CN104499436B - The antitorque balance pier of swivel bridges mobile load - Google Patents

The antitorque balance pier of swivel bridges mobile load Download PDF

Info

Publication number
CN104499436B
CN104499436B CN201410809676.5A CN201410809676A CN104499436B CN 104499436 B CN104499436 B CN 104499436B CN 201410809676 A CN201410809676 A CN 201410809676A CN 104499436 B CN104499436 B CN 104499436B
Authority
CN
China
Prior art keywords
tower
balance
pier stud
compensation
king
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410809676.5A
Other languages
Chinese (zh)
Other versions
CN104499436A (en
Inventor
惠斌
王明伟
钟晓松
孟敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201410809676.5A priority Critical patent/CN104499436B/en
Publication of CN104499436A publication Critical patent/CN104499436A/en
Application granted granted Critical
Publication of CN104499436B publication Critical patent/CN104499436B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/08Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections

Abstract

The invention discloses the antitorque balance pier of a kind of swivel bridges mobile load, comprising: there is the plummer of foundation pile, tumbler, main pier stud, king-tower, balance pier stud, compensation tower and balance drag-line; Described main pier stud is fixed on plummer centre by tumbler, is provided with a pair balance pier stud at main pier stud Bilateral Symmetry, is horizontal girder and vertical king-tower at main pier stud top, and the girder two ends being positioned at king-tower bilateral are arranged with a pair compensation tower equally; When girder turn balance pier stud overlap with compensation tower time, by affixed for the compensation tower lower end balanced on pier stud top and girder; Balance drag-line is separately fixed at king-tower and compensation tower is longitudinal.The present invention can solve the technical problem of the antitorque balanced adjustment of mobile load of horizontal ultra-wide degree bridge.

Description

The antitorque balance pier of swivel bridges mobile load
Technical field
The invention belongs to the antitorque balancing technique of swivel bridges mobile load in bridge construction.In particular to the device of the antitorque balanced adjustment of bridge mobile load of turning of large span, ultra-wide degree.
Prior art
Existing highway bridge construction turning technology is mainly flat turn method.The swing system of flat turn method is turned primarily of rotating support, is rotated traction and equilibrium system composition.For the domestic many employing counterweight forms of construction work of equilibrium system, good bridge system is had no for horizontal ultra-wide bridge and addresses this problem.
Summary of the invention
The object of this invention is to provide the antitorque balance pier of a kind of swivel bridges mobile load, to solve the technical problem of the antitorque balanced adjustment of mobile load of horizontal ultra-wide degree bridge.
In order to realize foregoing invention object, the technical scheme that the utility model adopts is as follows:
The antitorque balance pier of swivel bridges mobile load, comprising: have the plummer of foundation pile, tumbler, main pier stud, king-tower, balance pier stud, compensation tower and balance drag-line; Described main pier stud is fixed on plummer centre by tumbler, is provided with a pair balance pier stud at main pier stud Bilateral Symmetry, is horizontal girder and vertical king-tower at main pier stud top, and the girder two ends being positioned at king-tower bilateral are arranged with a pair compensation tower equally; When girder turn balance pier stud overlap with compensation tower time, by affixed for the compensation tower lower end balanced on pier stud top and girder; Balance drag-line is separately fixed at king-tower and compensation tower is longitudinal.
A pair balance pier stud as above is located at main pier stud bilateral with outward-dipping direction symmetry.
A pair compensation tower as above is located at girder bilateral with outward-dipping direction symmetry.
The antitorque balance pier of swivel bridges mobile load as above, the compensation tower of king-tower and bilateral is provided with the fixing hole of connection balance drag-line between the two.
Advantage of the present invention completes mobile load antitorque balance pier (tower) structure technology by turn pier (tower) and main beam structure of dead load, the unbalance stress of adjustment direction across bridge, the lower pier stud of pier (tower) simultaneously, can as the interim stretch-draw pier of turning, making turns itself arranges no longer separately interim stretch-draw pier.Ensure supplementing rotator construction technique, guarantee bearing capacity and the Stability Analysis of Structures of overall bridge construction load, significantly improve Long span, ultra-wide degree swivel bridges mobile load overturning or slip resistance analysis coefficient and to reduce drag-line face stress amplitude and anchor head tired.
Accompanying drawing explanation
Fig. 1 is the balance pier structure schematic diagram that the present invention forms cable stayed bridge and turns.
Fig. 2 is girder of the present invention and Construction of Pylon schematic diagram.
Fig. 3 be the present invention turn rotate before solid construction schematic diagram.
Fig. 4 be the present invention turn rotate before floor map.
Fig. 5 be the present invention turn rotate after floor map.
Fig. 6 is that the present invention constructs the construction schematic diagram of middle closure segment, Cheng Qiao.
Number in figure: 1, main pier stud, 2, bridge center line, 3, right balance pier stud, 4, above-ground route, 5, plummer, 6, pile foundation, 7, tumbler, 8, left balance pier stud, 9, girder, 10, left compensation tower, 11, left interim drag-line, 12, king-tower, 13, right interim drag-line, 14, right compensation tower, 15, rotate bridge pier rotation track, 16, main drag-line, 17, middle closure segment, 18, Cast-in-Situ Segment.
Detailed description of the invention
Structure of the present invention is see Fig. 1,2.The antitorque balance pier of described swivel bridges mobile load, comprising: have the plummer 5 of foundation pile, tumbler 7, main pier stud 1, king-tower 12, left-right balance pier stud 8,3, left-right balance tower 10,14 and balance drag-line (main drag-line) 16; Described main pier stud 1 is fixed on plummer 5 centre by tumbler 7, a pair outward-dipping balance pier stud 8,3 is provided with at main pier stud 1 Bilateral Symmetry, be horizontal girder 9 and vertical king-tower 12 at main pier stud 1 top, the girder two ends being positioned at king-tower 12 bilateral are arranged with outward-dipping a pair compensation tower 10,14 equally; When girder 9 turn balance pier stud 8,3 overlap with compensation tower 10,14 time, by affixed for compensation tower 10,14 lower end balanced on pier stud 8,3 top and girder 9; Balance drag-line 16 is separately fixed at king-tower 12 and compensation tower 10,14 is longitudinal.The compensation tower 10,14 of king-tower 12 and bilateral is provided with the fixing hole of connection interim balance drag-line 11,12 between the two.
Concrete construction sequence is as follows:
1), substructure construction
Then first construction stake basis is cushion cap, pre-buried main pier stud tumbler in cushion cap, then carries out main pier stud and the construction of balance pier stud.
2), main girder construction, simultaneously installation king-tower and king-tower suspension cable.
Main pier stud first to be constructed king-tower, then cantilever casting construction girder, main drag-line is installed simultaneously.
3), compensation tower of constructing, add interim rope, both sides compensation tower carries out simultaneously.
At girder horizontal correspondence position construction compensation tower, add interim rope simultaneously, prevent compensation tower from tilting, require that both sides compensation tower is constructed simultaneously.
4), cable stayed bridge is turned.
See Fig. 3,4,5, utilize balance pier stud to rotate device, superstructure is turned, turn to along alignment direction (becoming bridge location to put).
5), connect compensation tower and balance pier stud, make both consolidation be integrated.
Until superstructure complete in place after, complete compensation tower and balance pier stud consolidation, make both be connected as a single entity.
6), PHT (compensation tower) drag-line is installed, removes interim rope (king-tower does not show).
Compensation tower drag-line is installed, removes the interim rope of compensation tower.
7), closure segment in the middle of construction.
See Fig. 6, after realizing respectively turning until two sections of turning, compensation tower drag-line being installed, two section of turning girders are connected.
8), remove falsework, unification is built deck paving and is put into effect.

Claims (4)

1. the antitorque balance pier of swivel bridges mobile load, is characterized in that, comprising: have the plummer of foundation pile, tumbler, main pier stud, king-tower, balance pier stud, compensation tower and balance drag-line; Described main pier stud is fixed on plummer centre by tumbler, is provided with a pair balance pier stud at main pier stud Bilateral Symmetry, is horizontal girder and vertical king-tower at main pier stud top, and the girder two ends being positioned at king-tower bilateral are arranged with a pair compensation tower equally; When girder turn balance pier stud overlap with compensation tower time, by affixed for the compensation tower lower end balanced on pier stud top and girder; Balance drag-line is separately fixed at king-tower and compensation tower is longitudinal.
2. the antitorque balance pier of swivel bridges mobile load according to claim 1, is characterized in that, a pair described balance pier stud is located at main pier stud bilateral with outward-dipping direction symmetry.
3. the antitorque balance pier of swivel bridges mobile load according to claim 1, is characterized in that, a pair described compensation tower is located at girder bilateral with outward-dipping direction symmetry.
4. the antitorque balance pier of swivel bridges mobile load according to claim 1, is characterized in that, the antitorque balance pier of described swivel bridges mobile load, and the compensation tower of king-tower and bilateral is provided with the fixing hole of connection balance drag-line between the two.
CN201410809676.5A 2014-12-23 2014-12-23 The antitorque balance pier of swivel bridges mobile load Active CN104499436B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410809676.5A CN104499436B (en) 2014-12-23 2014-12-23 The antitorque balance pier of swivel bridges mobile load

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410809676.5A CN104499436B (en) 2014-12-23 2014-12-23 The antitorque balance pier of swivel bridges mobile load

Publications (2)

Publication Number Publication Date
CN104499436A CN104499436A (en) 2015-04-08
CN104499436B true CN104499436B (en) 2016-03-30

Family

ID=52940879

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410809676.5A Active CN104499436B (en) 2014-12-23 2014-12-23 The antitorque balance pier of swivel bridges mobile load

Country Status (1)

Country Link
CN (1) CN104499436B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108677749B (en) * 2018-01-18 2024-02-06 中铁二十三局集团第二工程有限公司 PLC frequency conversion control system for bridge swivel construction
CN108774955A (en) * 2018-01-18 2018-11-09 重庆溢权科技发展有限公司 A kind of Bridge Rotation Construction Technique intelligence control system
CN114673094B (en) * 2022-04-28 2023-03-21 中国十九冶集团有限公司 Construction method of river-crossing bridge

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205139A (en) * 2006-02-06 2007-08-16 Sumitomo Mitsui Construction Co Ltd Construction method of arch bridge
CN101078195A (en) * 2007-06-29 2007-11-28 中铁工程设计咨询集团有限公司 Bridge and construction method thereof
CN103243657A (en) * 2013-04-24 2013-08-14 中铁工程设计咨询集团有限公司 Pier-top rotator structure of bridge and method for constructing connector
CN204385632U (en) * 2014-12-23 2015-06-10 北京市市政工程设计研究总院有限公司 The antitorque balance pier of swivel bridges mobile load

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007205139A (en) * 2006-02-06 2007-08-16 Sumitomo Mitsui Construction Co Ltd Construction method of arch bridge
CN101078195A (en) * 2007-06-29 2007-11-28 中铁工程设计咨询集团有限公司 Bridge and construction method thereof
CN103243657A (en) * 2013-04-24 2013-08-14 中铁工程设计咨询集团有限公司 Pier-top rotator structure of bridge and method for constructing connector
CN204385632U (en) * 2014-12-23 2015-06-10 北京市市政工程设计研究总院有限公司 The antitorque balance pier of swivel bridges mobile load

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
徐得标.北京某铁路转体桥的设计.《特种结构》.2009,(第1期),全文. *
梁福雯.施工监控在斜拉转体桥中的应用.《公路交通科技》.2012,(第2期),全文. *

Also Published As

Publication number Publication date
CN104499436A (en) 2015-04-08

Similar Documents

Publication Publication Date Title
CN105442459B (en) Large-Span Continuous girder span building up station rotator construction rotor system and construction method
CN103243652B (en) A kind of large-span non-floor type cast-in-place beam falsework and construction method thereof
CN107761542B (en) A kind of arch oblique pull combined system bridge and its construction method
CN101864737B (en) Secondary vertical rotating construction method for arch rib of long-span steel arch bridge
CN103821075B (en) Long span oblique pull assembly type steel bridge on highway
CN106939553B (en) A kind of Steel Bridge Deck and steel box arch rib installation method
US20130174360A1 (en) Aligned support bridge
CN104695341A (en) Non-self-balanced beam string structure for reinforcing large-span continuous beam bridge
CN104499436B (en) The antitorque balance pier of swivel bridges mobile load
CN203296361U (en) Long-span steel structure cross assembling hoisting platform
CN206396615U (en) Suitable for the bridge structure of bridge pier differential settlement
CN108755385A (en) A kind of only Cable-stayed Bridge with Slanted Pylon structure and construction method of active balance main span horizontal force
CN102839598A (en) Mixed type cable-supported bridge
CN102535353A (en) Construction method for box beam swinging body striding on expressways and railways in rail transit
CN204385632U (en) The antitorque balance pier of swivel bridges mobile load
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN103806373B (en) Oblique pull assembly type steel bridge on highway suspension cable anchor system
CN206204758U (en) Tower anchor unifies suspension bridge
CN205775887U (en) A kind of large eccentricity rotary body device of Curved Stayed-cable Bridge
CN104452574A (en) Novel ramp bridge structure and construction method thereof
CN104963292B (en) Construction method of reinforced concrete continuous-span arch bridge or continuous box structure bridge
CN204703068U (en) A kind of up suspention section assembling traversing carriage bridge fabrication machine
CN106284049B (en) Tower anchor unifies suspension bridge
CN206591417U (en) A kind of only floating system cable stayed bridge structure of post wide cut rachis face half
CN202830732U (en) Mixing-type cable- rope bearing bridge

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant