CN104563767A - Process method for mounting glass extending and contracting structure on wall body - Google Patents

Process method for mounting glass extending and contracting structure on wall body Download PDF

Info

Publication number
CN104563767A
CN104563767A CN201410835327.0A CN201410835327A CN104563767A CN 104563767 A CN104563767 A CN 104563767A CN 201410835327 A CN201410835327 A CN 201410835327A CN 104563767 A CN104563767 A CN 104563767A
Authority
CN
China
Prior art keywords
glass
adhesive tape
faced adhesive
wall
double faced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410835327.0A
Other languages
Chinese (zh)
Other versions
CN104563767B (en
Inventor
徐国俭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Shanghai Architectural Decoration Engineering Co ltd
Original Assignee
SHANGHAI JUTONG DECORATION GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI JUTONG DECORATION GROUP Co Ltd filed Critical SHANGHAI JUTONG DECORATION GROUP Co Ltd
Priority to CN201410835327.0A priority Critical patent/CN104563767B/en
Publication of CN104563767A publication Critical patent/CN104563767A/en
Application granted granted Critical
Publication of CN104563767B publication Critical patent/CN104563767B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a process method for mounting a glass extending and contracting structure on a wall body. The process method is characterized in that one side of the mounting position of glass (4) is coated with a cement mortar layer (2); after the cement mortar layer (2) is solidified, a double-faced adhesive tape (6) is adhered to the inner surface of the cement mortar layer (2); one edge of the head of the glass (4) is adhered to the double-faced adhesive tape (6), a gap is reserved between the head of the glass (4) and the wall body (1), and a double-faced adhesive tape (7) is adhere to the other edge of the glass (4) in the vertical direction; or the double-faced adhesive tape (7) is adhere to one edge of the glass (4) in the vertical direction, the other edge of the head is adhered to the double-faced adhesive tape (6), and the gap is reserved between the head of the glass (4) and the wall body (1); the glass (4) is fixedly arranged in an interlayer between the cement mortar layer (2) and cement mortar (3) at a contracting opening (5) by using the cement mortar (3). By virtue of the gap which has an extending and contracting function to prevent heat expansion and cold contraction, the impact resistance is improved, the process is simplified, and the labor cost and the material cost are reduced.

Description

The process of mounting glass stretching structure on a kind of body of wall
Technical field
The invention discloses the process of mounting glass stretching structure on a kind of body of wall, belong to building decoration field.
Background technology
In upholstery process, when glass is installed to body of wall, the general aluminum alloy frame that adopts is fixed, and activities is more.
Aluminium alloy glass French window flow of installation is: establish installation fixing piece → frame on reference for installation and position → inspections subsidy diaphragm → frame enter hole adjustment locate → fix → fill jointing material with body of wall.
Aluminium alloy glass French window construction method of installation and main points:
Establish benchmark: find out installed height mark, mark the position in vertical, horizon and turnover direction, eject the line of ink marker if desired; Establish stator elevation location, reject when needing and plaster to deck, forbid that frame enters row rejecting again behind hole.
Visual inspection: inspection hatch is with or without damage phenomenon again, diaphragm comes off position with or without drawing, abrading, and as found, section bar has situations such as snapping, break, must not install wall.
Connect fastening means: material and the selecting of installation fitting of aluminium alloy glass French window must meet design and code requirement (expansion bolt >=8*65mm, nailing >=3.7*42mm, pulling-on piece >=140*20*1.5mm).The selection of tie point fastening means according to the difference of aluminium alloy glass French window pattern and residing installation site situation, should be determined according to installation contact plan.Aluminium alloy glass French window and wall connecting can adopt expansion bolt and stator.When adopting expansion bolt (directly connecting), electricity consumption is drilled on post and wall and holes, and then fills in expansion bolt, and tight a bolt and be fixed in wall hole, bolt exposed parts loads onto block after should smearing fluid sealant.Stator M4 × 20 recessed pan head tapping screw and window frame are fixed, the installation site of elementary gate window frame expansion bolt or stator, except special indicating, all apart from termination (or middle) 150-200mm, and spacing≤600mm configuration.
Frame enters hole: determine window frame upper and lower, inside and outside towards, frame corner and horizontal frame position pad jam-pack, lower frame long with 900mm time, central authorities also use pad jam-pack.
Adjustment location: vertical, level, the squareness of adjustment window frame and the installation site in thickness of wall body direction, hole, allow to meet following provisions: the two diagonal difference ± 3mm positive lateral vertical degree ± monolateral gap≤5mm in 2mm levelness ± 3mm frame hole (metope of plastering).
Fix with body of wall: be directly connected with aluminium alloy glass French window dedicated expansion screw bolt, all must not be fixed on brickwork joint place.As connected with stator, select different methods of attachment according to material difference.
Dress combined aluminium glass alloy French window ingredient: jointing material steel lining imbeds reserved opening, then fixes, if need connect with stator without this hole with the fine-stone concrete pouring that strength grade is C20.Ingredient and window frame clamp the two-way tension of rear securing member, the sealant sealing process of securing member termination.
Fill gap: adopt the gap between polyurethane (polystyrene) blowing agent filling window frame and hole, filling recession, except temporary fixed cushion block, is mended and is filled out its position.Excessive blowing agent can be removed after 30 minutes.
Plaster inside hole: between the window frame inside hole with cement mortar or hemp cut lime floating, floated coat and window frame separate by easy employing sheet material temporarily, and its thickness should be less than 3mm, and the face of plastering exceeds window frame edge, highly should be less than 5mm, after floated coat sclerosis, remove sheet material.
Cleaning mortar: cement is by wet cloth wiped clean before its sclerosis, and frame table face scraped by not handy hard material shovel.
Remove pad pasting wallpaper cutter outside first diaphragm and window frame and remove diaphragm, should avoid scratching section bar.
Filleting plays glue: use the gap with hole outside construction sealant pointing frame, require that closely knit smooth width is even, form the gradient.Fluid sealant process should be used between jointing material and window frame.
Glaze (sash): indoor glass cannot be entered from staircase and should look job site situation employing lifting handling facility.In window, be transported into room in advance place vertically, carry out protection work.Four limits of glass are encased inside the glass gasket of different-thickness, and frame cushion block PVC glue is fixed, and glass press strip is fixed.
Dress hardware: the attachment screw of door-window lockset is reliably connected with steel lining, and position is correct.
Removing surface: do glass surface, frame fan surface hygiene, remove the protection pad pasting of remainder.
Indoor filleting plays glue: require higher situation for insulation, sound insulation class, seal inside hole and between window frame with construction sealant.
Summary of the invention
Glass is being embedded cement mortar layer by the present invention, fixes with double faced adhesive tape, and the sponge cover glass simultaneously on double faced adhesive tape, forms shock proof buffering, leave gap in the junction of glass and body of wall, impacts when glass receives or leaves cushion space when expanding with heat and contract with cold.Process of the present invention has Telescopic, prevents the gap of expanding with heat and contract with cold, and improves shock resistance, Simplified flowsheet, saves artificial and material.
A process for mounting glass stretching structure on body of wall, is characterized in that: the step of the process of described structure is:
1) on the body of wall face of body of wall 1 glass to be installed, cement sand bed 2 is smeared in the side of glass 4;
2) after cement sand bed 2 solidifies, at described cement sand bed 2 inner surface bonding double faced adhesive tape 6;
3) by glass 4 head while be attached on double faced adhesive tape 6, glass 4 head and body of wall 1 leave gap, glass 4 another side in the vertical direction sticks double faced adhesive tape 7, or again by head another side be attached to double faced adhesive tape 6 on after by glass 4, in the vertical direction sticks double faced adhesive tape 7 on one side, glass 4 head and body of wall 1 leave gap;
4) in closing in 5 place cement mortar 3, glass 4 is fixed in the interlayer of cement sand bed 2 and cement sand bed 3.
The thickness of described glass 4 is not less than 8mm.
The width of described double faced adhesive tape 6 and double faced adhesive tape 7 is 2cm, and thickness is 0.25cm.
Described gap is 2mm ~ 15mm.
When body of wall 1 there being cement mortar layer, also comprise the step struck off by cement mortar layer.
Before cement mortar 3 is solidified, glass 4 is arranged on after on double faced adhesive tape 6, and on glass 4, also erection has for stationary device.
Accompanying drawing explanation
Fig. 1 is the process mounting structure figure of mounting glass stretching structure on a kind of body of wall;
Fig. 2 is the process step 2 of mounting glass stretching structure on a kind of body of wall) mounting structure figure;
Fig. 3 is the process step 3 of mounting glass stretching structure on a kind of body of wall) mounting structure figure.
Specific embodiments
Illustrate below in conjunction with embodiment
Embodiment 1: get the thick glass of 8mm 4, the width of double faced adhesive tape 6 and double faced adhesive tape 7 is 2cm, and thickness is 0.25cm.On the body of wall face of body of wall 1 glass to be installed, the side smearing thickness of glass 4 is the cement sand bed 2 of 25mm, after cement sand bed 2 solidifies, at described cement sand bed 2 inner surface bonding double faced adhesive tape 6; By glass 4 head while be attached on double faced adhesive tape 6, glass 4 head and body of wall 1 leave gap, glass 4 another side in the vertical direction sticks double faced adhesive tape 7, or again by head another side be attached to double faced adhesive tape 6 on after by glass 4, in the vertical direction sticks double faced adhesive tape 7 on one side, glass 4 head and body of wall 1 leave the gap of 3mm; Glass 4 is fixed in the interlayer of cement sand bed 2 and cement sand bed 3 by the cement mortar 3 being 25mm at closing in 5 place thickness.Before cement mortar 3 is solidified, glass 4 is arranged on after on double faced adhesive tape 6, glass 4 sets up the fastening devices with mat.
Embodiment 2: get the thick glass of 10mm 4, the width of double faced adhesive tape 6 and double faced adhesive tape 7 is 2cm, and thickness is 0.25cm.Scraped off by cement sand bed original on body of wall 1, on the body of wall face of body of wall 1 glass to be installed, the side smearing thickness of glass 4 is the cement sand bed 2 of 25mm, after cement sand bed 2 solidifies, at described cement sand bed 2 inner surface bonding double faced adhesive tape 6; By glass 4 head while be attached on double faced adhesive tape 6, glass 4 head and body of wall 1 leave gap, glass 4 another side in the vertical direction sticks double faced adhesive tape 7, or again by head another side be attached to double faced adhesive tape 6 on after by glass 4, in the vertical direction sticks double faced adhesive tape 7 on one side, glass 4 head and body of wall 1 leave the gap of 5mm; Glass 4 is fixed in the interlayer of cement sand bed 2 and cement sand bed 3 by the cement mortar 3 being 25mm at closing in 5 place thickness.Before cement mortar 3 is solidified, glass 4 is arranged on after on double faced adhesive tape 6, glass 4 sets up the fastening devices with mat.

Claims (6)

1. the process of mounting glass stretching structure on body of wall, is characterized in that: the step of the process of described structure is:
1) on the body of wall face of body of wall (1) glass to be installed, cement sand bed (2) is smeared in the side of glass (4);
2) after cement sand bed (2) solidifies, at described cement sand bed (2) inner surface bonding double faced adhesive tape (6);
3) by glass (4) head while be attached on double faced adhesive tape (6), glass (4) head and body of wall (1) leave gap, glass (4) another side in the vertical direction sticks double faced adhesive tape (7), or be attached to by head another side on double faced adhesive tape (6) after by glass (4), in the vertical direction sticks double faced adhesive tape (7) on one side, glass (4) head and body of wall (1) leave gap again;
4) in closing in (5) place cement mortar (3), glass (4) is fixed in the interlayer of cement sand bed (2) and cement sand bed (3).
2. the process of mounting glass stretching structure on a kind of body of wall according to claim 1, is characterized in that: the thickness of described glass (4) is not less than 8mm.
3. the process of mounting glass stretching structure on a kind of body of wall according to claim 1, is characterized in that: the width of described double faced adhesive tape (6) and double faced adhesive tape (7) is 2cm, and thickness is 0.25cm.
4. the process of mounting glass stretching structure on a kind of body of wall according to claim 1, is characterized in that: described gap is 2mm ~ 15mm.
5. the process of mounting glass stretching structure on a kind of body of wall according to claim 1, is characterized in that: when body of wall (1) there being cement mortar layer, also comprise the step struck off by cement mortar layer.
6. according to the process of mounting glass stretching structure on the arbitrary described a kind of body of wall of Claims 1 to 5, it is characterized in that: before cement mortar (3) is solidified, glass (4) is arranged on after on double faced adhesive tape (6), and on glass (4), also erection has for stationary device.
CN201410835327.0A 2014-12-23 2014-12-23 The process of mounting glass stretching structure on a kind of body of wall Active CN104563767B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410835327.0A CN104563767B (en) 2014-12-23 2014-12-23 The process of mounting glass stretching structure on a kind of body of wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410835327.0A CN104563767B (en) 2014-12-23 2014-12-23 The process of mounting glass stretching structure on a kind of body of wall

Publications (2)

Publication Number Publication Date
CN104563767A true CN104563767A (en) 2015-04-29
CN104563767B CN104563767B (en) 2016-03-30

Family

ID=53080755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410835327.0A Active CN104563767B (en) 2014-12-23 2014-12-23 The process of mounting glass stretching structure on a kind of body of wall

Country Status (1)

Country Link
CN (1) CN104563767B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001014680A1 (en) * 1999-08-20 2001-03-01 Dorma Gmbh + Co. Kg Point fitting for insulating glass panes
CN102102477A (en) * 2009-12-22 2011-06-22 浙江华悦木业有限公司 Combined installation method for door panel products
EP2476852A2 (en) * 2011-01-14 2012-07-18 GEZE GmbH Assembly aid for a leaf of a door, window or the like
EP2525039A2 (en) * 2011-05-18 2012-11-21 Smits Gemert B.V. Glass-frame-combination as well as window and door provided with the glass-frame-combination
CN203035016U (en) * 2013-01-15 2013-07-03 刘春梅 Novel bonding structure for metro shielding door body and glass panel
CN103527043A (en) * 2013-10-28 2014-01-22 北京北玻安全玻璃有限公司 Method of bonding glass and stainless steel profile frame

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2001014680A1 (en) * 1999-08-20 2001-03-01 Dorma Gmbh + Co. Kg Point fitting for insulating glass panes
CN102102477A (en) * 2009-12-22 2011-06-22 浙江华悦木业有限公司 Combined installation method for door panel products
EP2476852A2 (en) * 2011-01-14 2012-07-18 GEZE GmbH Assembly aid for a leaf of a door, window or the like
EP2525039A2 (en) * 2011-05-18 2012-11-21 Smits Gemert B.V. Glass-frame-combination as well as window and door provided with the glass-frame-combination
CN203035016U (en) * 2013-01-15 2013-07-03 刘春梅 Novel bonding structure for metro shielding door body and glass panel
CN103527043A (en) * 2013-10-28 2014-01-22 北京北玻安全玻璃有限公司 Method of bonding glass and stainless steel profile frame

Also Published As

Publication number Publication date
CN104563767B (en) 2016-03-30

Similar Documents

Publication Publication Date Title
US10352040B1 (en) Casing bead control joint
CA2906557C (en) Facade structure
CN106193499B (en) Anchoring and supporting structure of composite heat-insulation integrated plate and process method
CN106284706A (en) The construction method of external wall outer insulation rock cotton board
CN113186985B (en) Anti-seepage treatment method for basement bottom plate construction joint
CN106988440B (en) Waterproof structure for main body and auxiliary interface of subway station and construction method of waterproof structure
CN104499614B (en) Wall heat-preservation integration point hanging system and mounting method thereof
CN104563767B (en) The process of mounting glass stretching structure on a kind of body of wall
CN111910842A (en) Anti-aging rigid waterproof layer separation seam layered fine-work construction process
CN111851896B (en) Construction method of heat-preservation decoration sintering integrated plate of building external wall
CN203441260U (en) Auxiliary steel frame system
KR101654781B1 (en) Moisture exhaust induction waterproof system and method of the structure
CN204225324U (en) Wall thermal insulating integration point extension system
CN110847757A (en) Sliding type windowsill flashing structure and installation method thereof
CN110424575A (en) Construction method for building exterior wall heat preserving integrated system
CN213626486U (en) Node structure of joint of wood floor and floor tile floor
CN210621967U (en) Shower room manger plate structure of mating formation
CN211286636U (en) Riser pipe hanger construction structures
CN216075804U (en) Closing-in structure of bathroom platform and curtain wall
CN214195340U (en) Heat-insulating decorative composite board
CN216740147U (en) External thermal insulation system for external wall of expanded and vitrified small ball thermal insulation board
CN101570990A (en) Cast-in-situ concrete heat-insulation wall
CN209353585U (en) A kind of interim whole drain structure of roofing
CN116905747A (en) External wall heat preservation construction method
CN117513690A (en) Indoor internal corner embedded treatment structure and construction method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20230508

Address after: Room 318, Building 8, No. 68 Dongheyan, Chengqiao Town, Chongming District, Shanghai, 202150 (Shanghai Chengqiao Economic Development Zone)

Patentee after: Shanghai Shanghai Architectural Decoration Engineering Co.,Ltd.

Address before: 200126, No. 2A, Shanggang San Village, Pudong New Area, Shanghai

Patentee before: SHANGHAI JUTONG DECORATION GROUP Co.,Ltd.