CN104533132A - 一种10kV电线杆线路防风拉线结构 - Google Patents
一种10kV电线杆线路防风拉线结构 Download PDFInfo
- Publication number
- CN104533132A CN104533132A CN201510007487.0A CN201510007487A CN104533132A CN 104533132 A CN104533132 A CN 104533132A CN 201510007487 A CN201510007487 A CN 201510007487A CN 104533132 A CN104533132 A CN 104533132A
- Authority
- CN
- China
- Prior art keywords
- stay wire
- electric pole
- fixed
- hanging ring
- bracing wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/20—Side-supporting means therefor, e.g. using guy ropes or struts
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
本发明公开了一种10kV电线杆线路防风拉线结构,包括固定在电线杆的杆体上的U型挂环,所述U型挂环上均衡通过多个拉线组件与地面连接固定;所述U型挂环由与杆体固定的抱箍以及环绕抱箍设置的挂环组成,所述抱箍外表设有多个支撑叶片,挂环依次穿过支撑叶片固定。采用麻绳带U型挂环固定,防止振荡碰及带电部位,U型挂环安装完毕后人员立即下杆,使用紧线器收紧拉线,受力均匀后组装拉线UT,简化优化了带电打拉线的施工作业流程,保证了施工作业的安全。通过上述措施能够改善配电网目前电杆自然土基础占比较大、打拉线占比较小的现状,提高基础抗倾覆能力,提高电杆抗弯能力,减少因台风等恶劣天气造成的大面积倒、断杆的现象。
Description
技术领域
本发明涉及一种电线杆给的加固结构,尤其是一种用于10kV线路的电线杆防风结构。
背景技术
沿海地区海岸线较长,易受台风、雷暴等极端天气影响。同时由于土质多为冲积层淤泥,土质差,通常内陆使用的自然土基础和卡盘等方法无法提供足够抗倾覆弯矩。针对沿海地区配电网现状还存在抗风能力不足的普遍问题(旧式设计的抗风能力是25米/秒),有必要开展专题研究,用最佳的经济成本效益在短时间内快速提高配电网的抗风能力(设计抗风能力达到35米/秒以上)。
发明内容
本发明的目的是提供一种10kV电线杆线路防风拉线结构,改善配电网目前电杆自然土基础占比较大、打拉线占比较小的现状,提高基础抗倾覆能力,提高电杆抗弯能力,减少因台风等恶劣天气造成的大面积倒、断杆的现象。
本发明是这样来实现上述目的的:
一种10kV电线杆线路防风拉线结构,包括固定在电线杆的杆体上的U型挂环,所述U型挂环上均衡通过多个拉线组件与地面连接固定;所述U型挂环由与杆体固定的抱箍以及环绕抱箍设置的挂环组成,所述抱箍外表设有多个支撑叶片,挂环依次穿过支撑叶片固定。
其中,所述U型挂环位于电线杆的下横担下方1米或以上。
其中,所述U型挂环由至少两弧形部首尾拼合而成,所述弧形部的抱箍外缘延伸设有连接板,相邻连接板之间通过螺栓固定。
其中,所述连接板与抱箍之间固定有增强板。
其中,所述拉线组件包括拉线板、楔形线夹、钢绞线、UT线夹、拉线棒以及拉线盘,所述拉线板与U型挂环中的挂环连接,拉线板、楔形线夹、钢绞线、UT线夹、拉线棒以及拉线盘依次首尾相连,拉线盘埋入地面。
本发明的有益效果是:无地形限制的砼杆,U型挂环安装在距离下横担1米处(10kV线路),采用麻绳带U型挂环固定,防止振荡碰及带电部位,U型挂环安装完毕后人员立即下杆,使用紧线器收紧拉线,受力均匀后组装拉线UT,简化优化了带电打拉线的施工作业流程,并通过作业表单固化来应用推广,保证了施工作业的安全。通过上述措施能够改善配电网目前电杆自然土基础占比较大、打拉线占比较小的现状,提高基础抗倾覆能力,提高电杆抗弯能力,减少因台风等恶劣天气造成的大面积倒、断杆的现象。
附图说明
下面结合附图和实施例对本发明进一步说明:
图1是本发明的结构示意图;
图2是U型挂环的主视图。
具体实施方式
参照图1及图2,一种10kV电线杆线路防风拉线结构,包括固定在电线杆的杆体上的U型挂环1,所述U型挂环1上均衡通过多个拉线组件与地面连接固定;所述U型挂环1由与杆体固定的抱箍2以及环绕抱箍2设置的挂环3组成,所述抱箍2外表设有多个支撑叶片4,挂环3依次穿过支撑叶片4固定。无地形限制的砼杆,U型挂环1安装在距离下横担1米处(10kV线路),采用麻绳带U型挂环1固定,防止振荡碰及带电部位,U型挂环1安装完毕后人员立即下杆,使用紧线器收紧拉线,受力均匀后组装拉线UT,简化优化了带电打拉线的施工作业流程,并通过作业表单固化来应用推广,保证了施工作业的安全。通过上述措施能够改善配电网目前电杆自然土基础占比较大、打拉线占比较小的现状,提高基础抗倾覆能力,提高电杆抗弯能力,减少因台风等恶劣天气造成的大面积倒、断杆的现象。
为了便于U型挂环1与电线杆进行固定,所述U型挂环1由至少两弧形部4首尾拼合而成,所述弧形部4的抱箍2外缘延伸设有连接板5,相邻连接板5之间通过螺栓固定。优选是采用两弧形部4首尾拼合,使用时只要将两弧形部4的两端通过螺栓固定即可,非常简单,能够实现快速安装。
由于弧形部4的抱箍2通过螺栓固定时会产生较大的拉力,为增加连接部位的强度,所述连接板5与抱箍2之间固定有增强板6。
其中所述拉线组件包括拉线板7、楔形线夹8、钢绞线9、UT线夹10、拉线棒11以及拉线盘12,所述拉线板7与U型挂环1中的挂环3连接,拉线板7、楔形线夹8、钢绞线9、UT线夹10、拉线棒11以及拉线盘12依次首尾相连,拉线盘12埋入地面。上述配件皆为现有电线杆拉线固定的常用配件,可直接在市场上购买获得。
下面,通过相关的实验数据来验证本发明结构所产生的实际效果。
以下是12米及15米砼杆打拉线及不打拉线的抗风能力比较
1、12米砼杆打拉线及不打拉线的比较
根据工程的气象条件、导线型号及安全系数、杆型的使用档距情况下:
不打拉线Z1C-12各关键点在控制工况条件下抗弯计算结果:
打拉线Z1C-12-2L各关键点在控制工况条件下抗弯计算结果:
由上表可以看出,不打拉线情况下杆身弯矩最大设计值为75.28KN*m, 打拉线情况下杆身弯矩最大设计值仅为56.39KN*m,比上者减少了25%,其断杆的风险大大减少。
2、15米砼杆打拉线及不打拉线的比较
不打拉线Z1C-15各关键点在控制工况条件下抗弯计算结果:
打拉线Z1C-15-2L各关键点在控制工况条件下抗弯计算结果:
由上表可以看出,不打拉线情况下杆身弯矩最大设计值为133.73KN*m, 打拉线情况下杆身弯矩最大设计值仅为104.83KN*m,比上者减少了23%,其断杆的风险大大减少。
以下是12米及15米砼杆拉线安装距离下横担0.1米及1米的抗风能力比较。
1、12米砼杆拉线安装距离下横担0.1米及1米的比较
根据工程的气象条件、导线型号及安全系数、杆型的使用档距情况下:
打拉线杆(距离下横担0.1米)Z1C-12-2L各关键点在控制工况条件下抗弯计算结果:
打拉线杆(距离下横担1米)Z1C-12-2L各关键点在控制工况条件下抗弯计算结果:
由上表可以看出,拉线距离下横担0.1米情况下杆身弯矩最大设计值为56.39KN*m, 拉线距离下横担1米情况下杆身弯矩最大设计值为58.42KN*m,两者只相差5%,砼杆弯矩变化不大。另外当拉线距离下横担0.1米时需要停电操作才能进行打拉线的工序,而当拉线距离下横担1米或以上时不需停电操作就能够进行打拉线的工序,相比而言后者操作更为简便、灵活。
2、15米砼杆拉线安装距离下横担0.1米及1米的比较
根据工程的气象条件、导线型号及安全系数、杆型的使用档距情况下:
打拉线杆(距离下横担0.1米)Z2Z-15-2L各关键点在控制工况条件下抗弯计算结果:
打拉线杆(距离下横担1米)Z2Z-15-2L各关键点在控制工况条件下抗弯计算结果:
由上表可以看出,拉线距离下横担0.1米情况下杆身弯矩最大设计值为104.83KN*m, 拉线距离下横担1米情况下杆身弯矩最大设计值为107.74KN*m,两者只相差4%,砼杆弯矩变化不大。另外当拉线距离下横担0.1米时需要停电操作才能进行打拉线的工序,而当拉线距离下横担1米或以上时不需停电操作就能够进行打拉线的工序,相比而言后者操作更为简便、灵活。
Claims (5)
1.一种10kV电线杆线路防风拉线结构,其特征在于:包括固定在电线杆的杆体上的U型挂环(1),所述U型挂环(1)上均衡通过多个拉线组件与地面连接固定;所述U型挂环(1)由与杆体固定的抱箍(2)以及环绕抱箍(2)设置的挂环(3)组成,所述抱箍(2)外表设有多个支撑叶片(4),挂环(3)依次穿过支撑叶片(4)固定。
2.根据权利要求1所述的一种10kV电线杆线路防风拉线结构,其特征在于:所述U型挂环(1)位于电线杆的下横担下方1米或以上。
3.根据权利要求1所述的一种10kV电线杆线路防风拉线结构,其特征在于:所述U型挂环(1)由至少两弧形部(4)首尾拼合而成,所述弧形部(4)的抱箍(2)外缘延伸设有连接板(5),相邻连接板(5)之间通过螺栓固定。
4.根据权利要求1所述的一种10kV电线杆线路防风拉线结构,其特征在于:所述连接板(5)与抱箍(2)之间固定有增强板(6)。
5.根据权利要求1所述的一种10kV电线杆线路防风拉线结构,其特征在于:所述拉线组件包括拉线板(7)、楔形线夹(8)、钢绞线(9)、UT线夹(10)、拉线棒(11)以及拉线盘(12),所述拉线板(7)与U型挂环(1)中的挂环(3)连接,拉线板(7)、楔形线夹(8)、钢绞线(9)、UT线夹(10)、拉线棒(11)以及拉线盘(12)依次首尾相连,拉线盘(12)埋入地面。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510007487.0A CN104533132B (zh) | 2015-01-08 | 2015-01-08 | 一种10kV电线杆线路防风拉线结构 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510007487.0A CN104533132B (zh) | 2015-01-08 | 2015-01-08 | 一种10kV电线杆线路防风拉线结构 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104533132A true CN104533132A (zh) | 2015-04-22 |
CN104533132B CN104533132B (zh) | 2017-08-04 |
Family
ID=52848739
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510007487.0A Active CN104533132B (zh) | 2015-01-08 | 2015-01-08 | 一种10kV电线杆线路防风拉线结构 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104533132B (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298205A (zh) * | 2015-11-30 | 2016-02-03 | 熊达煜 | 一种电网电线杆加固加高装置及其施工方法 |
CN106593070A (zh) * | 2016-11-10 | 2017-04-26 | 广东电网有限责任公司惠州供电局 | 用于10kV直线杆的抗风加固的方法和撑杆装置 |
CN106836941A (zh) * | 2017-03-08 | 2017-06-13 | 长葛市恒瑞电瓷电器有限公司 | 一种新型拉线下拔装置 |
CN107355121A (zh) * | 2017-08-24 | 2017-11-17 | 国网江苏省电力公司金湖县供电公司 | 便于监测的电线杆防锈拉线结构 |
CN109785725A (zh) * | 2019-03-18 | 2019-05-21 | 国网上海市电力公司 | 一种培训用模拟拉线盘装置 |
CN111075024A (zh) * | 2020-01-16 | 2020-04-28 | 广东省建筑构件工程有限公司 | 一种飞碟建筑钢梁安装结构及其施工方法 |
CN112012890A (zh) * | 2019-05-29 | 2020-12-01 | 北京金风科创风电设备有限公司 | 连接组件、拉索式塔架以及风力发电机组 |
CN112360221A (zh) * | 2020-11-11 | 2021-02-12 | 国网安徽省电力有限公司安庆供电公司 | 线路砼杆全方位抗倾稳定性检测系统及检测方法 |
CN114123081A (zh) * | 2021-11-02 | 2022-03-01 | 国网福建省电力有限公司电力科学研究院 | 适用于10kV配电线路杆塔的防风紧固拉线装置及安装方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2765982Y (zh) * | 2004-12-13 | 2006-03-22 | 徐尚仁 | 电杆柱防攀登防盗线抱箍架 |
JP2009287229A (ja) * | 2008-05-28 | 2009-12-10 | Chugoku Electric Power Co Inc:The | 支柱の支持構造 |
CN203097401U (zh) * | 2012-12-14 | 2013-07-31 | 国家电网公司 | 220千伏猫头塔防风侧拉结构 |
CN203201221U (zh) * | 2012-11-05 | 2013-09-18 | 重庆市电力公司永川供电局 | 防倒杆装置 |
CN103545778A (zh) * | 2013-10-30 | 2014-01-29 | 国家电网公司 | 复合功能异型抱箍 |
CN204510990U (zh) * | 2015-01-08 | 2015-07-29 | 广东电网有限责任公司江门台山供电局 | 一种10kV电线杆线路防风拉线结构 |
-
2015
- 2015-01-08 CN CN201510007487.0A patent/CN104533132B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2765982Y (zh) * | 2004-12-13 | 2006-03-22 | 徐尚仁 | 电杆柱防攀登防盗线抱箍架 |
JP2009287229A (ja) * | 2008-05-28 | 2009-12-10 | Chugoku Electric Power Co Inc:The | 支柱の支持構造 |
CN203201221U (zh) * | 2012-11-05 | 2013-09-18 | 重庆市电力公司永川供电局 | 防倒杆装置 |
CN203097401U (zh) * | 2012-12-14 | 2013-07-31 | 国家电网公司 | 220千伏猫头塔防风侧拉结构 |
CN103545778A (zh) * | 2013-10-30 | 2014-01-29 | 国家电网公司 | 复合功能异型抱箍 |
CN204510990U (zh) * | 2015-01-08 | 2015-07-29 | 广东电网有限责任公司江门台山供电局 | 一种10kV电线杆线路防风拉线结构 |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105298205A (zh) * | 2015-11-30 | 2016-02-03 | 熊达煜 | 一种电网电线杆加固加高装置及其施工方法 |
CN105298205B (zh) * | 2015-11-30 | 2017-09-19 | 国网山东省电力公司枣庄供电公司 | 一种电网电线杆加固加高装置及其施工方法 |
CN106593070A (zh) * | 2016-11-10 | 2017-04-26 | 广东电网有限责任公司惠州供电局 | 用于10kV直线杆的抗风加固的方法和撑杆装置 |
CN106836941A (zh) * | 2017-03-08 | 2017-06-13 | 长葛市恒瑞电瓷电器有限公司 | 一种新型拉线下拔装置 |
CN107355121A (zh) * | 2017-08-24 | 2017-11-17 | 国网江苏省电力公司金湖县供电公司 | 便于监测的电线杆防锈拉线结构 |
CN109785725A (zh) * | 2019-03-18 | 2019-05-21 | 国网上海市电力公司 | 一种培训用模拟拉线盘装置 |
CN112012890A (zh) * | 2019-05-29 | 2020-12-01 | 北京金风科创风电设备有限公司 | 连接组件、拉索式塔架以及风力发电机组 |
CN112012890B (zh) * | 2019-05-29 | 2022-07-05 | 北京金风科创风电设备有限公司 | 连接组件、拉索式塔架以及风力发电机组 |
CN111075024A (zh) * | 2020-01-16 | 2020-04-28 | 广东省建筑构件工程有限公司 | 一种飞碟建筑钢梁安装结构及其施工方法 |
CN112360221A (zh) * | 2020-11-11 | 2021-02-12 | 国网安徽省电力有限公司安庆供电公司 | 线路砼杆全方位抗倾稳定性检测系统及检测方法 |
CN112360221B (zh) * | 2020-11-11 | 2021-09-21 | 国网安徽省电力有限公司安庆供电公司 | 线路砼杆全方位抗倾稳定性检测系统及检测方法 |
CN114123081A (zh) * | 2021-11-02 | 2022-03-01 | 国网福建省电力有限公司电力科学研究院 | 适用于10kV配电线路杆塔的防风紧固拉线装置及安装方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104533132B (zh) | 2017-08-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104533132A (zh) | 一种10kV电线杆线路防风拉线结构 | |
US8307593B2 (en) | Tower with adapter section | |
CN201671391U (zh) | 轻型线路抢修塔 | |
CN204510990U (zh) | 一种10kV电线杆线路防风拉线结构 | |
CN206401811U (zh) | 一种跨越带电线路架线施工的跨越网 | |
EP3916220A1 (en) | Tower arrangement for a wind turbine, wind turbine comprising the tower arrangement and method for erecting a wind turbine | |
CN205046927U (zh) | 改进型配网架空线路防风拉线装置 | |
CN216489661U (zh) | 适用于10kV配电线路杆塔的防风紧固拉线装置 | |
CN218920362U (zh) | 一种山地柔性光伏支架 | |
CN208266866U (zh) | 一种抗风稳固型拉线地锚 | |
CN218030450U (zh) | 拉索式风电塔筒 | |
CN103840396A (zh) | 一种高压铁塔更换避雷线的方法 | |
CN105089325A (zh) | 改进型配网架空线路防风拉线装置 | |
CN202543803U (zh) | 一种钢绞线成品拉索 | |
CN208966123U (zh) | 一种大截面格构式钢管抱杆正装提升装置 | |
CN212376389U (zh) | 一种110kV鼓型双回路复合横担塔 | |
CN210041128U (zh) | 一种带电跨越的绝缘滚杠 | |
CN212223581U (zh) | 一种基于光伏发电的桥梁主梁结构 | |
CN111622576A (zh) | 一种高强度金属电力杆塔结构及架设方法 | |
CN202906300U (zh) | 绝缘独脚梯 | |
CN204858475U (zh) | 一种防输电线路反光膜的倒刺机构 | |
CN205259191U (zh) | 平衡力均布的鱼腹式平衡梁 | |
CN201459604U (zh) | 一种适用于钢箱梁悬索桥施工中主缆间的横撑结构 | |
CN206293856U (zh) | 一种铜合金绞线用张线夹 | |
CN221283072U (zh) | 一种光伏支架及光伏设备 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |