CN104360189B - A kind of grid power blackout event judgment method - Google Patents

A kind of grid power blackout event judgment method Download PDF

Info

Publication number
CN104360189B
CN104360189B CN201410638448.6A CN201410638448A CN104360189B CN 104360189 B CN104360189 B CN 104360189B CN 201410638448 A CN201410638448 A CN 201410638448A CN 104360189 B CN104360189 B CN 104360189B
Authority
CN
China
Prior art keywords
energy data
power
event
reading part
energy
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410638448.6A
Other languages
Chinese (zh)
Other versions
CN104360189A (en
Inventor
魏星
张云峰
吴建新
裴建成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, Huzhou Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201410638448.6A priority Critical patent/CN104360189B/en
Priority claimed from CN201410116891.7A external-priority patent/CN103926485B/en
Publication of CN104360189A publication Critical patent/CN104360189A/en
Application granted granted Critical
Publication of CN104360189B publication Critical patent/CN104360189B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The invention discloses a kind of grid power blackout event judgment method, based on energy collection terminal, the energy collection terminal is included:Energy data reading part, display part and energy data analysis portion, wherein:The energy data analysis portion determines first reference mode according to the node location of power network scene negative control terminal, second reference mode is determined according to the outage information and auxiliary information of the initial plant, the 3rd reference mode is determined according to the outage information and auxiliary information of the by-pass line again, an optimization node is generated by second reference mode and the 3rd reference mode, is used for reading continuation judgement after the field load terminal is power-off event in first time.The present invention can conveniently be powered reliability statistics and troubleshooting, improve power customer satisfaction.

Description

A kind of grid power blackout event judgment method
The application is Application No. 2014101168917, and the applying date is on March 26th, 2014, entitled based on electricity The divisional application of the power-off event determination methods of energy acquisition terminal.
Technical field
The present invention relates to a kind of grid power blackout event judgment method.
Background technology
Power supply enterprise can have accurately judgement to line outage by systems such as dispatching automations, to certain in circuit Individual larger power user or the power failure in platform area, the power-off event for being reported mainly by power load control terminal and Distribution transformer at present To judge, but due to negative control and distribution transformer terminals there are problems that battery problems, criterion and, cause to report Event wrong report phenomenon can often occur, be allowed to be not used to accurately judge whether to have a power failure.The present invention is using existing inaccurate Event information, and terminal called analyzed judgement, formed accurate power-off event, made it possible to effective for stopping again Electricity judges and troubleshooting.
The content of the invention
Accurately judge whether large power customers or the distribution transforming of platform area have a power failure and stop present invention mainly solves power supply enterprise The problem of electric duration, reliability statistics and troubleshooting are powered to facilitate, and improve power customer satisfaction.
When scene occurs the event of power failure or upper electricity, live negative control terminal or Distribution transformer meeting active reporting are corresponding Event.In view of communication or the various factors such as on-site terminal failure, the power-off event that on-site terminal is reported there may exist wrong report, leak Report situation, the technical solution adopted for the present invention to solve the technical problems mainly includes two parts, and one is examined again by event It is disconnected, the situation of power-off event wrong report is solved, two is the situation for solving to fail to report by power-off event pairing
Technical scheme 1:Power-off event determination methods based on energy collection terminal, wherein the energy collection terminal includes :Energy data reading part, the energy data for obtaining at least one live negative control terminal in power network;Display part, for showing Show these energy datas;And energy data analysis portion, the energy data reading part and display part are connected, for according to being obtained Energy data judges the initial plant of the live negative control terminal, and judges stopping for its by-pass line according to the initial plant Power information and the auxiliary information for being associated the by-pass line with initial plant;Wherein:
The energy data analysis portion determines first reference node according to the node location of power network scene negative control terminal Point, second reference mode is determined according to the outage information and auxiliary information of the initial plant, and according to the bypass The outage information and auxiliary information of circuit determine the 3rd reference mode, are referred to by second reference mode and the 3rd Node generates an optimization node, for reading the field load terminal to continue after power-off event to judge in first time Use.
Further, the energy data reading part is designed with after a Preset Time, by first reference node Point reads the instantaneous three-phase voltage and current value at the field load terminal node.
In one embodiment, designing the energy data analysis portion cannot correctly obtain with the energy data reading part Take after instantaneous three-phase voltage and current value, judge that the field load terminal occurs power-off event.Adopted based on electric energy described Collect in the power-off event determination methods of terminal, it is described to be judged by the optimization node to design the energy data reading part There is power-off event in on-site terminal.
Further, design the energy data analysis portion and correctly obtain instantaneous three-phase with the energy data reading part Voltage and current value and its value are after zero, to judge that the field load terminal occurs power-off event.
Further, design the energy data analysis portion and correctly obtain instantaneous three-phase with the energy data reading part After thering is one to be mutually not zero in voltage and current value and its value, judge that the energy data reading part misreads event.
Technical scheme 2:A kind of grid power blackout event judgment method, based on energy collection terminal, the energy collection terminal Include:Energy data reading part, the energy data for obtaining at least one live negative control terminal in power network;Display part, uses In these energy datas of display;And energy data analysis portion, the energy data reading part and display part are connected, for basis Obtained energy data judges the initial plant of the live negative control terminal, and judges its by-pass line according to the initial plant Outage information and the auxiliary information that is associated the by-pass line with initial plant;Including step:
The energy data of field load terminal is obtained by energy data reading part;
One first ginseng is determined according to the node location of power network scene negative control terminal by the energy data analysis portion Examine node;
The energy data analysis portion determines one second according to the outage information and auxiliary information of the initial plant Reference mode, the energy data reading part obtains field load terminal and whether there is power failure thing by this first reference mode Part;
The 3rd reference mode, the electric energy number are determined according to the outage information and auxiliary information of the by-pass line The instantaneous three-phase voltage and current value of field load terminal are obtained by this second reference mode according to reading part;By described second Reference mode and the 3rd reference mode generate an optimization node, and the energy data reading part sentences according to this optimization node Whether the fixed instantaneous three-phase voltage and current value are zero.
In one embodiment, design the energy data analysis portion and correctly obtain wink with the energy data reading part When three-phase voltage and current value and its value be after zero, to judge that the field load terminal occurs power-off event.
In one embodiment, design the energy data analysis portion and correctly obtain wink with the energy data reading part When three-phase voltage with there is one to be mutually not zero in current value and its value after, judge that the energy data reading part misreads thing Part.
In one embodiment, energy data analysis portion carries out the electric event pairing that has a power failure/go up according to the power-off event Operation.
In one embodiment, 1) in the case of only power-off event is obtained without carrying out electric alarm, according to instantaneous three-phase Voltage, current data are judged, if there is normal service data, are judged to incoming call, are made with the time point of normal service data It is the incoming call moment;2) in the case of calling event is only obtained without power failure alarm, elapsed forward according to incoming call time point, sought Nearest one load point for having normal service data is looked for, as power off time point, with closest to a time point for normal data As the moment that has a power failure.
Specific embodiment
Accurately judge whether large power customers or the distribution transforming of platform area have a power failure and stop present invention mainly solves power supply enterprise The problem of electric duration, reliability statistics and troubleshooting are powered to facilitate, and improve power customer satisfaction.
When scene occurs the event of power failure or upper electricity, live negative control terminal or Distribution transformer meeting active reporting are corresponding Event.In view of communication or the various factors such as on-site terminal failure, the power-off event that on-site terminal is reported there may exist wrong report, leak Report situation, the technical solution adopted for the present invention to solve the technical problems mainly includes two parts, and one is examined again by event It is disconnected, the situation of power-off event wrong report is solved, two is the situation for solving to fail to report by power-off event pairing
Technical scheme 1:Power-off event determination methods based on energy collection terminal, wherein the energy collection terminal includes :Energy data reading part, the energy data for obtaining at least one live negative control terminal in power network;Display part, for showing Show these energy datas;And energy data analysis portion, the energy data reading part and display part are connected, for according to being obtained Energy data judges the initial plant of the live negative control terminal, and judges stopping for its by-pass line according to the initial plant Power information and the auxiliary information for being associated the by-pass line with initial plant;Wherein:
The energy data analysis portion determines first reference node according to the node location of power network scene negative control terminal Point, second reference mode is determined according to the outage information and auxiliary information of the initial plant, and according to the bypass The outage information and auxiliary information of circuit determine the 3rd reference mode, are referred to by second reference mode and the 3rd Node generates an optimization node, for reading the field load terminal to continue after power-off event to judge in first time Use.
Further, the energy data reading part is designed with after a Preset Time, by first reference node Point reads the instantaneous three-phase voltage and current value at the field load terminal node.
In one embodiment, designing the energy data analysis portion cannot correctly obtain with the energy data reading part Take after instantaneous three-phase voltage and current value, judge that the field load terminal occurs power-off event.
In the power-off event determination methods based on energy collection terminal, the energy data reading part is designed with logical The optimization node is crossed to judge the on-site terminal generation power-off event.
Further, design the energy data analysis portion and correctly obtain instantaneous three-phase with the energy data reading part Voltage and current value and its value are after zero, to judge that the field load terminal occurs power-off event.
Further, design the energy data analysis portion and correctly obtain instantaneous three-phase with the energy data reading part After thering is one to be mutually not zero in voltage and current value and its value, judge that the energy data reading part misreads event.
Technical scheme 2:Power-off event determination methods based on energy collection terminal, wherein the energy collection terminal includes :Energy data reading part, the energy data for obtaining at least one live negative control terminal in power network;Display part, for showing Show these energy datas;And energy data analysis portion, the energy data reading part and display part are connected, for according to being obtained Energy data judges the initial plant of the live negative control terminal, and judges stopping for its by-pass line according to the initial plant Power information and the auxiliary information for being associated the by-pass line with initial plant;Including step:
The energy data of field load terminal is obtained by energy data reading part;
One first ginseng is determined according to the node location of power network scene negative control terminal by the energy data analysis portion Examine node;
The energy data analysis portion determines one second according to the outage information and auxiliary information of the initial plant Reference mode, the energy data reading part obtains field load terminal and whether there is power failure thing by this first reference mode Part;
The 3rd reference mode, the electric energy number are determined according to the outage information and auxiliary information of the by-pass line The instantaneous three-phase voltage and current value of field load terminal are obtained by this second reference mode according to reading part;By described second Reference mode and the 3rd reference mode generate an optimization node, and the energy data reading part sentences according to this optimization node Whether the fixed instantaneous three-phase voltage and current value are zero.
In one embodiment, design the energy data analysis portion and correctly obtain wink with the energy data reading part When three-phase voltage and current value and its value be after zero, to judge that the field load terminal occurs power-off event.
In one embodiment, design the energy data analysis portion and correctly obtain wink with the energy data reading part When three-phase voltage with there is one to be mutually not zero in current value and its value after, judge that the energy data reading part misreads thing Part.
In one embodiment, energy data analysis portion carries out the electric event pairing that has a power failure/go up according to the power-off event Operation.
In one embodiment, 1) in the case of only power-off event is obtained without carrying out electric alarm, according to instantaneous three-phase Voltage, current data are judged, if there is normal service data, are judged to incoming call, are made with the time point of normal service data It is the incoming call moment;2) in the case of calling event is only obtained without power failure alarm, elapsed forward according to incoming call time point, sought Nearest one load point for having normal service data is looked for, as power off time point, with closest to a time point for normal data As the moment that has a power failure.

Claims (4)

1. a kind of grid power blackout event judgment method, based on energy collection terminal, it is characterised in that the energy collection terminal bag Include:Energy data reading part, the energy data for obtaining at least one live negative control terminal in power network;Display part, is used for Show these energy datas;And energy data analysis portion, the energy data reading part and display part are connected, for according to institute Obtain the initial plant that energy data judges the live negative control terminal, and its by-pass line is judged according to the initial plant Outage information and the auxiliary information for being associated the by-pass line with initial plant;Including step:
The energy data of live negative control terminal is obtained by energy data reading part;
One the first reference node is determined according to the node location of power network scene negative control terminal by the energy data analysis portion Point, the energy data reading part obtains live negative control terminal and whether there is power-off event by this first reference mode;
The energy data analysis portion determines one second reference according to the outage information and auxiliary information of the initial plant Node, the energy data reading part obtains the instantaneous three-phase voltage and electric current of live negative control terminal by this second reference mode Value;
The 3rd reference mode is determined according to the outage information and auxiliary information of the by-pass line;
An optimization node, the energy data reading part root are generated by second reference mode and the 3rd reference mode Optimize node accordingly to judge whether the instantaneous three-phase voltage and current value are zero.
2. grid power blackout event judgment method according to claim 1, it is characterised in that:The energy data analysis portion with The energy data reading part correctly obtains instantaneous three-phase voltage and current value and its value is after zero, to judge the negative control in the scene There is power-off event in terminal.
3. grid power blackout event judgment method according to claim 1, it is characterised in that:The energy data analysis portion with After the energy data reading part correctly obtains instantaneous three-phase voltage and has one to be mutually not zero in current value and its value, institute is judged State energy data reading part and misread event.
4. the grid power blackout event judgment method according to Claims 2 or 3, it is characterised in that:Energy data analysis portion according to The power-off event is come the electric event matching operation that have a power failure/go up.
CN201410638448.6A 2014-03-26 2014-03-26 A kind of grid power blackout event judgment method Active CN104360189B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410638448.6A CN104360189B (en) 2014-03-26 2014-03-26 A kind of grid power blackout event judgment method

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201410638448.6A CN104360189B (en) 2014-03-26 2014-03-26 A kind of grid power blackout event judgment method
CN201410116891.7A CN103926485B (en) 2014-03-26 2014-03-26 Power failure event judging method based on electric energy collecting terminal

Related Parent Applications (1)

Application Number Title Priority Date Filing Date
CN201410116891.7A Division CN103926485B (en) 2014-03-26 2014-03-26 Power failure event judging method based on electric energy collecting terminal

Publications (2)

Publication Number Publication Date
CN104360189A CN104360189A (en) 2015-02-18
CN104360189B true CN104360189B (en) 2017-05-31

Family

ID=52527471

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410638448.6A Active CN104360189B (en) 2014-03-26 2014-03-26 A kind of grid power blackout event judgment method

Country Status (1)

Country Link
CN (1) CN104360189B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107045088A (en) * 2016-12-30 2017-08-15 国网天津武清供电有限公司 A kind of supply line's power failure point determination methods
CN108181546B (en) * 2017-12-08 2020-06-26 囯网河北省电力有限公司电力科学研究院 Power distribution network fault positioning method and device and terminal equipment

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102012467A (en) * 2009-09-04 2011-04-13 山东卓尔电气有限公司 Discrimination system for breakdown failures on mainline or branch line of power grid
CN102590711A (en) * 2012-03-16 2012-07-18 山西省电力公司太原供电分公司 Method and device for determining power failure range
CN102608497A (en) * 2012-03-16 2012-07-25 山西省电力公司太原供电分公司 Power failure diagnosis method and device
CN103279895A (en) * 2013-04-27 2013-09-04 广东电网公司佛山供电局 Method and system for monitoring power failure
CN103530816A (en) * 2013-10-10 2014-01-22 国家电网公司 Power supply reliability-oriented secondary optimization evaluation model for reliability of power distribution network

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0761181B2 (en) * 1985-06-29 1995-06-28 マツダ株式会社 Diagnostic device for multiplex transmission system
JP3401160B2 (en) * 1997-03-28 2003-04-28 三菱電機株式会社 Distributed shared memory network device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102012467A (en) * 2009-09-04 2011-04-13 山东卓尔电气有限公司 Discrimination system for breakdown failures on mainline or branch line of power grid
CN102590711A (en) * 2012-03-16 2012-07-18 山西省电力公司太原供电分公司 Method and device for determining power failure range
CN102608497A (en) * 2012-03-16 2012-07-25 山西省电力公司太原供电分公司 Power failure diagnosis method and device
CN103279895A (en) * 2013-04-27 2013-09-04 广东电网公司佛山供电局 Method and system for monitoring power failure
CN103530816A (en) * 2013-10-10 2014-01-22 国家电网公司 Power supply reliability-oriented secondary optimization evaluation model for reliability of power distribution network

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
基于停电区域及广域同步信息的电网故障快速诊断研究;戴志辉 等;《电力系统保护与控制》;20100616;第38卷(第12期);第50-53页 *

Also Published As

Publication number Publication date
CN104360189A (en) 2015-02-18

Similar Documents

Publication Publication Date Title
CN104182815B (en) A kind of power supply reliability acquisition methods and system
CN103926485B (en) Power failure event judging method based on electric energy collecting terminal
CN202230153U (en) Abnormal power utilization real-time monitoring system for rural power grid distribution station
CN105894172A (en) Joint outage judging method based on marketing and distribution fusion
CN103701212B (en) A kind of method for monitoring and analyzing for safety and stability control device of electric network and system
KR101278309B1 (en) Outage schedule management apparatus and method in ems
CN109345786A (en) A kind of non-resident user power utilization abnormal conditions automatic alarm system of low pressure
CN104360189B (en) A kind of grid power blackout event judgment method
CN105867290B (en) Office space safety utilization of electric power monitoring system and its method
CN103928986B (en) Dispatching of power netwoks wiring diagram error checking and correction system and method for calibration thereof
CN107632198B (en) Dual-power electric quantity acquisition device and application method thereof
CN103077439A (en) Detection system and detection method for electrical energy waste
JP2017123705A (en) Distribution board monitoring system, distribution board, and distribution board monitoring device that can be installed in them
CN105098995A (en) Switch state monitoring device in transformer substation cabinet
CN102967783A (en) Load trip identification method based on WAMS (Wide Area Measurement System) and SCADA (Supervisory Control And Data Acquisition) comprehensive data
CN103296756A (en) Managing and monitoring system for transformer substation
CN113824109B (en) Regional topology network power consumption data consistency accounting method
CN108802567B (en) Island monitoring method for new energy power supply
CN110736870A (en) Current detection device and control method thereof, medium, platform end and monitoring system
CN105158599B (en) A kind of method for judging scheduling system busbar power-off telegram in reply in time
CN109390923A (en) Power distribution control method and device for low-voltage direct controller switching equipment
CN214799042U (en) Industrial alternating current monitoring and management system
CN211014609U (en) Detection apparatus for contactor front end fuse
CN206834840U (en) Power distribution automation DC-capable AC decompression alarm-monitor system
CN115099562A (en) Intelligent scheduling method and system based on multiple platforms

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant