CN102535348A - Method for tensioning stayed cables of hinged tower cable stayed bridge - Google Patents
Method for tensioning stayed cables of hinged tower cable stayed bridge Download PDFInfo
- Publication number
- CN102535348A CN102535348A CN201210067088XA CN201210067088A CN102535348A CN 102535348 A CN102535348 A CN 102535348A CN 201210067088X A CN201210067088X A CN 201210067088XA CN 201210067088 A CN201210067088 A CN 201210067088A CN 102535348 A CN102535348 A CN 102535348A
- Authority
- CN
- China
- Prior art keywords
- cable
- tower
- stayed
- bridge
- cables
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 40
- 238000010276 construction Methods 0.000 claims abstract description 19
- 238000012544 monitoring process Methods 0.000 claims description 4
- 239000000725 suspension Substances 0.000 claims 1
- 238000010586 diagram Methods 0.000 description 8
- 229910000831 Steel Inorganic materials 0.000 description 7
- 239000010959 steel Substances 0.000 description 7
- 238000005452 bending Methods 0.000 description 6
- 239000000463 material Substances 0.000 description 5
- 239000004567 concrete Substances 0.000 description 3
- 239000011513 prestressed concrete Substances 0.000 description 3
- 238000011160 research Methods 0.000 description 3
- 239000002131 composite material Substances 0.000 description 2
- 238000007667 floating Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域 technical field
本发明涉及一种斜拉桥斜拉索的张拉方法,尤其涉及一种铰塔斜拉桥斜拉索的张拉方法。The invention relates to a tensioning method for cable-stayed cables of a cable-stayed bridge, in particular to a tensioning method for cable-stayed cables of a hinged tower cable-stayed bridge.
背景技术 Background technique
斜拉桥又称斜张桥,是将梁体用许多斜拉索直接拉在桥塔上的一种桥梁,是由承压的桥塔、受拉的斜拉索和承弯的梁体组合起来的一种结构体系。其可看作是斜拉索代替支墩的多跨弹性支承连续梁。其可使梁体内弯矩减小,降低建筑高度,减轻结构重量,节省材料。Cable-stayed bridge, also known as cable-stayed bridge, is a bridge in which the girder body is directly pulled on the bridge tower by many cable-stayed cables. a structural system. It can be regarded as a multi-span elastically supported continuous beam with cable-stayed cables instead of buttresses. It can reduce the bending moment in the beam body, reduce the height of the building, reduce the weight of the structure, and save materials.
斜拉桥作为一种拉索体系,比梁式桥的跨越能力更大,是大跨度桥梁的最主要桥型。斜拉桥由桥塔、梁体、斜拉索组成,其中桥塔、梁体作为桥面体系受压,斜拉索作为支承体系受拉的一种组合桥梁结构体系。桥塔型式有A型、倒Y型、B型、独柱,材料有钢和混凝土的。斜拉索布置有单索面、平行双索面、斜索面等。斜拉桥主要结构体系有:漂浮体系、半漂浮体系、塔梁固结体系、刚构体系、T构体系、部分地锚体系、矮塔部分斜拉桥体系等。斜拉桥斜拉索的布置形式主要有:辐射形、竖琴形、扇形等。As a cable system, the cable-stayed bridge has a larger spanning capacity than the girder bridge, and is the most important type of long-span bridge. A cable-stayed bridge consists of a bridge tower, a beam body, and cable-stayed cables. The bridge tower and beam body are used as a bridge deck system for compression, and the cable-stayed cables are used as a support system for tension. A composite bridge structure system. The types of bridge towers are A type, inverted Y type, B type, and single column, and the materials are steel and concrete. There are single cable plane, parallel double cable plane, oblique cable plane and so on for stay cable layout. The main structural systems of cable-stayed bridges are: floating system, semi-floating system, tower-beam consolidation system, rigid frame system, T-frame system, partial ground anchor system, low tower partial cable-stayed bridge system, etc. The cable-stayed cables of cable-stayed bridges are mainly arranged in the following forms: radial, harp-shaped, fan-shaped, etc.
在斜拉桥施工中,斜拉索张拉方法多以主、副跨对称张拉为主,调整斜拉索索力时,主、副跨亦均需调整。In the construction of cable-stayed bridges, the tensioning method of the cable-stayed cables is mostly based on symmetrical tensioning of the main and auxiliary spans.
目前多以“恒载平衡法”进行斜拉索索力的初拟。“恒载平衡法”主要假定包括两方面:一是对于主跨,忽略梁体抗弯刚度的影响;二是对于副跨,忽略桥塔的抗弯刚度。因此,传统的斜拉索张拉方式的缺点是斜拉索需对称张拉,即主跨斜拉索与副跨斜拉索同时张拉,图1示出的斜拉桥主要由梁体1、桥塔(包括主塔2和下塔柱4)和斜拉索3构成,桥塔的一侧为主跨侧,桥塔的另一侧为副跨侧,斜拉索3的张拉方式为张拉a1同时张拉副跨侧的斜拉索b1;再张拉主跨侧的斜拉索a2同时张拉副跨侧的斜拉索b2;然后张拉主跨侧的斜拉索a3同时张拉副跨侧的斜拉索b3;以此类推,张拉全部斜拉索。由于斜拉索使用的液压顶有误差,因此,与下塔柱4(或梁体1)刚性连接的主塔2受弯,梁体1水平力不平衡。At present, the "dead load balance method" is mostly used for the preliminary drafting of the cable forces of the stay cables. The main assumptions of the "dead load balance method" include two aspects: one is that for the main span, the influence of the bending stiffness of the girder is ignored; the other is that for the auxiliary span, the bending stiffness of the bridge tower is ignored. Therefore, the disadvantage of the traditional cable-stayed cable tensioning method is that the cable-stayed cables need to be tensioned symmetrically, that is, the cable-stayed cables of the main span and the cable-stayed cables of the auxiliary span are simultaneously tensioned. The cable-stayed bridge shown in Fig. 1. The bridge tower (including the
发明内容 Contents of the invention
针对上述现有技术,本发明提供一种铰塔斜拉桥斜拉索的张拉方法,适用于主、副跨均布置斜拉索的斜拉桥,对桥塔两侧的斜拉索,仅需张拉桥塔一侧的斜拉索,而另一侧的斜拉索无需进行张拉,不但简化了斜拉索的张拉过程,同时消除了因桥塔两侧斜拉索索力不平衡而造成桥塔弯曲的缺陷。Aiming at the above-mentioned prior art, the present invention provides a kind of tensioning method of the cable-stayed cables of the hinged pylon cable-stayed bridge, which is suitable for cable-stayed bridges in which the main and auxiliary spans are arranged with cable-stayed cables. Only the stay cables on one side of the bridge pylon need to be stretched, while the stay cables on the other side do not need to be stretched, which not only simplifies the tensioning process of the stay cables, but also eliminates the tension caused by the tension of the stay cables on both sides of the bridge pylon. The defect of bridge tower bending due to balance.
为了解决上述技术问题,本发明一种铰塔斜拉桥斜拉索的张拉方法予以实现的技术方案是:其中斜拉桥包括梁体、桥塔和斜拉索,所述桥塔由位于梁体上方的主塔和与所述梁体刚性连接的下塔柱构成,所述主塔与所述下塔柱之间采用铰接;所述斜拉索的张拉方法包括以下步骤:In order to solve the above-mentioned technical problems, the technical scheme realized by the tensioning method of the cable-stayed cables of a hinged-tower cable-stayed bridge in the present invention is: wherein the cable-stayed bridge includes a girder body, a bridge tower and a cable-stayed cable, and the bridge tower is located at The main tower above the beam body and the lower tower column rigidly connected with the beam body are formed, and the main tower and the lower tower column are hinged; the tensioning method of the stay cable includes the following steps:
步骤一、施工桥梁基础,所述桥梁基础包括桩基、承台和墩柱,完成梁体架设的同时完成下塔柱的施工;Step 1, construction bridge foundation, described bridge foundation comprises pile foundation, cap and pier column, finishes the construction of lower tower column while erecting beam body;
步骤二、施工与下塔柱铰接的主塔,并完成位于主塔一侧斜拉索的挂索;
步骤三、完成位于所述主塔另一侧斜拉索的挂索及张拉。Step 3, completing the hanging and tensioning of the stay cables on the other side of the main tower.
进一步讲,在上述步骤一中,所述下塔柱的位置与所述桥梁的其中一个墩柱的位置重合。Further, in the above step 1, the position of the lower tower coincides with the position of one of the piers of the bridge.
还有,在步骤二和步骤三中,挂索的顺序是自铰接点最近处的斜拉索开始依次向外挂索。Also, in
另外,在步骤三中包括下述两种情形之一:将该侧的斜拉索依次全部挂索后,再依次进行张拉或每挂完一根斜拉索后,随即对该根斜拉索进行张拉。在步骤三的斜拉索张拉过程中,根据对斜拉索索力的监控结果,确定是否对该斜拉索进行索力调整。In addition, step 3 includes one of the following two situations: after all the stay cables on this side are hung in sequence, then tensioning is carried out sequentially or after each stay cable is hung, the stay cable is then pulled The cable is stretched. During the tensioning process of the stay cable in step 3, it is determined whether to adjust the cable force of the stay cable according to the monitoring result of the stay cable force.
与现有技术相比,本发明的有益效果是:Compared with prior art, the beneficial effect of the present invention is:
(1)减少张拉次数。只张拉位于桥塔一侧的斜拉索,张拉次数为传统张拉工艺的50%,大大缩短了张拉时间,节省工期。(1) Reduce the number of stretches. Only the stay cables on one side of the bridge tower are stretched, and the number of stretches is 50% of the traditional stretching process, which greatly shortens the stretching time and saves the construction period.
(2)减小张拉误差。由于张拉斜拉索采用的千斤顶自身存有误差,因此斜拉索的每次张拉均会产生误差,而只张拉桥塔一侧的斜拉索,通过计算可以确定另一侧斜拉索相应的索力,千斤顶的使用系数为传统张拉工艺的50%,从而减小了由于千斤顶自身误差而造成的斜拉索张拉力误差。(2) Reduce the tension error. Due to the error of the jack used in tensioning the cable stay, there will be an error every time the cable is stretched, and only the cable on one side of the bridge tower is stretched, and the cable on the other side can be determined by calculation. The corresponding cable force of the cable, the use coefficient of the jack is 50% of the traditional tensioning process, thereby reducing the error of the cable tension caused by the error of the jack itself.
本发明一种铰塔斜拉桥斜拉索的张拉方法可以广泛应用于各种主、副跨均布置斜拉索的斜拉桥的施工,不但可以大幅度提高斜拉索张拉的工作效率,而且保证了施工的精确性。为今后斜拉桥的施工提供足够的技术支撑和理论保障,具有非常重要的现实意义。A cable tensioning method of a hinged tower cable-stayed bridge according to the present invention can be widely used in the construction of various cable-stayed bridges in which cable-stayed cables are arranged on the main and auxiliary spans, and can not only greatly improve the tensioning work of the cable-stayed cables Efficiency, but also to ensure the accuracy of construction. It has very important practical significance to provide sufficient technical support and theoretical guarantee for the construction of cable-stayed bridges in the future.
附图说明 Description of drawings
图1是现有技术中一种桥塔与梁体刚接斜拉桥斜拉索张拉方法示意图;Fig. 1 is a schematic diagram of a cable tensioning method for a cable-stayed bridge rigidly connected to a bridge tower and a beam body in the prior art;
图2是本发明一种铰塔斜拉桥斜拉索的张拉方法示意图;Fig. 2 is a schematic diagram of the stretching method of the cable-stayed cables of a hinged tower cable-stayed bridge of the present invention;
图3-1至图3-5是本发明铰塔斜拉桥斜拉索的张拉方法实施例的示意图;Fig. 3-1 to Fig. 3-5 are the schematic diagrams of the tensioning method embodiment of the cable-stayed cable of hinged tower cable-stayed bridge of the present invention;
其中:图3-1是完成步骤一后的示意图,Among them: Figure 3-1 is a schematic diagram after step 1 is completed,
图3-2是完成步骤二的示意图,Figure 3-2 is a schematic diagram of completing
图3-3是步骤三中完成第一个斜拉索挂索张拉后的示意图,Figure 3-3 is a schematic diagram of the first stay cable hanging cable tensioning completed in step 3,
图3-4是完成全部斜拉索挂索及张拉后的示意图,Figure 3-4 is a schematic diagram after completing all stay cable hanging and tensioning.
图3-5采用本发明铰塔斜拉桥斜拉索的张拉方法完成的斜拉桥的示意图;Fig. 3-5 adopts the schematic diagram of the cable-stayed bridge that the stretching method of hinged tower cable-stayed bridge cable-stayed cable of the present invention completes;
具体实施方式 Detailed ways
下面结合具体实施方式对本发明作进一步详细地描述。The present invention will be further described in detail below in combination with specific embodiments.
如图2所示,本发明一种铰塔斜拉桥斜拉索的张拉方法,其中斜拉桥包括梁体1、桥塔和斜拉索3,所述桥塔由位于梁体1上方的主塔2和与所述梁体1刚性连接的下塔柱4构成,所述主塔2与所述下塔柱4之间采用铰接;即根据“恒载平衡法”斜拉索索力初拟的原理,在初始斜拉索索力拟定时,所述斜拉索3的张拉方法包括以下步骤:As shown in Fig. 2, a kind of tensioning method of the cable-stayed cable of hinge tower cable-stayed bridge of the present invention, wherein cable-stayed bridge comprises girder body 1, bridge tower and cable-stayed cable 3, and described bridge tower is positioned at beam body 1 top The
步骤一、施工桥梁基础,所述桥梁基础包括桩基、承台和墩柱,完成梁体1架设的同时完成下塔柱4的施工;其中所述的下塔柱4的位置可以与桥梁的其中一个墩柱的位置重合。Step 1, construction bridge foundation, described bridge foundation comprises pile foundation, cap and pier column, finishes the construction of lower tower column 4 while finishing beam body 1 erection; Wherein the position of lower tower column 4 can be with the bridge's The position of one of the piers coincides.
步骤二、施工与下塔柱4铰接的主塔2,并完成位于主塔2一侧斜拉索的挂索;
步骤三、完成位于所述主塔2另一侧斜拉索的挂索及张拉。在张拉斜拉索时,可以是将该侧的斜拉索依次全部挂索后,再依次进行张拉;也可以是每挂完一根斜拉索后,随即对该根斜拉索进行张拉。另外,根据对斜拉索索力的监控结果,确定是否对该斜拉索进行索力调整。Step 3, completing the hanging and tensioning of the stay cables on the other side of the
为了施工方便,无论位于桥塔哪一侧(至于是主跨侧还是副跨侧均不受限制)的斜拉索挂索的顺序均可以是自铰接点最近处的斜拉索开始依次向外挂索,但其他的顺序均不受限制。For the convenience of construction, no matter which side of the bridge tower is located (there is no restriction on the side of the main span or the side of the auxiliary span), the order of the stay cables can be hung outwards from the stay cables closest to the hinge point. , but other orders are not restricted.
根据“恒载平衡法”斜拉索索力初拟的原理,在初始斜拉索索力拟定时,本发明通过采用铰塔(所述主塔2与所述下塔柱4之间采用铰接)方式达到忽略塔的抗弯刚度的目的,以消除斜拉索张拉过程中桥塔抗弯刚度的影响。本发明的特点是:位于桥塔一侧的斜拉索不张拉,且通过数值计算可确定该侧斜拉索索力。斜拉索张拉完成后,可将铰塔的铰固结,因此,本发明斜拉索的张拉方法既适用于铰塔斜拉桥也可应用于其它结构体系斜拉桥的斜拉索张拉。According to the principle of the preliminary drafting of the cable force of the "constant load balance method", when the initial cable force of the cable stay is drafted, the present invention adopts a hinged tower (hinged between the
以下通过实施例讲述本发明的详细过程,提供实施例是为了理解的方便,绝不是限制本发明,诸如,斜拉索的挂索张拉的顺序等。The following describes the detailed process of the present invention through the examples. The examples are provided for the convenience of understanding, and are not intended to limit the present invention, such as the sequence of tensioning the cables of the stay cables.
实施例:Example:
研究材料简介:如图3-5所示,采用铰塔的斜拉桥形式,桥塔向河道中心方向倾斜18°,桥塔与下塔柱铰接、梁体与下塔柱固结,主桥跨径布置为:45m前副跨+138m主跨+2x30m后副跨。梁体采用钢与混凝土组合结构,即主跨采用钢箱梁结构,副跨采用预应力混凝土箱梁结构。主跨侧斜拉索锚固区位于中央分割带,索水平间距12m,副跨斜拉索锚固区位于人行道外侧,索水平间距3.75m。副跨斜拉索布置为梁体上距桥塔近的斜拉索锚点与塔上最高的锚点相对应,依此类推。Brief introduction of research materials: As shown in Figure 3-5, a cable-stayed bridge with hinged towers is adopted. The bridge towers are inclined 18° towards the center of the river. The span arrangement is: 45m front auxiliary span + 138m main span + 2x30m rear auxiliary span. The beam body adopts a steel and concrete composite structure, that is, the main span adopts a steel box girder structure, and the auxiliary span adopts a prestressed concrete box girder structure. The anchorage area of the side stay cables of the main span is located in the central dividing zone, with a horizontal spacing of 12m, and the anchorage area of the side stay cables of the auxiliary span is located outside the sidewalk, with a horizontal spacing of 3.75m. The stay cables of the auxiliary span are arranged such that the stay cable anchor point on the girder body closest to the bridge tower corresponds to the highest anchor point on the tower, and so on.
桥塔为铰塔,全长120m,下塔柱的位置与桥梁的主墩柱的位置重合,主塔与下塔柱(也是桥梁的主墩柱)之间为铰接。实现铰接的铰由上下两个构件组成,其中,上构件与主塔的底部连接,下构件与下塔柱的顶部(即桥梁基础的一个墩柱)之间通过精轧螺纹钢筋锚固。The bridge tower is a hinged tower with a total length of 120m. The position of the lower tower column coincides with the position of the main pier column of the bridge, and the main tower and the lower tower column (also the main pier column of the bridge) are hinged. The hinge that realizes the hinge is composed of upper and lower components, wherein the upper component is connected to the bottom of the main tower, and the lower component is anchored to the top of the lower tower column (that is, a pier column of the bridge foundation) through a fine-rolled threaded steel bar.
上述研究材料所对应的铰塔斜拉桥斜拉索的张拉过程如下:The tensioning process of the cable-stayed cables of the hinged tower cable-stayed bridge corresponding to the above research materials is as follows:
步骤一、施工桥梁基础(桩基、承台和墩柱),完成梁体架设的同时完成下塔柱的施工,包括支架拼装钢梁,同时在满堂支架上浇筑前、后副跨混凝土梁段,张拉混凝土梁段预应力,完成主跨钢箱梁和副跨预应力混凝土箱梁的连接,梁体连接后拆除副跨支架,如图3-1所示;Step 1. Construction of the bridge foundation (pile foundation, cap and pier column), complete the erection of the beam body and the construction of the lower tower column at the same time, including the steel beam assembled by the bracket, and pour the front and rear auxiliary span concrete beam sections on the full hall bracket at the same time , the prestressed concrete beam section is prestressed, and the connection of the steel box girder of the main span and the prestressed concrete box girder of the auxiliary span is completed. After the beam body is connected, the support of the auxiliary span is removed, as shown in Figure 3-1;
步骤二、施工与下塔柱铰接的主塔后,安装如图3-2所示后副跨一侧的斜拉索,自A9斜拉索至A1斜拉索所示的挂索方向依次完成后副跨一侧斜拉索的挂索,主塔达到预定位置后拆除主塔支架;Step 2: After constructing the main tower hinged with the lower tower column, install the stay cables on the side of the rear auxiliary span as shown in Figure 3-2, and complete the hanging cables in sequence from A9 stay cables to A1 stay cables The hanging cable of the stay cable on one side of the rear auxiliary span, and the main tower support is removed after the main tower reaches the predetermined position;
步骤三、依次完成主跨一侧斜拉索的挂索,如图3-3所示,自铰接点最近处的斜拉索B1开始依次向外挂索(即按照B1、B2、B3、B4、B5、B6、B7、B8、B9的顺序),每挂接一根斜拉索后随即张拉该斜拉索,到达设计索力后拆除该斜拉索对应的钢箱梁支架,直至完成主跨一侧全部斜拉索的挂索-张拉,如图3-4所示。在此过程中后副跨一侧的所有的斜拉索A1、A2、A3、A4、A5、A6、A7、A8、A9均不用张拉。Step 3. Complete the hanging cables of the stay cables on one side of the main span in sequence. As shown in Figure 3-3, hang the cables from the stay cable B1 closest to the hinge point to the outside in sequence (that is, according to B1, B2, B3, B4, The order of B5, B6, B7, B8, B9), each time a stay cable is connected, then the stay cable is stretched, and the steel box girder bracket corresponding to the stay cable is removed after the design cable force is reached, until the completion of the main Hanging cable-tensioning of all stay cables on one side, as shown in Figure 3-4. During this process, all the stay cables A1, A2, A3, A4, A5, A6, A7, A8 and A9 on one side of the rear auxiliary span need not be stretched.
在步骤三的斜拉索张拉过程中,根据对斜拉索索力的监控结果,确定是否对该斜拉索进行索力调整,即:对比实测斜拉索索力数值与目标索力数值调整主跨侧斜拉索索力。例如,在本实施例中对于主跨一侧的斜拉索,按照如图3-4中所示的B9、B8、B7、B6、B5、B4、B3、B2、B1顺序进行补拉调索。During the tensioning process of the stay cable in Step 3, according to the monitoring results of the stay cable force, it is determined whether to adjust the cable force of the stay cable, namely: compare the measured cable force value with the target cable force value to adjust the main Cable forces across side stays. For example, in this embodiment, for the stay cables on one side of the main span, follow the sequence of B9, B8, B7, B6, B5, B4, B3, B2, and B1 shown in Figure 3-4 to carry out supplementary cable adjustment. .
综上,按照上述步骤对研究材料所提供的斜拉桥的斜拉索进行张拉,可节省副跨侧斜拉索A1~A9共九对十八根拉索的张拉,大大降低了由张拉引起的斜拉索索力误差,相比传统的斜拉桥斜拉索张拉施工工艺有着显著的优势。To sum up, according to the above steps, the cable-stayed cables of the cable-stayed bridge provided by the research materials can be stretched, which can save the tension of nine pairs of eighteen cables in the auxiliary span side cable-stayed cables A1-A9, and greatly reduce the tension caused by The force error of the cable-stayed cables caused by the tension has obvious advantages compared with the traditional cable-stayed cable tensioning construction technology of the cable-stayed bridge.
尽管上面结合图对本发明进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,而不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨的情况下,还可以作出很多变形,这些均属于本发明的保护之内。Although the present invention has been described above in conjunction with the drawings, the present invention is not limited to the above-mentioned specific embodiments, and the above-mentioned specific embodiments are only illustrative, rather than restrictive. Under the inspiration, many modifications can be made without departing from the gist of the present invention, and these all belong to the protection of the present invention.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210067088 CN102535348B (en) | 2012-03-14 | 2012-03-14 | Method for tensioning stayed cables of hinged tower cable stayed bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210067088 CN102535348B (en) | 2012-03-14 | 2012-03-14 | Method for tensioning stayed cables of hinged tower cable stayed bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102535348A true CN102535348A (en) | 2012-07-04 |
CN102535348B CN102535348B (en) | 2013-10-30 |
Family
ID=46343254
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201210067088 Active CN102535348B (en) | 2012-03-14 | 2012-03-14 | Method for tensioning stayed cables of hinged tower cable stayed bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102535348B (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102839605A (en) * | 2012-09-25 | 2012-12-26 | 长沙理工大学 | Sag control method for small-sag datum strand |
CN105155426A (en) * | 2015-09-30 | 2015-12-16 | 中铁港航局集团有限公司 | Method for combining cable-stayed bridge deck cable unreeling manner and air cable unreeling manner under condition of limited space |
CN105401523A (en) * | 2015-09-30 | 2016-03-16 | 中铁港航局集团有限公司 | Hanging mounting method of long heavy stay cable under space limited condition |
CN107201721A (en) * | 2016-03-16 | 2017-09-26 | 中铁十五局集团有限公司 | Stay cable installation construction method |
CN110184930A (en) * | 2019-05-27 | 2019-08-30 | 法尔胜泓昇集团有限公司 | The stayed Cable Construction method of low-pylon cable-stayed bridge |
CN111560831A (en) * | 2020-04-21 | 2020-08-21 | 中铁武汉勘察设计研究院有限公司 | Continuous bridge without fixed support |
CN113737649A (en) * | 2021-08-19 | 2021-12-03 | 中铁十六局集团第五工程有限公司 | Bridge suspension cable tensioning device |
Families Citing this family (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
TWI548796B (en) * | 2013-12-30 | 2016-09-11 | Univ Chienkuo Technology | Oblique bridge cable vibration dampers |
CN108301309A (en) * | 2018-01-11 | 2018-07-20 | 浙江省交通运输科学研究院 | A kind of asymmetric assembled steel cable-stayed bridge bridge end wall bracket sets support construction |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2741896A1 (en) * | 1995-12-04 | 1997-06-06 | Freyssinet Int Stup | IMPROVEMENTS TO PROCESSES FOR REHABILITATING SUSPENDED BRIDGES AND TO BRIDGES THUS REHABILITED |
JP3356417B2 (en) * | 1999-11-09 | 2002-12-16 | 株式会社エスイー | Construction method and construction structure at the saddle part of the cable, and bridge |
CN101457514A (en) * | 2008-12-31 | 2009-06-17 | 广东省基础工程公司 | Cable stayed bridge construction method |
CN201581344U (en) * | 2009-12-31 | 2010-09-15 | 中铁二院工程集团有限责任公司 | Double track railway steel truss cable-stayed bridge |
CN201648942U (en) * | 2010-02-02 | 2010-11-24 | 中冶建筑研究总院有限公司 | Combined cable-truss stretch-draw integral structure for mast stayed-cables and suspension cables |
CN102121234A (en) * | 2011-04-23 | 2011-07-13 | 中铁三局集团有限公司 | Quick construction method of two-tower five-span steel truss girder cable-stayed bridge |
-
2012
- 2012-03-14 CN CN 201210067088 patent/CN102535348B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2741896A1 (en) * | 1995-12-04 | 1997-06-06 | Freyssinet Int Stup | IMPROVEMENTS TO PROCESSES FOR REHABILITATING SUSPENDED BRIDGES AND TO BRIDGES THUS REHABILITED |
JP3356417B2 (en) * | 1999-11-09 | 2002-12-16 | 株式会社エスイー | Construction method and construction structure at the saddle part of the cable, and bridge |
CN101457514A (en) * | 2008-12-31 | 2009-06-17 | 广东省基础工程公司 | Cable stayed bridge construction method |
CN201581344U (en) * | 2009-12-31 | 2010-09-15 | 中铁二院工程集团有限责任公司 | Double track railway steel truss cable-stayed bridge |
CN201648942U (en) * | 2010-02-02 | 2010-11-24 | 中冶建筑研究总院有限公司 | Combined cable-truss stretch-draw integral structure for mast stayed-cables and suspension cables |
CN102121234A (en) * | 2011-04-23 | 2011-07-13 | 中铁三局集团有限公司 | Quick construction method of two-tower five-span steel truss girder cable-stayed bridge |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102839605A (en) * | 2012-09-25 | 2012-12-26 | 长沙理工大学 | Sag control method for small-sag datum strand |
CN105155426A (en) * | 2015-09-30 | 2015-12-16 | 中铁港航局集团有限公司 | Method for combining cable-stayed bridge deck cable unreeling manner and air cable unreeling manner under condition of limited space |
CN105401523A (en) * | 2015-09-30 | 2016-03-16 | 中铁港航局集团有限公司 | Hanging mounting method of long heavy stay cable under space limited condition |
CN107201721A (en) * | 2016-03-16 | 2017-09-26 | 中铁十五局集团有限公司 | Stay cable installation construction method |
CN110184930A (en) * | 2019-05-27 | 2019-08-30 | 法尔胜泓昇集团有限公司 | The stayed Cable Construction method of low-pylon cable-stayed bridge |
CN111560831A (en) * | 2020-04-21 | 2020-08-21 | 中铁武汉勘察设计研究院有限公司 | Continuous bridge without fixed support |
CN113737649A (en) * | 2021-08-19 | 2021-12-03 | 中铁十六局集团第五工程有限公司 | Bridge suspension cable tensioning device |
CN113737649B (en) * | 2021-08-19 | 2023-03-14 | 中铁十六局集团第五工程有限公司 | Bridge suspension cable tensioning device |
Also Published As
Publication number | Publication date |
---|---|
CN102535348B (en) | 2013-10-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102535348A (en) | Method for tensioning stayed cables of hinged tower cable stayed bridge | |
Zheng et al. | Concrete-filled steel tube arch bridges in China | |
CN104975566B (en) | Apply the steel pipe support in cable-stayed bridge arch tower is constructed | |
CN103088750B (en) | Especial-big span suspension bridge of uniparted hyperboloid space rope net main cable and construction method thereof | |
CN102418315B (en) | Construction Method of Concrete Steel Tube Arch Bridge with Large Bridge Width Erected by Low Buckle Towers | |
CN102286938B (en) | Diagonal tension system reinforcement structure suitable for large-span box girder bridge and continuous rigid frame bridge | |
CN211815489U (en) | Super large span flying swallow type concrete filled steel tube arch bridge with self-anchoring suspension cable system | |
CN110331668A (en) | A kind of back-cable-free cable-stayed bridge inclined in two-way V-shaped bridge tower construction method | |
CN111335142A (en) | Self-anchored cable-stayed arch bridge | |
CN101353882B (en) | A method for the structure of a continuous rigid frame bridge with oblique legs and its cantilever pouring construction method | |
CN103243658B (en) | The spelling method of cable stayed bridge dragging suspension basket | |
CN203270457U (en) | Suspension bar anchoring structure capable of initiatively reinforcing concrete tied-arch bridge | |
CN107761542B (en) | An arch cable-stayed composite system bridge and its construction method | |
CN102261039A (en) | Integral thrusting construction method of network tied arch bridge | |
CN201933419U (en) | Arch bridge arch rib cast-in-situ bracket | |
CN102322019A (en) | Cooperative system bridge of tied arch and T-shaped rigid framework | |
CN211815595U (en) | Lower tower column tension and compression structure for cable tower | |
CN107905124A (en) | A kind of symmetrical expression rigid frame-continuous girder construction technology | |
CN106702909A (en) | Integral swiveling structure for double-body steel box girder and construction method thereof | |
CN114781026A (en) | A construction control method for a cable-stayed bridge with a single leaning tower | |
CN106988202A (en) | A kind of hybrid structure of arch and beam formula concrete continuous girder bridge structure | |
CN104314013B (en) | Two Cantilever Construction Methods of a kind of pole asymmetrical array beam | |
CN203613467U (en) | Steel pipe bracket for construction of arch tower in oblique arch tower double-cable plane pre-stressed concrete cable-stayed bridge | |
CN103469735A (en) | Method for mounting curve ultrahigh hollow column plate type pier top solid section template | |
CN105603879B (en) | The construction technology in large-scale pipeline crossing construction cat road |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 300051 No. 239, Yingkou Road, Heping District, Tianjin Patentee after: Tianjin municipal engineering design and Research Institute Co.,Ltd. Address before: 300051 No. 239, Yingkou Road, Heping District, Tianjin Patentee before: TIANJIN MUNICIPAL ENGINEERING DESIGN & Research Institute |
|
CP01 | Change in the name or title of a patent holder |