CN104532787A - Earth retaining method for rear shore connection of high-pile beam-slab wharf - Google Patents

Earth retaining method for rear shore connection of high-pile beam-slab wharf Download PDF

Info

Publication number
CN104532787A
CN104532787A CN201510006353.7A CN201510006353A CN104532787A CN 104532787 A CN104532787 A CN 104532787A CN 201510006353 A CN201510006353 A CN 201510006353A CN 104532787 A CN104532787 A CN 104532787A
Authority
CN
China
Prior art keywords
wharf
earth retaining
girder
slab
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510006353.7A
Other languages
Chinese (zh)
Other versions
CN104532787B (en
Inventor
顾列平
姜仁萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Shipbuilding NDRI Engineering Co Ltd
Original Assignee
China Shipbuilding NDRI Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Shipbuilding NDRI Engineering Co Ltd filed Critical China Shipbuilding NDRI Engineering Co Ltd
Priority to CN201510006353.7A priority Critical patent/CN104532787B/en
Publication of CN104532787A publication Critical patent/CN104532787A/en
Application granted granted Critical
Publication of CN104532787B publication Critical patent/CN104532787B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/06Moles; Piers; Quays; Quay walls; Groynes; Breakwaters ; Wave dissipating walls; Quay equipment
    • E02B3/068Landing stages for vessels

Abstract

The invention discloses an earth retaining method for rear shore connection of a high-pile beam-slab wharf. The earth retaining method is characterized in that a cantilever beam is arranged below a cross beam at the rear edge of the high-pile beam-slab wharf, an edge longitudinal beam, the cross beam and the cantilever beam form a supporting structure for arranging an earth retaining board, and then earth retaining for rear shore connection of the high-pile beam-slab wharf is achieved; the earth retaining board is of a prefabricated or cast-in-situ continuous wall structure and is connected with the edge longitudinal beam, the cross beam and the cantilever beam through reinforced concrete; the upper end of the cantilever beam is connected with the cross beam through reinforced concrete, and the lower end of the cantilever beam and the earth retaining board are inserted into earth. Compared with the prior art, the earth retaining method has the advantages that under the condition that the use function and structural strength of the wharf are not influenced, the project quantity is reduced, and construction is simplified; the structural weight and resisting horizontal force of wharf project facilities are fully utilized, so that the structural form of an independent earth retaining wall in the rear of the high-pile wharf is broken through, the earth excavation quantity and concrete use quantity are reduced, and the project cost is lowered.

Description

A kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank
Technical field
The present invention relates to harbour and port infrastructure, especially a kind of gear indigenous method utilizing the high-piled slab & girder wharf rear of harbour infrastructure to connect bank.
Background technology
In the long piled wharf connecing bank, in order to reduce dock structure width and with being connected of bank, usually adopt various independent soil-baffling structure to realize.Independent soil-baffling structure can adopt gravity, half gravity retaining wall according to ground soil property situation, sometimes also can adopt cantilevered, counterfort retaining wall, or adopts sheet pile wall, after high pile pier structure, the most generally arrange the short retaining wall of various gravity.Long piled wharf generally adopts under soft base condition, ground top layer is made up of sedimentary soil in modern times, and hardpan position is lower, and topsoil is relatively soft, gravity retaining wall, the frictional force relying on the weight of wall body and base plate etc. to produce prevent body of wall from sliding, in order to there be larger friction factor, require higher to soil property, as needed medium solid ground, in order to there be enough weight, need add big-wall body and base plate, consumptive material is many, and excavated volume is large.Sheet-pile retaining wall, be useful on soft foundation, sheet pile wall can select steel sheet pile, reinforced concrete sheet pile or diaphragm wall etc., these self expenses of wall body are all higher, particularly ground soil property is soft, for ensureing that sheet pile wall is stablized, the degree of depth that sheet pile wall inserts the soil body is comparatively dark, or increases anchorage structures after wall.Self expense of wall body is just higher, and construction approach facility is many, and excavated volume is large.As adopted anchor rod retaining wall, because will construct wall rear anchor pole, anchor pole is laid in Xu You place, rear, and excavated volume is large.
The retaining wall structure of prior art fails to utilize the engineering services bases such as harbour can bear the function of soil pressure, causes the wasting of resources and increases the duration.
Summary of the invention
A kind of high-piled slab & girder wharf rear that the object of the invention is to provide for prior art deficiency connects the gear indigenous method of bank, after utilizing high-piled slab & girder wharf, edge indulges, crossbeam is supported retaining plated construction, realize the gear soil object that high-piled slab & girder wharf rear connects bank, engineering quantity is reduced when not affecting harbour using function and structural strength, simplify construction, make full use of deadweight and the opposing horizontal force of Wharf Engineering facility self structure, thus effectively change the independent retaining wall structure form at long piled wharf rear, there is easy construction, duration is short, decrease earthwork excavated volume and concrete use amount, reduce construction costs.
The object of the present invention is achieved like this: a kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank, comprise the high-piled slab & girder wharf of limit longitudinal and cross beam structure, after being characterized in utilizing high-piled slab & girder wharf edge crossbeam under semi girder is set, and with limit longeron, crossbeam and semi girder, the method for breast boards is set for braced structures, realize the gear soil that high-piled slab & girder wharf rear connects bank; Described breast boards is prefabricated or cast-in-place diaphragm wall structure and is that steel concrete is connected with limit longeron, crossbeam and semi girder; Described semi girder upper end and crossbeam are that steel concrete is connected, and its lower end and breast boards insert the soil body.
The present invention compared with prior art has and to reduce engineering quantity when not affecting harbour using function and structural strength, simplifies construction, deadweight and the opposing horizontal force of Wharf Engineering facility self structure can be made full use of, thus breach the independent retaining wall structure form at long piled wharf rear, easy construction, duration is short, decrease earthwork excavated volume and concrete use amount, reduce construction costs.
Accompanying drawing explanation
Fig. 1 is structural representation of the present invention;
Fig. 2 is Fig. 1 left view;
Fig. 3 is the invention process illustration.
Detailed description of the invention
Accompanying drawings 1 ~ accompanying drawing 2, the present invention includes the high-piled slab & girder wharf of limit longeron 2 and crossbeam 3 structure, and after high-piled slab & girder wharf, the crossbeam on edge arranges semi girder 43 times, and with limit longeron 2, crossbeam 3 and semi girder 4 for braced structures arranges breast boards 1; Described breast boards 1 is prefabricated or cast-in-place diaphragm wall structure and with limit longeron 2, crossbeam 3 and semi girder 4 for steel concrete is connected; Described semi girder 4 upper end is with crossbeam 3 for steel concrete is connected, and its lower end and breast boards 1 insert the soil body.
For certain outfitting quay engineering, the invention will be further described below, and this outfitting quay is about 132m, wide 32 meters, and harbour crossbeam is high 2.4 meters, rear low 1.0 meters along locally falling.
Embodiment 1
Accompanying drawings 3, after harbour, the crossbeam 3 on edge divides into the semi girder 4 setting high 2.8 meters, and with the breast boards 1 of limit longeron 2, crossbeam 3 and semi girder 4 high 3 meters for braced structures is arranged.During construction, first prefabricated semi girder 4 and breast boards 1, then the lower part of cast-in-place crossbeam 3 and limit longeron 2 in the pile foundation that injection is good, when building crossbeam 3, semi girder 4 is installed, that reserves installation breast boards 1 when building limit longeron 2 hangs muscle, utilize crossbeam 3, limit longeron 2 and semi girder 4, for supporting, breast boards 1 is installed, the upper part of finally construct crossbeam 3 and limit longeron 2 and surface layer.This outfitting quay engineering adopts the present invention to construct, and saves 132m Retaining Wall Engineering, not only decreases construction costs, and substantially reduce the duration, and operating efficiency improves, and achieves good economic and social benefit.
More than just the present invention is further illustrated, and be not used to limit this patent, allly implements for the present invention's equivalence, within the right that all should be contained in this patent.

Claims (1)

1. a high-piled slab & girder wharf rear connects the gear indigenous method of bank, comprise the high-piled slab & girder wharf of limit longitudinal and cross beam structure, after it is characterized in that utilizing high-piled slab & girder wharf edge crossbeam under semi girder is set, and with limit longeron, crossbeam and semi girder, the method for breast boards is set for braced structures, realize the gear soil that high-piled slab & girder wharf rear connects bank; Described breast boards is prefabricated or cast-in-place diaphragm wall structure and is that steel concrete is connected with limit longeron, crossbeam and semi girder; Described semi girder upper end and crossbeam are that steel concrete is connected, and its lower end and breast boards insert the soil body.
CN201510006353.7A 2015-01-07 2015-01-07 A kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank Active CN104532787B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510006353.7A CN104532787B (en) 2015-01-07 2015-01-07 A kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510006353.7A CN104532787B (en) 2015-01-07 2015-01-07 A kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank

Publications (2)

Publication Number Publication Date
CN104532787A true CN104532787A (en) 2015-04-22
CN104532787B CN104532787B (en) 2017-03-08

Family

ID=52848395

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510006353.7A Active CN104532787B (en) 2015-01-07 2015-01-07 A kind of high-piled slab & girder wharf rear connects the gear indigenous method of bank

Country Status (1)

Country Link
CN (1) CN104532787B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592517A (en) * 2016-12-28 2017-04-26 中交航局第二工程有限公司 Construction method for constructing long piled wharf on land
CN107119628A (en) * 2017-05-12 2017-09-01 山东海诺港务有限公司 A kind of high-piled slab & girder wharf rear connects the earth-retaining method of bank

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003113608A (en) * 2001-07-19 2003-04-18 Penta Ocean Constr Co Ltd Impervious wall structure and impervious bank protection structure using the same
CN201649036U (en) * 2009-10-16 2010-11-24 王锦文 Pipe pile platform used for building dock
CN102061678A (en) * 2009-11-13 2011-05-18 王锦文 Method for building seaport wharf on soft soil base of coastal beach
CN203256681U (en) * 2013-05-23 2013-10-30 天津港航工程有限公司 Frame-wall pile type wharf
CN103898868A (en) * 2014-04-08 2014-07-02 天津港航工程有限公司 Novel high-pile wharf
CN204401556U (en) * 2015-01-07 2015-06-17 中船第九设计研究院工程有限公司 A kind of high-piled slab & girder wharf rear connects the soil-baffling structure of bank

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003113608A (en) * 2001-07-19 2003-04-18 Penta Ocean Constr Co Ltd Impervious wall structure and impervious bank protection structure using the same
CN201649036U (en) * 2009-10-16 2010-11-24 王锦文 Pipe pile platform used for building dock
CN102061678A (en) * 2009-11-13 2011-05-18 王锦文 Method for building seaport wharf on soft soil base of coastal beach
CN203256681U (en) * 2013-05-23 2013-10-30 天津港航工程有限公司 Frame-wall pile type wharf
CN103898868A (en) * 2014-04-08 2014-07-02 天津港航工程有限公司 Novel high-pile wharf
CN204401556U (en) * 2015-01-07 2015-06-17 中船第九设计研究院工程有限公司 A kind of high-piled slab & girder wharf rear connects the soil-baffling structure of bank

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
周洋: "灌注桩-地连墙组合码头结构抗震性能有限元分析", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106592517A (en) * 2016-12-28 2017-04-26 中交航局第二工程有限公司 Construction method for constructing long piled wharf on land
CN107119628A (en) * 2017-05-12 2017-09-01 山东海诺港务有限公司 A kind of high-piled slab & girder wharf rear connects the earth-retaining method of bank

Also Published As

Publication number Publication date
CN104532787B (en) 2017-03-08

Similar Documents

Publication Publication Date Title
CN204370431U (en) A kind of occlusion long-short pile space enclosing structure
CN104652443B (en) Construction method of the interim horizontal support of deep basal pit as permanent structure beam
US11149395B2 (en) Cellular sheet pile retaining systems with unconnected tail walls, and associated methods of use
CN205314116U (en) Continuous type of combined type drilling cling compound structure
CN106869138A (en) A kind of load retaining wall Retaining Structure with Double-row Piles and its foundation ditch excavation method
CN104631468A (en) Supporting method for foundation pit excavation project
JP2013170354A (en) Raising technique for breakwater
CN202865855U (en) Stabilizing plate type anchoring pile retaining structure
CN109577277B (en) Wall-mounted drainage anchor rod retaining wall structure and construction method thereof
CN107165173A (en) A kind of foundation pit supporting system and its construction method
CN204401556U (en) A kind of high-piled slab & girder wharf rear connects the soil-baffling structure of bank
CN203977432U (en) Multistage H type soil blocking pile
CN104532787A (en) Earth retaining method for rear shore connection of high-pile beam-slab wharf
CN103628487B (en) Circular deep foundation ditch retaining wall reversed construction method
CN201416177Y (en) T-shaped pile combined plank sinking pit bracing construction
JPH11193648A (en) Base-isolated and settlement-countermeasured structure utilizing buoyancy
CN203373753U (en) Pile anchor retaining wall concrete anchor cable top beam structure of foundation ditches
CN104631467A (en) Method for erecting L-shaped support replacement plate for foundation pit excavation project
CN201738286U (en) Tetrapod pier type structure
CN204898700U (en) Bridge foundation structure
CN205062744U (en) Half gravity type two -stage view anti -flood wall on half cantilever
CN103215965A (en) Laminate type high-rise platform pile tower crane foundation and construction method
CN215593865U (en) Improved generation wharf integrated configuration
KR20090011681U (en) Hybrid underground wall structure by H-type in-situ concrete
CN216640435U (en) Dense-row pile supporting and retaining reinforcing structure under deep soft soil condition

Legal Events

Date Code Title Description
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant