection, the concrete grammar of steel sleeper is:
Artificial lift by D beam two ends respectively puts big coaster in circuit, steel sleeper lift is put to big coaster, promotes big coaster respectively To specified location, the urgent big coaster of timber wedge walks wheel, fixed lateral position, connection steel sleeper, fastening bracket.
4th step, the concrete grammar of described falling D beam is:
Shore lower section in D beam two ends steel and hydraulic jack, overall jack-up D beam are installed, so that big coaster is not stressed, by big coaster Extract out steel sleeper above circuit, fall jack after rise, make D beam integrally drop down onto D beam-ends requirement position, remove steel sleeper above circuit, Reinforcement by connection D beam.
The construction method of the present invention can achieve the quick vertical shift of D beam, reduces block main points and working procedure, reduces D beam and moves The unstability of disorder of internal organs and the risk easily toppled over, have a power failure without contact net, greatly release railway transport capacity, do not limited by station track System, reduces block main points, saves the engineering time.
Brief description
Fig. 1 is provided in an embodiment of the present invention line D beam entirety longitudinal shift construction method flow chart.
Specific embodiment
In order that the objects, technical solutions and advantages of the present invention become more apparent, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that specific embodiment described herein, only in order to explain the present invention, is not used to Limit the present invention.
Below in conjunction with the accompanying drawings and specific embodiment is further described to the application principle of the present invention.
In the 2-16m frame structure jacking construction of Xinzhou City peace East Street, divide holes prefabricated in existing railway west side, cross north same Pu up-downgoing, Xin Hexian, shunting neck, 4 station track altogether, adopt 24m D beam hardened link in construction, according to live D deck-molding position cloth Put to calculate D beam and need to lift 45cm and exceed flange of rail steel sleeper, existing line is put six big coasters, each big coaster places one Steel sleeper, installs steel sleeper at D beam two ends respectively 2.01m, 4.69m, 7.37m, connects bracket, D beam lifting big coaster after putting in place Sheeting caps stuff up a crack urgent timber wedge is used, vertical shift to this line is reinforced position, slightly played D beam, remove between the steel sleeper of top and big coaster Big coaster, falling jack makes D beam drop down onto and requires position, removes steel sleeper above circuit, connection fastening D beam.Concrete grammar is as follows:
S101, " taking out one every six " rule of being engaged according to work require, and sleeper replacement at the reinforcing of this line is steel sleeper;
S102, in the range of the D beam vertical shift of this line cleaning D beam walk row of channels;
S103, prepare 6 big coasters outside circuit, every big coaster piece steel sleeper of placement, headblock assorted by big coaster Plate, timber wedge, crowbar;
S104, hydraulic jack is transported in advance circuit D beam two ends, D beam two ends are installed steel and shored, install oil pipe and Oil pump, jack withstands steel and shores;
S105, artificial lift by D beam two ends respectively put big coaster in circuit, steel sleeper lift is put to big coaster, promotes respectively To at D beam two ends 2.01m, 4.69m, 7.37m, the urgent big coaster of timber wedge walks wheel, fixed lateral position to big coaster, connects steel Pillow, fastening bracket;
S106, D beam two ends steel shore lower section install join 4 70cm stroke hydraulic jack, so that 2 D beams is integrally lifted, D beam bottom is made to be higher than flange of rail steel sleeper 5cm, space plug sheeting caps between big coaster and circuit, wheel walked by the urgent big coaster of timber wedge;
S107, remove big coaster and walk timber wedge at wheel, promote big coaster simultaneously, position, timber wedge are reinforced in D beam vertical shift to this line Kill big coaster and walk wheel;
S108, D beam two ends steel shore lower section install hydraulic jack, overall jack-up D beam, so that big coaster is not stressed, will Extract out big coaster steel sleeper above circuit, fall jack after rise, make D beam integrally drop down onto to require position, remove steel sleeper above circuit, Reinforcement by connection D beam.
Note in construction:
1. ensure that every big coaster wheel normally runs.
2. above circuit, steel sleeper requires to be connected fastening with D beam, using electric wrench fastening.
3. measure good big coaster in advance and fall position after rise it is ensured that para-position accurately, quickly carries out next procedure.
4. adopt during hydraulic jack jack-up D beam it is desirable to D beam entirety jack-up, steadily, safety.
5. after D back is risen and is connected with steel sleeper above circuit, D beam lower end uses 4m they sup-port, during guaranteeing to fall after rise D beam Do not conflict with steel sleeper at reinforcing position.
6. D back rises, sliding, whereabouts will be assumed unified command of, acting in agreement guarantees safety.
Conventional construction method need to be using movement defeated D beam loaded down with trivial details, the construction to reinforcing position, working procedure in length and breadth of the big coaster of slide rail " skylight point " time is short, and the monolithic beam center of gravity of D type just beam is higher, and bottom surface is narrow, is easy to topple in movement.Especially The D24m just long 24.5m of beam girder, wide 45cm, high 130cm, height is 3 times of bottom width, and such configuration is steady in monolithic directly moves Qualitative extreme difference, directly has potential safety hazard and risk in tearing assembling construction open, does not have larger security reliability.Using entirety D beam connects and coordinates big coaster straight skidding, can guarantee that the stability in the large of D beam, saves working procedure it is ensured that open-minded on schedule.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Any modification, equivalent and improvement made within god and principle etc., should be included within the scope of the present invention.

Claims (1)

1. a kind of this line D beam entirety longitudinal shift construction method is it is characterised in that described line D beam entirety longitudinal shift construction method includes:
Step one, the outer preparation of point:
The first step, by sleeper replacement at the reinforcing of this line be steel sleeper;
Second step, in the range of the D beam vertical shift of this line cleaning D beam walk row of channels;
3rd step, prepare big coaster outside circuit, a steel sleeper placed by every big coaster, and big coaster is assorted sheeting caps, wood Wedge, crowbar;
4th step, hydraulic jack is transported in advance circuit D beam two ends, D beam two ends are installed steel and shored, and install oil pipe and oil Pump, jack withstands steel and shores;
Operation in step 2, point:
The first step, upper installation connect steel sleeper above former D beam hardened link;It is specially artificial sliding greatly by D beam two ends lift pendulum respectively Car in circuit, steel sleeper lift is put to big coaster, is promoted big coaster respectively to specified location, the urgent big coaster of timber wedge walk wheel, Fixed lateral position, connection steel sleeper, fastening bracket;
Second step, D beam two ends steel shore lower section install hydraulic jack, overall jack-up D beam, make D beam bottom be higher than flange of rail steel sleeper, Space plug sheeting caps between big coaster and steel sleeper, wheel walked by the urgent big coaster of timber wedge;
3rd step, remove big coaster and walk timber wedge at wheel, promote big coaster simultaneously, position is reinforced in D beam vertical shift to this line, timber wedge is beaten Tightly wheel walked by big coaster;
4th step, falling D beam;It is specially and shores lower section installation hydraulic jack, overall jack-up D beam in D beam two ends steel, make to slide greatly Car does not stress, and will extract out, fall jack after rise, make D beam integrally drop down onto D beam-ends requirement position big coaster steel sleeper above circuit, Remove steel sleeper above circuit, reinforcement by connection D beam.
CN201510036765.5A 2015-01-24 2015-01-24 Existing line D beam overall longitudinally-moving construction method Expired - Fee Related CN104612004B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510036765.5A CN104612004B (en) 2015-01-24 2015-01-24 Existing line D beam overall longitudinally-moving construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510036765.5A CN104612004B (en) 2015-01-24 2015-01-24 Existing line D beam overall longitudinally-moving construction method

Publications (2)

Publication Number Publication Date
CN104612004A CN104612004A (en) 2015-05-13
CN104612004B true CN104612004B (en) 2017-02-22

Family

ID=53146633

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510036765.5A Expired - Fee Related CN104612004B (en) 2015-01-24 2015-01-24 Existing line D beam overall longitudinally-moving construction method

Country Status (1)

Country Link
CN (1) CN104612004B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113897822A (en) * 2021-11-13 2022-01-07 大同市陆宏铁路建设有限公司 Transverse and longitudinal moving device for construction based on D-shaped temporary beam and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line
CN102839578A (en) * 2012-08-30 2012-12-26 中铁十局集团有限公司 Construction method for manually longitudinally moving temporary beam in reinforcing multi-track line by use of D type temporary beam
CN202705829U (en) * 2012-08-30 2013-01-30 中铁十局集团有限公司 Convenient beam slider for manually and longitudinally moving D-shaped convenient beam
CN104213512A (en) * 2014-09-24 2014-12-17 中铁六局集团有限公司 Integrated trolley for transporting and erecting D beams of railway and method for mounting D beams

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101963061A (en) * 2010-10-19 2011-02-02 浙江省建工集团有限责任公司 Construction method for underground box culvert of existing railway line
CN102839578A (en) * 2012-08-30 2012-12-26 中铁十局集团有限公司 Construction method for manually longitudinally moving temporary beam in reinforcing multi-track line by use of D type temporary beam
CN202705829U (en) * 2012-08-30 2013-01-30 中铁十局集团有限公司 Convenient beam slider for manually and longitudinally moving D-shaped convenient beam
CN104213512A (en) * 2014-09-24 2014-12-17 中铁六局集团有限公司 Integrated trolley for transporting and erecting D beams of railway and method for mounting D beams

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
营业线D梁便梁纵移、横移施工方法;徐幼成;《上海铁道科技》;20111225(第4期);第2页,2.2.3.2 *

Also Published As

Publication number Publication date
CN104612004A (en) 2015-05-13

Similar Documents

Publication Publication Date Title
CN103938538B (en) Railroad bridge evacuation platform
US6684793B2 (en) Viaduct for a railway line or the like
CN104563158B (en) Existing subway station realizes the construction method of transfer with new subway station platform layer
CN104631345A (en) Rapid replacing method of concrete bridge beam of dual-line electric railway
KR101269868B1 (en) A method for bridge improving
CN104612004B (en) Existing line D beam overall longitudinally-moving construction method
KR101872265B1 (en) Eco Mega Lighting system
CN204825527U (en) Construction structures is moved to whole indulging of this line D roof beam
CN110055894A (en) A kind of flow type bridge erecting machine and its heavy grade erecting beam construction method
CN203321529U (en) Train type rapid lifting and folding work platform for tunnel engineering
KR101187282B1 (en) Railway bridge constructing method using 2 post type abutment structure
KR101234090B1 (en) Method for changing girder of railway plate girder bridge
CN112048952A (en) Ballastless track breaking and outward transportation construction method for high-speed rail operation line
KR20100021874A (en) Method for removing, installing and replacing an upper structure of bridge, and lifting apparatus and transportation vehicle of the upper structure of bridge for the method
CN203741723U (en) Automatic traveling type movable formwork used for bridge construction
CN213772957U (en) Artificial longitudinal moving stool beam device
CN105603878B (en) A kind of quick method for traversing in concrete box girder high-altitude
CN110626943B (en) Special chassis of inverted gantry crane for single-line T-beam bridge and mounting method
CN215104790U (en) Reinforced structure for existing railway underpass frame bridge construction
CN104164838A (en) Light combined type beam moving trolley
CN103726449A (en) Automatic beam placement platform device and construction method of replacing railway beams thereby
JP7368685B2 (en) Bridge reconstruction method and bridge superstructure
KR100638578B1 (en) Method for carrying out replacement of an upper structure of a railway bridge
CN107143336A (en) A kind of road constructing structure against the wind with shield synchronous construction rail
CN107447672B (en) The construction method of jacking babinet under a kind of hump line

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170222

Termination date: 20190124

CF01 Termination of patent right due to non-payment of annual fee